Professional Documents
Culture Documents
S11192975 - Knowledge Assessment - Project Cost Managemnent
S11192975 - Knowledge Assessment - Project Cost Managemnent
1. How is the WBS used for estimating costs for the project? (5
marks)
The tasks that are captured in the WBS must be assigned resources to help
achieve the desired outcomes for that particular task. The total cost of using
that particular resource will depend on the type and the time that was estimated
/ indicated in the WBS. For example, two weeks were allocated in the WBS to
finish painting an entire house. Using the 8/80 rule and the hourly rate of a
painter, one can estimate the amount needed to pay the laborer(s) to complete
the task.
Contingency reserves are important to help safeguard you from any unknown
risks that may occur during the life cycle of the project. Whether there was an
error in the design, your estimations on resources were off, material prices went
up and so on, the contingency reserve is there to help cater for those extra
costs.
Variation is the main concern when reporting budget performance as this report
measures how much you estimated for the entire project work against how
much you actually spent to get the project deliverables achieved. Some
additional information could be what task needed more resources to complete on
time or if a particular resource needed to be replaced to keep the project on
schedule.