Project Proposal

Case 8.1 Blue Mountain Cabin

Tori Handerson
BUS 302 12/3/2021
PROJECT TITLE
Blue Mountain Cabin
SCOPE STATEMENT
PROJECT OBJECTIVE: Build a Cabin in the blue mountains of Vermont within
20 days, starting 8/1/2016, at a cost not to exceed $68,563.
DESCRIPTION: Small and basic cabin
CLIENT INFO Deliverables:
Jack Smith, Jill Smith  Foundation / Frame
 Roof
2423 Route 302  Windows
 Plumbing / Electrical
Wells River, VT 05081
Milestones:
 Site prepped – 8/2/2016
 Foundation Poured – 8/4/2016
PROJECT #  Framing, roofing, windows, plumbing, electrical – 8/23/2016
 Clean up & customer approval – 8/26/2016
0001
Limits and Exclusions:
COMPANY:  Cabin to be built to the specifications of the blueprint approved by
customer.
D H Contracting
 Contractor has the right to contract out work.
CONTACT:  Contractor is responsible for subcontracted work.
 Site work is limited to Monday – Friday, 8 A.M. to 6 P.M.
Daryl Hannah Customer review: Jack and Jill Smith

PHONE: TIMEFRAME
8/1/16 – 8/26/16
360-123-1234
ESTIMATED BUDGET
EMAIL: MATERIALS & PERMITS = $40,000
LABOR:
darylh@dhcontracting.com EMPLOYEE RATE DAYS TOTAL
DICK $300 18 $5,400
HARRY $300 16 $4,800
TOM $200 20 $4,000
TOTAL $14,200

DARYL = 15% LABOR & MATERIALS = $8,130


MANAGEMENT RESERVE = 10% = $6,233

TOTAL BUDGET: $68,563


GANTT CHART & WBS

ID , TASK NAME DURATION (DAYS) START FINISH PREDECESSORS


A, PREPARE SITE 2 8/1/2016 8/2/2016 0
B, POUR FOUNDATION 2 8/3/2016 8/4/2016 A

C, ERECT FRAME 4 8/5/2016 8/10/2016 B


D, ROOF 3 8/11/2016 8/15/2016 C
E, WINDOWS/ DOORS 2 8/16/2016 8/17/2016 D

F, ELECTRICAL 2 8/18/2016 8/19/2016 D


G, PLUMBING 2 8/22/2016 8/23/2016 D
H, ROUGH IN FRAME 2 8/24/2016 8/25/2016 E, F, G

I, CLEAN UP 1 8/26/2016 8/26/2016 H