1 PROCESS PARAMETERS ................................................................................................... 1
2 RESOURCES ..................................................................................................................... 3
2.1 GENERIC RESOURCE ............................................................................................................. 3
2.2 PLANT RESOURCES .............................................................................................................. 6
2.3 OSP RESOURCE .................................................................................................................. 8
3 ACTIVITIES....................................................................................................................... 8
4 PROCESS OPERATIONS .................................................................................................... 9
5 PROCESS OPERATION CLASSES ...................................................................................... 15
6 PROCESS ROUTINGS ...................................................................................................... 15
7 PROCESS ROUTING CLASSES .......................................................................................... 18
8 FORMULAS.................................................................................................................... 19
9 RECIPES ......................................................................................................................... 22
10 RECIPE APPROVAL ......................................................................................................... 29
TRAINING MANUAL OPM-PRODUCT DEVELOPMNET
1 PROCESS PARAMETERS
Processing parameters are used to provide operators with information needed for managing
equipment that is used during the preparation of a product.
Define Parameters
Text
If the Parameter type is Text, then the process parameter accepts any alphanumeric free
text which is not validated. Once this value is selected, the fields associated with the
Numeric Range, Units, and the list of values buttons are disabled.
Numeric Range
If the Parameter Type is Numeric value, then you can enter the Minimum, and Maximum
values, and the Units field. Once this type is selected, the fields associated with the list of
values are disabled.
List of Values
List Value: If the Parameter Type is List Value, then you can enter the list of values in the
detail section. This selection indicates that all possible values for this process parameter are
defined in a static table of entries.
2 RESOURCES
Resources are the assets you use to produce batches, including production equipment and
employee labor.
Capacity (Optional):
1. Enter the Minimum and Maximum amount per vessel capacity (maximum output a
resource can produce at one point of time) for this resource.
2. Enter the Capacity UOM for this resource. This is usually specified in mass or volume
not time.
3. Save your work.
Resource Classes: (Optional)
User can define resource classes using the Resource Classes window in OPM Process
Planning.
Navigate to OPM Process Planning > Capacity Planning > Setup > Resource Classes. Assign
the resource class to resource in Resources Window.
Parameters
1. Enter the Target Value for the process parameter. Target value is the ideal setting
for the process being run.
2. Enter the Min Value for the process parameter. The minimum value is the lowest
acceptable value for a numeric type process parameter. Do not exceed the range
defined for the process parameter.
3. Enter the Max Value for the process parameter. The maximum value is the highest
acceptable value for a numeric type process parameter. Do not exceed the range
defined for the process parameter.
4. Enter the units of measure for the process parameter in the Units field.
5. Save your work.
1. Enter the Resource for which you are establishing available capacity parameters and
production costs when used in the designated organization (production).
2. Enter the Count. This is the number or quantity of the resource used in the specified
inventory organization for which you are defining production costs and usage
availability.
3. Enter the Planning Cost of this resource when used in the specified inventory
organization. It is used for reporting purposes only.
Capacity
1. Enter the Range for the resource's minimum and maximum amount per vessel
capacity unit at this inventory organization.
2. Enter the Ideal for the resource's optimum amount per vessel capacity unit at this
inventory
3. organization.
4. Enter the UOM by which the resource capacity is measured in this inventory
organization.
5. Save your work.
Process parameters for that resource can be viewed by clicking on process parameters
1. The Seq number for storing the process parameters in a unique sequence.
2. The Process Parameters name.
3. Edit the Target Value for the process parameter. This is the ideal setting for the
process being run.
4. Enter the Min Value for the process parameter. The minimum value is the lowest
acceptable value for a numeric type process parameter. Do not exceed the range
defined for the process parameter.
5. Enter the Max Value for the process parameter. The maximum value is the highest
acceptable value for a numeric type process parameter. Do not exceed the range
defined for the process parameter.
6. The Units field displays the unit of measure for a numeric type process parameter.
3 ACTIVITIES
An Activity is an action performed during the manufacturing process, such as mixing or
heating.
Defining Activities
To define an Activity, Navigate to Process Engineer > Setup > Activities
1. Enter an Activity Code for the name of the activity. Activities are the components
that make up an operation.
2. Enter a brief Description of the activity.
3. Enter the cost Analysis Code.
4. Save the work.
4 PROCESS OPERATIONS
An operation is an ordered set of activities that have to be completed for a predetermined
step in a production batch, and includes specified resource requirements.
Defining Operations
1. Enter an Activity required for this operation. A Description of this activity displays.
2. Enter the Activity Factor to specify the number of times the activity is performed in
this operation.
2. Change the Current Status displayed by selecting a different Status from the Change
Status To list.
3. Click OK.
Throughput
1. Enter the planned Process Quantity for the resource. The UOM entered on the
header displays. This is the unit of measure for the planned process quantity.
2. This value combined with the Usage quantity defines the usage rate.
3. Enter the planned resource Usage. This is typically expressed in hours.
4. Enter the UOM as the unit of measure for the resource.
Cost Information
1. Enter the Component Class code. The component class is set up in the Oracle
Process Manufacturing Cost Management application and defaults from the
Resource.
Navigation
Valuation Option indicator lets you identify whether the component class must
be used for valuing inventory or not. The valid values are:
Scheduling Information
1. Enter the Plan Type to define the resource as Primary, Secondary or Auxiliary
2. Enter the Count as the number of resources needed for the activity entered. For
example, if two blenders are used for mixing, enter a 2 in the count.
3. Enter the Offset Interval as the time delay from the start of the activity to the point
where the resource is actually required.
4. Select the Scale Type as Proportional
6 PROCESS ROUTINGS
A routing is a sequenced set of operations to perform to complete a production batch. The
operations are presented in a series of steps that organize these operations into an orderly
set of activities that have individual resources associated to them.
7. Enter a Valid to date for the expiration of this routing. If there is no expiration date
for this routing, then leave the field blank.
8. Enter the process Quantity for this routing. This is the total quantity of material for
the routing, and is used to scale individual step requirements.
9. Enter the process quantity UOM associated with this routing.
Routing Steps
3. Change the Current Status displayed by selecting a different Status from the Change
Status To list.
4. Click OK.
Once status is changed routing status will be changed accordingly and can be viewed on the
Process Routing Detail form.
8 FORMULAS
Formulas are lists of ingredients and products with their associated quantities and
processing instructions. Production batches are based on formulas defined in Product
Development.
Products
1. The Line number for each product listed displays. These fields cannot be edited.
2. Enter the Product Code for each item produced by this formula. If the formula code
entered is the same as an item code, then that item code displays as the default for
the first product line. A minimum of one product is required for a formula.
3. The Description of the product entered displays.
4. Enter Quantity of the product that this formula yields.
5. Enter the UOM for the quantity entered
6. Scale Type is Selected to be Proportional
By-Products
1. The Line number for each byproduct listed displays. These fields cannot be edited.
2. Enter the By-Product code for byproduct items produced by this formula.
3. The Description of the byproduct entered displays. This defaults from the Item
Master table.
4. Enter the Quantity of the byproduct that this formula yields.
5. Enter the UOM for the quantity entered.
Ingredients
1. The Line number for each ingredient listed displays. These fields cannot be edited.
2. Enter the Ingredient code for each item required by this formula. A minimum of one
ingredient is required for a formula.
3. The Description of the ingredient entered displays. This defaults from the Item
Master table.
4. Enter Quantity of the ingredient that this formula requires. The quantity entered in
this field is the default standard quantity used for the recipe. It can be changed at
the recipe level.
5. Enter the UOM for the Quantity entered.
9 RECIPES
Recipes standardize the structure of all information that describes production of one or
more products.
1. The Output Quantity displays the sum of the product quantities entered in the
formula. UOM is the unit of measure for the formula associated with this recipe.
2. Enter the Formula for the recipe. The formula Version displays.
Note:This field cannot be edited after you save this recipe. You cannot use an inactive
formula in a recipe.
3. Enter a Routing for the recipe. A routing can be added to an existing recipe. The
Version for the routing entered displays.
Plant/Laboratory
The following fields are display only:
4. Organization displays the Organization code that the process loss is being defined
for.
5. Organization Name displays a description of the plant or laboratory.
6. Type indicates whether this is a plant or a laboratory.
7. Process Loss displays the material that is lost through the process. This field is blank
if you did not enter a routing. You can override the default process loss.
8. Contiguous is selected if routings in this recipe must be run in one contiguous block
of time.
Step quantity regarding particular operations can also be viewed at recipe details window.
1. Formula displays the formula used in the recipe with its Version and Description.
2. Routing displays the routing used in the recipe with the routing Version and
Description.
3. Return to this window to change status by selecting Change Status from the Actions
menu after entering all relevant information and saving the validity rule with the
default Status of New.
1. Navigate to the Recipe Organization Details window. The Find Recipe Organization
Details window displays.
Attention: The first time you enter recipe organization details, click New.
Otherwise, enter the required information in the Find Recipe Organization
Details window.
2. Enter the Organization where you want to override information that is defined for
specific operations and routings. Required.
3. Click Find.
4. The following fields are display only:
Organization indicates the code for the plant or laboratory that owns the recipe.
Type displays Plant if the organization is a plant, or a Laboratory if the organization is
a laboratory.
Organization Name displays the description assigned to the organization. This field
defaults to the entry from the Recipe Details window. Required.
Planned Process Loss displays the loss of process material observed during
production of a batch using the recipe as a percentage. You can enter and save a
different planned process loss value for the recipe used in the organization
displayed. This value defaults to the theoretical process loss when no entry is made
on the Recipe Details window.
Theoretical Process Loss displays the hypothetical loss of process material associated
to a routing. If no routing is associated to the recipe, this field is blank
Activities:
The following fields are display only:
Step indicates the step number associated with the listed operation. Steps
cannot be added or deleted here.
Operation displays the operation associated with the step. The operation
Version and Description display.
Activity displays the activity associated with the operation. The activity
Description displays
Factor display the no of times an activity performed in the operation.
Capacity:
Step indicates the step number associated with the listed operation. Steps
cannot be added or deleted here.
Operation displays the operation associated with the step. The operation
Version displays.
Activity displays the activity associated with the operation. Activities cannot
be added or deleted here.
Resources displays the resource associated to each displayed activity.
Minimum Capacity shows the resource minimum capacity
Maximum capacity shows the maximum output can be generated by
resource at one point of time.
UOM displays the unit of measure for both Min Capacity and Max Capacity
entries.
Throughput:
Step indicates the step number associated with the listed operation. Steps
cannot be added or deleted here.
Operation displays the operation associated with the step. The operation
Version displays.
Activity displays the activity associated with the operation. Activities cannot
be added or deleted here.
Resources displays the resource associated to each displayed activity
Process Qty displays the total quantity of material for the step with its UOM.
Usage displays the unit of the resource used to perform the activity on the
displayed step.
10 RECIPE APPROVAL
All recipes will be defined in the system in new status. Once all information relating to
recipe is entered, user will send the recipe for approval.
User will select the Approved for General Use and enter the Ok button.
System generate a pop up to navigate to HTML page for sending recipe for approval.
Click on yes
Upon clicking yes button recipe will be send for approval to the relevant approver.
User will go back to the application screen and will click on ok tab.
Once recipe is sent for approval, approver will receive a notification for recipe approval.
Recipe number
Version
Recipe description
Formula
Formula version
Formula description
Routing number
Routing version
Routing description
Ingredients Quantity & UOM
Operations
Step material association
Approver will read all the e-record relevant to the recipe and will enter yes that he read
all the information’s. and the click on approve button.
Approver will enter the name and password and the click on sign.
User can open the recipe and can see the status.
Once recipe is approved user will change the status of the validity rules of the recipe.
User will change the status “Approved for General Use” and click on ok.