i. 111 days delay in handing over of project site to start the work.
ii. 402 days delay in Casting of civil structure of Plant room
iii. 540 days delay in First floor Civil works i.e Structure work, Block works and false
ceiling work.
iv. 226 days delay in providing the trench to install the chilled water pipe in between
building and plant room.
v. 540 days delay in providing the civil work clearance in aero bridge area at first
floor level.
vi. 402 days Delay in providing the Area clearance for water softener installation.
vii. Due to all the above delay from the construction part the project has been delayed
500 days.
viii. The EOT was approved by AAI vide letter number-AAI/CL/Engg (E)/HVAC-
BMS/2020/034 dated 18.03.2020.
Got the Extra Items & Deviation items approval as per the CPWD DSR-
2018.
Successfully close the final account for the job..
Got the EOT approval without any penalty for delay.
ORGANIZATION CHART
Appendix B
PROJECT DOCUMENTS
Appendix C
NIT-F.No.: AAI/CHQ/ENGG(E)/CALICUT/HVAC/2016-17 dated:
18th July 2016
Agreement No. vide letter ref-
AAI/CHQ/ENGG(E)CALICUT/HVAC/2016-17/857 dated- 10th Nov
2019.
EOT letter submitted to client for approval vide letter ref-
Calicut/Airport/AAI/HVAC/UNIQUE/02/2019-20 dated 15th April
2019.
Claim withdrawn letter submitted to client vide letter ref-
Calicut/Airport/AAI/HVAC/UNIQUE/03/2019-20 dated 26th Feb
2020.
EOT and Completion approval vide letter ref-
AAI/CL/Engg(E)/HVAC-BMS/2020/034 dated 18th March 2020.