This document outlines design assist procedures for precast structural concrete assemblies, including holding collaborative design assist meetings between the contractor and design team to finalize design details. Key responsibilities include the contractor appointing a design assist project manager and assisting the architect and engineer in completing construction documents while developing shop drawings. Final designs will be approved by the architect and engineer.
This document outlines design assist procedures for precast structural concrete assemblies, including holding collaborative design assist meetings between the contractor and design team to finalize design details. Key responsibilities include the contractor appointing a design assist project manager and assisting the architect and engineer in completing construction documents while developing shop drawings. Final designs will be approved by the architect and engineer.
This document outlines design assist procedures for precast structural concrete assemblies, including holding collaborative design assist meetings between the contractor and design team to finalize design details. Key responsibilities include the contractor appointing a design assist project manager and assisting the architect and engineer in completing construction documents while developing shop drawings. Final designs will be approved by the architect and engineer.
A. Section includes design assist procedures for the following
assemblies:
1. Section 034100 Precast Structural Concrete
1.02 DESIGN ASSIST PROGRAM
A. Collaborative Design Assist (CDA): A process that engages
CDA contractor and delegated design engineer in finalizing details for indicated scope of work in compliance with indicated criteria.
1. The goal of CDA is to engage with all team members,
progressively reviewing development of shop drawings. At the end of the process, designers and CDA contractor are aware of all parameters of design, why and how the details developed as they have and architect drawing approvals are finished.
B. Conduct multiple processes in parallel:
1. Assist Architect and Structural Engineer in completion
of construction documents for permitting and construction.
2. Develop and complete shop drawings in parallel with
Architect’s and Structural Engineer’s documents.
3. Accelerate approval and release of materials for
fabrication.
C. CDA Scope:
1. Refer to Drawings for scope of work requiring design
assist.
2. The design assist scope of work identified on the
drawings is not the full scope of work for the garage. Design assist includes coordinating with other trades necessary to complete the garage scope of work and other work, including but not limited to cast in place concrete scope, miscellaneous metals and their attachments, prefabricated roof structures, toppings, earthwork, and other adjacent and intersecting materials and systems.
BRANDYWINE REALTY TRUST PERMIT ISSUE
155 KOP RD - OFFICE BUILDING & PARKING GARAGE BALLINGER - 19005.00 & 19006.00 013515.G - 1 DESIGN ASSIST PROCEDURES D. The qualifications of the delegated design engineer and each member of the CDA contractor’s team are part of the selection process. Individuals named must be part of the contract and continue through the Project, beginning to end. Any changes in staffing requires approval by the Owner and the Architect
E. The Architect and Structural Engineer are not relinquishing
authorship of the design to the Contractor, the CDA contractor nor to the delegated design engineer. All final approvals and all design decisions shall be made by the Architect and Structural Engineer.
F. Contractor and CDA Contractor: The design assist process
is included in and an integral part of the overall construction contract between the Owner and the Contractor.
1. The Contractor shall appoint a CDA Project Manager who
shall direct and administer the process.
2. Roles and responsibilities of the Contractor under the
Owner-Contractor contract beyond those described herein for the CDA contractor are not altered by the CDA process. The Contractor shall provide, but is not limited to, the following services as part of CDA.
a. Coordinate the work of the various sub-
contractors and suppliers, both included in the CDA scope and in typical delivery. b. Assign different portions of the total scope of work to various sub-contractors and suppliers, both included in the CDA scope and in typical delivery. c. Schedule the work. d. Review, comment on, stamp, sign and process submittals. e. Manage and monitor the work for quality and compliance with the contract.
1.03 PROPOSAL DOCUMENTATION
A. Provide with bid or proposal for the complete CDA program
scope of work, information demonstrating approach to project, understanding of design intent and performance requirements, qualifications, and other pertinent information.
1. Submit information from each of the sections required
for the parking garage.
2. Acknowledgement Certification:
BRANDYWINE REALTY TRUST PERMIT ISSUE
155 KOP RD - OFFICE BUILDING & PARKING GARAGE BALLINGER - 19005.00 & 19006.00 013515.G - 2 DESIGN ASSIST PROCEDURES a. Provide written certification that CDA contractor has studied the documents, understands the design intent and the criteria indicated, and has conducted sufficient engineering review necessary to certify that solution included in proposal complies or can be made to comply with the requirements of the contract within the proposed contract sum and within the proposed schedule. b. Design Assist Engineer certification that engineer has studied the documents, understands the design intent and the criteria indicated, and has conducted sufficient engineering review necessary to certify that solution included in proposal complies or can be made to comply with the requirements of the contract.
3. Manufacturers and products proposed.
4. Substitutions proposed.
5. Typical plan, section and elevation drawings at
suitable scales.
6. Samples of assembly or major components, including
finish samples.
7. Typical detailed drawings at large scales, including
laboratory test reports and certification demonstrating compliance with performance criteria.
9. Preliminary calculations demonstrating compliance with
specification.
10. Proposals for connections to and support from garage
foundation system
11. .
12. Preliminary Schedule from Design Assist through
Substantial Completion. Include key decision points and long-lead items.
13. Highlight any areas of non-compliance with the
Contract.
14. Qualifications for the following:
a. Each CDA contractor’s company history and
qualifications.
BRANDYWINE REALTY TRUST PERMIT ISSUE
155 KOP RD - OFFICE BUILDING & PARKING GARAGE BALLINGER - 19005.00 & 19006.00 013515.G - 3 DESIGN ASSIST PROCEDURES b. CDA contractor’s Project Manager. c. CDA contractor’s Superintendent. d. Delegated Design Assist Engineer.
1.04 DESIGN ASSIST MEETINGS
A. General: Schedule and conduct two, half-day (4-hour)
coordination meetings at Architect's office. Schedule and conduct weekly, one-hour, web-based online coordination meetings.
1. Attendees: Inform participants and others involved,
and individuals whose presence is required, of date and time of each meeting. Coordinate scheduled meeting dates and times with Architect and Owner.
a. Required Attendance for Each Meeting:
Construction Manager, CDA Contractor, CDA Design Engineer, Architect, Structural Engineer of Record, and installer for each design assist assembly.
2. Agenda: Prepare and distribute agenda to invited
attendees, minimum two days before meeting.
a. Prepare agenda consistent with design assist
methodology to ensure design issues are addressed in specified priority order. b. Require review of previous meeting minutes at start of each meeting.
3. Minutes: Record significant discussions and
agreements achieved. Distribute meeting minutes to attendees, Owner, and other concerned parties within two days of meeting.
B. Prepare slides of individual meeting agenda items using
PowerPoint presentation. Markup presentation to record decisions from meeting.
1. Distribute meeting presentation and recorded markups
with meeting minutes.
C. Following each design assist meeting, revise design assist
drawings incorporating meeting results. Resubmit design assist drawings for review five days before next scheduled meeting.
1.05 DESIGN ASSIST SUBMITTALS
A. General: Prepare design assist drawings. The Architect
will provide design intent documents and, as a courtesy,
BRANDYWINE REALTY TRUST PERMIT ISSUE
155 KOP RD - OFFICE BUILDING & PARKING GARAGE BALLINGER - 19005.00 & 19006.00 013515.G - 4 DESIGN ASSIST PROCEDURES provide a Revit model. The Architect accepts no liability for the Contractor’s use of the Revit model. The Contractor will update and make available the Contractor’s Revit model to the Architect and Owner.
B. For each submittal:
1. Submit one PDF file for each drawing produced.
2. Submit Revit model from which drawings are produced in
to be imported into Architect's Revit model as background information from which Architect will develop Construction Document system details.
C. Design Assist Drawings: Prepare, review, resolve, and
revise drawings, as required, for the following before shop drawing submission:
1. Constructability Analysis: Include typical and unique
details for each assembly and attachments to and interfaces with building structure and adjacent Work.
a.
2. Structural Analysis: Include determination of,
location of, and magnitude of loads imposed on foundation elements. Include both gravity and lateral loads in this analysis.
D. Present, review, and revise the following material and
finish selections before final submittals for approval:
1. Metal finishes exposed to view.
2. Joint sealants exposed to view.
3. Structural precast concrete exposed to view.
4. Architectural precast concrete for each component,
including spandrel panels, stairs and bollards.
1.06 DESIGN ASSIST METHODOLOGY
A. Review and resolve priorities in specified order for each
design assist assembly. Architect may vary specified timeframe and duration for completing each priority, depending on design assist progress and issues discovered during design assist process.
B. First Priority: At the first meeting, confirm assumptions
made in design intent documents, including spans, component sizes, clearances, locations of interfaces between cast-in-
BRANDYWINE REALTY TRUST PERMIT ISSUE
155 KOP RD - OFFICE BUILDING & PARKING GARAGE BALLINGER - 19005.00 & 19006.00 013515.G - 5 DESIGN ASSIST PROCEDURES place concrete and precast concrete elements, and location and size of expansion joints.
C. Second Priority: Resolve engineering of structural precast
components. Develop draft details of typical joints, edges and systems. Review finish samples. Develop design loads for cast-in-place structural concrete. Complete by conclusion of third design assist meeting.
D. Third Priority: Finalize engineering of structural and
architectural precast concrete components. Finalize finishes. Finalize design loads or cast-in-place structural concrete foundations. Complete by the conclusion of the last design assist meeting.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION - Not Used
+ + END OF SECTION + +
BRANDYWINE REALTY TRUST PERMIT ISSUE
155 KOP RD - OFFICE BUILDING & PARKING GARAGE BALLINGER - 19005.00 & 19006.00 013515.G - 6 DESIGN ASSIST PROCEDURES