You are on page 1of 12

June 29, 2020

India Power Regulation Weekly


An update on regulatory developments in the Indian power sector

INSIDE THIS ISSUE


GENERATION 2
CERC disposes of CGPL’s petition regarding capital expenditure for FGD installation 2
UPERC allows UPRVUNL to withdraw its petition regarding fly-ash transportation cost 2
UPERC allows UPRVUNL to withdraw its petition regarding ash dyke at Anpara TPS 2
CERC to hold public hearing on draft ‘Terms and Conditions of Tariff (First Amendment) Regulations, 2020 2
OERC disposes of petition filed by GRIDCO regarding PPA dispute with Vedanta Limited 3
TRANSMISSION 4
BERC initiates suo-motu proceedings with regard to development of intra-state transmission projects under TBCB 4
MERC partly allows TPC-T’s petition seeking review of order dated March 30, 2020 4
DISTRIBUTION 4
CSERC notifies CSERC (SoP in Distribution of Electricity) Regulations, 2020 4
UERC determines additional surcharge to be levied by UPCL 5
TNERC approves provisional tariff subsidy for 2020-21 5
KERC dismisses BESCOM’s petition seeking amendment to clauses of CoS 6
WBERC determines tariff for DVC for 2006-07 to 2008-09 6
HERC passes order regarding reduction in LPS payment 8
KSERC notifies Kerala Electricity Supply (Amendment) Code, 2020 8
RENEWABLE 8
CERC notifies ‘Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2020’ 8
UPERC disposes of Continental Carbon India’s petition regarding PPA dispute with UPPCL 9
UPERC determines disallowance towards secondary energy changes and tax on income for Vishnuprayag HEP 9
UERC passes suo-motu order regarding deployment of customised RPOCS web tool in Uttarakhand 9
UERC allows time extension to solar PV plant developers for commissioning of their power plant 10
BERC disposes of BREDA’s petition seeking approval of ceiling tariff for 250 MW solar power 10
KERC disposes of Messrs Adani Green’s petition regarding dispute with GESCOM 10
KERC dismisses Shree Renuka Sugars’ petition regarding payment issues with state discoms 11
KERC allows carry forward of excess banked energy on account of COVID-19 11
MERC partly allows ACME Heergarh Powertech’s petition against MSEDCL 11
MERC partly allows ReNew Solar Power’s petition regarding imposition of safeguard duty 12
JERC disposes of DNHPDCL’s petition regarding PSA for sale of 50 MW wind power 12

www.Indiapowerregulation.com
GENERATION
expenses on pro-rata basis corresponding to 4,000
MW in terms of the PPA.
CERC disposes of CGPL’s petition regarding capital
expenditure for FGD installation Petition No. 168/MP/2019
The Central Electricity Regulatory Commission Read Order :CERC_O_20_06_05_01.pdf,
(CERC) has disposed of a petition filed by Coastal
Gujarat Power Limited (CGPL), regarding approval
UPERC allows UPRVUNL to withdraw its petition
of capital expenditure to be incurred due to
regarding fly-ash transportation cost
installation of flue-gas desulfurization (FGD) system
at its 4,150 MW (5x830 MW) Mundra ultra mega The Uttar Pradesh Electricity Regulatory
power project (UMPP) in Gujarat. The commission Commission (UPERC) has allowed Uttar Pradesh
accorded approval to the petitioner for Rs 15,473.30 Rajya Vidyut Utpadan Nigam Limited (UPRVUNL)
million as capital cost on provisional basis against to withdraw its petition seeking in-principle
the proposed amount of Rs 16,343.30 million. The approval of recovery of additional operation and
commission also allowed the petitioner to claim maintenance expenditure on account of fly ash
expenditure towards interest during construction transportation cost. The commission gave the liberty
(IDC) (at actuals); Goods and Services Tax, taxes to the petitioner to file fresh a petiton, if needed.
and duties (as applicable); foreign exchange rate Petition no. 1441 of 2019
variation (if any); and expenditure towards owner’s
cost (at actuals) after commissioning of the FGD Read Order :UPERC_O_20_06_05_02.pdf,
system, which may be allowed after prudence
check. UPERC allows UPRVUNL to withdraw its petition
As regards contingency, the commission noted regarding ash dyke at Anpara TPS
that the petitioner has not given proper justification The Uttar Pradesh Electricity Regulatory
and therefore the cost may be allowed subject to Commission (UPERC) has allowed Uttar Pradesh
proper justification for such expense and subject to Rajya Vidyut Utpadan Nigam Limited (UPRVUNL)
prudence check by the commission after the to withdraw its petition seeking in-principle
installation of FGD system is completed. As regards approval for incurring additional capital
the claim towards restoration of existing access expenditure by the petitioner towards raising the
roads and re-routing of utilities (Rs 120 million) and height of the existing ash dyke at the Anpara power
miscellaneous costs- installation of electrical and fire station in order to ensure the efficient and complete
safety system (Rs 750 million), the commission handling and management of the ash.
observed that the Central Electricity Authority
The commission allowed withdrawal of the
(CEA) has stated that these are not directly required
petition and granted liberty to approach, if and
for installation of FGD system and the petitioner has
when need so arises, in terms of applicable
to assess its requirements. These costs may be
Generation Tariff Regulations, 2019.
allowed after installation of FGD system and after
considering proper justification of expenditure, Petition no. 1493 of 2019
subject to prudence check by the commission.
Read Order :UPERC_O_20_06_05_03.pdf,
The commission held that it is not considering
the opportunity cost at this stage. However, the
CERC to hold public hearing on draft ‘Terms and
same would be considered on actual number of
Conditions of Tariff (First Amendment) Regulations,
days of shutdown after prudence check to the effect 2020
that the petitioner has tried to synchronise the
interconnection of FGD system with annual The Central Electricity Regulatory Commission
overhaul and has consulted the beneficiaries in this (CERC) has decided to hold a public hearing for the
respect. The commission further held that the draft CERC (Terms and Conditions of Tariff) (First
calculations for capital expenditure, operating Amendment) Regulations, 2020. The commission
expenditure and auxiliary power consumption will had notified the draft regulations on April 1, 2020. It
be done corresponding to installed capacity of 4,150 has been decided to hold a public hearing on the
MW, but the respondents will be liable to pay the above subject on July 13, 2020 at 10:30 am via video
conferencing. The commission has requested that

India Power Regulation Weekly | June 29, 2020 January 4, 2016 2


the names of proposed participants from OERC disposes of petition filed by GRIDCO regarding
participating organisations may be registered on the PPA dispute with Vedanta Limited
SAUDAMINI portal after clicking public hearing
The Odisha Electricity Regulatory Commission
registration hyperlink on its homepage (www.cerc-
(OERC) has disposed of a petition filed by GRIDCO
efiling.gov.in) at least two days in advance.
Limited for resolution of disputes regarding
No. L-1 /236/2018/CERC execution of revised power purchase agreement
(PPA) for its Jharsuguda power plant in compliance
Read Order :CERC_R_20_06_05_02.pdf,
with the commission’s order dated January 27, 2016
passed in Case No.21 of 2015.

Issue Decision
a. Whether the basis If Vedanta injects less power in any 15-minute block, GRIDCO has to source the
of calculation needs shortfall quantity in that time block only from other generators/sources. Therefore,
to be 15 minutes GRIDCO must be compensated on 15-minute block basis. The computation of bill and
block wise or compensation due to shortfall shall be made on 15-minute basis and the bill shall be
monthly? paid on monthly basis after deducting the compensation
b. Definition of Marginal sources should include un-requisitioned power from inter-state generating
marginal sources stations (ISGS), power overdrawn under deviation settlement mechanism and power
and priority of drawn from Indian Energy Exchange. The price of the power drawn from the above
marginal sources marginal sources in 15 minute block should be utilized for computation of loss.
In case of low or no generation in Unit-2, Vedanta has to supply state entitlement of
power from its captive generating plant (CGP) units or from other sources. Such
c. Methodology of
supply of power from CGP units or other sources shall be deemed to have been
annual fixed
supplied from the IPP unit-2. Hence, plant availability factor achieved during the
charge/capacity
month (PAFM) of Unit-2 will be calculated by the state load despatch centre (SLDC)
charges calculation
based on the actual energy supplied by Vedanta. Accordingly, capacity charge shall
be computed.
In case of Jindal India Thermal Power Limited (JITPL) it supplies 12 per cent/14 per
d. Compensation
cent of generated power to GRIDCO on variable cost basis only whereas Vedanta
for short supply
supplies power on full cost basis which consists of both fixed and variable charges. In
and incorporation
case of short supply or no supply of power from Unit-II (IPP unit) of Vedanta, it is
of compensation
duty bound to replenish the same from its converted CGPs which is not the case of
clause in PPA
JITPL.
Since both GRIDCO and Vedanta have agreed for applicability of compensation
e. Period of short
towards short supply with effect from April 1, 2015, that is the date of conversion of
supply
three IPP units to CGP, the revised PPA should mention the same.
Whenever GRIDCO procures additional power from other
sources due to short supply of power by Vedanta Limited and pays additional point
f. Additional PoC
of connection (POC) charges to the central transmission utility beyond the fixed POC
charges and losses
charges on account of such additional power purchase, the additional cost borne by
GRIDCO towards PoC charges shall be recovered from Vedanta
Since Vedanta has agreed to compensate GRIDCO for its actual loss/damages due to
g. Opportunity loss short supply of power
of GRIDCO due to the opportunity loss as claimed by GRIDCO, which is very difficult to quantify,
short supply of should not form part of the PPA. However, GRIDCO has the liberty to file separate
power by Vedanta petition before the commission, when GRIDCO is genuinely affected and the
opportunity loss it claims is quantified.
The commission has directed both the parties to make necessary amendments in the consolidated PPA
dated December 19, 2012 keeping in view the directions of the commission in its order dated January 27,
2016 passed in Case No. 21/2015. The commission has directed GRIDCO to reconcile the arrear amounts of
Vedanta Limited at the earliest in view of the above observations of the commission and accordingly settle
the payments within two months from the date of issue of this order.

India Power Regulation Weekly | June 29, 2020 January 4, 2016 3


Case No. 68/2018
Read Order :OERC_O_20_06_05_01.pdf,

TRANSMISSION
Read Order :BERC_O_20_06_05_01.pdf,
BERC initiates suo-motu proceedings with regard to
development of intra-state transmission projects
MERC partly allows TPC-T’s petition seeking review
under TBCB
of order dated March 30, 2020
The Bihar Electricity Regulatory Commission
The Maharashtra Electricity Regulatory Commission
(BERC) has initiated suo-motu proceedings with
(MERC) has partly allowed a petition filed by the
regard to with regard to development of intra-state
Tata Power Company Limited (Transmission) (TPC-
transmission projects under tariff-based competitive
T) seeking review of certain aspects of the multi-
bidding (TBCB). The commission had issued a
year tariff (MYT) order issued on March 30, 2020 for
notification dated December 23, 2019 fixing the
TPC-T in Case No. 299 of 2019 in the matter of
threshold limit for TBCB mode at Rs 1 billion.
truing-up of aggregate revenue requirement (ARR)
Through the same notification the commission had
for 2017-18 and 2018-19, provisional truing-up of
also directed the Bihar State Transmission Company
ARR for 2019-20 and ARR for fourth MYT control
Limited and Bihar State Power (Holding) Company
period from 2020-21 to 2024-25.
Limited (BSPHCL) to come up with detailed
guidelines for operationalisation of regulatory The request of the petitioner for removal of
provisions within three months from the date of income of Rs 36.50 million and Rs 24.30 million for
notification. amortisation of service line contributions from the
non-tariff income for 2017-18 and 2018-19,
However, due to COVID-19, the commission
respectively, was allowed by the commission
did not receive the guidelines in time. Meanwhile, a
without carrying cost. The financial impact of the
directive under from the state government section
same will be considered at the time mid-term
108 of the Electricity Act, 2003 was issued to the
review for the present control period. The second
commission via a letter dated April 27, 2020 stating
request of the petitioner to allow surplus amount of
that the state government has decided of not opting
Rs 273.20 million as against approved Rs 1,019.80
for TBCB as of now. The commission, therefore, in
million for the total past recovery to be adjusted in
the interest of equity and transparency deems it
2020-21 was dismissed as being without merit. The
proper to deliberate and act upon the aforesaid
request to allow expenses of Rs 40.80 million
directive of the state government by giving
towards renovation and modernisation expenses for
opportunity of being heard to the state government,
2018-19 was dismissed as being without merit. The
intra-state transmission licensees, BSPHCL and
commission allowed capitalisation of Rs 4.3 million
other stakeholders.
in 2017-18 towards merged detailed project report
The last date to file the written comments to the for replacement of 22 kV and 33 kV bus sections at
commission is by July 10, 2020. Further due to Carnac receiving station. The commission ordered
pandemic isolation protocol and social distancing that the consequential financial impact of the same
norms, there will not be any open court public may be filed by TPC-T at the time of mid-term
hearing of this case. Based on the written review for the present control period.
objections/comments/suggestion received from the
Case No. 95 of 2020
respondents and other stakeholders, the commission
will decide the issue. Read Order :MERC_O_20_06_05_01.pdf,

Suo-Motu Proceeding No. 17/2020


DISTRIBUTION
The Chhattisgarh State Electricity Regulatory
CSERC notifies CSERC (SoP in Distribution of Commission (CSERC) has notified the CSERC
Electricity) Regulations, 2020 (Standards of Performance in Distribution of
Electricity) Regulations, 2020. These regulations will

India Power Regulation Weekly | June 29, 2020 January 4, 2016 4


be applicable to all the distribution licensees and standards in the short term and gradually move
deemed licensees engaged in the distribution of towards improved customer service standards in
electricity in Chhattisgarh and will be effective from the long term.
the date of their publication in the Chhattisgarh
Read Order :CSERC_R_20_06_05_01.pdf,
Rajpatra.
The objectives of these performance standards
UERC determines additional surcharge to be levied
are to lay down standards of performance; to
by UPCL
measure performance against the standards for the
licensee in providing service; to ensure that the The Uttarakhand Electricity Regulatory Commission
distribution network performance meets a (UERC) has determined Rs 1.11 per unit as
minimum standard which is essential for the additional surcharge to be levied by Uttarakhand
consumers' installation to function properly; to Power Corporation Limited (UPCL) for April 1, 2020
enable the consumers to design their systems and to September 30, 2020 to meet the fixed cost arising
equipment to suit the electrical environment that out of its obligation to supply electricity to the open
they operate in; and to enhance the quality of the access consumers.
services to meet acceptable customer service

UPCL-determined additional surcharge to be levied by UPCL


a Stranded power due to open access consumers at state periphery (MUs) 142.89
b Stranded power due to open access at consumer end (MUs) 120.77
Billed fixed cost of four generating stations during April 2019 to September 2019 (Rs
c 388.00
million)
Energy received at state periphery from the four ISGS stations during the period April 2019
d 410.58
to September 2019 (MUs)
Corresponding energy received from the four ISGS stations during the period at consumer
e 347.00
end (MUs)
f Weighted average fixed cost of four stations at consumer end (Rs per unit) [(c)*10/(e)] 1.12
g Total cost of stranded power due to open access consumers (Rs million) [(f)*(b)/10] 135.00
h Total open access units at state periphery for April 2019 to September 2019 (MUs) 143.77
i Corresponding open access power at consumer end (MUs) 121.51
Applicable additional surcharge for April 2020 to September 2020 (Rs per unit) based on
j 1.11
the open access units for the period April 2019 to September 2019 [(g)*10/(i)]
Source: UERC

Petition No. 04 of 2020


Read Order :UERC_O_20_06_05_02.pdf,
and Distribution Corporation Limited
(TANGEDCO). TANGEDCO has been directed to
TNERC approves provisional tariff subsidy for 2020-
reconcile the subsidy allowed with the actual
21
consumption and revenue assessed for 2019-20 and
The Tamil Nadu Electricity Regulatory Commission to furnish the report on or before September 30,
(TNERC) has approved provisional tariff subsidy 2020.
for 2020-21 as requested by Tamil Nadu Generation
TNERC-approved tariff subsidy for 2020-21
Categories of consumers Rs million
Domestic (free supply/reduction in tariff) 33,773.70
Agricultural consumers under normal category (free supply) 33,099.30
Agricultural consumers under self-sustained farming system category (free supply) 9,659.30
Hut consumers (free supply) 1,940.30
Actual place of public worship (reduction in tariff) 162.40
Power loom weavers (free supply/reduction in tariff) 3,847.00

India Power Regulation Weekly | June 29, 2020 January 4, 2016 5


Hand loom weavers (free supply) 61.60
Lift irrigation co-operative societies (free supply) 153.70
Total 82,697.30
Add: Additional subsidy payable for 2018-19 1,442.50
Net amount payable by state government to TANGEDCO for 2019-20 84,139.80
Source: TNERC

Order No.7 of 2020


Read Order :TNERC_O_20_06_05_01.pdf,
materials/equipment from the market. As submitted
by the petitioner, the consumers have to purchase
KERC dismisses BESCOM’s petition seeking
the materials from the approved vendors. The
amendment to clauses of CoS
approved vendors have already agreed to provide a
The Karnataka Electricity Regulatory Commission guarantee period of five years. In such a situation,
(KERC) has dismissed a petition filed by Bangalore BESCOM may also specify the quality of materials /
Electricity Supply Company Limited (BESCOM) equipment so as to ensure quality and duration of
requesting the commission to amend the clauses of such materials / equipment. Hence, it was held that
the Conditions of the Supply of Electricity of the there is no need to amend the KERC (Recovery of
Distribution Licensees in the State of Karnataka, Expenditure) Regulations 2004.
2006 (CoS) and KERC (Recovery of Expenditure for
Supply of Electricity) Regulations 2004 (RoE) by OP No.38/2019
substituting the existing requirement of one year Read Order :KERC_O_20_06_05_03.pdf,
guarantee with the proposed requirement of five
years guarantee.
WBERC determines tariff for DVC for 2006-07 to
The commission held that there is no restriction 2008-09
on the distribution licensee to increase this
The West Bengal Electricity Regulatory Commission
guarantee period as per its requirement of electrical
(WBERC) has determined tariff for Damodar Valley
equipment/material and techno-economic feasibility
Corporation (DVC) for 2006-07, 2007-08 and 2008-09
of its works/projects and therefore, the grounds
in terms of order passed by the High Court of
made out for amending the specific clauses of CoS
Calcutta passed on March 5, 2019. The commission
are not tenable and liable to be rejected.
has retained the demand charge rate at Rs 365 per
The commission further noted that provisions in KVA per month for all the three years in line with
the Recovery of Expenditure Regulations are the proposal of DVC to recover a part of the
supplemental to the Conditions of Supply are admitted fixed cost through demand charge and
enable the licensees to recover the expenditure balance part through variable charge. However, the
incurred in providing the electricity to the refundable amount of fixed cost will be passed on to
consumers. In most of the self-executed works, the consumers through reduced level of energy charge
consumers himself will procure the determined in this order.
WBERC-determined tariff for DVC for 2006-07
Name of Customer Name of Energy charge (Paise per KWh) Fixed charge/
consumer category tariff Demand
scheme Summer Monsoon Winter charge as admitted (Rs
per KvA per month)
L&MV Normal 250 250 250 5
Industrial and
Commercial (33 l-2(H) Normal 198 198 198 365
kV)
Industrial and
Commercial (132 l-3(H) Normal 195 195 195 365
kV)
Industrial and
l-4(H) Normal 191 191 191 365
Commercial (220

India Power Regulation Weekly | June 29, 2020 January 4, 2016 6


kV)
Traction T Normal 195 195 195 365
Source: WBERC

WBERC-determined tariff for DVC for 2007-08

Name of Customer Name of Energy charge (Paise per KWh) Fixed charge/
consumer category tariff Demand
scheme Summer Monsoon Winter charge as admitted (Rs per
KvA per month)
L&MV Normal 210 210 210 5
Industrial
and
l-2(H) Normal 142 142 142 365
Commercial
(33 kV)
Industrial
and
l-3(H) Normal 138 138 138 365
Commercial
(132 kV)
Industrial
and
l-4(H) Normal 132 132 132 365
Commercial
(220 kV)
Traction T Normal 138 138 138 365
Source: WBERC

WBERC-determined tariff for DVC for 2008-09


Name of Customer Name of Energy charge (Paise per KWh) Fixed charge/
consumer category tariff Demand
scheme Summer Monsoon Winter charge as admitted (Rs per
KvA per month)
L&MV Normal 210 210 210 5
Industrial
and
l-2(H) Normal 142 142 142 365
Commercial
(33 kV)
Industrial
and
l-3(H) Normal 138 138 138 365
Commercial
(132 kV)
Industrial
and
l-4(H) Normal 132 132 132 365
Commercial
(220 kV)
Traction T Normal 138 138 138 365
Source: WBERC

India Power Regulation Weekly | June 29, 2020 January 4, 2016 7


Case no: TP-80/19-20
Read Order :WBERC_O_20_06_05_01.pdf,
Electricity Supply Code, 2005, had a contracted
connected load exceeding the limit of 100 kVA, may
HERC passes order regarding reduction in LPS
be permitted, subject to realisation of low voltage
payment
supply surcharge, to operate with the same
The Haryana Electricity Regulatory Commission contracted connected load at the same voltage level
(HERC) has ordered that given the rapid recovery in of supply until an upward revision of connected
power demand and restoration of the economic load is sought for by the consumer.”;
activities to a large extent, there will be no extension
in reduced late payment surcharge (LPS) beyond (iii) In the Code, the proviso to Sub-regulation
May 31, 2020. The commission has earlier provided (2) of Regulation 11 of the Code, the following
relief to the state distribution companies on account provisos shall be substituted, namely:
of COVID-19 by reducing the rate of LPS for the “Provided that the consumers who existed on
delayed payment to the state generation company the date of implementation of Kerala Electricity
and transmission company from 14.6 per cent to Supply Code, 2005, and who were permitted to
8.65 per cent. operate at low tension up to a connected load of 150
Case No. HERC/PRO-21 of 2020 kVA in accordance with clause (b) of sub
Regulation(5) of Regulation 4 of the Kerala
Read Order :HERC_O_20_06_05_01.pdf, Electricity Supply Code, (Fourth Amendment)
Regulations 2008 and subsequently opted for
KSERC notifies Kerala Electricity Supply contract demand based billing shall be allowed to
(Amendment) Code, 2020 operate at the same voltage level and contract
demand as on the date of implementation of the
The Kerala State Electricity Regulatory Commission
Code, subject to realisation of low voltage surcharge
(KSERC) has notified Kerala Electricity Supply
until an upward revision of contract demand is
(Amendment) Code, 2020. The regulation will be
granted on application submitted by the consumer
effective from the date of publication of the same in
or becomes otherwise necessary.”
the official gazette.
“Provided further that the contract demand for
Some key amendments include:
an Industrial consumer in Industrial parks /
(i) In Sub-regulation (1) of Regulation 11 of the industrial estate notified by notified by Government
Code, the words “except in the case of consumers of Kerala and/or by Government of India except in
billed on the basis of contract demand” shall be multi storied buildings shall be limited to 150 kVA
added at the end; in low tension subject to payment of low voltage
surcharge in which their LT metering point shall be
(ii) In the Code, the proviso to sub Regulation
at the transformer point”
(1) of Regulation 11 shall be substituted, namely:
Read Order :KSERC_R_20_06_05_01.pdf,
“Provided that a low tension consumer who, as
on the date of implementation of the Kerala

RENEWABLE
effective to March 31, 2023. The tariff norms
specified in these regulations will continue to
CERC notifies ‘Terms and Conditions for Tariff
remain applicable until notification of the revised
determination from Renewable Energy Sources)
norms through subsequent re-enactment of these
Regulations, 2020’
regulations.
The Central Electricity Regulatory Commission
(CERC) has notified CERC (Terms and Conditions These regulations will apply to cases where
for Tariff determination from Renewable Energy tariff for a grid connected generating station or a
Sources) Regulations, 2020. These regulations will unit thereof commissioned during the control
be effective from July 1, 2020, and unless reviewed period and based on renewable energy sources, is to
earlier or extended by the commission, will remain be determined by the commission under Section 62
read with Section 79 of the Electricity Act, 2003. In

India Power Regulation Weekly | June 29, 2020 January 4, 2016 8


cases of wind power projects, small hydro projects, disposed of the petition and held that the parties
biomass power project with rankine cycle should honors the terms and conditions of the PPA.
technology, non-fossil fuel based co-generation
Petition no. 1533 of 2020
projects, solar photovoltaic power projects, floating
solar projects, solar thermal power projects, Read Order :UPERC_O_20_06_05_01.pdf,
renewable hybrid energy projects, renewable energy
with storage projects, biomass gasifier based power UPERC determines disallowance towards
projects, biogas based power projects, municipal secondary energy changes and tax on income for
solid waste based power projects and refuse derived Vishnuprayag HEP
fuel based power projects, these regulations will
apply subject to the fulfilment of eligibility criteria In response to a petition filed by Jai Prakash Power
specified in Regulation 4 of these Regulations. Ventures Limited, the Uttar Pradesh Electricity
Regulatory Commission (UPERC) has determined
Read Order :CERC_R_20_06_05_01.pdf, disallowance towards secondary energy charges
and tax on income for 400 MW Vishnuprayag
UPERC disposes of Continental Carbon India’s hydroelectric project (HEP).
petition regarding PPA dispute with UPPCL The commission held that the power purchase
The Uttar Pradesh Electricity Regulatory agreement (PPA) signed with Uttar Pradesh Power
Commission (UPERC) has disposed of a petition Corporation Limited (UPPCL)stipulates that the tax
filed by Continental Carbon India Limited, against on income would be computed as an expense at
Uttar Pradesh Power Corporation Limited (UPPCL), actuals for any under/over recovery to be adjusted
regarding power purchase agreement (PPA) every year on the basis of auditor’s certificate. It
disputes. The petitioner submitted that UPPCL has further held that the PPA was executed before 2009,
not made timely payments for power purchased and therefore, the norms of operation and terms and
from its waste-heat recovery plant set up at its conditions for determination of tariff in respect of
industrial unit in Ghaziabad. secondary energy charges will be governed by the
terms of PPA. However, this would be applicable
The commission noted that the petitioner has
only for the control period 2009-14 as the Tariff
received payment till December 2019, which is
Regulations 2014, approved by the commission have
reflective of the payment intentions of UPPCL and it
withdrawn such dispensation.
is adhering to the PPA. Hence, the commission
UPERC-determined disallowance for Vishnuprayag HEP (Rs million)
Particulars 2007-08 to 2013-14 2014-15 to 2017-18 Total
Disallowance in secondary energy
4.40 236.50 240.90
charges
Disallowance in taxes on charges 271.90 1,479.10 1,750.90
Total disallowance 1,991.80
Source: UPERC

Petition no. 1464 of 2019


Read Order :UPERC_O_20_06_05_04.pdf,
procedures to collect the relevant information for
verification purpose. Further, taking cognizance of
UERC passes suo-motu order regarding deployment
the fact that there are numerous captive users in
of customised RPOCS web tool in Uttarakhand
Uttarakhand and it will be a tedious job for UPCL to
The Uttarakhand Electricity Regulatory Commission collect and verify the data of each and every captive
(UERC) has passed a suo-motu order regarding user, the commission held that RPO shall be
deployment of customised renewable purchase applicable on all captive users having contracted
obligation compliance system (RPOCS) web tool in load of 75 kW/88 kVA and above. Accordingly,
Uttarakhand. UPCL should verify the information uploaded by
The commission has directed Uttarakhand the captive users on the RPOCS webtool having
Power Corporation Limited (UPCL) to issue proper contracted load of 75 kW/88 kVA and above. The
directions to its concerned officers and specify the commission held that based on the information

India Power Regulation Weekly | June 29, 2020 January 4, 2016 9


required for verification and validation of the The Bihar Electricity Regulatory Commission
information uploaded by the open access (BERC) has disposed of a petition filed by Bihar
consumers, the state load despatch centre (SLDC) Renewable Energy Development Agency (BREDA),
and UPCL may form a procedure mutually for seeking approval of ceiling tariff for procurement of
sharing of information/documents so that SLDC can 250 MW (AC) solar power from grid connected
validate the information uploaded by open access ground mounted solar power plants to be set up in
consumers on the RPOCS webtool. Accordingly, Bihar on a long-term basis (25 years) through
SLDC should verify the information uploaded by competitive bidding.
open access consumers on the RPOCS webtool. The
The commission held that there is no need to set
obligated entities shall upload the consumption
“Cap” or upper ceiling tariff in the instant proposal.
details along with supporting documents for the
The commission further held that e-reverse auction
month by the 30th of the following month.
process (such as being done through DEEP portal)
Petition No.: 12 of 2020 (Suo-Motu) should be followed in the bids as e-reverse auction
will help in discovering competitive tariff rates. The
Read Order :UERC_O_20_06_05_01.pdf,
commission further directed that e-reverse auction
process shall be conducted through a reliable and
UERC allows time extension to solar PV plant suitable portal which will not only ensure
developers for commissioning of their power plant transparency in the auction process but also
Taking cognisance of COVID-19 pandemic situation improves chances of participation of maximum
and ongoing monsoon season that will last up to number of bidders.
September 2020, the Uttarakhand Electricity Case No. 04/2020
Regulatory Commission (UERC) has allowed the
solar power developers to develop and commission Read Order :BERC_O_20_06_05_02.pdf,
their respective plants by March 31, 2021 to get the
tariff rates as specified in respective power purchase KERC disposes of Messrs Adani Green’s petition
agreements (PPAs) executed with UPCL. Further, in regarding dispute with GESCOM
case of any delay beyond March 31, 2021 the lower
The Karnataka Electricity Regulatory Commission
of the tariff determined by the commission for the
(KERC) has disposed of a petition filed by Messrs
year of commissioning of the proposed plant and
Adani Green Energy (UP) Limited requesting the
determined through competitive bidding/PPA tariff
commission to declare that the petitioner was
will be applicable.
prevented from performing the obligation under the
The commission reiterated that the solar power purchase agreement (PPA) due to ‘force
photovoltaic (PV) plants developers selected majeure’ events affecting it and to grant concurrence
through the competitive bidding for setting up of to the supplemental power purchase agreement
the solar PV plants having cumulative capacity of (SPPA) dated December 26, 2016.
200 MW and the solar PV plant developers who
The commission held that there was no direction
have been allowed to execute PPA with
given to the parties that after entering into the
Uttarakhand Power Corporation Limited (UPCL)
SPPA, the same should be again approved by the
with zero central finance assistance by the
commission. It further held that the non-production
commission vide its order dated September 17, 2019
of documents of title relating to the project lands is
are required to commission their respective projects
due to ‘force majeure’ event and hence, the
by the end of March 2021 to get the tariff as
petitioner is not liable for consequences under
determined through competitive bidding or as
Article 4.3 of the PPA.
mentioned in their respective PPA, as the case may
be. The commission ordered Gulbarga Electricity
Supply Company Limited (GESCOM) to refund Rs
Petition No.: 13 of 2020 (Suo-Motu)
1.2 million recovered (if any) from the petitioner,
Read Order :UERC_O_20_06_05_03.pdf, towards damages within eight weeks from the date
of this order. In the event of default, the said
amount will carry interest at the rate of 8 per cent
BERC disposes of BREDA’s petition seeking approval
per annum from the date of default till the date of
of ceiling tariff for 250 MW solar power
payment.

India Power Regulation Weekly | June 29, 2020 January 4, 2016 10


OP No.205/2017 shall be deemed to have been supplied to the
concerned escoms at no cost. No carry forward of
Read Order :KERC_O_20_06_05_01.pdf,
banked energy is allowed to renewable projects
under renewable energy certificate (REC) route and
KERC dismisses Shree Renuka Sugars’ petition to the renewable projects under non-REC route
regarding payment issues with state discoms other than the mini hydel project. Accordingly,
The Karnataka Electricity Regulatory Commission Article-9 of WBA has been amended for mini hydel
(KERC) has dismissed a petition filed by Shree projects.
Renuka Sugars Limited requesting the commission KERC/Misc/Banking/2020-21
to direct the Bangalore Electricity Supply Company
Limited, Chamundeshwari Electricity Supply Read Order :KERC_O_20_06_05_04.pdf,
Company Limited, Mangalore Electricity Supply
Company Limited, and Gulbarga Electricity Supply MERC partly allows ACME Heergarh Powertech’s
Company Limited, to release the payments to the petition against MSEDCL
petitioner as per the invoices raised along with the
The Maharashtra Electricity Regulatory Commission
interest at 18 per cent per annum.
(MERC) has partly allowed a petition filed by
The commission noted that the respondents did ACME Heergarh Powertech Private Limited
not make any representation for supply of power (AHPPL), a special purpose vehicle of , ACME Solar
from December 26, 2016 to January 1, 2017 andin Holding Limited (ASHL) seeking directions against
the absence of such representation, the principles of Maharashtra State Electricity Distribution Company
estoppel are not applicable. Limited (MSEDCL) by declaring that the power
purchase agreement (PPA) dated August 21, 2019
It was submitted that Hubli Electricity Supply
executed between AHPPL and MSEDCL stands
Company Limited (HESCOM) paid its share
invalid on account of force majeure. The petitioner
towards the energy supplied to the petitioner. The
has also requested for consequential relief under
commission noted that the petitioner had on
Section 86 of the Electricity Act, 2003 along with
December 12, 2016 itself made a request for supply
statutory framework governing procurement of
of energy and the HESCOM had replied through its
power through competitive bidding and Article 8 of
letter dated December 23, 2016, intimating the
the PPA.
petitioner that it would pay for its share of liability
only, for the energy supplied to the grid from ASHL was declared one of the successful
December 26, 2016 onwards on fulfilling certain bidders for development of 300 MW solar project at
conditions stated therein. However, the petitioner tariff of Rs 2.74 per kWh following the competitive
failed to obtain the consent of other escoms before bidding process. After adoption of competitively
injecting the energy in advance. Therefore, the discovered rate by the commission vide order dated
commission held that the payment by HESCOM May 27, 2019 in Case No. 87 of 2019 and furnishing
does not in any way improve the case of the of performance bank guarantee of Rs 420 million,
petitioner and the said payment does not create any PPA between AHPPL, SPV of ASHL and MSEDCL
liability on other ESCOMs. was signed on August 21, 2019 with the effective
date of PPA as June 26, 2019. As per the timelines in
OP No.69/2018
PPA, AHPPL was required to achieve financial
Read Order :KERC_O_20_06_05_02.pdf, closure and submit evidence of clear possession of
land required along with land documents within 10
KERC allows carry forward of excess banked energy months of effective date, that is, by April 25, 2020
on account of COVID-19 and scheduled commercial operation date within 24
months from the effective date that is, by June 25,
The Karnataka Electricity Regulatory Commission 2021.
(KERC) has ordered to allow carry forward of the
banked energy remaining unutilised as on May 31, The commission held that disruption in global
2020 up to July 31, 2020, in respect of mini hydel supply chain due to outbreak of COVID-19 and
generators who have executed wheeling and imposition of consequential lockdown in India is
banking agreement (WBA), subject to the condition considered as event of force majeure and therefore
that any banked energy allowed to be carried exempted AHPPL from its obligation for the period
forward and remaining unutilised till July 31, 2020, granted under force majeure without any

India Power Regulation Weekly | June 29, 2020 January 4, 2016 11


compensation. MSEDCL has been directed to will be at risk and cost of the petitioner. The
ascertain the exact period for relief under force commission has ordered MSEDCL to complete this
majeure after lock down is completely lifted and process within 15 days from date of this order. The
accordingly the timeline for financial closure and commission has stated that, based on the scrutiny of
SCoD will be extended with additional 30 days documents (to be completed in 45 days) and/or
thereafter. physical verification of radio frequency
identification tag (to be completed in six months),
Case No. 78 of 2020
compensation amount ascertained earlier should be
Read Order :MERC_O_20_06_05_02.pdf, re-verified and in case of any deviation, same
should be adjusted with holding/carrying cost in
MERC partly allows ReNew Solar Power’s petition future payments.
regarding imposition of safeguard duty Case No. 8 of 2020
The Maharashtra Electricity Regulatory Commission Read Order :MERC_O_20_06_05_03.pdf,
(MERC) has partly allowed a petition filed by
ReNew Solar Power Private Limited seeking an
appropriate mechanism for grant of
JERC disposes of DNHPDCL’s petition regarding PSA
adjustment/compensation to offset
for sale of 50 MW wind power
financial/commercial impact of change in law events The Joint Electricity Regulatory Commission for the
on account of imposition of safeguard duty on solar state of Goa and Union Territories (JERC) has
cells/modules. disposed of a petition filed by DNH Power
Distribution Corporation Limited (DNHPDCL),
The commission held that the central
regarding power sale agreement (PSA) for sale of 50
government’s notification dated July 30, 2018
MW wind power on a long-term basis.
imposing safeguard duty qualifies as ‘change in
law’ event. It further held that the petitioner is The commission examined the PSA in detail and
eligible for claiming compensation on account of also considered the submissions of the petitioner
imposition of safeguard duty (including additional and the respondent, Solar Energy Corporation of
GST) under change in law provisions of the power India Limited (SECI). The commission held that it is
purchase agreement (PPA) for capacity of 362.50 not convinced with the arguments made by SECI to
MW of solar module/panel installed at project justify charging of 7 paise per kWh trading margin.
location. The petitioner shall provide undertaking The commission was of the view that the petitioner
that all modules installed at project site for and the respondent should revisit the trading
supplying power to Maharashtra State Electricity margin to be charged by the respondent and resolve
Distribution Company Limited (MSEDCL) have the issue amicably with mutual consent along with
been imported from the countries which are justification. The commission directed both the
subjected to safeguard duty. parties to place on record the trading margin
mutually agreed on affidavit within two weeks.
MSEDCL has been further directed to act upon
such undertaking given by the petitioner and Petition No. 28/2019
ascertain the compensation amount under change in
Read Order :JERC_O_20_06_05_01.pdf,◆
law. Such ascertainment of compensation amount

India Power Regulation Weekly | June 29, 2020 January 4, 2016 12

You might also like