Professional Documents
Culture Documents
future.
Fig. 1.2 (b) : Project life cycle phases with
intensity of activities
1. Project Initiation Phase or Conceptualization
It is the 1st phase in the Project Life Cycle, as it involves
starting up a new project.
A new project can be started by defining its objectives,
scope, purpose and deliverables to be produced.
We can also hire our project team, setup the Project
Office and review the project, to gain approval to
Fig. 1.1 begin the next phase.
[Nov.46,May/Feba A feasibility study can be conducted for investigation
PROJECT LIFE CYCLE
in this phase.
The project manager and project team have one
2. Project Planning Phase
shared goal: to carry out the work of the project for the
purposeof meeting the project's objectives. The all-important second step of any successful project
managementlife cycle is planning and should include
Every project has a beginning, a middle period during
a detailed breakdownand assignment of each task of
which activities move the project toward completion,
and an ending. your project from beginning to end.
• The Planning Phase will also include a risk assessment
A Standard Project Typically Has The Following
Four Major Planning, in addition to defining the criteria needed for the
Phases; Initiation,
successful completion of each task.
Implementation, And Closure.
(1.1)
PROJECT MANAGEMENT (BATU CIVIL) (1.2) INTRODUCTION TO PROJECT MANAGEMENT
3. Project Execution Phase He is least bothered about how the execution is taking
During the third phase, the implementation phase, the place. Project stake goes on increasing as the project
project plan is put into motion and the work of the approaches completion.
project is performed. The creativity is required at conceptualization, planning
It is important to maintain control and communicate as and execution stage for minimizing the cost,
needed during implementation. maximizing quality and benefits.
Progress is continuously monitored and appropriate Least creativity is required at termination stage. In the
adjustments are made and recorded as variances from initial phases of project, uncertainty level is high from
the Original plan. In any project, a project manager duration, expenses and resources point of view.
spends most of the.time in this step. In the termination stage, as activities are also less, the
During projett implementation, people are carrying uncertainty is very low.
out. the tasks, and progress information .is being
8
1.9 MATERIALS MANAGEMEN
reported •thtoUÉh regular.te.am.•meetirigs,
Material Management is the process which involves all
4. Project Closure Phase or Terminatiön the activities concerning materials right from the time
The Project Closure Phase is the fourth and last phase the need for the materials is established until they are
in the project life cycle.
issued to the construction site.
In this phase, projectis formally closed.
Materialconstitutes40% to 60% of the total project
Project Closure involves handing over the deliverables
cost and hence the success of the project depends
to your- customer, passing the documentation to the
upon the materials management.
business, cancelling supplier contracts, releasing staff
and equipment and . informing stakeholders of the It is very necessaryto have proper planning for the
closure of the project. materials management before and during the project
work.
1.2.1 Advantages of Project Life Cycle
If required materials,in quality and quantity, are •made
This curve is used for progress review and control the
slippage. available at the proper time, there will be substantial
saving in cost, time and also there will be improvement
On this curve, •the project performance is shown very
in quality of construction or the project.
clearly and in a very simple manner.
Following is the Project •Life Cycle (PLC) for different It decides scientifically what to purchase, when to
parameters on site. purchase, how much to purchase, from where to
purchase, where and how to store and general flow of
Client interes! materials for any project and therefore, forms an
important part of big projects.
Project stake
> The materials management covers all the aspects of
materials costs, materials supply and materials
Resources utilisation.
Creativity
Uncertainty
• To have proper value analysis of the stores. Sometimes purchasing of different material is affected
through agencies. Such agencies should be reliable.
• To see that excess use of materials is avoided and bad
There should be a list of materialsnecessaryfor the
workmanship is prevented.
project with the specifications and the quantity.
• To see to the proper disposal of surplus(materialand
It is also necessary that a list of reliable suppliers and
also of the scrap and rejected material if any.
agencies supplying the various materials be
1.4.1 Qualities of a Material Manager [May171
maintainedand this list should be modified from time
Material manager should possess the following qualities or to time to accommodate new reliable suppliers and
skills : agencies.
Know the market trends. It is also responsibility of the purchase department that
Know newly introduced materials. payments are made within reasonable period after the
purchase is affected and found satisfactory.
Understand the system in the organisation thoroughly.
Purchasing is a service function that supports the
Possess ability in' analysis'. organisation, and
activitiesof other operations.There must be steady
communication.
and reliable flow of information between concerned
Possess ability to, use computer equipment and departments.
softwares.
The different concerned departments may be :
Familiarwiththe supply chain management systems.
Design
Should have training in project management to Accounts
support production schedule, to plan requirements for
Different suppliers in market
purchasing materials etc.
Stores for receiving the material
1.5 FUNCTIONS IN MATERIAL > Actual construction or production
MANAGEMENT
Legal department for disputes.
As stated above the functions involved in material The structure of purchase department and relationship
management are: with other departments is illustrated in Fig. 1.6.
1. Purchasing
Desigm
2. Material handling n
3. Inventory.
1.5.1 Purchasing
• The purchasing function has to be efficientand there epispths &
legal, urchasi rK
should be effectivecontrol over the expenditurefund partm
and inventory flow of material.
Though purchasing has to be done at a reasonable
onstrü ateria
price, quality of the material has to be maintained and ction receiving
it is not necessarythat the purchase be made always store
from the lowest bidder as it may not maintain the
Fig. 1.6
needed quality.
1.5.2 Method of Purchasing
For maintaining the quality, the• specifications laid
down should be in details without any ambiguity. It is Various methods of purchasing are adopted depending
necessary that the right quality material should be upon the conditions,time and urgency. The two popular
purchased at right time at reliable right rate. methods adopted for market purchasing are :
The suppliers from whom the purchase is made should 1. Inviting tenders
be reliable. 2. Rate contract purchase.
PROJECTMANAGEMENT (BATU CIVIL) (1.5) INTRODUCTION TO PROJECT MANAGEMENT
In the first method,.a list of reliable suppliers is A sample purchase order is as shown below :
prepared for different materials and tenders are invited xyz co. LTD.
from them. Construction Department
The information about the quality of the material Tel. : 12345678 fax : 87654321
requiredin the form of specifications and the quantity
Purchase Order
and the period of supply is given in the tender.The
Supplier's Name P.o. No. :
tenders are published in leading newspapers.
Address : Date :
• The suppliers desirous of accepting the offer for supply
of the material are required to quote their rates for the Site :
supply. Dear Sir,
After receiving the tenders, a comparative statement is We are pleased to place this order for the
prepared and order is placed with the firm normally following material, subject to the terms and conditions
quoting the lowest bid. printed overleaf.
However,in some cases lowest bid may be rejectedif
Sr,- Description* Branå Unit Qty. 'Unifi Am
there are reasons to do so depending upon factors like Maw
with sizes
past experience etc.
1.5.3Procurement of Materials
• Materials for construction are procured by direct
purchasing or obtained from the stores.
• For small works and small organisationsthe materials
are purchased directly as and when required keeping
particular purchase schedule.
• However, for big organisations the purchasing etc. is
done by the materials management department and is
procured for the construction from the stores. Supplier's Quotation No. : Guarantee / Warranty:
• The purchase department has the following Octroi : Extra / Inclusive Requisition No. :
responsibilities and functions :
Freight: Extra/ Inclusive
1. To get the right quantity of materialsof the
Delivery Schedule :
required specifications, at the minimum overall
cost including transportation etc.
Director
2. To adopt the proper procedure for the purchase.
1.5.4 Material Handling and Control
n purchases made by Government and Semi-Govt. bodies,
ublic undertakings, proper procedures has to be
adopted It is the movement of material from receiving to
nd rules and regulations have to be followed. finished goods storage through manufacturing or in
process storing.
hereare following methods of purchases.
locally In Civil engineering project, it is the movement of
Market Purchasing : Method adopted (for
materialsto its use as it is a raw materialor after
available materials by private concerns.
by processing if any in actual construction.
Centralised Purchasing : Method adopted Timber may be purchased as a raw materialand then
Governmentbodies and also when the construction may be processed at sight for preparationof doors
organisation has several projects undertaken
and window frames, shutters or trusses which are used
simultaneously.
in construction.
Rate Contract Purchasing : This is for specific items Material handling, therefore, is the movement from
which are required regularly in large quantities. raw material to finished goods ready for dispatch.
Normally rate contract is for aperiod of one year.
PROJECT MANAGEMENT (BATU CIVIL) (1.6) INTRODUCTIONTO PROJECT MANAGEMENT
Material handling also includes the supply of, material should always be kept clean. The surplus material and
at the place of use from the stores or the market and the scrap should be disposed bff and the value should
involves transportation. be recovered.
• The transportation cost of the materials in India is The materials used for auxiliary services (e.g. materials
quite high and at times good time is also required for used for scaffolding, centering etc.) should be properly
transportation. and economically used and wastage and wasteful use
Material handling system has to be efficient with good of such indirect materials (Bamboo, corrugated iron
control over the same. sheets, roaps etc.) are avoided on large constructions.
Materialjssue sli is used for issuin material. The small tools and plants such as ghamelas, pawadas,
XYZ CO. LTD. pickaxes etc. are properly used and they are not
Construction Site misused so that their life is not reduced.
Material Issue Slip 1.7 INDENT, STORING OF MATERIAL AND
No. : ISSUE
Site : 1. Indent
Date : cement,
For Governmentworks some materials such as
To Store : are
steel, G.I. Sheets, asbestos sheets or some tools
Issue to Contractor :
supplied by the Government to the contractor, as per
Throu h His Re resentative
the conditions of contract.
Item with Building No. / Location the
Quantity The materials to be supplied are specified in
Size contract. For receiving such materials from the
Government stores the contractor has to put up a
requisition in writing in prescribed form which is called
Issued by indent.
a
Storekeeper : The indent is in prescribed Form No. 7 and is in
Recd. b booklet form, each page in triplicate. This indent book
, is machine numbered and consists of indent,
General Purchase R ister For r ates counterfoil and invoice.
sr. DateCPR Challan Truck Bill Bill Rate Amt. Sign Remark With each subdivision of Government Engineering
No. Q , Date Department, there is an indent book and for the
required materials the indent is prepared by the Sub-
divisional Officer or the Deputy Engineer or the
Assistant Engineer incharge of the subdivision and sent
1.6 ECONOMICAL USES OF MATERIALS to the officer incharge of the stores.
Economic use of the materials is of prime importanceand The indenting officer will fill the details on the indent
is one of the most important responsibilitiesof Materials and the counterfoil and the officer incharge of the
Manager. The economic use of materialsleads to economy stock will issue the materials as per the availability in
in general and reduction in time of completion of the the stock and will correct the indent according to the
project. To achieve this, the materials manager has to look actual material issued and accordingly will make the
carefully to the following points. entries in the invoice and will send the indent book
Costly material like cement, steel, timber etc. is stored back to the indenting officer.
in closed space with lock and key arrangement and After receiving the materials, the indenting officer will
they are properly stacked and stored and only the return the invoice to the stores officer after signing the
required material is issued. invoice as acknowledgment of having received the
Scattering of other materials like sand, coarse material as per the invoice.
aggregate is avoided and they are stocked properly so The invoice is the voucher for the issue of the materials
that loss is avoided. from the central stores.
If excess material is supplied from the stores, this If the material is issued to the contractor, the signature
excess material is recovered and redeposited in the
of the contractor is taken on the invoice and the cost
stores.
of such materials issued to the contractor is recovered
All the surplus materials and the scrap should be s
constantly collected from the worksite and the stores from his running bills at the issue rate.
PROJECTMANAGEMENT (BATU CIVIL) (1.7) INTRODUCTION TO PROJECT MANAGEMENT
For such materials unstamped receipt in triplicate is 2. Storing
obtained from the contractor, where in allfthe details
On any civil engineering works different types of
of the materials issued are incorporated. A form of
indent is given below.
materials are required simultaneously and hence the
storing of materials has to be done systematically so
System of indents may be followed by very big
constructioncompanies which may have central stores that the materialscan be received, stored and issued
and where some works are in progress in nearby areas. for use without any difficulty.
FORM OF INDENT For such storing a proper layout of the stores is very
No. :
essential. Proper arrangements are also necessary for
Site : security of the materials from theft, and from
Requisition Slip Date : manhandling.
Materialslike petrol, diesel etc. have to be stored very
r. Descrip New Deli' Total Store Remark/ For Purchase carefully and absolute care has to be taken for them.
o. .tionof Qty. very Recei- Regd. Material Dept. Remark • In general, materials are stored as per the nature of the
Material Reqd. Reqd. ved up Page for Bldg.
upto to Date
materials and their cost. The stores may consist of
No.
Date sheds and open area with compound wall or barbed
wire fencing.
red Order•
Construction Materials are Generally Stored as Below:
to ed no.
& Date
• Materials like cement, timber, doors and windows,
grills, paints, fuels, small tools are störed in sheds.
Proper arrangement is made for stocking cement bags,
timber etc. Fuels and any materials which can catch-fire
easily should be stored separately. Such stores must
Scrolling have locking arrangement.
D & D / Project Coordinator Materials like sand, rubble, coarse, aggregate, bricks
can be stored in open area without any enclosure.
Site Name : Group GRN No. :
Materialslike steel, bituman drums, pipes, C.I. and A.C%
SupplierName : Date : and their fillings may be stored in open space with
enclosures.
PurchaseOrder No, : Goods Truck No. : Materialslike small parts, pipe fitting, door fittings etc.
Receipt to •be stored in sheds and are properly stored in
ChallanNo, & Date : Note Time : containers, properly labelled.
Perishablematerialsrequiring careful handling may
be
stored in open sheds.
Sr. Description Received Accepted Rejected Remarks Security Measures for the Stores May Include
o. Qty. QW. Qty.
the
Following :
Providing chaukidar and/or other security
staff.
Adopting gate pass system.
Providing locking arrangement for sheds.
Providing double lock systems for the
materials
issued by Government to the
contractor on
Government works.
Proper maintenance of the stores,
and also stores
account is very important. Annual
stock verification,
inventory etc. are the routine
part of stores
management but surprise checks are
StorageIncharge QA also carried out.
Incharge Project Manger Proper account of receipt, and
issue of the materials is
maintained and total value of
the stock in stores
PROJECT MANAGEMENT (BATU CIVIL) (1.8) INTRODUCTIONTO PROJECT MANAGEMENT
should be known. The stock verification is carried to transportation of the different incoming materials and
verify if there are any excesses or shortages and then outgoing materials has to be assigned to separate
the responsibility of such has to be fixed. person or separate department.
must have many
Also some times losses are written off and surplus As such the purchase department
materials are disposed off after taking due permission subdivisions specialising in different lines depending
with proper procedures. Proper registers are upon the requirements.
maintained for the stores. In case the money involved in purchasing is very high
3. Issue of Materials there may be a purchase research department
Any issue of materials from the stores should be involving continuing research regarding availability of
against the authorised indent only. If the central store various materials, their costs trend and their substitutes
record of
is very big one, the issue can be systematized by fixing if any. This department may keep a thorough
the days/dates of issue of different materials or market fluctuations and try to make use of it by
days/dates for different subdivisions or sections. purchasing inventories at the lowest cost.
However, on every day the stock books must be An additional subdivision may keep all record such as
updated and balance of every item and value of stocks invoice checking, order-writing, record keeping etc.
must be worked out everyday. Such systematic up-to-date record keeping will be
Duties of Store-Keeper: useful in bringing out any information needed at any
To receive material on site. Check its specification and time which will be useful to the purchase department
quality. in procuring quality materials in required quantity
• timely at low cost.
Make , necessary , entries in the general, purchase
register. A sample of the purchase organisation working under
Materials Manager may be as under.
Keep separate registers for important items such as
cement, steel, etc. Materials Manager or Purchase Manager
1.9 HUMAN RESOURCE MANAGEMENT There had been a requirement of more field work
hours per dollar of contract.
(MANPOWER PLANNING)
The construction industry lagged behind other
• Human resource is the most valuable asset in
industries in development and in the application of
construction indüstry. labour saving ideas and in finding several measuresto
Human resource practices are mostly concerned with substitute equipment for labour.
gaining value through increased skills, Productivity, The casual nature of the employment in the
autonomy, contribution, and cost consciousness. construction industry makes planning a vague exercise.
Productivity is one of the most important factors The construction industry is one of the largest sectors
affecting the overall performance of any construction employing large number of people, providing work to
company. significant proportion of the labour market and
providing significant share of the world Gross
Construction industry involves in its vicinity a diverse
Domestic Product (GDP).
labour force, contributing towards the long and
Any construction project involves skilled manual labour
enduring "Process of Creation". In India, construction
which gets support from management.
ihdustry employs over millions of people and provides
It is a duty of the managementto co-ordinatemany
millions of additional support jobs in related fields.
professional, construction and supplier organizations
Yet, it is least lucrative profession for many as it whose involvement can change through the course of
involves peripatetic work schedule, along' with-it job the project.
insecurity associated with poor working conditions, The dynamism that involves in the process and the
health and safety records and employee welfare need to integrate a wide range of occupational
provisions within the industry. cultures, gives the construction one of the most
The main reason behind the construction industry to complex project related industry in which there is a
be poorly regarded is generally thought to stem from need to apply good HRM practices.
the nature of the work •andthe terms on which the The process of manpower planning involves
labour is recruited. Determining the objectives of man power
planning,
The construction industry in number of countries has
Preparation of current man power inventoryn
also been characterizedby the outsourcingof labour Demand forecasting,
through sub-contractors and other intermediariesthat Supply forecasting,
prohibits them from taking the advantage of Estimationof the man power requirements,
employment schemes. Making an action plan for redeployment and
Over and above, it has been portrayed as the image of redundancy,
discriminatory "Macho culture". Moreover, in number Determiningjobs,
of developing nations there are no safety measuresfor Requirements of the jobs to be filled,
Employment plan,
labourers.
Trainin and develo ment Ian.
The managers in this industry are often heard saying
1.10 CHALLENGES OF HUMAN RESOURCE
our people are our most important asset'. However,
IN CONSTRUCTION SECTOR
Human Resource Management (HRM) in the
• Matching skilled labour supply and demand.
construction industry is severely underdeveloped as • Creating a responsive apprenticeship system.
compared to the other industrial sectors. • Establishing an innovative training system.
This we may owe to the fragmented structureof the • Facilitating worker mobility.
construction sector. However, industrial leaders have Matching the projected demand for qualified trade people
started realizing •the importance of the 'human with the future supply of skilled labour :
Initiatives :
resource' in this competitive environment.
Career Awareness :
As stated by Paul Teicholz (1994), there was decline in • Improve the image of construction occupations.
the construction industry, Over the past 40 years the • Promote career as a viable option for youth.
industry increased at an average compound rate Of • Share generic aspects of program with the
0.59%/year. construction industry.
PROJECTMANAGEMENT(BATU CIVIL) (1.11) INTRODUCTION TO PROJECT MANAGEMENT
Having a focused sub-project for each milestone gives Fundamentally,the CPM and PERT networksare the
those task leaders a framework for planning and two techniques of project management which are used
tracking project activities. in planning, scheduling and controlling the different
The MilestoneChart is the schedulereportingformat operations involved in the project.
that can be used on full-scale and complex projects. The basic theory and the method of graphical
Project Reqt's
start definition
Design
freeze
representation of the network in both the above
methods are same.
.15 CRITICAL PATH METHOD (CPM)
Feb Mar Apr May Feb.
Fig. 1.8 Critical path method is based on mathematical
1.13 DEVELOPMENT OF NETWORK FROM calculations and it is used for scheduling project
BAR CHART activities.
Ton overcome the limitation of bar chart for not This methodwas first introducedin 1950s as a joint
showing the interdependence of activities clearly, a venture between Remington Rand Corporation and
modification is done in which arrows are used. DuPont Corporation.
Consider an example in which activity. In the critical path method, the critical activities of a
(1) is the starting activity, (2) and (3) Starts only after program or a project are identified.
completion of activity (1), Activity (4) cannot start Critical activities are the activities which have a direct
before completion of activities (2) and (3). impact on the completion date of the project.
This can be shown with the help of arrows as below CPM network are usually used for repetitive type of
projects, where fairly accurate estimates of time can be
made for the activities of the project.
The activities of these projects are characteristically
2 subject to relatively small amount of variation. Hence
CPM is not suitable for research and development type
3 of projects.
In research or innovative development projects, the
4 stress is on events and in such projects which are event
oriented 'Project Evaluation and Review Technique'
Fig. 1.9 (PERT) is used.
If the bars are representedas a node, the same bar Examplesfrom fairly diverse field where application of
chart can be shown as a network using arrows and CPM can be made:
circles as below:
Building a new bridge across river ganga,
2
Constructing a multi-storeyed building, extension
of a factory building etc.
3 4
1.16 TYPES OF CPM NETWORK
Fig. 1.10
1.16.1 CPM Method of Project Planning
.14 TYPES OF NETWORK
CPM Method of Project Planning involves identification
Networks are basically two types :
of specific activities, their time of completion i.e.
1. Critical Path Method (CPM)
duration and their interrelationship.
2. Programme Evaluation and Review Technique
In general, there are two types of networks used.
(PERT)
The CPM network is activity oriented whereas the PERT 1. Activity On Arrow (A-O-A) type of arrow
network is event oriented depending upon the diagramming.
importance of the activities and events in those 2. Activity On Node (A-O-N) type of precedence
methods. diagramming.
(1.14) INTRODUCTION TO PROJECT MANAGEMENT
PROJECT MANAGEMENT (BATU CIVIL)
c D
1 2 3 4
1. Activity on Arrow Type Network
• As said earlier the events are shown by numbers in
geometrical.figure like circle or square and the 5
activity shown and by an arrow.
Fig. 1.11
The head and the tail of an arrow represent event.
The event is a point and it does not,consume any 2. Activity On Node Type Network
time. The event is also called as Node or The problem in Activity On Arrow type or AOA network
connector. is necessity of Dummy activities for maintaining the
The activity is representedby letters like A or B or logic and the right sequence in the network.
C or D ... etc. They are also representedby pair of This increasesthe length of the tables, enlarges the
numbers as 1-2, 2— 3, 3—4 etc. network graph and takes time for calculation work and
In activityi —2, the points 1 and 2 are the two increasethe complexityof the networkfor large and
nodes of •theactivity. Out of the two nodes, 1 is a complex projects.
'From' node and-2 is a 'Tot node and the From Another type of network is the Activity On Node
node must be a lower number than To node. diagram or precidence diagram which overcomes the
In this way, the direction of activity arrow is clearly problem of AOA network.
established. In AON network diagram, the activities are represented
The project is <ivided into different activities, inter- by boxes and arrows, and are used for designating the
relationship between the activities and the inter-relationship between the activities. The AON
sequence is decided and the CPM diagram is diagram is simpler to prepare and is easier to explain.
prepared. It presents a clearer picture of the project as compared
Fig. 1.11 shows construction of network by Activity to AOA diagram.
On Arrow method (AOA). The AON diagram for the same problem (used for
Activity Activity Description Inter Duration in AOA) is represented in Fig. 1.12.
Symbol endency Days Both methods have their own advocates. The principal
Study of plan layout Start Acüvity under both the methods should' be understood. But
the A —O —A method was first developed and is very
B Clearance of site Follows A
widely used.
C Earthwork in Follows B 6
Further,the use of numbersfor events in A —O —A
Excavation method has made it amenable to programming on
D Laying of foundation FollowsC 5 computer and the Dummy activities used make the
Concrete Constant after B 3
logic more clear. Hence A —O —A or Activity on Arrow
method is more popularly used in CPM.
F of Bricks Follows D and E
Procurement 10
Brick work.
E Procureme
of bricks
Fig. 112
1.17 TERMINOLOGIES IN NETWORK It is, therefore,the commencementor completion of
1. Event and Activity an activity. It does not consume time or resources.
Event is well-defined point or stage or accomplishment Activity is a specificjob or unit task in any project and
of the project. event is start or end of the activity.
An event is that particularinstant of time at which In construction project, excavation for foundation is an
some specific part of a plan has been or is to be activity whereas starting of excavation for foundation is
achieved. an event.
PROJECT MANAGEMENT (BATU CIVIL) (1.15) INTRODUCTION TO PROJECT MANAGEMENT
An event is a well-defined point in a project and hence i.e. tail event is 5 and head event is
is represented by a node. Fig. 1.14
The shape used to represent the node may be (i) Activities can be identified with the use of English
circular, (ii) square, (iii) rectangle, (iv) oval shape or (v) alphabets•suchas above activity is A.
any other regular geometrical figure such as triangles
Activity A —Excavationof earth work
(see Fig. 1.13).
Activity B —Foundationconcrete
However, vgenerally a circle has been chosen to
ActivityC —Constructionof brick work in foundation
represent the nodes. and plinth
*Eventsare numbered for their identification and these Activity D —Layingof D P C
numbers are written inside the geometrical figure Activity E —Brickworkin superstructure
representing the node.
1.17.1 Different Types of Activities and Their
Inter-Relationship
A project is broken into different types of unit tasks or
Circular Square Rectangular
activities.
Depending upon their interdependency, some
activities are to be taken serially whereas some of the
Triangular Oval shape activities can be undertaken simultaneously which are
Fig. 1.13 subsequently called as predecessor Activities and
2. Activity Successor Activities.
It is the actual performance of a task or a unit job. It is Depending upon their way of occurrence, the different
a recognisable part or item or operation of the project. activities can be termed as below :
1. Parallel Activities
It, therefore, consumes time and resources in the form
Activities which can be undertaken and completed
of manpower, material, use of machinery or any other
simultaneouslyand independently to each other are
facility.
called parallel activities.
It is a positive specific tangible and meaningful effort 2. Serial Activities
having a proper description understandable by all Those activities which are performed immediately one
•concerned with the project. after the another are called serial activities. They are
Representationof Activity dependent on each other and cannot be performed
independently.
Activities are represented by simple arrows in network
3. Predecessor Activities
diagram.
Activity or number of activities which are necessary to
The arrow runs from left to right generally so that the
be performed before a particular activity is undertaken,
tail is towards left and the arrow head is towards right.
they are called predecessor activities. Unless these
The tail of the arrow represents the start of the activity predecessor activities are completed, the next activity
and arrow head represents the end of the activity. cannot commence.
PROJECT MANAGEMENT (BATU CIVIL) (1.16) INTRODUCt10N TO PROJECT MANAGEMENT
In Fig. 1.15.
3
C and E are parallel activities, D and E are also parallel
activities. Fig. 1.16
A and B are serial activities.
Event (1) —Leave A
A is predecessor activity of activity B.
B is predecessor activity of activities C and E. Events (2) and (3) —Reach B
B is successor activity of activity A. The two activities P and Q are represented as below.
C and E are successor activities of activity B. Activity P —representedas 1 —2
F is successor activity of activities D and E. Activity Q -represented as 1 —3
5. Dummy Activity or Dummy [Feb. 161
Since Activity 2 —3 is a dummy activity practically event (2)
A Dummy activity is an imaginary activity which does
and event (3) are same i.e. reach B. But to represent that
not exist in the Project activities.
activitiesA and B are different, a dummy activity 2 —3 is
It is used in the netwotk diagram to show dependency
introduced so that activity P or 1 —2 represents activity
relationship or connectivity between two or more
that person with scooter is moving from A to B and activity
activities.
3 representsactivity that person with car is
It does not consume any time and resource
moving from A to B.
It is representedby a dotted arrow.
With the help of dummy activity, logical sequence is
Activity2 — 3 is dummy activity for first person with
scooter. The same can also be represented meaningfully as
maintained and confusion is avoided.
below.
Dummy serves the grammatical purpose as well as
logical purpose. 2
Grammatical Purpose of Dummy
It will be illustrated with following example. Two 1 3
persons are to leave place A and to go to place B,
The first person uses a scooter and second uses a car. Fig. 1.17
Event (1) is leave A whereas event (2) is reaches B. Events (1) and (2) —Leave A
This cannot be properly representedfor the two
Event (3) —Reach B
persons as the diagram would be as shown below.
p Activity 1 —2 is Dummy activity.
1
Activity P is 2 —3 activity for person with scooter.
Activity Q is 1 —3 activity for person with car.
Fig. 1.15
Activity 1 —2 is Dummy activity for first person.
Activity P —Personwith scooter going from A to B.
(Activity 1 - 2) However, it should be noted that dummy activities
Activity Q —Personwith car going from A to B. should be provided only if it is necessary.
(Activity 1 —2) Provision of redundant dummy in the network may
With this type of representation,uniquenessof the lead to confusion.
identification is lost as Activity P and Activity Q though
Hence in initial stages, dummy activities may be
different, are representedand treated like one single
introduced liberally which can further be removed by
activity. (1-2) this inconvenience leads to mistake and
has to be solved suitably for which dummy activity is careful inspection of the network wherever such
used. dummy activities are unnecessary.
PROJECTMANAGEMENT (BATU CIVIL) (1.17) INTRODUCTION TO PROJECT MANAGEMENT
ConstruCtioå
C. Putting Prepare the 4
pipes for water Wall plasterin
3c connection house plan
Construct 58
Completing«
the house
woodworki2
c Fix the door 2
/ windows
Fig. 1.18
D Wiring the 2
Solution : house
Activity 1 —2 Construction of Brickwork. Paint the c 1
Polish the D
Activity 2 —4 Fixing GI pipes for water connections.
doors /
Activity 2—5 . Completing woodwork in doors and windows
windows.
Solution:
Activity 5 —6 Plastering the brickwork, Fix the doors (2 days) Paint the house
4 (1 day)
3 Prepare the Constructthe C
house plan house
c 3
2 6
(4 days) (58 days) D
5 Polish the doors
4 Wiring the (1 day)
house (2 days)
Fig. 1.19 Fig. 1.20
1.17.2 Fulkerson's Rule Example 1.3 : UsingFulkerson'smethod,number the events
in the network shown below.
• An event represents the accomplishment of task.
• In a network diagram, beginning and ending of an
activity are represented as events.
Step 1: Number the start or initial event as 1.
Step 2: From event 1, strike off all outgoing activities. This (a)
Example 1.4 : Draw a networkdiagram forprojectlaying a Example 1.5 : Draw the network for the activities and
drainage pipeline. events shown in the table given below
Solution : The project can be , broken. into different Activity Events / Duration Activity Inter-Rélationship
activities events as shown below Nodes in Days
Activities : Layout (10 —20) Preceeding Succeeding Parallel
B Excavation .fqr_trenches(20 -- 40) Node Node
Procurement of pipes (10 —30) 10 20 3
Pipe laying in excavated trenches B 20 30 3 C
(40 —50) 40 4
C 20
E- Pipe testing (50 —60) D 30 40 0
Refilling of trenches (60 —70) E 30 50 6 D
Events : A Start of the project F 40 50 2
Starting layout G 50 60 4
2- Layout completed, excavation started
Solution :
3- Procurementof pipe started
Pipes procuied 6
3
Excavation completed, Pipe laying DIO 50 4 60
1
3 20
started
c
2
Pipe laying ended testing of pipes 4
30
started
Pipe testing started earth filling started Fig. 1.23
8 Earth filling completed Activities are denoted by Letters A, B, C ... and also by the
Predecessoi Even Sugcessor ven tail node and head node. The tail nodes and head nodes
are in general denoted by I nodes and J nodes. The
Start of layout Layout completed
duration of the activity is shown below the activity arrow
Start of Excavation Layoutgompleted Excavation and identification of the activity above the arrow. Duration
completed
of an activity is the estimated time required to complete
Procurement of pipe Procurement of pipe the activity.
started completed
Pipe laying started Excavation Pipe laying
1.18 TIME ESTIMATES
completed, pipe completed. The time duration used for different activities is any
procured convenient unit consistent throughout the network.
Pipe testing started Pipe laying Pipe testing The unit is usually either days or weeks.
completed completed. For estimating time duration, a normal work crew
Refilling started Pipe testing Refilling of trench depending upon the type of the work and experience
completed ends. is assumed.
Pipe Pipe Refilling of
laying
Generally in CPM the duration of the different activities
Layout Excavation testin tranche
2 4 6 in the project are deterministic and can be estimated
fairly precisely.
remeot
3
Depending upon the duration of different activities,
Pipe the project duration will be decided.
2 5 6 7 1.18.1 Event Times
Layout Layout cavation Pipelaying Testing Earth
For each event two type of times are expressed
A start completed completed completed completed filling depending upon occurrence of that event.
Excavation Pipe laying Testing Earth completed
Pro ect Starts starts starts Filling Earliest Occurrence Time (EOT) of any event is the time
starts
3
stars wherein al] the activities emerging to the event are
4
ProcurementOf Procurement
of completed in the least period possible. This is
pipestarts pipecompleted computed by adding the duration of all the activities
Fig. 1.22 along an activity path leading to that event.
PROJECT MANAGEMENT (BATU CIVIL) (1.19) INTRODUCTION TO PROJECT MANAGEMENT
If more than one activity path is leading to that eventi t (ij) = duration of activity i •j i.e. intervening
then the maximum of earliest occurrence time of the activity
different activity paths is taken as Earliest Event The first event in the- network occurs at zero time and
Occurrence time and is denoted by TE.
with this basis the EOT of 41 •the 'ubsequent events
EOT for an event = EOT of preceding event + Duration and project duration can be calculated.
of activity This is the minimum-period in which the project can be
EOTj = EOTi + tij completed.
or 1.18.3 Backward Pass
E E ij
Similarly, Latest Occurrence Time (LOT) for any event is Normally, the earliest event occurrence time of last
the maximum time for completion of any event event is the project duration and the same is taken as
the latest event occurrence time of the last event.
without causing any delay in completion of the project.
This time is computed by subtractingthe durationof However, if there is any •imposed duration for the
all activities along the activity path from the project that is taken as the _latest_event occurrence
time for the last event.
concluding event to the event in question.
Assuming this latest event .occurrence time of the last
If more than one event is emerging out, then the latest
event, sequentially the latest event occurrence time for
occurrence time is least of the time calculated from successive predecessor events can be calculated.
different activity paths.
The latest event occurrence time for any event in the
LOTi = LOTj-tij
I
i.e. TL - FL tij network is the latest allowable event occurrence time
for the succeeding event minus the duration of
EOT for an event = EOT of preceding event + intervening activity.
Duration of leading activity.
LOT for an event = LOT of following event —Duration LOT(i) = LOT(j) - tij i.e:TLl -tij
of leaving activity. where, LOT(i) = Latest _event occurrence time of ith
In case more than one activities are leading to an event i.e. preceding event
event, EOT is taken maximum of all leading paths, •
LOT(J) = latest event Occurrence -time of jth
while LOT is taken minimüm of all activity paths event i.e. succeeding event
leaving the node. t(lJ) duration of activity (i j) i.e.
EOT is calculated by forward pass method and.LOT is intervening activity.
calculated by backward pass method. In case there are more than one bursting activities
1.18.2 Forward Pass originating from event), the LOT(i) is calculated by all
The minimum or expected duration of any project is possible paths and whichever is minimum is taken as
the LOT for that event.
the earliest occurrence time of the last event. Hence, to
find out the duration of the project, one has to find out Thus, starting from the last event, LOT of all the events
EOT of last event in the network of the project.
can be calculated and this will lead to finding LOT of
first event as zero. This will help in finding the
This is done by calculating thé EOT for each event of allowable delay in occurrence of different events
the network by forward pass method till the last event without affecting the overall duration of the project.
is reached. The allowable delay in occurrence of any event is the
In case of merge events, EOT is calculatedby all the difference between the LOT and EOT for the-event.This
possible paths and the maximum of values of EOT allowable delay is the slack period of the event.
calculated from different paths is considered EOT for 1.18.4 Activity Times
that event. This will give the duration of the project.
• For the different activities there is a time of start and
EOT(j) = EOT(i)+ t j time of finish.
Where, • -- Earliest occurrence time of jth event
EOT(J), For forward pass,
i.e. succeeding event Activity finish time = Activity start time + Duration
EOT(i) = Earliest occurrence time of ith event and for backward pass,
i.e. preceding event. Activity start time = Activity finish time —duration
PROJECT MANAGEMENT (BATU CIVIL) (1.20) INTRODUCTION TO PROJECT MANAGEMENT
Represents
For the different activities, following times are Represents name of activity Represents
calculated : EST of D EST of F
(6) (8)
7 (8)
(3) (6) (6)
c
(4 3
(10) (2)
Fig. 1.32
ActivityDurationEST EFT LST LFT TF FF IntF IndF The details of preparing the network and calculation of
3 6 3 o 3
floats will comprise of the following steps
3 0 3
Step 1 : Table of inter-relation between different activities.
of networkwith the help of above
Step 2 : Preparation.
c 4 3 7 6 10 3
table.
5
D 6 3 9 8 14
Step 3 : Calculationof EST and EFT of differentactivities
by Forward Pass Method.
Step 4 : Calculationof LFT and LST of differentactivities
by BackwardPass Method.
Step 5 : Marking the Critical Path.
Step 6 : Calculation of Project Duration.
step7: Calculation of Total Float and Free Float.
All the above are worked out in tabular form
Srs Descriptiono Job orthe* i VActivity„ Estimat
Example 1.7 : Analysethe workof constructionof a Steel Activity symboÉ Duration in
Rolling Mill and construct a CPM Network for the same.
Calculate the project duration after marking the critical Prelimina Investi ation 5
path. Also calculate the Total Float and Free Float. 2. Desi n of Buildin 10
Solution : The work of erectionof a steel mill on analysis 3. Preparation of specifications of c 4
can be divided into different independentjobs as shown machine ande ui ment
4. Procuring Machinery and D
below. The estimated duration of completion of these 32
E ui ment
activities is also indicated in table below. The duration of
5. Construction of Building 12
each activity has been estimated by proper analysis and Foundation
with experience of duration of similar activities undertaken 6. Construction of Machinery 7
in earlier projects. The correlation and sequence of Foundation
different activities is properly studied and if necessary 7. Construction of Building 14
dummy activities are introduced to maintain proper flow Su erstructure
and sequence of work. Conti...
PROJECT MANAGEMENT (BATU CIVIL) (1.25) INTRODUCTION TO PROJECT MANAGEMENT
8. Layingunderground
pipes, Example 1.8 : Work out the project duration and indicate
conduits and other anciliary
the critical path. Also calculate the interfering float.
utili
Installation of Machinery and 18 05
E ui ment 06
10. Installation of Electrical Driving 07
12 08 15
Unit 12
Installation of Wiring and 10 15 27
01
Control E ui ment 05 02 29 03
12. Final Checkin and Testin
13. Clearin ite
10 37
Solution : 08 02
Sr. Åcüvity Duration Preceding Succeeding Remarks 35
Activ Activi
Fig. 1.34
Starting
10 Activity
Critical path = 1-2-4-5-8-9 & 1-2-8-9
Project Duration = 40 days
32 Activity Duration EST EFT LST
12
1-2
14 1-3 05
08
18
01
10. 12
10 2-8 05 12 21. 26 14 14
12. 3-6 08 13 19 27 14
End
12 19 19
Activi
07 19 26 19 26
(12) (14
5-7 02 19 21 27 29
(4)
10 13 15 27 29 14
(10) (10) (9) (2)
18)
(5
03 21 24 29 32
Example 1.9 : For construction of a small residential block,
(4) (32) (12)
prepare the network and calculate the duration of the
Fig. 1.33 project by CPM.
Total duration of ro•ect : 80 da s. Solution : The project is broken into differentunit jobs or
Du o ES EFT ST L Remarks' activities and depending upon the resources available, the
Critical activity duration is decided.
Table is prepared for the different activities with the
Critical
predecessor and successor activity as shown below
32 41 41 Critical
Sre Activity Description Duration Preceding ucceeding
41
in Activity Activity
15 22 34 19 19
Weeks
A Excavation,
15 19 55 59 40 40 Foundation, Plinth,
18 41 59 41 59 Critical Mason and DPC
12 41 57 69 16 16 BB work in
59 69 59 69 Critical superstructure
Critical including fixing door
69
and window frames,
78 80 80 80 Critical
castin lintels,shelves
Critical path : A-C-D-I-K-L-M
Conti...
PROJECT MANAGEMENT (BATU CIVIL) (1.26) INTRODUCTION TO PROJECT MANAGEMENT
(2) (3)
Fig. 1.35
Activity Duration EST EFT LST LFT Activi DurationEST EFT LST LFT IndF Intf
eeks 1-2
1-3
14 14
14 17 14 Example 1.11 : Find out EST,EFT,LST,LFT, TF, FF, IDE and
17 19 17 19 IF for the following network diagram. Also draw critical path.
14 16 19
21 23
[Nov. 15, 8 Ml
21 23
19 21 19 21
14 11 14
15 19 23
Total duration of project = 23 weeks.
Critical
pathA-C- B-J -E- F-I-H 11
12
Example 1.10 : Calculate EST,EFT,1ST,LFT,IDF and IF for
the following activities. Tabulate the result with sample
calculation. [Ma 15, 6M] Fig. 1.37
Activi 1-2 1-3 Solution : Calculation of various arameters :
Duration in 'Da Activi Duratio ST EFT LST LFT Ind.F
Solution : The network is drawn as given below 14 19 14 14
14
12 19 26 14 -14 12
19 26 15 14
12 12
14
12 20 26 34 14 14
12 23 12 23
10
Fig. 1.36 12
Critical path = 1-3-4-5 12 21 23
Project Duration = 14 days 23 34 23 34 0
Now Draw the network.
PROJECT MANAGEMENT (BATU CIVIL) (1.27) INTRODUCTION TO PROJECT MANAGEMENT
5 14 25 25
24 36 46
12 10 Fig. 1.40
11 24 36 46 Total project duration 34 days
Critical path = —4—5 —6
17
10 Durajoo. EST EFT LSI LFT Remark
1-2
36 1-3 14
Fig. 1.39 11 18 18
Critical path = 1-2-4-6-8-9-10 14 18
Pro•ectduration = 46 da s
10 20 25
uratiom
4-5 18 25 18 25
1-2 18 20 32 34
2-3 26 31 5-6 25 24 25 34
2-5 32 36 EXERCISE
3-10 15 24 15 46 1. Explain the two important methods of project
11 18 11 18 planning in brief and bring out the difference
Dumm between the two.
5-10 10 18 36 46
2. What do you understand by Bar chart ? With suitable
example, describe the process of construction of
18 17
Gantt's chart.
12 24 36 24 36
9-10 46 36 46 3. What are different strong points and shortcomings
10 36
Critical path = 1-2-4-6-8-9-10 of a Gantt's chart ?
PROJECT MANAGEMENT (BATU av1L) (1.28) INTRODUCTION TO PROJECT
4. How the different shortcomings of bar chart can be 16 Inter-relationship between the different activities in a
removed ? project is as shown below. Draw the network and
5. How milestone chart differ from a bar chart ? How it find the critical ath.
overcomes some of the short-comings Of bar chart ? Activity Predecessor Successor. Duration
6. Give out the advantages and limitations of milestone ctiv
chart. 6
7. Draw the bar chart for a project with 8 different 8
activities as shown below and calculate the total time c D 9
of com letion. c 4
B 3
E 6
3 B 10
2 5 *Cannot 8
c 1
3 start unless
4 D 5 60% work of 2
5 C* Cis 4
6 5 D completed. 6
7 6 c 5
8 5 Last Acti 17. Define Free Float and bring out its importance. How
If there is increase of 3 days in the time of is it determined ?
completion of agtivity A, calculate the corresponding 18. What are logical errors in case of CPM ? Draw
delay in completion of the project. sketches to illustrateyour answer.
8. What is AOA networkand AON network? Explain 19. Define
with suitable examples. (i) Interfering floats (ii) Independent float
9. Differentiate between CPM and PERT network. 20. Compare Gantt chart with CPM network.
Explain where each is used. 21. Explain with sketches, the various relationships in a
10. What are different types of events ? Explain with PrecedenceNetwork.
examples. 22. Give definitions of following with suitable example of
11. Describe the different types of activities in a network
each
and explain the use of dummy activity.
(i) Dummy activity, (ii) Critical activity, (lii) Critical
12. What are difficulties in logic in the network ? Explain
looping and dangling. path, (iv) Concurrent activity, (v) Preceding activity,
13. What åre the different rules to be observed in (vi) Succeeding activity.
framing of netWork? 23. Bring out importance of materials. management in
14. A project consists of 6 events ind inter-relationship construction industry.
between them is as shown below. Draw the network. 24. Write in details about the functions of the Materials
.Event Predecesso Event Manager.
25. How economic use of materials can be effected ?
26. What are various methods of purchasing ? Explain
them briefly.
27. What are the qualities required for Material
6 5 Manager ?
15 Differentiate between the following terms 28. State and explain any four functions of a Project
(i) Activity and Event (ii) Dummy activity and Critical Manager on a construction site.
activity Clii)Total float and Free float (iv) Looping and 29. Explain fleet management.
Dangling. 30. Explain aspect of fleet management.