PROJECT NAME- NIAB, CALICUT

AIRPORT NEW TERMINAL


BUILDING, CALICUT

BY:-TANUJ KUMAR KHARD


INTRODUCTION
The AAI given approval for the construction of an new
international arrival block at Calicut airport in Kerala.
The proposed block to come up at a HVAC cost of Rs 7.29 crore and
had a floor area of 1.81 lakh sq ft. It had two floors with the arrival
hall located in the ground floor. The top floor included an
immigration hall. The new block is a green building with a three-
star Green Rating for Integrated Habitat Assessment.
KITCO had been roped in as the engineering consultant for the
construction of the new block and for taking up internal
modification of the international arrival terminal. They were
responsible for structural design, MEP design and tender
documents etc.
The schedule as per the tender for the completion was 298 Days
from 24th Nov 2016 but in actual the project was delayed for 798
days and completed on 31st Jan 2019.
BRIEF ABOUT NEW INTERNATIONAL ARRIVAL
BLOCK, CALICUT (HVAC & BMS Works)
 Official name :- NIAB, Calicut Airport, Calicut
 Carries :- International Arrival hall
 Agreement Number :- AAI/CHQ/ENGG(E)CALICUT/HVAC/2016-17/857
 Locale :- Calicut, India
 Owner :- Airport Authority of India
 Engineering consultant :- KITCO Ltd.
 Civil Contractor :- URC Constructions Pvt. Ltd.
 HVAC Contractor :- Unique Engineers Pvt. Ltd
 Awarded HVAC Cost :- Rs. 7,08,16,122.00
 Actual Completion cost :- Rs. 7,29,32,286.00
 Start date as per NIT :- 24th Nov 2016
 Completion as per NIT :- 18th Sept 2017
 Completion date Actual :- 31st Jan 2019
MY APPROACH-
 Joined Unique Engineers Pvt Ltd. in Oct 2018.
 The Project was directly awarded to M/s UEPL
from M/s AAI.
 Due to delay M/s AAI was withholding the
payments due to delay in project.
 Management involved me to get the EOT
certified and final bill closure to get the final
payments.
 Interface between client & civil contractor to get
the EOT approval and final account
reconciliation.
MY ACHIEVEMENTS
In absence of justification of delay from client and other contractors ,the
provisional EOT’s was issued and amount was withhold against the
delay from the running bill.
In Dec 2018 the extra and deviated items statements was shared with
client for the approval and same was approved by client in Jan 2019.
In order to my role, the biggest problem was the EOT approval from
client to get the withhold amount release and in April 2019, the final
EOT was submitted to the client for approval with all evidence and
justification for the delays.
During the preparation of EOT, it has been observed that based on the
actual schedule submitted to client the completion date was Sept 2017,
and maximum all the major material was delivered at site till July 2017
and due to delay in work front and site clearance from client end, the
installation and commissioning got delayed.
In order to approval various commination was done and EOT got
approved in March 2020 from Client.
In EOT the additional claim of Rs. 34,79,557.00 against the additional
cost paid for supervision charges and based on request from AAI the
withdrawn letter for claim was submitted to AAI.
CONCLUSION
Appendix A
Competencies Achieved
 Justified the following delays with evidences for EOT approval–

i. 111 days delay in handing over of project site to start the work.
ii. 402 days delay in Casting of civil structure of Plant room
iii. 540 days delay in First floor Civil works i.e Structure work, Block works and false
ceiling work.
iv. 226 days delay in providing the trench to install the chilled water pipe in between
building and plant room.
v. 540 days delay in providing the civil work clearance in aero bridge area at first
floor level.
vi. 402 days Delay in providing the Area clearance for water softener installation.
vii. Due to all the above delay from the construction part the project has been delayed
500 days.
viii. The EOT was approved by AAI vide letter number-AAI/CL/Engg (E)/HVAC-
BMS/2020/034 dated 18.03.2020.

 Got the Extra Items & Deviation items approval as per the CPWD DSR-
2018.
 Successfully close the final account for the job..
 Got the EOT approval without any penalty for delay.
ORGANIZATION CHART
Appendix B
PROJECT DOCUMENTS
Appendix C
 NIT-F.No.: AAI/CHQ/ENGG(E)/CALICUT/HVAC/2016-17 dated:
18th July 2016
 Agreement No. vide letter ref-
AAI/CHQ/ENGG(E)CALICUT/HVAC/2016-17/857 dated- 10th Nov
2019.
 EOT letter submitted to client for approval vide letter ref-
Calicut/Airport/AAI/HVAC/UNIQUE/02/2019-20 dated 15th April
2019.
 Claim withdrawn letter submitted to client vide letter ref-
Calicut/Airport/AAI/HVAC/UNIQUE/03/2019-20 dated 26th Feb
2020.
 EOT and Completion approval vide letter ref-
AAI/CL/Engg(E)/HVAC-BMS/2020/034 dated 18th March 2020.
THANK YOU….!!!