Professional Documents
Culture Documents
www.Indiapowerregulation.com
GENERATION
expenses on pro-rata basis corresponding to 4,000
MW in terms of the PPA.
CERC disposes of CGPL’s petition regarding capital
expenditure for FGD installation Petition No. 168/MP/2019
The Central Electricity Regulatory Commission Read Order :CERC_O_20_06_05_01.pdf,
(CERC) has disposed of a petition filed by Coastal
Gujarat Power Limited (CGPL), regarding approval
UPERC allows UPRVUNL to withdraw its petition
of capital expenditure to be incurred due to
regarding fly-ash transportation cost
installation of flue-gas desulfurization (FGD) system
at its 4,150 MW (5x830 MW) Mundra ultra mega The Uttar Pradesh Electricity Regulatory
power project (UMPP) in Gujarat. The commission Commission (UPERC) has allowed Uttar Pradesh
accorded approval to the petitioner for Rs 15,473.30 Rajya Vidyut Utpadan Nigam Limited (UPRVUNL)
million as capital cost on provisional basis against to withdraw its petition seeking in-principle
the proposed amount of Rs 16,343.30 million. The approval of recovery of additional operation and
commission also allowed the petitioner to claim maintenance expenditure on account of fly ash
expenditure towards interest during construction transportation cost. The commission gave the liberty
(IDC) (at actuals); Goods and Services Tax, taxes to the petitioner to file fresh a petiton, if needed.
and duties (as applicable); foreign exchange rate Petition no. 1441 of 2019
variation (if any); and expenditure towards owner’s
cost (at actuals) after commissioning of the FGD Read Order :UPERC_O_20_06_05_02.pdf,
system, which may be allowed after prudence
check. UPERC allows UPRVUNL to withdraw its petition
As regards contingency, the commission noted regarding ash dyke at Anpara TPS
that the petitioner has not given proper justification The Uttar Pradesh Electricity Regulatory
and therefore the cost may be allowed subject to Commission (UPERC) has allowed Uttar Pradesh
proper justification for such expense and subject to Rajya Vidyut Utpadan Nigam Limited (UPRVUNL)
prudence check by the commission after the to withdraw its petition seeking in-principle
installation of FGD system is completed. As regards approval for incurring additional capital
the claim towards restoration of existing access expenditure by the petitioner towards raising the
roads and re-routing of utilities (Rs 120 million) and height of the existing ash dyke at the Anpara power
miscellaneous costs- installation of electrical and fire station in order to ensure the efficient and complete
safety system (Rs 750 million), the commission handling and management of the ash.
observed that the Central Electricity Authority
The commission allowed withdrawal of the
(CEA) has stated that these are not directly required
petition and granted liberty to approach, if and
for installation of FGD system and the petitioner has
when need so arises, in terms of applicable
to assess its requirements. These costs may be
Generation Tariff Regulations, 2019.
allowed after installation of FGD system and after
considering proper justification of expenditure, Petition no. 1493 of 2019
subject to prudence check by the commission.
Read Order :UPERC_O_20_06_05_03.pdf,
The commission held that it is not considering
the opportunity cost at this stage. However, the
CERC to hold public hearing on draft ‘Terms and
same would be considered on actual number of
Conditions of Tariff (First Amendment) Regulations,
days of shutdown after prudence check to the effect 2020
that the petitioner has tried to synchronise the
interconnection of FGD system with annual The Central Electricity Regulatory Commission
overhaul and has consulted the beneficiaries in this (CERC) has decided to hold a public hearing for the
respect. The commission further held that the draft CERC (Terms and Conditions of Tariff) (First
calculations for capital expenditure, operating Amendment) Regulations, 2020. The commission
expenditure and auxiliary power consumption will had notified the draft regulations on April 1, 2020. It
be done corresponding to installed capacity of 4,150 has been decided to hold a public hearing on the
MW, but the respondents will be liable to pay the above subject on July 13, 2020 at 10:30 am via video
conferencing. The commission has requested that
Issue Decision
a. Whether the basis If Vedanta injects less power in any 15-minute block, GRIDCO has to source the
of calculation needs shortfall quantity in that time block only from other generators/sources. Therefore,
to be 15 minutes GRIDCO must be compensated on 15-minute block basis. The computation of bill and
block wise or compensation due to shortfall shall be made on 15-minute basis and the bill shall be
monthly? paid on monthly basis after deducting the compensation
b. Definition of Marginal sources should include un-requisitioned power from inter-state generating
marginal sources stations (ISGS), power overdrawn under deviation settlement mechanism and power
and priority of drawn from Indian Energy Exchange. The price of the power drawn from the above
marginal sources marginal sources in 15 minute block should be utilized for computation of loss.
In case of low or no generation in Unit-2, Vedanta has to supply state entitlement of
power from its captive generating plant (CGP) units or from other sources. Such
c. Methodology of
supply of power from CGP units or other sources shall be deemed to have been
annual fixed
supplied from the IPP unit-2. Hence, plant availability factor achieved during the
charge/capacity
month (PAFM) of Unit-2 will be calculated by the state load despatch centre (SLDC)
charges calculation
based on the actual energy supplied by Vedanta. Accordingly, capacity charge shall
be computed.
In case of Jindal India Thermal Power Limited (JITPL) it supplies 12 per cent/14 per
d. Compensation
cent of generated power to GRIDCO on variable cost basis only whereas Vedanta
for short supply
supplies power on full cost basis which consists of both fixed and variable charges. In
and incorporation
case of short supply or no supply of power from Unit-II (IPP unit) of Vedanta, it is
of compensation
duty bound to replenish the same from its converted CGPs which is not the case of
clause in PPA
JITPL.
Since both GRIDCO and Vedanta have agreed for applicability of compensation
e. Period of short
towards short supply with effect from April 1, 2015, that is the date of conversion of
supply
three IPP units to CGP, the revised PPA should mention the same.
Whenever GRIDCO procures additional power from other
sources due to short supply of power by Vedanta Limited and pays additional point
f. Additional PoC
of connection (POC) charges to the central transmission utility beyond the fixed POC
charges and losses
charges on account of such additional power purchase, the additional cost borne by
GRIDCO towards PoC charges shall be recovered from Vedanta
Since Vedanta has agreed to compensate GRIDCO for its actual loss/damages due to
g. Opportunity loss short supply of power
of GRIDCO due to the opportunity loss as claimed by GRIDCO, which is very difficult to quantify,
short supply of should not form part of the PPA. However, GRIDCO has the liberty to file separate
power by Vedanta petition before the commission, when GRIDCO is genuinely affected and the
opportunity loss it claims is quantified.
The commission has directed both the parties to make necessary amendments in the consolidated PPA
dated December 19, 2012 keeping in view the directions of the commission in its order dated January 27,
2016 passed in Case No. 21/2015. The commission has directed GRIDCO to reconcile the arrear amounts of
Vedanta Limited at the earliest in view of the above observations of the commission and accordingly settle
the payments within two months from the date of issue of this order.
TRANSMISSION
Read Order :BERC_O_20_06_05_01.pdf,
BERC initiates suo-motu proceedings with regard to
development of intra-state transmission projects
MERC partly allows TPC-T’s petition seeking review
under TBCB
of order dated March 30, 2020
The Bihar Electricity Regulatory Commission
The Maharashtra Electricity Regulatory Commission
(BERC) has initiated suo-motu proceedings with
(MERC) has partly allowed a petition filed by the
regard to with regard to development of intra-state
Tata Power Company Limited (Transmission) (TPC-
transmission projects under tariff-based competitive
T) seeking review of certain aspects of the multi-
bidding (TBCB). The commission had issued a
year tariff (MYT) order issued on March 30, 2020 for
notification dated December 23, 2019 fixing the
TPC-T in Case No. 299 of 2019 in the matter of
threshold limit for TBCB mode at Rs 1 billion.
truing-up of aggregate revenue requirement (ARR)
Through the same notification the commission had
for 2017-18 and 2018-19, provisional truing-up of
also directed the Bihar State Transmission Company
ARR for 2019-20 and ARR for fourth MYT control
Limited and Bihar State Power (Holding) Company
period from 2020-21 to 2024-25.
Limited (BSPHCL) to come up with detailed
guidelines for operationalisation of regulatory The request of the petitioner for removal of
provisions within three months from the date of income of Rs 36.50 million and Rs 24.30 million for
notification. amortisation of service line contributions from the
non-tariff income for 2017-18 and 2018-19,
However, due to COVID-19, the commission
respectively, was allowed by the commission
did not receive the guidelines in time. Meanwhile, a
without carrying cost. The financial impact of the
directive under from the state government section
same will be considered at the time mid-term
108 of the Electricity Act, 2003 was issued to the
review for the present control period. The second
commission via a letter dated April 27, 2020 stating
request of the petitioner to allow surplus amount of
that the state government has decided of not opting
Rs 273.20 million as against approved Rs 1,019.80
for TBCB as of now. The commission, therefore, in
million for the total past recovery to be adjusted in
the interest of equity and transparency deems it
2020-21 was dismissed as being without merit. The
proper to deliberate and act upon the aforesaid
request to allow expenses of Rs 40.80 million
directive of the state government by giving
towards renovation and modernisation expenses for
opportunity of being heard to the state government,
2018-19 was dismissed as being without merit. The
intra-state transmission licensees, BSPHCL and
commission allowed capitalisation of Rs 4.3 million
other stakeholders.
in 2017-18 towards merged detailed project report
The last date to file the written comments to the for replacement of 22 kV and 33 kV bus sections at
commission is by July 10, 2020. Further due to Carnac receiving station. The commission ordered
pandemic isolation protocol and social distancing that the consequential financial impact of the same
norms, there will not be any open court public may be filed by TPC-T at the time of mid-term
hearing of this case. Based on the written review for the present control period.
objections/comments/suggestion received from the
Case No. 95 of 2020
respondents and other stakeholders, the commission
will decide the issue. Read Order :MERC_O_20_06_05_01.pdf,
Name of Customer Name of Energy charge (Paise per KWh) Fixed charge/
consumer category tariff Demand
scheme Summer Monsoon Winter charge as admitted (Rs per
KvA per month)
L&MV Normal 210 210 210 5
Industrial
and
l-2(H) Normal 142 142 142 365
Commercial
(33 kV)
Industrial
and
l-3(H) Normal 138 138 138 365
Commercial
(132 kV)
Industrial
and
l-4(H) Normal 132 132 132 365
Commercial
(220 kV)
Traction T Normal 138 138 138 365
Source: WBERC
RENEWABLE
effective to March 31, 2023. The tariff norms
specified in these regulations will continue to
CERC notifies ‘Terms and Conditions for Tariff
remain applicable until notification of the revised
determination from Renewable Energy Sources)
norms through subsequent re-enactment of these
Regulations, 2020’
regulations.
The Central Electricity Regulatory Commission
(CERC) has notified CERC (Terms and Conditions These regulations will apply to cases where
for Tariff determination from Renewable Energy tariff for a grid connected generating station or a
Sources) Regulations, 2020. These regulations will unit thereof commissioned during the control
be effective from July 1, 2020, and unless reviewed period and based on renewable energy sources, is to
earlier or extended by the commission, will remain be determined by the commission under Section 62
read with Section 79 of the Electricity Act, 2003. In