7.5
8
HOURS
3.6
4
2
0
0
1 2
Actual Rainy 7.5 3.6
Actual Slippery 6.3 2.2
Plan Rainy 1.36 1.36
Plan Slippery 0.82 0.82
WEEK 17
Slippery
7%
Mining Stripping
44%
Plan Vs Actual
Rain & Slippery
13.30
2.2
3 4 5 6 7 8
0 2.2 0.00 0.00 0.00 13.30
0 1.8 0.00 0.00 0.00 10.30
1.36 1.33 1.33 1.33 1.33 9.41
0.82 0.80 0.80 0.80 0.80 5.65
CUMMULATIVE P
15-May-22 16-May-22 17-May-22
WEEK 17
EXC DT DZ VB EXC DT DZ VB EXC DT
PLAN UNIT 6 10 3 0 11 6 6 6 6 6
ACTUAL UNIT 0 0 0 0 0 0 0 0 0 0
PLAN EWH 81.52 135.87 40.76 - 149.46 81.52 81.52 81.52 81.52 81.52
ACTUAL HOUR 0 0 0 0 0 0 0 0 0 0
6
4
2
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
EXC DT DZ VB EXC DT DZ VB EXC DT DZ VB EXC DT DZ VB EXC
15-May-22 16-May-22 17-May-22 18-May-22
PLAN UNIT 6 10 3 0 11 6 6 6 6 6 6 6 6 6 6 6
ACTUAL UNIT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
CUMMULATIVE PLAN VS ACTUAL UNIT
17-May-22 18-May-22 19-May-22 20-May-22
DZ VB EXC DT DZ VB EXC DT DZ VB EXC DT DZ
6 6 6 6 6 6 6 6 6 6 6 6 6
0 0 0 0 0 0 0 0 0 0 0 0 0
81.52 81.52 81.52 81.52 81.52 81.52 81.52 81.52 81.52 81.52 81.52 81.52 81.52
0 0 0 0 0 0 0 0 0 0 0 0 0
AL UNIT
160.00
140.00
120.00
100.00
Hours
80.00
60.00
40.00
20.00
0 0 0 0 0 0 0 0 0 0 0 0 -
EX DT
EXC DT DZ VB EXC DT DZ VB EXC DT DZ VB C
19-May-22 20-May-22 21-May-22 15-May-22
6 6 6 6 6 6 6 6 6 6 6 6 PLAN EWH 81 13
0 0 0 0 0 0 0 0 0 0 0 0 ACTUAL HOUR 0 0
-May-22 21-May-22
VB EXC DT DZ VB
6 6 6 6 6
0 0 0 0 0
81.52 81.52 81.52 81.52 81.52
0 0 0 0 0
DT DZ VB EX DT DZ VB EX DT DZ VB EX DT DZ VB EX DT DZ VB EX DT DZ VB EX DT DZ VB
C C C C C C
15-May-22 16-May-22 17-May-22 18-May-22 19-May-22 20-May-22 21-May-22
13 40 - 14 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81 81
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
REVIEW ORE PRODUCTION
22-Apr-19 23-Apr-19 24-Apr-19 25-Apr-19 26-Apr-19
DESCRIPTION
Monday Tuesday Wednesday Thursday Friday
PLAN ORE 6,522 6,522 6,522 6,450 6,522
ACTUAL ORE 0 2,655 0 1,350 1,530
LOSS OORE -6,522 -3,867 -6,522 -5,100 -4,992
TOTAL 6,522 9,177 6,522 7,800 8,052
ORE PRODUCTION
7,000
6,000
5,000
Axis Title
4,000
3,000
2,000
1,000
0
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
22-Apr-19 23-Apr-19 24-Apr-19 25-Apr-19 26-Apr-19 27-Apr-19 28-Apr-19
PLAN ORE 6,522 6,522 6,522 6,450 6,522 6,522 6,522
ACTUAL ORE 0 2,655 0 1,350 1,530 0 0
50,000
40,000
5,535
30,000
20,000
10,000
AXIS TITLE
0
-10,000
-20,000
-30,000
-40,000 -40,046
-50,000
1
PLAN ORE 45,581
ACTUAL ORE 5,535
LOSS OORE -40,046
LOSS OORE -40,046
UCTION
27-Apr-19 28-Apr-19 TOTAL PER
Saturday Sunday WEEK 2,174 2,174
6,522 6,522 45,581 2,174 2,174
12%
0 0 5,535 4,348 4,348
-6,522 -6,522 -40,046
6,522 6,522 1.5 1.5
6,521.81 6,521.81
KENDALA – KENDALA :
1. Hujan
2. Slippery
3. Keterlambatan Keputusan Analisa Lab
4. No Production Activity Due to Run Out Ore
5. Villagers Demonstration
Sunday
28-Apr-19
6,522
2,174 2,150 2,174 2,174 2,174
2,174 2,150 2,174 2,174 2,174
4,348 4,300 4,348 4,348 4,348
OB PRODUCTION KENDALA
PLAN OB/WS ACTUAL OB HAUL 1. Hujan
2. Prestart & L
13,044 13,044 13,044 12,900 13,044 13,044 13,044 3. Standby
4. Slippery
5. Villagers D
0 0 315 0 495 0 0
KENDALA – KENDALA :
1. Hujan
2. Prestart & Last Time shit
3. Standby
4. Slippery
5. Villagers Demonstrain
EQUIPMENT PLAN
UNIT REQUIRED EQUIPMENT UNIT ACTUAL UNIT
LOCATION ACTIVITY Remarks
EQUIPMENT TOTAL UPDATED RFU SB BD TOTAL
MINING EQUIPMENT PROJECT ORE GETTING PC300 9 0 0 9
STRIPPIN OB EXC-20T 3 PC200 18 0 0 18