Professional Documents
Culture Documents
Processing instructions
Refractory concretes
Storage instructions 3
Setting accelerator 71
Storage instructions 3
Storage instructions
Any deviations from these preconditions may cause Reduced material consumption by:
an underconsumption or an increased consumption
of refractory concretes. • gunning behind linings and formwork as well as
in bottom areas.
Higher material consumption or higher
compaction are due to:
Processing instructions
Regular cement vibration castables
(RC-Vib.)
Shelf life
12 or 18 months (see respective data sheet).
Do not use any castable that has become lumpy.
Processing
If the castable is placed in a formwork or a mould,
good stable bracing is required (particularly when
a bottle vibrator is used). The formwork has to be
clean, made of water-repellent material, and well
covered with mould oil.
the castable and mix for about 2 minutes. Then the Vibrating
remaining 20% of water are to be added and mixed Place the castable slowly and carefully, and vibrate
for another 1 to 2 minutes. The whole mixing time it. Vibrate only until no more air escapes. Remove
should ideally not exceed 4 minutes. the bottle vibrator slowly from the castable in order
to avoid any air inclusions.
The ball-in-hand test is a simple way to control the
consistency of the castable. A ball formed out of If water accumulates on the surface during pro
castable by hand must neither seem to be too dry cessing and compaction, the castable is too wet.
or crumbly nor must it slip through the fingers. Any formation of layers due to surplus water has
to be avoided by all means.
The water temperature should range between
12 and 25 °C, but must never fall below 5 °C. During For larger batches of castable, shuttering areas pro-
processing, the temperature of the materials to be vided with corresponding expansion joints should be
mixed and the finished mix should range between placed. For more details, please refer to the respec-
10 and 25 °C. Lower or higher temperatures either tive drawing.
reduce or accelerate the setting process significantly.
Setting and hardening
For to accelerate the setting process at low pro Low ambient and setting temperatures (< 10 °C)
cessing temperatures, the bagged material and the prolong the setting time significantly. For to shorten
water should be preheated. It is advisable to pre- the setting time, the ambient air should be preheat-
heat the bagged material 1 to 2 days before use ed above 10 °C (using for instance a radiant burner).
in a warm storage place or in a covered area. The During hardening, the castable must not freeze at
addition of any setting accelerator to regular cement any rate. Temperatures above 25 °C accelerate the
vibration castables is not required. Should a pro- setting time significantly.
longed period of time be required for completing pro-
cessing at elevated processing temperatures, cool Cement-containing castables generate heat during
the bagged material and the water (place the pallets the setting process. As a result of this heat being
in the shade) or add some ice (water amount to be generated, some of the moisture contained in the
considered). The mixer is to be positioned as close lining evaporates, causing an incomplete setting
as possible to the place of installation. and hence a reduced strength of the castable. For
to reduce the heat being generated and thus the
After having placed the castable behind the form- evaporation of the moisture, the surface of the
work, one has to compact it by vibration. The time lining must be kept damp and cool by slightly and
required for processing the castable is temperature- regularly spraying water on the surface, which
dependent and should therefore not exceed may be covered with jute for example.
20 minutes.
The formwork must not be removed before the The castable expands during heating-up and within
castable has reached its full dimensional stability. the process. Therefore it is necessary to provide
Before that step, there should be carried out a sound expansion joints at regular distances (see installa-
test (bright sound) or a nail test (metal nail that has tion instructions in the drawings). A panel size of
been driven-in should bend) to the set castable. For 0.8-1.0 m2 with a maximum edge length of 1 m is
hardening and until first heating-up, the castable commonly chosen.
requires at least 24-48 hours. Any processing of the
built-in castable must be avoided during that period. Heating-up of the lining is to be carried out strictly
Once the hardening process has been completed, in accordance with the heating-up recommenda-
drying and heating-up can be started, according to tions, as otherwise damages to the structure of
the instructions. the castable are to be expected. Once started, the
heating-up process must not be stopped or inter-
Drying and heating-up rupted. For instance in case of a possible breakdown
Evaporation holes of 3 to 4 mm in diameter being of a burner, the lining will have to be kept warm. If
placed at a distance of approximately 100-150 mm cooling down is inevitable, heating-up is to be done
each, depending on the application conditions, have to very carefully once again, beginning with the first
be provided, particularly in case of wall thicknesses/ heating-up step.
linings exceeding 230 mm and linings without any
insulation layer (independently of the wall thickness), In order to achieve optimum product properties, the
in order to support evaporation of water during heating- processing instructions and heating-up recommen-
up. During the setting process, the evaporation holes dations must be strictly followed.
should be driven as far as the back lining, at least
to a depth of 80% of the lining thickness. This should Personnel protection and safety
not be done too soon after installation of the castable, Always wear your personal protective equipment
as otherwise the holes will close again. Evaporation (respiratory protection, tightly sealed safety goggles,
holes can be formed, for example, by insertion of safety gloves and tightly fitting protective clothing).
greased steel pins or rods (which are removed before Wash thoroughly after processing of refractory
the end of the setting process) or by drilling etc. concretes. Always refer to the material safety
Installation instructions are to be strictly followed. data sheet.
Processing instructions
Low cement vibration castables
(LC-Vib.)
Shelf life
12 months (see data sheet).
Do not use any castable that has become lumpy.
Processing
If the castable is placed in a formwork or mould,
good stable bracing is required (particularly when
a bottle vibrator is used). The formwork has to be
clean, made of water-repellent material, and well
covered with mould oil.
The formwork must not be removed before the The castable expands during heating-up and within
castable has reached its full dimensional stability. the process. Therefore it is necessary to provide
Before that step, one may carry out a sound test expansion joints at regular distances (see installa-
(bright sound) or a nail test (metal nail that has tion instructions in the drawings). A panel size of
been driven-in should bend) to the set castable. For 0.8-1.0 m2 with a maximum edge length of 1 m is
hardening and until first heating-up, the castable commonly chosen.
requires at least 24-48 hours. Any processing of the
built-in castable must be avoided during that period. Heating-up of the lining is to be carried out strictly
Once the hardening process has been completed, in accordance with the heating-up recommenda-
drying and heating-up can be started, according to tions, as otherwise damages to the structure of
the instructions. the castable are to be expected. Once started, the
heating-up process must not be stopped or inter-
Drying and heating-up rupted. For instance in case of a possible breakdown
Evaporation holes of 3 to 4 mm in diameter being of a burner, the lining will have to be kept warm. If
placed at a distance of approximately 100-150 mm each, cooling down is inevitable, heating-up is to be done
depending on the application conditions, have to be very carefully once again, beginning with the first
provided, particularly in case of wall thicknesses/ heating-up step.
linings exceeding 230 mm and linings without any
insulation layer (independently of the wall thickness), In order to achieve optimum product properties, the
in order to support evaporation of water during processing instructions and heating-up recommen-
heating-up. dations must be strictly followed.
During the setting process, the evaporation holes Personnel protection and safety
should be driven as far as the back lining, at least Always wear your personal protective equipment
to a depth of 80% of the lining thickness. This (respiratory protection, tightly sealed safety goggles,
should not be done too soon after installation of the safety gloves and tightly fitting protective clothing).
castable, as otherwise the holes will close again. Wash thoroughly after processing of refractory
Evaporation holes can be formed, for example, by concretes. Always refer to the material safety
insertion of greased steel pins or rods (which are data sheet.
removed before the end of the setting process) or by
drilling etc. Installation instructions are to be strictly
observed.
Processing instructions
No cement vibration castables
(ED-Vib.)
Shelf life
12 months (see data sheet).
Do not use any castable that has become lumpy.
Processing
If the castable is placed in a formwork or a mould,
good stable bracing is required (particularly when
a bottle vibrator is used). The formwork has to be
clean, made of water-repellent material, and well
covered with mould oil.
The formwork must not be removed before the Drying and heating-up process depend on the
castable has reached its full dimensional stability. dimensions of the lining, the castable, and the
For assessing whether the castable has already processing technique chosen.
reached its full dimensional stability, it is recom-
mended to determine the same under identical The castable expands during heating-up and within
installation conditions parallely in a cup test or using the process. Therefore it is necessary to provide
a separate test specimen. Contrary to cement- expansion joints at regular distances (see installa-
containing concretes, no cement castables show a tion instructions in the drawings). A panel size of
typically lower structural strength or do not have 0.8-1.0 m2 with a maximum edge length of 1 m is
any striking sound (sound test) after demoulding. commonly chosen.
After having reached its full dimensional stability
or once the hardening process has been completed, Heating-up of the lining is to be carried out strictly
drying and heating-up can be started, according to in accordance with the heating-up recommenda-
the instructions. At low processing temperatures and tions, as otherwise damages to the structure of
for obtaining a higher structural strength, it is par- the castable are to be expected. Once started, the
ticularly recommended to extend the hardening time heating-up process must not be stopped or inter-
of the castable until the first heating-up (e.g. 24-48 rupted. For instance in case of a possible breakdown
hours). Any processing of the built-in castable must be of a burner, the lining will have to be kept warm. If
avoided during that period. cooling down is inevitable, heating-up is to be done
very carefully once again, beginning with the first
Drying and heating-up heating-up step.
Evaporation holes of 3 to 4 mm in diameter are to be
placed at a distance of approximately 100-150 mm In order to achieve optimum product properties, the
each for supporting evaporation of water during processing instructions and heating-up recommen-
heating-up. Particularly in case of wall thicknesses/ dations (ED: Easy Dry) must be strictly followed.
linings exceeding 230 mm, linings without any insu-
lation layer (independently of the wall thickness) Personnel protection and safety
and projects, where the lined castable panels will Always wear your personal protective equipment
for instance only be dried after 4 weeks or more, (respiratory protection, tightly sealed safety goggles,
evaporation holes must have already been provided. safety gloves and tightly fitting protective clothing).
During the setting process, these evaporation holes Wash thoroughly after processing of refractory
must be driven as far as the back lining, at least to a concretes. Always refer to the material safety data
depth of 80% of the lining thickness. This should not sheet.
be done too soon after installation of the castable,
as otherwise the holes will close again. Evaporation
holes can be formed, for example, by insertion of
greased steel pins or rods (which are removed before
the end of the setting process) or by drilling etc.
Installation instructions are to be strictly followed.
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
28 Mixcrete vibration castables (Mix) 29
Processing instructions
Mixcrete vibration castables
(Mix)
AR-Mixcrete combinations
Mixing ratio*: 3:1 / 2:1 / 1:1
Z AR-Mixcrete combinations
Mixing ratio*: 1:1
Shelf life
12 months (see data sheet).
Do not use any castable that has become lumpy.
Processing
If the Mixcrete mix is placed in a formwork or mould,
good stable bracing is required (particularly when
a bottle vibrator is used). The formwork has to be
clean, made of water-repellent material, and well
©Refratechnik Cement GmbH covered with mould oil. ©Refratechnik Cement GmbH
30 Mixcrete vibration castables (Mix) Mixcrete vibration castables (Mix) 31
For mixing the two Mixcrete types always use a correct and suitable consistency of deflocculated
clean mechanical forced-action mixer. There must Mixcrete mixes is often achieved at the end of the
not be any impurities (e.g. concrete remainder) in wet mixing time only. That is why Mixcrete mixes
the mixer. possibly seem to be too dry and crumbly when start-
ing the mixing process.
The ideal mixing batch for a mixing ratio of
3:1 or 1:1 (e.g. 3 bags : 1 bag) is 100 kg. The ball-in-hand test is a simple way to control the
consistency of the castable. A ball formed out of the
The ideal mixing batch for a mixing ratio of castable by hand must neither seem to be too dry or
2:1 (e.g. 2 bags : 1 bag) is 75 or 150 kg. crumbly nor must it slip through the fingers.
When processing the Mixcrete mix, always make The water temperature should range between
sure that 12 and 25 °C, but must never fall below 5 °C. During
processing, the temperature of the materials to be
• the respective Mixcrete combination is used, since mixed and the finished mix should range between
the processing properties were optimally adjusted 15 and 25 °C. Lower or higher temperatures either
to each other; reduce or accelerate the setting process significantly.
• the full contents of the 25 kg bag is used up, since For to accelerate the setting process at low process-
segregations between coarse and fine grains may ing temperatures, the bagged material and the water
occur during transportation; are to be preheated, or the recommended powdery
setting accelerator (refer to chapter on “Setting
• the specified mixing ratio is applied, since pro- accelerator”) is to be added. It is advisable to preheat
cessing and product properties were adjusted to it the bagged material 1 to 2 days before use in a warm
accordingly; storage place or in a covered area. Should a pro-
longed period of time be required for completing pro-
• the specified amount of mixing water is used to cessing at elevated processing temperatures, cool
achieve optimum processing and product proper- the bagged material and the water (place the pallets
ties. in the shade) or add some ice (water amount to be
considered). The mixer is to be positioned as close as
Before adding water, the Mixcrete types are to be possible to the place of installation.
mixed in dry state for a short time (about 1 minute)
to avoid any segregations that may have occurred After having placed the castable behind the form-
in the bag. Then the whole amount of water is to work, compact it by vibration. The time required for
be added within 1 minute. Do only use clean water processing the castable is temperature-dependent
(of potable quality) for mixing. The whole wet mix- and should therefore not exceed 20 minutes.
ing time should ideally not exceed 4 minutes. The
The ball-in-hand test is a simple way to control the If water accumulates on the surface during process-
consistency of the castable. A ball formed out of ing and compaction, the castable is too wet. Any
castable by hand must neither seem to be too dry or formation of layers due to surplus water has to be
crumbly nor must it slip through the fingers. avoided by all means.
The water temperature should range between For larger batches of castable, shuttering areas pro-
12 and 25 °C, but must never fall below 5 °C. During vided with corresponding expansion joints should be
processing, the temperature of the materials to be placed. For more details, please refer to the respec-
mixed and the finished mix should range between tive drawing.
15 and 25 °C. Lower or higher temperatures either
slow down or accelerate the setting process signifi- Setting and hardening
cantly. Low ambient and setting temperatures (< 10 °C)
prolong the setting time significantly. For to shorten
For to accelerate the setting process at low process- the setting time, the ambient air should be preheat-
ing temperatures, the bagged material and the water ed above 10 °C (using for instance a radiant burner).
should be preheated. It is advisable to preheat the During hardening, the castable must not freeze at
bagged material 1 to 2 days before use in a warm any rate. Temperatures above 25 °C accelerate the
storage place or in a covered area. Should a pro- setting time significantly. In this case, the bagged
longed period of time be required for completing pro- material and the water should be cooled.
cessing at elevated processing temperatures, cool
the bagged material and the water (place the pallets These basic castables do not generate heat during
in the shade) or add some ice (water amount to be the setting process, but elevated outside tempera-
considered). The mixer is to be positioned as close as tures may additionally make some of the moisture
possible to the place of installation. contained in the lining evaporate prematurely,
resulting in an incomplete setting and hence in a
After having placed the castable behind the form- reduced strength of the castable. For to reduce the
work, one has to compact it by vibration. The time evaporation of the moisture at increased setting
required for processing the castable is temperature- temperatures, the surface of the lining must be kept
dependent and should therefore not exceed damp and cool by slightly and regularly spraying
20 minutes. water on the surface, which may be covered with
jute for example.
The formwork must not be removed before the The castable expands during heating-up and within
castable has reached its full dimensional stability. the process. Therefore it is necessary to provide
Contrary to cement-containing concretes, basic expansion joints at regular distances (see installa-
castables may show a typically lower structural tion instructions in the drawings). A panel size of
strength or may not have any striking sound (sound 0.8-1.0 m2 with a maximum edge length of 1 m is
test) after demoulding. After having reached its full commonly chosen.
dimensional stability or once the hardening process
has been completed, drying and heating-up can be Heating-up of the lining is to be carried out strictly
started, according to the instructions. At low process- in accordance with the heating-up recommenda-
ing temperatures and for obtaining a higher structural tions, as otherwise damages to the structure of
strength, it is particularly recommended to extend the castable are to be expected. Once started, the
the hardening time of the castable until the first heating-up process must not be stopped or inter-
heating-up (e.g. 24-48 hours). Any processing of the rupted. For instance in case of a possible breakdown
built-in castable must be avoided during that period. of a burner, the lining will have to be kept warm. If
cooling down is inevitable, heating-up is to be done
Drying and heating-up very carefully once again, beginning with the first
Independently of the wall thicknesses, of linings heating-up step.
with/without any insulation layer or the period of time
that has passed after lining of the castable panels or In order to achieve optimum product properties,
when drying is started, basic castable linings must the processing instructions and heating-up
be provided with evaporation holes of 3 to 4 mm in recommendations must be strictly followed.
diameter being placed at a distance of approximately
100-200 mm each, in order to support evaporation of Personnel protection and safety
water during drying and heating-up process. During Always wear your personal protective equipment
the setting process, the evaporation holes must be (respiratory protection, tightly sealed safety goggles,
driven as far as the back lining, at least to a depth of safety gloves and tightly fitting protective clothing).
80% of the lining thickness. This should not be done Wash thoroughly after processing of refractory
too soon after installation of the castable, as other- concretes. Always refer to the material safety
wise the holes will close again. Evaporation holes data sheet.
can be formed, for example, by insertion of greased
steel pins or rods (which are removed before the end
of the setting process) or by drilling etc. Installation
instructions are to be strictly followed.
Processing instructions
Dense dry gunning concretes
(G-MCG-LCG-ED G)
Shelf life
12 months (see data sheet).
Do not use any refractory concrete that has
become lumpy.
Processing
Placing of refractory concretes by dry gunning has
become a standard installation method. The used
gunning machine should operate on the rotor princi-
ple or be a two-chamber machine.
required. The formwork has to be clean, made of may range between 2.0 and 4.5 bar. For ensuring a
water-repellent material, and well covered with mould homogeneous conveying of the refractory concrete
oil. Any connection to existing brickwork must be and an optimum gunning result, a hose length or
properly sealed off. a conveying distance of 40-60 m is recommended.
The water pressure provided must be ≥ 12 bar.
The dry gunning equipment consists of a gunning
machine, a high-pressure water pump, a gunning Do only use clean water (of potable quality) for gun-
nozzle, a water hose, and a material hose. During ning. The water temperature should range between
gunning, the dry refractory material is fed via a 12 and 25 °C, but must never fall below 5 °C. During
sieving hopper and stirring star to the rotor, which processing, the temperature of the materials to be
is fixed between two packing washers and trans- mixed should range between 15 °C and 25° C at
ports the gunning material to the blow-off socket, maximum. For to accelerate the setting process at
from where it is blown by means of compressed air low processing temperatures, the bagged material
through a material hose to the nozzle. The water and the water should be preheated. It is advisable
is added through a separate hose connected to to preheat the bagged material 1 to 2 days before
the nozzle. In dependency of the adjusted gunning use in a warm storage place or in a covered area.
parameters, the used gunning material and the flow Dry gunning concretes do not need the addition of
rate, the wear parts, like packing washers, friction any setting accelerator. The required water amount
discs and gunning nozzle, are subjected to normal is determined as per the type of refractory concrete
wear. The extreme hardness of the raw materials used, the gunning behaviour and the installation
used for high alumina and silicon carbide contain- conditions prevailing, and is varied at the nozzle by
ing gunning concretes may contribute to an earlier a control valve.
wear. We therefore recommend to check these wear
parts and the conical connecting pieces after 40 to During gunning, a certain amount of material always
80 hours of operation. rebounds. The amount of rebound material depends
on the skill of the gunning crew, the position of the
The gunning machine requires a constant supply lining (e.g. a ceiling or wall), the anchor spacing,
of water and air at adequate pressure by an air and the type of refractory concrete to be gunned
compressor and a water pump. The water and air (strictly observe chapter on “Basis for calculation of
pressure depend on the distance between gunning material requirement – Dry gunning concretes”). It
machine and nozzle, the used nozzle size, the height is not advisable to prewet the dry gunning concrete
above ground level of the part being gunned, and the in a forced-action mixer to reduce the formation of
nature and quality of the material to be applied. The dust during gunning, since along with the addition
air compressor should supply an air flow rate of min. of water, some reaction processes will start that
8-12 m3/minute and an air pressure of 6-8 bar. The lead to the formation of granulates which, with a
gunning pressure being adjusted at the dry gunning changed grain distribution, normally cause increased
machine must not generate any pulsating conveying of rebound/material losses. Do neither reuse any
the refractory concrete. In dependency of the con- rebound material nor any dry gunning concrete that
veying distance (20-100 m), the gunning pressure has been scraped off.
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
44 Dense dry gunning concretes (G-MCG-LCG-ED G) Dense dry gunning concretes (G-MCG-LCG-ED G) 45
Hoses must be kept clean to avoid any clogging. Setting and hardening
Low ambient and setting temperatures (< 10 °C)
For dry gunning, the nozzle should be held at a right prolong the setting time significantly. For to shorten
angle to the surface in case of a vertical surface, the setting time, the ambient air should be preheat-
and at a slightly inclined angle in case of a horizon- ed above 10 °C (using for instance a radiant burner).
tal surface. This technique, in conjunction with a During hardening, the refractory concrete must
circular movement, gives minimum rebound, uniform not freeze at any rate. Temperatures above 25 °C
material structure and minimum risk of formation of accelerate the setting time significantly.
layers, which may result in subsequent spalling. For
to achieve an optimum gunning result, a distance of Cement-containing refractory concretes generate
0.5-1.0 m between wall and gunning nozzle should heat during the setting process. As a result of this
be kept. It is of special importance to build up the heat being generated, some of the moisture con-
material to full lining thickness gradually. In general tained in the lining evaporates, causing an incom-
it is advisable to gun marked-out panels or zones. plete setting and hence reduced strength of the
If necessary, the panels should be divided by stag- refractory concrete. For to reduce the heat being
gered shuttering joints. generated and thus the evaporation of the moisture,
the surface of the lining must be kept damp and cool
Always gun bottom surfaces before the top surfaces by slightly and regularly spraying water on the sur-
so that the anchors do not become covered with face, which may be covered with jute for example.
rebound material. If this happens, the anchors must
be cleaned before further gunning. The formwork must not be removed before the
refractory concrete has reached its full dimensional
When material is applied to a hot surface, it is stability. Contrary to cement-containing vibration
advisable to gun a thin intermediate layer at first. castables, dry gunning concretes may show a typi-
The water can rapidly dry in this area before further cally lower structural strength or may not have any
material is applied. This step prevents the formation striking sound (sound test). For hardening and until
of vapour pores, which would otherwise prolong the first heating-up, the refractory concrete requires
setting process of the material. at least 24-48 hours. Any processing of the built-in
refractory concrete must be avoided during that
Once the material is gunned, i.e. before the setting period. Once the hardening process has been
process starts, the surface is to be finished by completed, drying and heating-up can be started,
scraping off or drawing off with a straight-edge, but according to the instructions.
without smoothening the surface. For relatively large
batches of refractory concrete, shuttering areas Drying and heating-up
provided with corresponding expansion joints are Evaporation holes of 3 to 4 mm in diameter being
to be placed. For more details, please refer to the placed at a distance of approximately 100-150 mm each,
respective drawing. depending on the application conditions, have to be
provided, particularly in case of wall thicknesses/lin-
ings exceeding 230 mm and linings without any insu-
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
46 Dense dry gunning concretes (G-MCG-LCG-ED G) Dense dry gunning concretes (G-MCG-LCG-ED G) 47
lation layer (independently of the wall thickness), in Personnel protection and safety
order to support evaporation of water during heating- Always wear your personal protective equipment
up. During the setting process, the evaporation (respiratory protection, tightly sealed safety goggles,
holes should be driven as far as the back lining, at safety gloves and tightly fitting protective clothing).
least to a depth of 80% of the lining thickness. This Wash thoroughly after processing of refractory
should not be done too soon after installation of the concretes. Always refer to the material safety
refractory concrete, as otherwise the holes will close data sheet.
again. Evaporation holes can be formed, for example,
by insertion of greased steel pins or rods (which are
removed before the end of the setting process) or by
drilling etc. Installation instructions are to be strictly
observed.
Processing instructions
Insulating dry gunning concretes
(G-Iso.)
Shelf life
18 months (see data sheet).
Do not use any insulating dry gunning concrete
that has become lumpy.
Processing
Placing of insulating refractory concretes by dry
gunning has become a standard installation method.
The used gunning machine should operate on the
rotor principle or be a two-chamber machine.
gunning, the dry refractory material is fed via a mixed should range between 15 °C and 25° C at
sieving hopper and stirring star to the rotor, which maximum. For to accelerate the setting process at
is fixed between two packing washers and trans- low processing temperatures, the bagged material
ports the refractory material to the blow-off socket, and the water should be preheated. It is advisable to
from where it is blown by means of compressed air preheat the bagged material 1 to 2 days before use
through a material hose to the nozzle. The water in a warm storage place or in a covered area. Dry
is added through a separate hose connected to gunning concretes do not need the addition of any
the nozzle. In dependency of the adjusted gunning setting accelerator.
parameters, the used gunning material and the flow
rate, the wear parts, like packing washers, friction The required water amount is determined as per the
discs and gunning nozzle, are subjected to normal type of refractory concrete used, the gunning be-
wear. We therefore recommend to check these wear haviour, and the installation conditions prevailing,
parts after 40 to 80 hours of operation. and is varied at the nozzle by a control valve.
The gunning machine requires a constant supply of During gunning, a certain amount of material always
water and air at adequate pressure by an air com- rebounds. The amount of rebound material depends
pressor and a water pump. The water and air pres- on the skill of the gunning crew, the position of the
sure depend on the distance between the gunning lining (e.g. a ceiling or wall), the anchor spacing, and
machine and the nozzle, the used nozzle size, the the type of refractory concrete to be gunned (strictly
height above ground level of the part being gunned, observe chapter on “Basis for calculation of material
and the nature and quality of the material to be requirement – Dry gunning concretes”).
applied. The air compressor should supply an air flow
rate of min. 8-12 m3/minute and an air pressure of It is not advisable to prewet the insulating dry gun-
6-8 bar. The gunning pressure being adjusted at the ning concrete in a forced-action mixer to reduce the
dry gunning machine must not generate any pulsat- formation of dust during gunning, since along with
ing conveying of the refractory concrete. At short the addition of water, some reaction processes will
conveying distance of approx. 40 m, a gunning pres- start that lead to the formation of granulates, which,
sure of 0.5 up to 2.0 bar can be adjusted, depending with a changed grain distribution, do normally cause
on what is required. If possible, larger conveying increased rebound/material losses. Do neither reuse
distances should be avoided, since for achieving a any rebound material nor any insulating dry gunning
constant conveying behaviour, the gunning pressure concrete that has been scraped off.
can then be up to 3.5 bar. This in turn will result in
an unwanted increased material consumption. The Insulating materials tend to compact during gunning.
water pressure must be ≥ 12 bar. This may result in a higher material consumption and
in a higher density of the applied material than speci
Do only use clean water (of potable quality) for gun- fied by the manufacturer (strictly observe chapter on
ning. The water temperature should range between “Basis for calculation of material requirement – Dry
12 and 25 °C, but must never fall below 5 °C. During gunning concretes”).
processing, the temperature of the materials to be
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
52 Insulating dry gunning concretes (G-Iso.) Insulating dry gunning concretes (G-Iso.) 53
Hoses must be kept clean to avoid any clogging. concrete must not freeze at any rate. Temperatures
above 25 °C accelerate the setting time significantly.
For dry gunning, the nozzle should be held at a right
angle to the surface in case of a vertical surface, Cement-containing insulating dry gunning concretes
and at a slightly inclined angle in case of a horizon- generate heat during the setting process. As a result
tal surface. This technique, in conjunction with a of this heat being generated, some of the moisture
circular movement, gives minimum rebound, uniform contained in the lining evaporates, causing an
material structure and minimum risk of formation of incomplete setting and hence reduced strength of
layers, which may result in subsequent spalling. For the insulating dry gunning concrete. For to reduce
to achieve an optimum gunning result, a distance of the heat being generated and thus the evaporation
0.5-1.0 m between wall and gunning nozzle should of the moisture, the surface of the lining must be
be kept. It is of special importance to build up the kept damp and cool by slightly and regularly spraying
material to full lining thickness gradually. In general water on the surface, which may be covered with
it is advisable to gun marked-out panels or zones. jute for example.
Always gun bottom surfaces before the top surfaces The formwork must not be removed before the
so that the anchors do not become covered with insulating dry gunning concrete has reached its full
rebound material. If this happens, the anchors must dimensional stability. Contrary to cement-containing
be cleaned before further gunning. vibration castables, insulating dry gunning concretes
may show a typically lower structural strength or
When material is applied to a hot surface, it is do not have any striking sound (sound test) after
advisable to gun a thin intermediate layer at first. installation. For hardening and until first heating-up,
The water can rapidly dry in this area, before further the insulating dry gunning concrete requires at least
material is applied. This step prevents the formation 24-48 hours. Any processing of the built-in insulating
of vapour pores, which would otherwise prolong the dry gunning concrete must be avoided during that
setting process of the material. period. Once the hardening process has been com-
pleted, drying and heating-up can be started, accord-
Once the material is gunned, i.e. before the setting ing to the instructions.
process starts, the surface is to be finished by
scraping off or drawing off with a straight-edge, but Drying and heating-up
without smoothening the surface. Drying and heating-up process depend on the
dimensions of the lining, the insulating dry gunning
Setting and hardening concrete, and the processing technique chosen.
Low ambient and setting temperatures (< 10 °C)
prolong the setting time significantly. For to shorten In case of one-layer wall constructions with insu-
the setting time, the ambient air should be preheat- lating dry gunning concretes, the latter also expand
ed above 10 °C (using for instance a radiant burn- during heating-up and within the process. Therefore
er). During hardening, the insulating dry gunning it is necessary to provide expansion joints at regular
without having to shake it or by only slightly having has to be finished by drawing off with a straight-
to shake it by hand at first. edge or by smoothing.
The water temperature should range between For larger batches of refractory concrete, shuttering
12 and 25 °C, but must never fall below 5 °C. During areas provided with corresponding expansion joints
processing, the temperature of the materials to be should be placed. For more details, please refer to
mixed and the finished mix should range between the respective drawing.
15 and 25 °C at maximum. Lower or higher tempera-
tures either reduce or accelerate the setting process Strictly observe chapter on “Basis for calculation of
significantly. material requirement - Wet gunning concretes”.
For to accelerate the reaction behaviour at low pro- Setting and hardening
cessing temperatures, the big bags/bagged material Low ambient and setting temperatures (< 10 °C)
and the water should be preheated, but not above prolong the setting time significantly. For to shorten
25 °C. It is advisable to preheat the big bags/bagged the setting time, the ambient air should be preheat-
material 1 to 2 days before use in a warm storage ed above 10 °C (using for instance a radiant burner).
place or in a covered area. There must never be add- During hardening, the refractory concrete must
ed any powdery setting accelerator to wet gunning not freeze at any rate. Temperatures above 25 °C
concretes during the mixing process. If a prolonged accelerate the setting time significantly.
period of time is required for processing at elevated
processing temperatures, cool the big bags/bagged Even low cement concretes generate heat during the
material and the water (place the pallets in the setting process. Elevated outside temperatures may
shade), and protect the gunning equipment and the additionally make some of the moisture contained
pipes/hoses from direct solar radiation. in the lining evaporate prematurely, resulting in
an incomplete setting and hence reduced strength
During the gunning process of wet gunning con- of the refractory concrete. In order to reduce the
cretes, the required special liquid accelerator has to heat being generated and thus the evaporation of
be added at the gunning nozzle. Since the consistency/ the moisture, the surface of the lining must be kept
pumpability of the accelerator is temperature-depen damp and cool by slightly and regularly spraying
dent, a preheating at low processing temperatures water on the surface, which may be covered with
(< 10 °C) is indispensable. jute for example.
The processing time of the refractory concrete is For hardening and until first heating-up, the refrac-
temperature-dependent and should therefore not tory concrete requires at least 24-48 hours. Any
take more than 20 minutes. During installation by processing of the built-in refractory concrete is to be
gunning, the refractory concrete hardens rapidly and avoided during that period. Once the hardening pro-
becomes stable within a few seconds. Once having cess has been completed, drying and heating-up can
placed the refractory concrete, the surface therefore be started, according to the instructions.
Processing instructions
No cement wet gunning concretes
(ED-JC)
Shelf life
Big bags: 6 months,
bagged material (25 kg/bag): 12 months
(see data sheet).
Do not use any refractory concrete that
has become lumpy.
Processing
For preparing the refractory concrete always use a
clean gunning equipment and a clean mixer. There
must not be any impurities (i.e. concrete remainder),
neither in the gunning equipment nor in the mixer.
Do only use clean water (of potable quality) for mix-
ing. Never use any type of liquid binder. The water
is added continuously, while emptying the big bags
or the bagged material into the mixer. For preventing
the mixer from possibly reaching its limits at low
processing temperatures, the big bags should be
emptied with some delay. At recommended process-
ing temperatures, the whole wet mixing time should
last up to 5 minutes; at low processing and refrac
tory concrete temperatures (< 10 °C) it may be extend-
ed accordingly. The correct and suitable consistency
of deflocculated refractory concretes is often only
achieved at the end of the wet mixing time. That is
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
62 No cement wet gunning concretes (ED-JC) No cement wet gunning concretes (ED-JC) 63
why refractory concretes may seem to be too dry cretes), the accelerator added at the gunning nozzle
and crumbly at the beginning of the mixing process. requires a much finer dosage and a smaller quantity
of the same being added due to its high reactivity.
The ball-in-hand test is a simple way to control the
consistency of the refractory concrete. A ball formed The processing time of the refractory concrete is
out of refractory concrete slips through the fingers temperature-dependent and should therefore not
without having to shake it or by only slightly having take more than 20 minutes. During installation by
to shake it by hand at first. gunning, the refractory concrete hardens rapidly and
becomes stable within a few seconds. Once having
The water temperature should range between placed the refractory concrete, the surface therefore
15 and 35 °C, but must never fall below 10 °C. Dur- has to be finished by drawing off with a straight-
ing processing, the temperature of the materials to edge or by smoothing.
be mixed and the finished mix should range between
15 and 30 °C. Lower or higher temperatures either For larger batches of refractory concrete, shuttering
reduce or accelerate the setting process significantly. areas provided with corresponding expansion joints
should be placed. For more details, please refer to
For to accelerate the reaction behaviour with the the respective drawing.
special accelerator being added at the nozzle and
for a faster setting process at low processing tem- Strictly observe chapter on “Basis for calculation of
peratures, the big bags/bagged material and the material requirement - Wet gunning concretes”.
water have to be preheated, but not above 25 °C. It
is advisable to preheat the big bags/bagged mate- Setting and hardening
rial 1 to 2 days before use in a warm storage place Low ambient and setting temperatures (< 10 °C)
or in a covered area. During the mixing process, prolong the setting time significantly. For to shorten
there must never be added any powdery setting the setting time, the ambient air should be preheat-
accelerator to wet gunning concretes. If a prolonged ed above 10 °C (using for instance a radiant burner).
period of time is required for processing at elevated A higher compressed air amount being added at the
processing temperatures, cool the big bags/bagged nozzle or a higher compressor power may possibly
material and the water (place the pallets in the lead to a quicker hardening of the gunned deeper
shade), and protect the gunning equipment and the refractory concrete layers. During hardening, the
pipes/hoses from direct solar radiation. refractory concrete must not freeze at any rate.
Temperatures above 25 °C accelerate the setting
During processing of wet gunning concretes, the time significantly.
required special liquid accelerator has to be added
at the gunning nozzle. Since the consistency/pump- No cement ED-JC concretes do not generate any
ability of the accelerator is temperature-dependent, heat during the setting process. However, elevated
preheating at low processing temperatures (< 10 °C) outside temperatures may additionally make some
is indispensable. In case of no cement wet gunning of the moisture contained in the lining evaporate
concretes (contrary to low cement wet gunning con- prematurely, resulting in an incomplete reaction and
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
64 No cement wet gunning concretes (ED-JC) No cement wet gunning concretes (ED-JC) 65
hence reduced strength of the refractory concrete. the holes will close again. Evaporation holes can be
In order to reduce the evaporation of the moisture, formed, for example, by insertion of greased steel
the surface of the lining must be kept damp and cool pins or rods (which are removed before the end of
at increased setting temperatures by slightly and the setting process) or by drilling etc. Installation
regularly spraying water on the surface, which may instructions are to be strictly followed.
be covered with jute for example.
Drying and heating-up process depend on the
Contrary to cement-containing vibration castables, dimensions of the lining, the refractory concrete,
no cement concretes show a typical lower structural and the processing technique chosen.
strength and a not that pronounced sound (sound
test) after installation or demoulding. After having The refractory concrete expands during heating-up
reached its full dimensional stability, or after having and within the process. Therefore it is necessary to
completed the hardening process, drying and heating- provide expansion joints at regular distances (see
up can be started, according to instructions. At low installation instructions in the drawings). A panel
processing temperatures and for obtaining a higher size of 0.8-1.0 m2 with a maximum edge length of
structural strength, it is particularly recommended to 1 m is commonly chosen.
extend the hardening time of the refractory concrete
until the first heating-up (e.g. 24-48 hours). Any Heating-up of the lining is to be carried out strictly
processing of the built-in refractory concrete is to be in accordance with the heating-up instructions, as
avoided during that period. otherwise damages to the structure of the refractory
concrete are to be expected. Once started, the heating-
Drying and heating-up up process must not be stopped or interrupted. For
Evaporation holes of 3 to 4 mm in diameter are to be instance in case of a possible breakdown of a burn-
placed at a distance of approximately 100-150 mm er, the lining must be kept warm. If cooling down is
each, for supporting evaporation of water during inevitable, heating-up is to be done very carefully
heating-up. Particularly in case of wall thicknesses/ once again, beginning with the first heating-up step.
linings exceeding 230 mm, linings without any insu-
lation layer (independently of the wall thickness), In order to achieve optimum product properties, the
and in case of projects, where the lined refractory processing instructions and heating-up recommen-
concrete panels will for instance only be dried dations (ED: Easy Dry) must be strictly followed.
after 4 weeks or more, evaporation holes must be
provided. REFRA JETCRETE® (JC) types, which are Personnel protection and safety
not installed by gunning, but by pumping, casting Always wear your personal protective equipment
or vibratory compaction, must be provided with (respiratory protection, tightly sealed safety goggles,
evaporation holes, too. During the setting process, safety gloves and tightly fitting protective clothing).
these evaporation holes must be driven as far as the Wash thoroughly after processing of refractory
back lining, at least to a depth of 80% of the lining concretes. Always refer to the material safety
thickness. This should not be done too soon after data sheet.
installation of the refractory concrete, as otherwise
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
66 Poured insulating concretes (Iso.) 67
Processing instructions
Poured insulating concretes
(Iso.)
Shelf life
18 months (see data sheet).
Do not use any insulating concrete that has
become lumpy.
Processing
If the insulating concrete is placed in a formwork
or a mould, good stable bracing is required. The
formwork has to be clean, made of water-repellent
material, and well covered with mould oil.
tions that may have occurred in the bag. Do only use If water accumulates on the surface during process-
clean water (of potable quality) for mixing. ing and compaction, the insulating concrete is too
wet. Any formation of layers due to surplus water
Add about 80% of the water amount required to has to be avoided by all means.
the insulating concrete, and mix for about 1 minute.
Then the remaining 20% of water are to be added Setting and hardening
and mixed for 1 minute more. The whole mixing time Low ambient and setting temperatures (< 10 °C)
should ideally not exceed 2 minutes. prolong the setting time significantly. For to shorten
the setting time, the ambient air should be preheat-
The water temperature should range between ed above 10 °C (using for instance a radiant burner).
12 and 25 °C, but must never fall below 5 °C. During During hardening, the insulating concrete must not
processing, the temperature of the materials to be freeze at any rate. At temperatures above 25 °C the
mixed and the finished mix should range between setting time is accelerated significantly.
10 and 25 °C. Lower or higher temperatures either
reduce or accelerate the setting process significantly. Cement-containing insulating concretes generate
heat during the setting process. As a result of
For to accelerate the setting process at low process- this heat being generated, some of the moisture
ing temperatures, the bagged material and the water contained in the lining evaporates, causing an
should be preheated. It is advisable to preheat the incomplete setting and hence reduced strength of
bagged material 1 to 2 days before use in a warm the insulating concrete. In order to reduce the heat
storage place or in a covered area. Regular cement being generated and thus the evaporation of the
insulating concretes do not need the addition of moisture, the surface of the lining must be kept
any setting accelerator. If a longer period of time damp and cool by slightly and regularly spraying
is required for processing at elevated processing water on the surface, which may be covered with
temperatures, cool the bagged material and the jute for example.
water (place the pallets in the shade) or add some
ice (water amount to be considered). The mixer is The formwork must not be removed before the
to be positioned as close as possible to the place of insulating concrete has reached its full dimensional
installation. stability. Contrary to cement-containing vibration
castables, insulating concretes may show a typically
After having placed the insulating concrete behind lower structural strength or do not have any striking
the formwork, it has to be slightly compacted sound (sound test) after demoulding. For hardening,
by pouring, rodding or ramming layer by layer the insulating concrete requires at least 24-48 hours.
(10-15 cm), or vibrating. Before preparing the next Any processing of the insulating concrete is to be
layer, the surface of the anterior layer is to be slight- avoided during that period. Once the hardening pro-
ly roughened. This will avoid any formation of layers. cess has been completed, drying and heating-up can
The time required for processing the insulating be started, according to the instructions.
concrete is temperature-dependent and should not
exceed 20 minutes.
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
70 Poured insulating concretes (Iso.) Setting accelerator 71
Dosage
At processing temperatures ≤ 15 °C, the amount of
additive required ranges from 0.01 wt.% up to max.
0.05 wt.%.
Safety instructions
Strictly observe the attached material safety data
sheet when using setting accelerators. Always wear
your personal protective equipment (respiratory pro-
tection, tightly sealed safety goggles, safety gloves
and tightly fitting protective clothing) when using
setting accelerators. Valid as at: 03/2017
©Refratechnik Cement GmbH ©Refratechnik Cement GmbH
Refratechnik Cement GmbH
Rudolf-Winkel-Strasse 1
37079 Göttingen
Ce 1-084-05/2017
Germany
Phone +49 551 6941 0
Fax +49 551 6941 104
cement@refra.com