You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/336890371

Considerations on the Practical Development of the Geotechnical Baseline


Report (GBR) for the FIDIC Emerald Book and Similar Contract Forms

Preprint · October 2019

CITATIONS READS

0 996

1 author:

Alexandre R.A. Gomes


SMEC (member of the Surbana Jurong Group)
34 PUBLICATIONS   28 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Metro Bangkok View project

Snowy 2.0 Pump Storage Scheme View project

All content following this page was uploaded by Alexandre R.A. Gomes on 27 May 2021.

The user has requested enhancement of the downloaded file.


ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020

Considerations on the Practical Development of the Geotechnical Baseline Report


(GBR) for the FIDIC Emerald Book and Similar Contract Forms
A. R.A. Gomes1
1
Chief Technical Principal Tunnels and Underground, SMEC Australia Pty. Ltd., Sydney, Australia
E-mail: Alexandre.Gomes@Smec.com

ABSTRACT: In the framework of the FIDIC Emerald Book, the Geotechnical Baseline Report (GBR) plays a pivotal role in the
management and contractual allocation of geotechnical risks between the Parties. A major distinction of the GBR concept proposed in the
Emerald Book with respect to traditional GBR formats consists in the incorporation of a baseline of excavation, support and lining works,
which are applied during construction in accordance with the actual encountered subsurface conditions and used with the purpose of
remeasurement and adjustment of contractual construction time and cost. This paper presents a brief discussion on relevant concepts and
elements associated with the proposed GBR concept, including suggestions for its practical implementation under the Emerald Book and
similar contract forms.

KEYWORDS: Contracts for Underground Works, Geotechnical Baseline Report (GBR), FIDIC Emerald Book, Geotech. Risk-Allocation.

1. INTRODUCTION
Table 1: GBR’s structure and scope acc. to FIDIC guidelines (2018)
The first edition of the FIDIC Emerald Book Conditions of Contract
for Underground Works (2018), jointly prepared by FIDIC and the Sections Description of Scope
International Tunnelling and Underground Space Association (ITA- Part A Informative only and shall include general project
AITES), filled an important gap in the tunnelling industry by information, such as layout and descriptions of works
introducing the first international contract form specifically tailored with typologies and associated construction methods;
for underground works and with specific focus on the inherent typical geotechnical conditions; a discussion on project
geotechnical risks associated with this type of construction. challenges and identification of natural and man-made
The Emerald Book is essentially a modified FIDIC Yellow risks and constraints.
Book contract form drafted to combine the Design-Built approach Part B Corresponds to the actual contractual baselines of
with a balanced allocation of geotechnical risks between the Parties. physical and behavioural subsurface conditions,
It is based on the premise that risks must be allocated to the Party together with the baseline of “Excavation” (excavation
that is best positioned to manage them, implying in broader terms, and initial support) and “Lining” works for each
that ground-related risks are allocated to the Employer and risks relevant work type and section. (see note below)
associated with construction prices and production rates are assigned Appen- Shall include relevant supporting drawings (e.g. project
to the Contractor. dices layout, geotechnical and methodological longitudinal
The Geotechnical Baseline Report (GBR) is a key contractual profiles and sections, details of the various
document of the Emerald Book that defines the geotechnical excavation/support and lining classes) and the Ground
baselines agreed by the Parties and stipulates the contractual risk Classification System (GCS).
allocation mechanisms. A major distinction of the GBR concept Note: According to the Emerald Book, “Excavation” includes all
proposed in the Emerald Book with respect to traditional GBR works and activities associated with the excavation and initial
formats consists in the incorporation of a baseline of excavation, support of the openings, whereas “Lining” works correspond to the
support and lining works, which are applied during construction final/permanent support and associated waterproofing, contact
with the purpose of remeasurement and adjustment of contractual grouting and backfill (as applicable).
construction time and cost.
A brief discussion on relevant concepts and elements An example of a practical classification of the contractual
associated with the new proposed GBR concept is presented in the geotechnical baselines is suggested by the author in Table 2, where
following, including suggestions for its practical implementation items of work have been differentiated between Systematic and
under the Emerald Book and similar contract forms. Non-Systematic conditions. Further details are provided in section 4.

2. THE SCOPE OF THE GBR Table 2: E.g. Practical classification of the geotechnical baselines
The guideline for the preparation of the GBR included in the GBR Baselines Description (see also Section 5)
Emerald Book (2018) recommends the sub-division of the GBR into 1) Physical Baseline of Geotechnically Homogeneous
two parts and respective appendices. The first Part A shall be Subsurface Units (GHUs), groundwater and in-situ
informative only, whereas the actual contractual geotechnical Conditions stress conditions, natural and made
baselines shall be contained in Part B, as described in Table 1. geohazards and constraints.
The GBR’s basic structure can be understood as successive 2) Behavioural Baseline of ground behaviour types (GBs)
layers of information (baselines) which are derived from, and tacitly Conditions and acceptable impacts on the
reflects, the typical steps of the underground works’ geotechnical environment and adjacent infrastructure.
engineering design. These steps comprise the characterization of the 3) Systematic Baseline of typical project-specific
physical subsurface conditions, the assessment of ground behaviours
Conditions Tunnelling Classes (TCs) relative to the
and the design of sets of construction solutions and auxiliary
“Excavation” and “Lining” works (see
measures required to deal with the anticipated subsurface also TCs examples provided in Table 6).
conditions. In the GBR, the hierarchical relationship between the
4) Non- Baseline of construction measures and
baseline layers and elements is defined by the inclusion of a Ground
Systematic activities (NCs) required to deal with non-
Classification System (GCS), which stipulates how the items of
Conditions systematic geohazards, or other
work are assigned to anticipated subsurface conditions when they
hindrances not covered by the TCs.
are encountered during construction.
ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020

Conditions outside the scope of the baselines, here defined as version (for Bid) together with their respective bids. The definitive
systematic and non-systematic conditions, are regulated in the contractual document (called GBR-C, for the Contract) shall include
Emerald Book by a specific clause for “Contractual Unforeseeable the final Employer’s revision and any modifications that may result
Physical Conditions” (UPCs). from agreements met between the Parties during the contract
The level of uncertainty implicitly associated with each negotiation stage. It is important to mention that, when this approach
baselined element and how risks are distributed across the is applied, the Employer should clearly specify to Tenderers the
Systematic (TCs), Non-systematic (NCs) and Unforeseeable applicable GBR’s methodology and criteria to maintain
physical conditions (UPCs) represent the Employer’s preferred risk comparability between tender proposals and avoid undesirable shifts
profile. It is worth noting that unbalanced risks concealed within the of the Employer’s preferred risk profile.
scope of baselined elements may have a direct impact on the project Table 3 shows a summary of key GBR-related deliverables for
cost and overall risk profile, as Tenderers may be led to either price- the case of a three-stage GBR preparation.
in hidden risks or assume a disproportionate amount of risk (“dice- Table 3: Example of staged GBR preparation
rolling” approach).
The GBR’s risk allocation structure in accordance with the Project
Key Deliverables / Activities
terminology proposed in Table 2 is illustrated in Figure 1. Stage
Employer’s − GBR-A and associated Schedule of Baselines /
Tender Completion schedule.
documents − Supporting reference design, Technical
Requirements and Particular Conditions.
Preparation − GBR-B and associated Schedule of Baselines /
of Completion Schedule and required returnable
Tenderers’ documents.
proposals − Bid design
Contract − GBR-C and associated Schedule of Baselines /
negotiation Completion Schedule (to be agreed between the
and award Employer and the awarded Contractor).
Construction − Remeasurement and Adjustment of construction
phase cost and time-based on the conditions specified
in the GBR-C.

In the Emerald Book, the Contractor is responsible for the design of


the underground works to the extent specified in the Employer’s
Requirements and, where applicable, in accordance with the GBR.
As mentioned, it is expected that Tenderers submit reference-design
compliant proposals and, in the case of alternative proposals, a fully-
Figure 1: Illustration of the GBR’s risk-allocation structure developed set of supporting tender documents, including the
associated GBR, Schedule of Baselines and the Completion
3. PREPARATION OF THE GBR Schedule.
Notwithstanding that the GBR approach discussed in this paper
The quality of tender documents is key for the success of any project is oriented towards the Design-Build contract form of the Emerald
with a significant amount of underground works. Studies with Book, it can also be adapted to other types of contracts (e.g.
enough depth shall be carried out to ensure that risks have been Construct-only or EPC/Turn-key) provided that suitable particular
properly identified and managed and that a feasible construction conditions and provisions are built into the contractual framework to
solution has been developed to cover the full spectra of baselined regulate the risk-sharing mechanisms.
conditions, as requested by the Emerald Book.
The GBR is a pivotal component of the Emerald Book’s 4. GEOTECHNICAL BASELINE FRAMEWORK
contractual framework, being closely linked to the other contractual
documents, such as the Schedule of Baselines (quantities and As already mentioned, the contractual geotechnical baselines are
measurement of works), the Completion Schedule, the Employer’s essentially derived from the geotechnical design of the underground
technical requirements, the supporting drawings and the Risk works. Both processes should therefore follow a comprehensive and
Management Plans, among others. traceable methodology, which shall be set out by the Employer in
The preparation of the GBR requires therefore an integrated the tender documents. The next sections examine and discuss key
effort across several technical disciplines, including the contractual, aspects involved in the development of the contractual geotechnical
commercial and legal areas. It is noticeable that the process of baselines and the elaboration of the respective Ground Classification
preparing the GBR is often beneficial for the project, as it generates System (GCS).
a platform for interdisciplinary team collaboration both within each
Party’s organization and across the Parties, enabling a deeper 4.1 Baseline of Physical Conditions
understanding of the project’s technical challenges and risks ahead
The Employer is the Party who owns the risk associated with the
of the bid and the construction phase.
ground conditions and is therefore the Party that should be more
The Emerald Book seems to assume that the GBR shall be fully
interested in carrying out investigations and studies with enough
developed and owned by the Employer, except in the cases of
detail and to a depth which is commensurate with the nature, size
alternative proposals, where Tenderers shall produce similar
and level of complexity of the project.
supporting documents, particularly a GBR. An optional approach
The definition of a comprehensive baseline of physical
consists of adopting a three‐step GBR development process, as
subsurface conditions is an important step of the GBR, as it provides
suggested by the ASCE Guidelines (Essex R., 2007). This approach
the basic building blocks upon which the subsequent geotechnical
has the advantage that it promotes stronger engagement and a
baselines are developed to be used for remeasurement purposes.
shared-ownership of the GBR by the Parties.
One of the principles introduced by the Emerald Book is the
In the staged GBR development approach, the Employer shall
complete disclosure by Employers of all information obtained from
prepare an initial GBR (called GBR-A, for Tender), which is
the geotechnical studies and any other relevant geological and
reviewed and amended by Tenderers and submitted as the GBR-B
ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020

geotechnical information available (e.g. from data obtained from with respect to rock mass structures, groundwater, seepage and
previous projects carried out in the same area). This information hydraulic head and time-associated mechanisms, among others
shall be consolidated in a Geotechnical Data Report (GDR), which project-specific boundary conditions.
is part of the “other documents” section and has the lowest possible Table 4 provides a summary of some common high-level
contractual priority. Indeed, the GBR can and often will deviate ground behaviour types. These mechanisms often occur
from the GDR, as the geotechnical baselines are contractual concurrently in various levels of intensity and predominance and
baselines and not necessarily a geotechnical fact (Essex, 2007). detailed assessments and characterisation are required for each
A practical method to characterise the baseline of subsurface project-specific conditions and work section.
physical conditions considers the definition of “Geotechnically
Homogeneous Units” (GHUs) along the project alignment, which Table 4: Common high-level ground behaviour types
correspond to relevant ground volumes at the scale of the
underground works with similar geotechnical properties and Failure Description of controlling ground behaviour
characteristics concerning structural characteristics and key Mechanisms
parameters and properties required for design and construction Gravity and The ground is predominantly in the elastic domain
purposes. Structurally with failure controlled by discontinuities, including
The description of GHUs typically includes but is not limited to Controlled overbreak, fall of wedges or blocks, friable ground,
ground lithologies, mechanical and physical properties, structural Failure ravelling ground and progressive chimney failure.
geology, geomechanical classification indices and groundwater Ground Shear and/or spalling failure caused by stresses
conditions. Furthermore, the GHUs shall be defined not only in Failure due to exceeding the ground capacity.
terms of design parameters but also specify the conditions and Overstress
parameters that are specifically relevant to assess constructability
requirements and production rates. For example, whilst ground Effect of Deterioration and instability due to groundwater
permeability is required for design, anticipated and allowable water Ground-water seepage or pressure (e.g. loosening of blocks,
inflows should also be baselined as they are critical factors for the wash-out of fines, flowing ground,
assessment of required construction measures. slaking/swelling phenomena).
Other key aspects that must be addressed in the baseline are the Effect of Failure due to the presence of swelling/slaking
magnitude and orientation of in-situ ground stresses and the Minerals minerals either in the rock matrix or seams.
presence of non-systematic conditions (NCs), such as high water-
inflow, high rock abrasivity and natural or man-made constraints, Design approaches used for the assessment of ground failure
among other factors. The baselined characteristics shall be specified mechanisms and overall ground response consist typically of a
in terms of ranges and/or statistical distributions with clear combination of empirical, analytical and numerical analysis
indications with respect to the effective ranges that shall be used for methods, depending on the project specific requirements.
design purposes. For example, if the in-situ k-ratio is found to Experience and sound-engineering judgement are always
predominantly in the range of 0.7 to 1.5 but measurements indicate indispensable for the attainment of realistic assessments.
some potential outliers up to 2.5, the baseline should clearly specify Since the ground response cannot be precisely defined ahead of
which max/min or sensitivity values shall be considered for design construction, the definition of control parameters that can be
purposes. observed/measured on-site during construction (e.g. failure modes
In summary, the baseline of physical subsurface conditions and displacement characteristics) to verify and calibrate design
shall set out the anticipated GHUs, groundwater conditions, non- assumptions is always recommended.
systematic conditions (NCs) and any other identified As for the physical baselines, behavioural statements shall
geohazards/constraints at each relevant work section, including their include the anticipated percentual distribution of ground behaviour
estimated percentual distribution along the alignment. types (GBs), geohazards and specific constraints at each relevant
work section, establishing control parameters that can be effectively
4.2 Baseline of Behavioural Conditions used by the Ground Classification System (GCS) to correlate
conditions with required construction measures (See also table 8).
The excavation of underground works affects the primary
equilibrium conditions of the rock mass, causing the re-distribution 4.3 Baseline of Systematic Conditions - Tunnelling Classes
of stresses around the excavation, creating new rock blocks’ (TCs)
kinematic degrees of freedom and modifications of the surrounding
rock mass groundwater pore pressure, conductivity and flow Systematic excavation, support and lining works must be designed
conditions as well as changes in the thermal and chemical settings. for each singular work section and associated boundary conditions.
How the ground will respond to a specific construction method A common approach to deal with this type of works is the definition
applied for excavation and support, under particular physical and of various “Tunnelling Classes” (TCs), where each class
boundary conditions corresponds to the so-called “Ground corresponds to a set of construction measures and activities designed
Behaviour”. to deal with specific ranges of baselined conditions for any given
The Emerald Book considers the description of both the work type and methodology.
physical conditions and the ground behaviour as essential The design of the TCs implies the assessment of the complete
components of the description of the subsurface conditions. excavation and support process, including the definition of
Furthermore, it recommends that parameters contained in the GBR acceptable impacts on adjacent facilities and the environment (e.g.
shall focus majorly on ground behaviour and/or ground response permissible settlements and impact on groundwater table), the
rather than geologically oriented parameters. design of the final inner lining (if applicable to the project) and the
The Austrian Geomechanical Society Design Guideline (2011), verification of compliance with the project’s long term structural
for example, suggests general categories describing similar Ground and serviceability requirements.
Behaviours with respect to failure modes and displacement TCs shall cover the full range of baselined systematic
characteristics, which are denominated “Ground Behaviour Types” conditions specified in the GBR for each specific tunnel type, size
(GBs). GBs shall be assessed and described with consideration of and construction methodology. TCs are usually organised in the
all relevant influencing factors, including but not limited to: ground form of sets of construction measures with ascending/descending
conditions (GHUs), geohazards, in-situ stress conditions, shape and level of effort in terms of cost and time, which include all activities
size of the underground works, construction methodology, location or items of work upon which the Contractor commits costs,
with respect to surface or existing infrastructure, relative orientation
ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020

production rates and durations as set out in the schedule of transport and disposal conditions, TBM entrapment, need to
baselines, for remeasurement purposes during construction. reprofile section, etc. Examples of compensation items for NCs are
Table 5 provides some examples of relevant factors that affect listed in Table 7.
the cost and time of underground works, which should be Table 7: Examples of compensation items for NCs
considered for the definition of the project-specific TCs.
Non-Systematic Conditions (NCs) – E.g. Compensation Items
Table 5: Example of factors affecting the definition of TCs Care of water Specific for heading zones and rear zones and
compensated for an excess of n l/s (for selected
Item D&B TBM / Roadheader inflow ranges).
Excava- Round lengths Stroke length, cutter head penetration Abrasivity classes Use of Cerchar Abrasivity Index (CAI), with
tion and heading rates, tool wear and maintenance (ACs) compensation for values above certain pre-
works method (i.e. requirements, type of machine (e.g. defined ranges of abrasivity not covered by the
full-face or face pressure requirement, Boreability Classes.
partial drifts) gripper/single/double shield), etc. Geological Based on pre-defined criteria, such as those
Support Support type, D&B conditions apply for Gripper overbreak specified by SIA 198 or ÖNORM B 2203.
works quality, amount TBM and Roadheader. For Shield Ground treatment In accordance with different types of material
and location of TBM, a one-pass segmental lining (cement-based or chemical, scope and required
installation solution is typical (support with both methodologies).
(working or rear temporary and permanent character). Contaminated Special H&S, mucking and disposal
zone) ground requirements
Lining Inner lining D&B conditions apply for Gripper
works type, grouting, TBM and Roadheader. For Shield 4.5 Ground Classification System (GCS)
waterproofing. TBM, one-pass solution is typical.
Note: Other general factors include excavation size and layout, The GCS sets out the hierarchical correlations between the
accessibility conditions (e.g. tunnel gradient, length, etc.), face physical/behavioural baselines and the corresponding attributable
support or ground treatment requirements, mucking and ventilation TCs and NCs, being therefore a central component of the GBR.
requirements, among others. Table 8 presents a simplified example of an individual Ground
Behaviour type (GB) of a hypothetical conventional D&B
Table 6 provides examples of typical types of TCs applied for excavation, where the GCS is implicitly expressed by the cross-
systematic excavation, support and lining works of both references made to the underlying physical baselines and the
conventional and mechanised TBM excavations. attributable TCs and NCs for the respective ground behaviour type
Table 6: Examples of TCs – systematic conditions (e.g. GB9), including references to their respective Schedule of
Baselines and governing clauses.
TCs Description
Excavation Apply for Conventional D&B and Roadheader, with Table 8: Ground Classification – Simplified example of a GB
and Support ESCs catering for the combination of excavation
Classes sequence and support for each individual work. Ground Behaviour GB9 - Deep Shear Failure
(ESCs) Schematic Illustration
Boreability Apply for mechanised TBM excavation. BCs can be
Classes defined with basis on ground-related penetration
(BCs) and rates and cutter wear (e.g. Swiss TBM Field test
Support method, UCS / CAI abrasivity ranges, and models
Classes such as NTNU, RME, Qtbm, RME, CSM, Gehring, GHUs Prevalence GHU7, GHU9
(SCs) / and others). SCs are either standard rock support for Referential 20 ≤ RMR89 ≤ 40
(BCSCs) D&B/Gripper TBM or segmental lining for Shield Geomechanical Indices (acc. to Bieniawski, 1989)
TBM, among others. Orientation of major Sub-vertical to tunnel axis trending in
Lining Apply for D&B in-situ inner concrete lining, structural features E/W direction
Classes including waterproofing, contact grouting, etc. For
(LCs) one-pass solutions (e.g. Shield TBM segmental Deviatoric stress High rock mass overstress. 0.015 <
lining) LCs can be merged with the SC classes. conditions cm/max ≤ 0.05 (as per design values
or updated models based on monitoring
4.4. Baseline of Non-Systematic Conditions (NCs) and back-analysis results)
Groundwater Not relevant seepage expected during
The occurrence of geohazards and hindrances of sporadic and conditions excavation works.
localised nature, here denominated under the acronymic NC is very Ground Behaviour Deep-seated stress-controlled shear
common in underground works. These events may have significant Description failure with yielding and large
impact on the required construction effort and often require specific deformations (Pressure exerting).
positions in the Schedule of Baselines with the purpose of
Displacement Convergences in the range of 2.5-5.0%
measurement and payment.
Characteristics of the tunnel diameter.
Examples of such NCs include but are not limited to: handling
Face Stability Advanced support measures and ground
of water inflow or pressure in excess of pre-defined ranges; the
Conditions treatment may be required, acc. to NCs.
occurrence of extremely abrasive or strong rock; excessive
geological overbreak; ground treatment requirements (e.g. drilling Geotechnical Heavily constrained by geotechnical
and pre-grouting); specific environmental or logistic constraints Hindrances for conditions. Section reprofile may be
(areas with low acceptable ground settlements or stringent allowable Excavation required acc. to schedules of NCs.
water inflow, etc.); swelling ground, fault crossing, squeezing; Applicable ESC6 and ESC7, as per Schedule of TCs
presence of gas contaminated or aggressive ground or groundwater; Tunnelling Classes Baselines and drawings.
karst; rock strain bursts, seismicity; high temperature and hot water Note: the most robust ESC shall be adopted in case of: mixed
(e.g. due to hydrothermal sources); mixed or blocky ground (TBM), face conditions; discrepancy of multi-criteria; and changing
among others. These conditions can lead to various levels of impact ground conditions (install 2 diameters before and after the zone
to the construction, including construction downtime, stricter muck of change).
ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020

Figure 2: Overview of the GBR Framework

An overview of the GBR risk allocation framework is (Neuenschwander and Marulanda, 2019). Works subject to risks
illustrated in Figure 2. The correlation between the baseline related to the subsurface physical conditions, such as the TCs and
elements is graphically illustrated by the sub-vertical lines NCs shall be regularly remeasured with basis on the quantity- and
connecting the box symbols, representing the criteria established by time-related rate items included in the schedule of baselines for the
the GCS. specific items of work.
The GCS can be based on different approaches, spanning from On the other hand, works not affected by subsurface risks, such
empirical rock classification systems, through to semi-empirical as for example the contractor’s mobilisation, shall be remunerated
approaches and observational-methods or a combination of one or through lump sum components (fixed-rate prices) of the Contract
more methods. Independently of the selected approach, it important Price.
to ensure that the GCS criteria are effectively applicable to the In the case, of UPCs, adjustments and compensation shall be
project-specific subsurface conditions and construction methods and based on the measurement of additionally executed excavation and
that it is properly implemented on-site and that both Parties have a lining works and comparison with the benchmark production rates
good technical understanding of the inevitable and inherent and costs indicated in the initial GBR baselines.
theoretical and practical limitations associated with the selected
GCS criteria. 6. GBR IMPLEMENTATION DURING CONSTRUCTION
The adoption of multi-criteria approaches for the GCS with a
definition of hierarchal precedence, for example, can be a good The GBR is a multi-stage, multi-step procedure which starts at the
strategy to offset these limitations and generate redundancy around project’s initial planning stage and is only completed once
risks of bias, especially if decision criteria can be combined with construction is finished. Whilst the design shall ensure that risks
parameters/properties that can be observed and/or measured on-site have been properly identified and that a feasible construction
(observational method). In all cases, experience shows that a solution has been developed to cover the full spectra of expected
collaborative approach from both Parties and the application of physical conditions, the actual management and implementation of
sound technical criteria on-site always results in better project the GBR on-site, during the construction, is crucial for the success
outcomes, as oppose to adopting formalistic and legalistic positions, of the procurement model and for the overall project outcome.
which often lead to poor engineering decisions, claims and disputes Relevant geotechnical parameters and properties must be
collected, recorded, and evaluated on-site at each excavation cycle,
5. REMEASUREMENT OF COST AND TIME excavation round or construction stage, as required for ground
classification purposes, verification of design assumptions and
In the Emerald Book, both cost and time are based on the safety reserves. Typical geotechnical information collected during
contractual baselines defined in the Geotechnical Baseline Report, construction generally include but is not be limited to:
which are remeasured during construction for adjustment of the − Visual characterization of the ground (face mapping for
Contract Price and the Time for Completion. It implies that the time conventional/Gripper TBM excavation);
for completion and costs can either increase or reduce, depending if − Results of probe drilling / coring / sample testing;
the actual conditions are more or less onerous than anticipated. − Geophysical measurements;
In terms of payment, the Emerald Book distinguishes between − Groundwater measurements;
those parts of the Works that are subject to the risk related to the − Monitoring of stress, strain and displacements;
sub-surface physical conditions, and those parts that are not
ITA-AITES World Tunnel Congress, WTC2020 and 46th General Assembly Kuala Lumpur Convention Centre, Malaysia 15-21 May 2020

− TBM data, such as face pressure, thrust and penetration rates Norway, among others (mostly based on the re-measurement of unit
(field-test, if applicable); and rates, as in the FIDIC Red book) and promoted by various ITA-
− Verification of design assumptions regarding in-situ and AITES position papers in the last decades.
deviatoric stress conditions, etc. Nevertheless, the Emerald Book form of contract is the first
The collected and interpreted geotechnical data form the basis international contractual form for underground works, which
for the implementation of the Ground Classification System and the explicitly seeks a transparent and equitable allocation of ground
definition of the actions to be taken for the tunnelling work ahead, related risks.
including attribution of suitable TCs, NCs and any required It is a fact that there is no “one size fits all” regarding
additional construction measures. Conditions at the rear zones of construction contracts. The local industry context, laws and
excavated sections and at adjacent infrastructure must also be regulations may require important amendments to contractual forms
continuously assessed and observed to identify any abnormal and financing/insurance constraints may be determining in the
behaviour, presence of geohazards (e.g. water inflow) and define the selection of procurement models. However, it is fair to say that the
opportunity for the installation of the final/inner lining. Considering publication of the first version of the Emerald Book has been a
the strong focus of the Emerald Book in the management of risks, major contribution to the landscape of contract forms for
all relevant geohazards must be included in the risk register and underground works, by offering a functional initial contractual
treated in the geotechnical risk management plans prepared as part template for Employers seeking to incorporate a balanced allocation
of the overall construction risk management plan. of subsurface risks, more competitive Tenders and lower outturn
In view of the relevance of the GBR management during costs of the works.
construction, the Emerald Book foresees an important role for the Similarly, the GBR concepts put forward by the Emerald Book
Engineer, who has a duty of supervising the implementation of the also provide on their own a reasonable risk-allocation template,
works on site (Maclure, 2018). The decision on what measures to which can be applied either directly under the Emerald Book or
implement shall be made by the Contractor, as the Party responsible adapted to suit other types of contracts, provided that Particular
for the safety, however the Engineer shall assess to what extent it Conditions are built into the contract to stipulate the contractual
complies with the GCS and the contract, and if the Contractor's risk-allocation mechanisms that will govern the project’s
measurement should be accepted. This position requires a high underground works.
degree of impartiality as the Engineer plays a central role in the
resolution of day-to-day disputes between the Parties. 8. ACKNOWLEDGEMENTS
When an agreement cannot be reached, the Engineer makes a
The author would like to acknowledge the substantive work carried
fair determination and the Contractor then decide whether to claim
out by all members of the Task force 10 of ITA/FIDIC in the
or not. Following a Notice of Dissatisfaction (NOD) from one of the
preparation of the Emerald Book and their seminal contribution to
Parties, the matter is then referred to the Dispute Avoidance /
the underground construction industry.
Adjudication Board (DAAB), which is appointed for the whole
The author also would like to express its gratitude to Andreas
project duration. Only after these two avenues are exhausted, the
Neumaier, Ben Chapman, Francisco Cortes, Luke Drowley and
dispute will proceed to an external arbitration or litigation.
Nick Chapman, from SMEC, for their meaningful discussions,
Due to the significance of the GBR implementation, the
assistance and support in the preparation of this paper.
presence of a robust technical and commercial management on site,
by both the Employer and the Contractor, cannot be overstated, as it
Disclaimer: The views and opinions expressed in this paper are
enables Parties to deal more proactively and reasonably with
those of the author and do not necessarily reflect the official position
potential divergences and with the treatment of sensible changes and
of FIDIC and ITA.
adjustments that may be required due to the actually encountered
subsurface conditions.
9. REFERENCES
7. CONCLUSION Austrian Society for Geomechanics (2010). Guideline for the
geotechnical design of underground structures with
The paper discussed key concepts and elements associated with the
conventional excavation.
preparation of the Geotechnical Baseline Report (GBR) under the
Ericson, G. (2019). The Geotechnical Baseline Report in the new
framework of the FIDIC Emerald Book and similar contract forms
FIDIC Emerald Book – suggested developments.
and included practical suggestions on how to implement it.
Ertl, H. (2019). Risk allocation in the FIDIC forms of contract, and
Emphasis was given to the Emerald’s Book expanded GBR
the Emerald Book’s place in the Rainbow Suite.
scope and concepts, which differs from traditional GBR formats by
Essex R., (2007) “Geotechnical Baseline Reports for Construction,
the incorporation of a risk-sharing mechanism based on the re-
Suggested Guidelines”, UTRC ASCE.
measurement of executed constructions solutions (excavation,
FIDIC Conditions of Contract for Underground Works (2019) –
support and lining works) depending on the effectively encountered
Emerald Book; first edition.
geotechnical conditions during construction.
IMIA International Insurers Group / ITA-AITES (2012) Code of
As explained in the paper, The GBR is a multi-stage, multi-step
Practice for Risk Management of Tunnel Works.
process which commences in the early project stages, extends
ITA-AITES (2013) Guidelines on Contractual Aspects of
through to the reference design and tender period and is only
Conventional Tunnelling, WG-19 (and previous position
concluded once the contract is finished. This involves not only the
papers).
preparation of comprehensive contractual documents but also proper
Maclure, J. (2019). The role of the Engineer in the Emerald Book.
management and implementation on-site during construction. Past
Marulanda, A & Neuenschwander, M. (2019). Contractual time for
experiences have shown that cost overruns, delays and claims
completion adjustment in the FIDIC Emerald Book.
derived from poorly management of the GBR during construction
Nairac, C. (2019). The claims, dispute avoidance and dispute
greatly exceed costs associated with the provision of a robust
resolution procedure in the new FIDIC Emerald Book.
technical and contractual organization by both Parties during the
Neuenschwander, M & Marulanda, A. (2019). Measuring the
construction stage.
excavation and lining in the Emerald Book.
Several principles considered in the expanded GBR concept of
ÖNORM B 2203-1/2 (2001) - Austrian Standards, Underground
the Emerald Book have been around in the industry for several
Works - Contract Form.
decades, being particularly expressed in the contractual practices for
Swiss Standard SIA 507 198 (2007) – General Conditions for
underground works that have been developed and applied since the
Underground Construction.
70s in various European countries, such as Austria, Switzerland,

View publication stats

You might also like