FORWARD PAS = ES + DURATION= EF BACKWARDS = LF- DURATION=LS

0 5 5 13 13 9 22 22 6 28
5 8
A D E H

8 8 13 13 8 21 21 8 30 30 8 36

13 7 20
5 8 13

F G

0 5 5
21 8 29 29 8 36
B

16 8 21 5 4 9 9 4 13 13 8 21

I J K

0 8 8 20 8 24 24 8 28 8
28 36
C

0 0 8 14 10 24
8 6 14 24 12 36

L M N

14 0 24
8 0 14 24 0 36
B. A-D-E-H
A-F-G
B-I-J-K
C-L-M-N = Critical Path
C. The project is expected to finish on the week 36
D.
Activity ES EF LS LF Slack (LS-ES)
A 0 5 8 13 8
B 0 5 15 20 15
C 0 8 0 8 0
D 5 13 13 21 8
E 13 22 21 30 8
F 5 13 21 29 16
G 13 20 29 36 16
H 22 28 30 36 8
I 5 9 20 24 15
J 9 13 24 28 15
K 13 21 28 36 15
L 8 14 8 14 0
M 14 24 14 24 0
N 24 36 24 36 0