You are on page 1of 1

Larsen & Toubro Ltd - Construction Division

Power Transmission & Distribution Independent Company


Project :ODSSP - Phase - II, Package IV

Micro Plan for balance activities in KADALIGARH


Date : 28/02/2017
Customer : M/s OPTCL (WESCO) Consultant : M/s WAPCOS Ltd

Target Date for Test Charging of P 5/20/2017


REMARKS /
SL Activity Description UOM Scope Qty Executed Qty Balance Qty Status / Target Date
CONSTRAINTS
A Civil Construction Activities 0 0 0 5/15/2017
A.1 Construction of Compound Wall Rmt 175 40 135 3/31/2017
A.2 Construction of Control Room Building LS 1 0.6 0.4 3/31/2017
A.3 Transformer Foundation Nos 2 0 2 3/31/2017
A.4 Equipment Foundation Incl Station Transformer Nos 31 0 31 4/10/2017
A.5 Cable Trench Work Rmt 103.4 0 103.4 4/20/2017
A.6 Drainage Work Rmt 46 0 46 5/10/2017
A.7 Road Work Rmt 55 0 55 5/10/2017
A.8 Area Grading Sq Mtr 1500 0 1500 5/5/2017
A.9 Yard PCC Sq Mtr 60 0 60 5/10/2017
A.10 Gravel Spreading Sq Mtr 150 0 150 5/15/2017
A.11 Civil Finishing Works LS 1 0 1 5/15/2017
B Electrical Construction Activities 0 0 0 5/10/2017
B.1 Earthing (Main Grid & Mat) KM 2.55 0 2.55 4/30/2017
B.2 Lighting of Control Room Building & Switchyard LS 1 0 1 4/30/2017
B.3 Power Transformer Erection No 2 0 2 4/10/2017
B.4 Outdoor Structure erection LS 1 0.8 0.2 4/20/2017
B.5 Outdoor Equipment erection LS 1 0.5 0.5 4/25/2017
B.6 Indoor Equipment Erection Sets 6 2 4 4/15/2017
B.7 Cable Laying Kms 4.71 0 4.71 5/5/2017
B.8 Glanding & Termination No 860 0 860 5/10/2017
B.9 Stringing & Jumpering ( Inside Swyd) Ck 0.24 0 0.24 5/10/2017
C Line Works 0 0 0 5/20/2017
Forest Clearance &
C.1 33 kV Pole Erection No 304 190 114 3/31/2017 Railway Clearance
required
C.2 33 kV Stringing CK 14 0 14 4/10/2017 Subject to above clearance
C.3 11 kV Pole Erection No 164 0 164 4/10/2017
C.4 11 kV Stringing CK 6.2 0 6.2 4/15/2017
D Pre commissiong tests LS 1 0 1 5/15/2017
E Inspection of Electrical Inspector LS 1 0 1 5/17/2017
F Test Charging, Commissioning & Handing over LS 1 0 1 5/20/2017

** Forest Clearance & Railway Clearance are critical for completion of Overhead Line Works