Primavera Project Management
www.ProjacsTraining.com 2
Primavera Project Management
www.ProjacsTraining.com 3
Primavera Project Management
individuals.
Set up the enterprise project structure (EPS), which is the hierarchical
structure that identifies the company-wide projects and enables organization
and management of those projects in your organization.
Set up a resource hierarchy that reflects your organization’s resource structure
and supports the assignment of resources to activities.
For each project, set up the work breakdown structure (WBS), which is a
hierarchical arrangement of the products and services produced during and by
a project.
Once the OBS is established, the EPS can be set up. An EPS can consist of multiple
root nodes, which enable particular types of projects to be grouped together,
such as project templates or high-risk projects. Within each root node, you can
further break down an EPS into multiple EPS nodes, such as Capital Improvement
projects and Manufacturing projects, to categorize the types of templates
projects.
The WBS acts as a continuation of the EPS for the individual projects in the
organization. A WBS provides organization and control of project and activity
information through a hierarchy of WBS elements. When you create projects, the
Project Management module automatically creates a WBS element at the same
hierarchy level and with the same name as the project. You can set anticipated
project dates, budgets, and spending plans for a WBS at a high level to indicate
when the work should occur and how much its planned budget and monthly
spending will be before any projects are added to the EPS. In addition, you can
use the pre-established budget amounts and funding information you set for WBS
elements for their project and activity counterparts.
www.ProjacsTraining.com 4
Primavera Project Management
The following example represents how the OBS, EPS, and WBS structures
interrelate within one branch of the EPS.
www.ProjacsTraining.com 5
Primavera Project Management
Global Data
- Project structure
- Project codes
- Admin categories and performances.
Examples of centralized resource management include :
- Dates
- Work Breakdown Stricture ( WBS )
- Activities.
- Activity relationships
- Baselines
- Expenses
- Risks, Thresholds and Issues
- Work Products & Documents
- Project Web Site
www.ProjacsTraining.com 6
Primavera Project Management
- calendars
- reports
- Activity codes
www.ProjacsTraining.com 7
Primavera Project Management
www.ProjacsTraining.com 8
Primavera Project Management
Project Management
Projects are critical to the success of any organization. They are the activities
that results in new or changed products, services. Projects increase sales,
reduce costs, improve quality and customer satisfaction.
As organizations have recognized the criticality of projects to their success,
project management has become a focal point of improvement efforts.
Project management aims to finish the project on time, within budget and at
the required level of technical quality.
What is a project?
Organizations perform work. Work generally involves either operations or
projects, although the two may overlap. Operations and projects share many
characteristics; for example, they are:
- Performed by people.
- Constrained by limited resources.
- Planned, executed, and controlled.
Operations and projects differ primarily in that operations are ongoing and
repetitive while projects are temporary and unique.
Project is any work that:
- Has a temporary endeavor with a beginning and an end.
- Creates a unique product , service or result.
- Done for a purpose.
- Has interrelated activities.
www.ProjacsTraining.com 9
Primavera Project Management
www.ProjacsTraining.com 10
Primavera Project Management
These process groups represent the whole life of the project except under two
circumstances:
- Where a project ( program ) is broken down into multiple projects ;or
- A project is considered to have many phases.
In these cases the process groups may repeat throughout the project’s (program’s)
life. The processes groups do not necessary follow one after the other but
frequently overlaps during the life of the project. Look at the figure
www.ProjacsTraining.com 11
Primavera Project Management
Initiating Processes
Defining and authorizing the project or phase.
Planning Processes
Defining and refining objectives and selecting the best of the alternative
courses of action to attain the objectives that the project was undertaken to
address.
Executing Processes
Coordinating people and other resources to carry out the project management
plan for the project.
Monitoring and Controlling Processes
Regularly measures and monitor progress to identify variances from plan so
that corrective action can be taken when necessary.
Closing Processes
Formalizing acceptance of the product, service or result and brings the project
or phase to an orderly end.
www.ProjacsTraining.com 12
Primavera Project Management
Project Planning
Planning Techniques
- Network Planning :
o PERT (Program Evaluation & Review Technique).
o CPM (Critical Path Method).
Both can be represented either by arrow diagram or precedence diagram.
- Line of Balance.
- Linear Programming.
www.ProjacsTraining.com 13
Primavera Project Management
www.ProjacsTraining.com 14
Primavera Project Management
1. Schedule Control
2. Cost Control
www.ProjacsTraining.com 15
Primavera Project Management
Project Planning
1- Define the project: Create WBS
- The WBS subdivides the project work into smaller, more manageable pieces of
work, with each descending level of the WBS representing an increasingly
detailed definition of the project work. The planned work contained within the
lowest-level WBS components, which are called work packages, can be
scheduled, cost estimated, monitored, and controlled.
Work Package:
www.ProjacsTraining.com 16
Primavera Project Management
WBS Structure
2- Activity Definition
- Defining the schedule activities involves identifying and documenting the work
that is planned to be performed.
- The Activity Definition process will identify the deliverables at the lowest level
in the work breakdown structure (WBS), which is called the work package.
www.ProjacsTraining.com 17
Primavera Project Management
Upon finishing this step we get activity list, activity attributes ( identifier,
codes,..) and milestone list
3- Activity Sequencing
- Activity sequencing involves identifying and documenting the logical
relationships among schedule activities.
Dependency Determination
- Mandatory dependencies (Hard Logic)
Those dependencies which are inherent in the nature of the work being done.
They often involve physical limitations.
- Discretionary dependencies (soft logic)
Those dependencies that are defined by the project management team. These
dependencies can be changed if needed, while the others cannot easily be
changed.
- External dependencies
Those dependencies that are involve a relationship between project activities
and non-project activities.
www.ProjacsTraining.com 18
Primavera Project Management
Network Presentation
• ADM uses only finish-to-start dependencies and can require the use of
“dummy” relationship called dummy activity which has zero duration and
are shown as dashed line.
www.ProjacsTraining.com 19
Primavera Project Management
www.ProjacsTraining.com 20
Primavera Project Management
- The Activity Duration Estimating process requires that the amount of work
effort required to complete the schedule activity is estimated.
6- Schedule Development
- Project schedule development, an iterative process, determines planned start
(ES,LS) and finish dates (EF,LF) for project activities.
- Schedule development can require that duration estimates and resource
estimates are reviewed and revised to create an approved project schedule
that can serve as a baseline against which progress can be tracked.
- Schedule development continues throughout the project as work progresses,
the project management plan changes, and anticipated risk events occur or
disappear as new risks are identified.
- The critical path method includes determining the longest path in the network
diagram (the critical path) and the earliest and latest an activity can start and
the earliest and latest it can be completed.
- Critical Path : The critical path is the longest duration path through a network
diagram and determines the shortest time to complete the project.
www.ProjacsTraining.com 21
Primavera Project Management
- The critical path method calculates the theoretical early start and finish dates,
and late start and finish dates, for all schedule activities without regard for any
resource limitations, by performing a forward pass analysis and a backward
pass analysis through the project schedule network paths.
www.ProjacsTraining.com 22
Primavera Project Management
Forward calculation
EF = ES + D
Backward calculation
LS = LF – D
www.ProjacsTraining.com 23
Primavera Project Management
Critical Path
Paths:
- 1 - 2 - 5= 10
- 1 -2 - 4 - 5 = 12
- 1 - 4 - 5 = 10
- 1-3-4-5=8
The Critical Path is the longest duration path through a network diagram and
determines the shortest time to complete the project.
Critical activities
1- ES = LS 3- EF – ES = D
2- EF = LF 4- LF – LS = D
www.ProjacsTraining.com 24
Primavera Project Management
Floats calculation
www.ProjacsTraining.com 25
Primavera Project Management
Bar Charts
www.ProjacsTraining.com 26
Primavera Project Management
Schedule Compression
www.ProjacsTraining.com 27
Primavera Project Management
Resource Leveling
www.ProjacsTraining.com 28
Primavera Project Management
www.ProjacsTraining.com 29
Primavera Project Management
www.ProjacsTraining.com 30
Primavera Project Management
- Monitoring the ongoing project activities against the project management plan
and the project performance baseline so that;
o Corrective action can be taken when necessary.
o Recommendation of preventive action in anticipation of possible
problems .
- The key benefit of this process group is that project performance is observed
and measured regularly to identify variances from the project management
plan.
1- Schedule Control
Schedule Baseline
- The project schedule used for control is the approved project schedule,
which is referred to as the schedule baseline.
www.ProjacsTraining.com 31
Primavera Project Management
2- Cost control
Cost Baseline
The cost baseline is a time-phased budget that is used as a basis against which
to measure, monitor, and control overall cost performance on the project. It is
developed by summing estimated costs by period and is usually displayed in
the form of an S-curve, as illustrated in Figure. The cost baseline is a
component of the project management plan.
www.ProjacsTraining.com 32
Primavera Project Management
The earned value technique in its various forms is a commonly used method of
performance measurement. It integrates project scope, cost (or resource) and
schedule measures to help the project management team assess project
performance
The earned value technique uses the cost baseline assess project progress and
the magnitude of any variations that occur.
The earned value technique involves developing these key values for each
schedule activity, work package, or control account:
Planned value (PV):
PV is the budgeted cost for the work scheduled to be completed on an activity
or WBS component up to a given point in time.
Earned value (EV):
EV is the budgeted amount for the work actually completed on the schedule
activity or WBS component during a given time period.
Actual cost (AC):
AC is the total cost incurred in accomplishing work on the schedule activity or
WBS component during a given time period.
The PV, EV, and AC values are used in combination to provide performance
measures of whether or not work is being accomplished as planned at any
given point in time.
www.ProjacsTraining.com 33
Primavera Project Management
The most commonly used measures are cost variance (CV) and schedule
variance (SV).
Cost variance (CV):
CV equals earned value (EV) minus actual cost (AC).
Formula: CV = EV - AC
Schedule variance (SV):
SV equals earned value (EV) minus planned value (PV).
Formula: SV = EV - PV
These two values, the CV and SV, can be converted to efficiency indicators to
reflect the cost and schedule performance of any project.
www.ProjacsTraining.com 34
Primavera Project Management
www.ProjacsTraining.com 35
Primavera Project Management
PV = $42,000
EV = $38,000
AC = $48,000
SV = EV – PV
SPI = EV / PV
= $38,000 / $42,000
www.ProjacsTraining.com 37
Primavera Project Management
Forecasting
www.ProjacsTraining.com 38
Primavera Project Management
www.ProjacsTraining.com 39
Primavera Project Management
www.ProjacsTraining.com 40
Primavera Project Management
Getting Started
Start the Project Management module
Click Start, then choose Programs, Primavera, Project Management.
Log in
Before using the module, you must enter a valid login name and password.
- Click OK
www.ProjacsTraining.com 41
Primavera Project Management
The Workspace
When you first open a project, the Home workspace displays the main functions
available in the module. For example, click Activities to focus on activity data and
customize layouts. The workspace for each main window consists of a menu bar,
navigation bar, directory bar, toolbar, and command bar.
www.ProjacsTraining.com 42
Primavera Project Management
Home Window
Item Function
- Use the navigation bar to move between open windows, display and hide
the directory, and open Help quickly for a specific window
www.ProjacsTraining.com 43
Primavera Project Management
Open Project
Access Modes
- Read Only
o You can view data, but cannot input or change data.
- Shared
o Multiple users can view, input and change data
o The default setting
- Exclusive
o The current user is only user who can edit data on these projects
www.ProjacsTraining.com 44
Primavera Project Management
Activity Window
4
2
Item Function
www.ProjacsTraining.com 45
Primavera Project Management
What Is a Layout?
www.ProjacsTraining.com 46
Primavera Project Management
Activity Table
- Displays activity information in spreadsheet format. Use this type of layout
to quickly update a project. Use the Fill Down function to quickly copy and
paste contents of rows in the Activity Table. You can use filters and group
data to see only those activities that occur in your current status cycle. You
can customize Activity Table columns. You can also sort, filter, and group
activities in the Activity Table, as well as change the font of the activity
information and the color of the table background. The Activity Table is
displayed in the top and bottom layouts.
www.ProjacsTraining.com 47
Primavera Project Management
Gantt Chart
www.ProjacsTraining.com 48
Primavera Project Management
- Displays units, costs, or earned value data by activity over time. Use this
type of layout to review per period and rolled up activity resource/cost
data. The Activity Usage Spreadsheet is displayed in the top and bottom
layouts.
www.ProjacsTraining.com 49
Primavera Project Management
Activity Network
Activity Details
- Display detailed information for an activity you select in either the Activity
Table or Activity Network. You can also use Activity Details to enter and edit
an activity’s information, such as dates, resource assignments, and
predecessor and successor relationships. Activity Details is displayed in the
bottom layout only.
www.ProjacsTraining.com 50
Primavera Project Management
Trace Logic
- Provides a graphical display of dependency relationships for an activity you
select in either the Activity Table or Activity Network. Trace Logic is
displayed in the bottom layout only.
www.ProjacsTraining.com 51
Primavera Project Management
In this sample layout, the top part of the window shows activity data in a Gantt
Chart, and the lower part of the window displays the Activity Details.
www.ProjacsTraining.com 52
Primavera Project Management
Customizing Displays
Most windows and dialog boxes include a Display or Layout Options bar at the top
of the screen that contains commands that enable you to customize the current
display. Click this bar to display a menu of the commands available for that
window or dialog box. You can also access many of these commands from the
View menu.
www.ProjacsTraining.com 53
Primavera Project Management
www.ProjacsTraining.com 54
Primavera Project Management
www.ProjacsTraining.com 55
Primavera Project Management
- View project priorities, scope, budgets and resources across the entire
project structure or within a specific node.
- Manage projects separately while retaining the ability to roll up and
summarize data across multiple projects .
o Each node acts as a master project, rolling up all " child " nodes and
projects
o A node can be opened to view all detailed activity information from
the "member" project.
- View resource allocation across projects.
Assign security at any level of the project structure to provide users within
appropriate access to project information.
www.ProjacsTraining.com 56
Primavera Project Management
- The new node will be placed below the selected node in the hierarchy.
Click Add in the Enterprise Project Structure (EPS) dialog box.
- Type a unique ID and name for the node directly in the column cells, or in
www.ProjacsTraining.com 57
Primavera Project Management
the EPS ID and EPS Name fields. Accept the responsible manager shown, or
click the Browse button in the field to select a different OBS element for the
node.
www.ProjacsTraining.com 58
Primavera Project Management
www.ProjacsTraining.com 59
Primavera Project Management
Choose Enterprise, Projects. Select the EPS node to which you want to add a
project. Click Add.
The Create a New Project Wizard guides you through the steps required to add a
project, including selecting the node in which to place the project in the EPS,
naming the project, and identifying the responsible manager for the project.
2- Import projects
You may want to build your EPS using projects previously created in an earlier
version of the Project Management module, Microsoft Project, or Primavera
Project Planner 3.0 (P3). The Import Wizard prompts you to specify the
information to be imported and where the project should be placed in the current
EPS hierarchy.
www.ProjacsTraining.com 60
Primavera Project Management
www.ProjacsTraining.com 61
Primavera Project Management
- Use the calendar to select start and end dates for the project.
www.ProjacsTraining.com 62
Primavera Project Management
- Specify the resource rate type for new resource assignments. The default
rate type determines which price/unit is set on the resource assignment.
The list displays the rate types defined in the rate types tab in the admin
preferences dialog box
www.ProjacsTraining.com 63
Primavera Project Management
- Verify No. do not run the project architect is selected and then click Next.
www.ProjacsTraining.com 64
Primavera Project Management
www.ProjacsTraining.com 65
Primavera Project Management
Projects Window
The project has been created an opened to view high-level information about
the project, open the projects window.
The projects window displays the projects within the project structure that you
can access . you can also:
www.ProjacsTraining.com 66
Primavera Project Management
The project detail tabs are located in the bottom layout of the projects
window. They can be used to define the project properties and defaults that
are applied throughout the selected project
www.ProjacsTraining.com 67
Primavera Project Management
General Tab
The general tab enables you to view or modify general information about the
selected project ID, project name and responsible manager can be set when
you create the project. If necessary , you can change them here . the
remaining fields are set by default.
www.ProjacsTraining.com 69
Primavera Project Management
Dates Tab
The dates tab enables you to edit date information for selected project, the
planned start and must finish by dates can be set when you create the project .
if necessary, you can change them here.
Notebook Tab
- The Notebook Tab enables you to view or modify project notes, such as the
project's purpose, core requirements, or any other project-specific details.
www.ProjacsTraining.com 71
Primavera Project Management
Codes Tab
The Codes Tab enables you assign project codes value to the selected project.
Project codes allow you to group the projects in your project structure to
specific categories, such as location or division.
www.ProjacsTraining.com 72
Primavera Project Management
Default Tab
Default for new Activities – Indicates the settings that will be used when new
activities are added to the project; changing these sittings will not affect
existing activities .
www.ProjacsTraining.com 73
Primavera Project Management
Setting Tab
Settings tab consists of three sections:
- Summarize data – Indicate the data and the level to which the project
was last summarize
- Project Setting-sets the character used to separate WBS level; identifies
the month in which the fiscal year beings; and specification of baseline
used in eared value calculations
Define critical activities – indicate how critical activities will be displayed
www.ProjacsTraining.com 74
Primavera Project Management
Calculations Tab
Use this Tab to specify how to calculate cost and resource use when you
update activities.
www.ProjacsTraining.com 75
Primavera Project Management
- Values you specify override the application's values. If you clear the
checkbox, the application does not estimate actual and the actual field
remain blank unless you specify values.
- Link Actual and actual this period units and cost. Mark this checkbox to
recalculate Actual and actual this period units and cost when one of
them is updated.
www.ProjacsTraining.com 76
Primavera Project Management
www.ProjacsTraining.com 77
Primavera Project Management
When creating a project, the project manager typically develops the WBS first,
assigns work products and documents to each WBS element, and then defines
activities for performing the element’s work.
The WBS element added after the root level element is automatically indented to
form the second level of the hierarchy.
www.ProjacsTraining.com 78
Primavera Project Management
www.ProjacsTraining.com 79
Primavera Project Management
Click the Display Options bar, then choose Show on Top, Chart View. To change
the displayed information, click the Display Options bar and choose Chart Box
Template, then an information type.
www.ProjacsTraining.com 80
Primavera Project Management
www.ProjacsTraining.com 81
Primavera Project Management
Activities
Activities are the fundamental work elements of a project. They are the
lowest level of a WBS and the smallest subdivision of work that directly
concerns the project manager.
- Most detailed work unit tracked in a project schedule.
- Contains all information about the work to be performed.
- Also known as a task, item, event, or work package.
Activity Components
www.ProjacsTraining.com 82
Primavera Project Management
Adding Activities
Use the Activities window to create , view , and modify activities for the open
project. To add an activity to a project , perform one of the following actions :
The New Activity wizard walks you through the process of adding an activity.
Once you become familiar with the process, you can disable the wizard and add
activities directly to the project.
While in the Activities , you can Add from the Command bar to add new activities.
The New Activity wizard appears only when you click Add from the Command bar.
www.ProjacsTraining.com 83
Primavera Project Management
www.ProjacsTraining.com 84
Primavera Project Management
Start Milestone – This type is typically used to mark the beginning of a phase or to
communicate project deliverables.
- Zero – duration activity.
- Only has a start date.
- You can assign constraints, steps, expenses, work products, and documents.
Finish Milestone – This type is typically used to mark the end of a phase or to
communicate project deliverables.
- Zero – duration activity.
- Only has a finish date.
- You can assign constraints, steps, expenses, work products, and documents.
www.ProjacsTraining.com 85
Primavera Project Management
Task Dependent – This type is typically used when the work needs to be
accomplished in a given time frame, regardless of the assigned resources
availability.
Resource Dependent - This type is typically used when multiple resources assigned
to the same activity can work independently.
Level of Effort - This type is typically used for ongoing tasks dependent on other
activities.
www.ProjacsTraining.com 86
Primavera Project Management
- You can use the Activity Details tabs to add an activity, and then enter
additional information about the activity.
- In the Edit menu, click Add, or right-click and then click Add.
www.ProjacsTraining.com 87
Primavera Project Management
General Tab
- You can add the information about this activity in the Activity Details
tabs.
www.ProjacsTraining.com 88
Primavera Project Management
Status Tab
- Use the Status tab to define the selected activity’s duration, constraint, start
and finish dates, labor and nonlabor units and costs, and material costs. You
can also use the Status tab to view the selected activity’s float, actual, and
completion percentages.
www.ProjacsTraining.com 89
Primavera Project Management
Notebook Tab
The Notebook tab enables you to assign notes to an activity. Notebook topics are
typically instructions or descriptions that further describe the activity according to
specific categories of information.
www.ProjacsTraining.com 90
Primavera Project Management
www.ProjacsTraining.com 91
Primavera Project Management
Adding Steps
Activity steps allow you to break activities into smaller units and track the
completion of those units. Steps provide a list of procedures required to complete
the task and provide extra guidance to the resources assigned to the activity.
- You can assign an unlimited number of steps per activity.
- Steps can be marked completed in Primavera and by the primary resource in
timesheets.
You can also update an activity’s physical percent complete based on the weight
you assign to each activity step. Weighted steps enable you to track the progress
of an activity based on the number of steps completed.
www.ProjacsTraining.com 92
Primavera Project Management
www.ProjacsTraining.com 93
Primavera Project Management
Step Templates
Activity step templates enable you to define a group of steps common to multiple
activities, then assign the template to activities.
Weights may also be defined for steps in the template. if a commonly used step or
set of steps have already been defined for an activity , you can convert the steps to
a template.
www.ProjacsTraining.com 94
Primavera Project Management
Establishing Relationships
- Create relationships between activities to indicate whether an activity can
begin only after other activities start or finish. Once you assign
relationships, schedule the project to calculate early and late dates for each
activity.
- Display Activity Details by clicking the Layout Options bar and choosing
Show on Bottom, Activity Details, then click the Relationships tab. Click
Assign in either the Predecessors or Successors section.
- Select the predecessor or successor activity you want to assign, click the
Assign button, then click the Close button. Double-click the Relationship
Type field, then select a relationship type. Double-click the Lag field, then
type the relationship’s lag time value.
www.ProjacsTraining.com 95
Primavera Project Management
www.ProjacsTraining.com 96
Primavera Project Management
Chapter 7 : Scheduling
www.ProjacsTraining.com 97
Primavera Project Management
Scheduling
What is the Data Date?
- The data date is the date that is utilized as the starting point for schedule
calculations.
- Date used to schedule all remaining work.
- During the Planning phase the data date should match the project start
date.
Open Ends
It is recommended that each project have only two open ends, the first activity
and the last activity.
www.ProjacsTraining.com 98
Primavera Project Management
Scheduling a Project
When you schedule a project, activity dates are calculated according to durations
and logic.
Schedule Log
Scheduling/leveling settings
Statistics
Errors
Warnings
Scheduling/leveling results
Exceptions
www.ProjacsTraining.com 99
Primavera Project Management
www.ProjacsTraining.com 100
Primavera Project Management
Driving Relationship
An activity may have a relationship from a predecessor that determines its Early
Start. This logic tie is called a driving relationship.
www.ProjacsTraining.com 101
Primavera Project Management
Constraints
Use constraints to build a schedule that more accurately reflects the real-world
aspects of the project, provide added control to the project, and impose a
restriction on the entire project or an individual activity
www.ProjacsTraining.com 102
Primavera Project Management
Must Finish By
www.ProjacsTraining.com 103
Primavera Project Management
The next step is to reschedule the project to see the effect of the imposed
deadline on the late dates and total float in the project plan. , some of the
activities contain negative total float.
www.ProjacsTraining.com 104
Primavera Project Management
Start On or After
Use the Start On or After constraint to set the earliest date an activity can begin.
www.ProjacsTraining.com 105
Primavera Project Management
Finish On or Before
Start On
Start On or Before
Finish On
Finish On or After
As Late as Possible
www.ProjacsTraining.com 106
Primavera Project Management
www.ProjacsTraining.com 107
Primavera Project Management
www.ProjacsTraining.com 108
Primavera Project Management
Creating Calendars
Calendar can be created and assigned to each activity and resource. Calendar
assignments are used to schedule activities and level resources.
- An unlimited number of calendars can be created.
- The Activity Type determines whether the activity calendar or resource
calendar is used during scheduling.
Calendar Types
Worktime Types
Standard
- Worktime matches the hours set up in the calendar weekly hours dialog
box.
- Define which days of the week are workdays.
- Define the number of work hours in a workday.
Nonwork
- All 24 hours are nonworktime.
Exception
- Does not match the work/nonwork setup in the standard calendar weekly
hours dialog box.
www.ProjacsTraining.com 109
Primavera Project Management
Global calendars
- Mark the Default checkbox next to the global calendar to set the
default calendar assignment for all new projects added to the
database.
- To change the default calendar assignment for an individual
project, click Enterprise, Projects and elect the Defaults tab.
- You can link resource and project calendars, your changes are
applied to all resource and project calendars linked to the
modified global calendar.
www.ProjacsTraining.com 110
Primavera Project Management
www.ProjacsTraining.com 111
Primavera Project Management
www.ProjacsTraining.com 112
Primavera Project Management
www.ProjacsTraining.com 113
Primavera Project Management
Define the workweek for the selected calendar by defining the days of the
week and hours per day.
To Set Nonworktime,
- Select a day.
www.ProjacsTraining.com 114
Primavera Project Management
Setting Exceptions
www.ProjacsTraining.com 115
Primavera Project Management
Calendar Assignments
Use the Select Activity Calendar dialog box to select the calendar an activity
should use in the project. Calendars can be global or project specific.
- Select activity.
- Click the General tab.
- In the Activity Calendar field, click to select a new calendar assignment.
- In the Display Options bar, click Global Calendars.
- View the available calendars and close the dialog box.
www.ProjacsTraining.com 116
Primavera Project Management
www.ProjacsTraining.com 117
Primavera Project Management
- You can use activity codes to view and roll up activities in the activity table; build
reports in the Report Wizard or Report Editor; Organize a layout by grouping
activities into specific categories; and select and summarize activities.
- Examples of activity codes include Phase, Area, Site, and Division.
Activity codes can be global, which means they are available to all projects in the
database.
- Organize activities within a project or across the project structure.
- Create an unlimited number of global activity codes.
www.ProjacsTraining.com 118
Primavera Project Management
Activity codes can be project – specific, which means they are available only in the
project in which they were created.
- Filter and organize activities based on unique , project specific
requirements.
- Create up to 500 activity codes per project.
- Each activity code ( global and project ) may contain an unlimited number
of activity code values.
- Activity code values can be organized in a hierarchy.
www.ProjacsTraining.com 119
Primavera Project Management
- To add values to a project code, click Close in the Project Code Definitions
dialog box. In the Project Codes dialog box, select the project code for which
you want to establish values, then click Add and type the values and
descriptions.
www.ProjacsTraining.com 120
Primavera Project Management
- Select an activity .
- In Activity Details, click the Codes tab, click Assign.
- Select an activity code value, click Assign , and then click Close.
www.ProjacsTraining.com 121
Primavera Project Management
www.ProjacsTraining.com 122
Primavera Project Management
www.ProjacsTraining.com 123
Primavera Project Management
Customizing layouts
Modifying columns
- You can customize the look and content of the columns included in tables
and spreadsheets in the Activities window. Choose which columns you
want to include; change the column widths, the order in which columns are
displayed, and the row height; specify column fonts and colors; edit column
titles; and copy column formats from other layouts.
Add or remove columns
- In the Activities window, click the Layout Options bar, then choose
Columns.
www.ProjacsTraining.com 124
Primavera Project Management
www.ProjacsTraining.com 125
Primavera Project Management
- Click Add. Type a name for the new bar, then select the timespan the bar
represents from the Timescale drop-down list. Double-click the Filter field,
then mark each filter you want to apply. Click OK.
- To delete a bar, select it in the Bars dialog box, then click Delete.
www.ProjacsTraining.com 126
Primavera Project Management
Use Bar style tab to specify the shape, color, pattern and position (Row) of
the bar.
Use bar setting to define grouping bar setting and bar necking setting.
Use bar labels to select what to display in bar area.
Grouping data
www.ProjacsTraining.com 127
Primavera Project Management
Customize grouping
In the Activities window, click the Layout Options bar, then choose Group and
Sort. You can also click the Display Options bar from the Projects or Resources
window and then choose Group and Sort By, Customize.
- When grouping by a hierarchical item, such as WBS, mark the indent checkbox
to indent each level
www.ProjacsTraining.com 128
Primavera Project Management
Sorting Data
- Sorting determines the sequence in which projects, activities, or resources
are listed in the current window. You can sort alphabetically, numerically, or
chronologically based on the data item you choose.
www.ProjacsTraining.com 129
Primavera Project Management
Filtering Data
www.ProjacsTraining.com 130
Primavera Project Management
If you specify that all criteria must be met, each statement is joined
with an “And”. If any criteria can be met, an “Or” is used
www.ProjacsTraining.com 131
Primavera Project Management
Combining Filters
To create a filter that selects any activity from one selection criteria and any
activity from another selection criteria, you must define two separate filters and
then combine them when you run the filters.
www.ProjacsTraining.com 132
Primavera Project Management
www.ProjacsTraining.com 133
Primavera Project Management
www.ProjacsTraining.com 134
Primavera Project Management
www.ProjacsTraining.com 135
Primavera Project Management
- If displaying the Gantt Chart in your layout, you can choose to display the
Gantt Chart Legend in the header or footer.
www.ProjacsTraining.com 136
Primavera Project Management
www.ProjacsTraining.com 137
Primavera Project Management
Previewing Layouts
- The Print Preview option enables you to review the layout or report before
sending it to a printer.
- As you move your mouse over the Print Preview window, the pointer
changes to a magnifying glass. Click the Zoom In button in the toolbar to
zoom in on details and the Zoom Out button to zoom back out.
www.ProjacsTraining.com 138
Primavera Project Management
Printing Layouts
- You can print layouts and reports by sending them directly to a printer,
publishing them as HTML files.
Print a layout
- To send a layout directly to your printer, open the layout you want to print,
then choose File, Print. You can also click the Print button from the Print
Preview window.
www.ProjacsTraining.com 139
Primavera Project Management
www.ProjacsTraining.com 140
Primavera Project Management
Roles
- If you are in the planning stage of your project or want to see how certain
resource assignments will affect the schedule, you can assign roles as
temporary placeholders for resource assignments. Roles are project personnel
job titles or skills. They represent a type of resource with a certain level of
proficiency—rather than a specific individual. Roles can also be assigned to
specific resources to further identify that resource’s skills.
Primary resources
- An activity’s primary resource is typically the resource who is responsible
for coordinating an activity’s work. The primary resource updates the
activity’s start date, finish date, and expected end date. In addition, if an
activity has any material resources, the primary resource may be responsible
for reporting the material resource’s hours/units.
www.ProjacsTraining.com 141
Primavera Project Management
www.ProjacsTraining.com 142
Primavera Project Management
View resources
www.ProjacsTraining.com 143
Primavera Project Management
Add a resource
- Choose Enterprise, Resources. Click the Display Options bar, then choose
Group and Sort By, Default, to display the resource hierarchy.
- Select the resource immediately above and at the same level as the resource
you want to add, then click Add.
www.ProjacsTraining.com 144
Primavera Project Management
General information
Use the General tab to enter general information about the selected resource,
including the resource’s ID, name, title, employee ID, e-mail address, office phone
numbers, and status.
www.ProjacsTraining.com 145
Primavera Project Management
Details
- Use the Details tab to specify a resource’s labor classification—labor
(personnel), nonlabor (equipment), or material (supplies), indicate whether
a resource can log overtime hours, assign a calendar to the selected
resource, specify the resource’s default units/time, specify how actual and
remaining units are applied for a resource’s assignments, and indicate that
any assignments for a resource will have its quantities recalculated
whenever any cost changes occur.
Default Units/Time
You can enter the default units/time value as a numeric value followed by a forward
slash (/) and the appropriate time duration, depending on your user preference
setting for time units, or as a percentage for labor and nonlabor resources.
www.ProjacsTraining.com 146
Primavera Project Management
You can set varying limits and prices over time by specifying the effective start date
for each change
Note: to level resources, you must set availability limits (max units/time)
www.ProjacsTraining.com 147
Primavera Project Management
Setting Up Roles
Roles are project personnel job titles or skills, for example, project planner, quality
assurance tester, and engineer. You can create a standard set of roles that you can
assign to labor and nonlabor resources and activities in all projects in the
organization.
View roles
Choose Enterprise, Roles, then click the Display Options bar.
- To view only those roles that have assignments in the open project, choose
Filter By, Current Project’s Roles.
- To view all roles, choose Filter By, All Roles.
www.ProjacsTraining.com 148
Primavera Project Management
www.ProjacsTraining.com 149
Primavera Project Management
Add a role
- Choose Enterprise, Roles. Select the role immediately above and at the same
level as the role you want to add, then click Add. Type the role’s ID and name.
To create a hierarchy of roles, click the right arrow key to indent the selected
role one level.
www.ProjacsTraining.com 150
Primavera Project Management
- To add rates to a role choose Enterprise, Roles. If tabs are not displayed in
the Roles dialog box, click the Display Options bar and choose Roles Details.
Select the role you want to assign rates to, then click the Prices tab. Enter
up to five Price/Unit rates for the selected role.
www.ProjacsTraining.com 151
Primavera Project Management
- You can assign roles to resources in two ways: from the Resource Details
window or from the Roles dialog box.
Assign roles to resources from the Resource Details window
- Choose Enterprise, Resources, select the resource to which you want to
assign a role, click the Display Options bar, then choose Details.
www.ProjacsTraining.com 152
Primavera Project Management
www.ProjacsTraining.com 153
Primavera Project Management
- Click Add Resource to assign a resource to the selected activity; click Add
Role to assign a role to the selected activity.
- Select the resource or role you want to assign. To assign multiple resources
or roles, hold down the Ctrl key, then click each resource/role you want to
assign. Click the Select button, then click the Close button.
www.ProjacsTraining.com 154
Primavera Project Management
www.ProjacsTraining.com 155
Primavera Project Management
www.ProjacsTraining.com 156
Primavera Project Management
www.ProjacsTraining.com 157
Primavera Project Management
- Select the cost account immediately above and at the same level as the
cost account you want to add, then click Add. Type the cost account’s ID
and name.
www.ProjacsTraining.com 158
Primavera Project Management
Add expenses
- Choose Project, Expenses. Click Add. Select the activity that incurs the
expense, then click the Select button.
- Click the General, Activity, Costs, and Description tabs, and enter the
expense’s information.
General information
- Use the General tab to define general information for the selected expense
item, such as the item name and category. You can also specify the item’s
vendor, cost account, and document number.
www.ProjacsTraining.com 159
Primavera Project Management
Activity information
- Use the Activity tab to change the selected expense item’s activity
assignment and specify the expense item’s accrual type. You can also view
the item’s activity assignment according to WBS element, activity status,
activity start and finish dates, and primary resource.
www.ProjacsTraining.com 160
Primavera Project Management
Costs
- Use the Costs tab to specify cost amounts for the selected expense item,
including price/unit, budgeted cost, actual cost, and remaining cost. You
can also indicate if you want to calculate an expense item’s actual cost
according to activity completion percentage.
www.ProjacsTraining.com 161
Primavera Project Management
- Click Add, then type the expense’s name. Double-click the item’s expense
category listing, click the category you want to assign, then click the Select
button. then select the expense’s accrual type. Type the number of
budgeted units you expect the selected activity to use. Type the cost of
each unit. The module calculates and displays the expense’s budgeted cost
(budgeted units * price/unit) in the Budgeted Cost field.
www.ProjacsTraining.com 162
Primavera Project Management
www.ProjacsTraining.com 163
Primavera Project Management
You can determine the level of detail displayed on resource/cost usage profiles/
spread sheets.
-All projects
- All closed projects- Displays resource/cost usage across all projects that
have been summarized in the EPS as well as open projects.
- All closed projects with a leveling priority- when electing to show remaining
values for open versus closed projects, choose this option to include data
for all closed projects with a specific leveling priority.
- Opened projects only- focus on resource/cost usage in the projects
currently opened.
www.ProjacsTraining.com 164
Primavera Project Management
- In the full menu, click Close All, when promoted, click Yes.
- In the Edit menu, click User Preferences. Click the Resource Analysis tab.
Select All closed projects (except what-if projects).
Selecting All closed projects (except what-if projects) displays resource
information for all projects that do not have What-if status, not just the
project that is currently open.
www.ProjacsTraining.com 165
Primavera Project Management
Use the profile to determine how many hours each resource is scheduled to work;
identify over-allocated resources; track expenditures per time period; and display
a “banana curve” to compare early and late dates.
www.ProjacsTraining.com 166
Primavera Project Management
- Right Pane Display Options bar; Displays a menu of the formatting options available for
the resource/role usage profile
- Legend; Displays a legend for the profile’s b bars and or/ lines. This will change depending
on the data/formatting options selected.
- Timescale; Displays the date intervals: major increment displayed on the bottom and
minor increment displayed on the top.
- Display Activities for Selected; When viewing Open Projects Only, you can mark Time
Period or Resource to Filter the activities in the top layout.
-
www.ProjacsTraining.com 167
Primavera Project Management
- Resource/ Role Hierarchy; Lists the names of the resources/roles. Can be filtered to show
shorter list e.g., the Current Project’s resources.
- Left Pane Display Options bar; Displays a menu of the formatting options available for the
resource/role hierarchy.
The Resource Usage profile can be modified by adjusting Data and Graph settings
in the Resource Usage Profile Options dialog box.
www.ProjacsTraining.com 168
Primavera Project Management
Data settings:
In the right-pane Display Options bar, click Resource Usage Profile Options.
Select Data tab
www.ProjacsTraining.com 169
Primavera Project Management
Graph settings :
Vertical Lines- Choose to display major/minor sight lines based on the timescale
interval.
Horizontal Lines- Choose the line style and color.
Additional display options:
www.ProjacsTraining.com 170
Primavera Project Management
You can specify the timescale you want to display in the Resource Usage profile
and the Gantt Chart.
- Timescale Start- Specify the date from which the timescale should start for
the profile or Gantt Chart.
- Date Interval- Choose the units of the timescale in years, quarters, months,
weeks, days, hours and shifts.
- Date Format- Select the format in which to display date intervals: Calendar,
Fiscal, Week of the Year, or Ordinal Dates.
www.ProjacsTraining.com 171
Primavera Project Management
You can also format the timescale by using click and drag in the timescale
onscreen.
- Place your mouse on the minor date interval on the timescale. Click and
drag to expand or contract the timescale.
- Click the Display Options bar and choose Stacked Histogram. Then click the
Display Options bar and choose Resource Usage Profile Options. Click the
Data tab, then specify the type of data to display in the profile and the way
it will be represented.
www.ProjacsTraining.com 172
Primavera Project Management
Data settings
www.ProjacsTraining.com 173
Primavera Project Management
Use the Resource Usage Spreadsheet to analyze quantity or cost usage for
resources or roles. For every role and resource in the project, you can review cost
or quantity information for a specific project or for all projects. You can also select
the spreadsheet fields to specify which cost or quantity information you want to
view and set the timescale for displaying data values.
This spreadsheet can be displayed in the bottom layout only.. use this layout type
to view resource allocation over time, according to the timescale specified.
The Resource Usage Spreadsheet has two views: a two-section view and a three-
section view. By default, the three-section view displays.
The two-section view is displayed when the user selects the Display Options bar
menu item Show All Projects. If the menu item, Open Projects Only is selected,
www.ProjacsTraining.com 174
Primavera Project Management
Left Pane:
Middle Pane:
- You can view the list of activities assigned to the selected resource in the
middle pane.
www.ProjacsTraining.com 175
Primavera Project Management
Right Pane:
- Select the fields to view in the spreadsheet and set the timescale. If the
data cells are too narrow to reveal the entire value, the width of the data
cells may be expanded. Moving the mouse to the right will expand the
timescale and the data cells. Moving the mouse to the left will contract the
timescale and the data cells.
- Click the right Display Options bar and choose spreadsheet fields.
- Choose customize
www.ProjacsTraining.com 176
Primavera Project Management
www.ProjacsTraining.com 177
Primavera Project Management
www.ProjacsTraining.com 178
Primavera Project Management
Leveling Resources
- Level resources in your projects to ensure that resource demand does not
exceed resource availability. Resource leveling is an automated process
that changes the start of certain activities. During leveling, the resource
requirements of all scheduled activities are compared to the maximum
quantity available at the time of leveling. An activity is delayed if too few
resources are available at any time during the activity’s duration.
- You can select the resources to be leveled, and you can add leveling
priorities that specify which project or activity is leveled first when a
conflict occurs.
www.ProjacsTraining.com 179
Primavera Project Management
Leveling Rules
The following rules are used to determine the order for leveling activities.
- Mandatory constraints
o Primavera leaves activities that have a mandatory start/finish date on
their early dates.
o Network logic may be violated.
- Topological order (predecessor / successor relationships)
o Respects network logic
- Leveling priority “tiebreaker”
o If two activities can be leveled at the same time, leveling priorities
are used to break the tie.
www.ProjacsTraining.com 180
Primavera Project Management
Level resources
- Open the projects that contain the resources you want to level. Choose
Tools, Level Resources. You can set several resource leveling options to
meet your requirements. Click Level after you make your selections.
www.ProjacsTraining.com 181
Primavera Project Management
Selecting Resources
www.ProjacsTraining.com 183
Primavera Project Management
* Indicates that the priority is available only if you mark the Level Resources
Only Within Activity Total Float checkbox in the Level Resources dialog box.
www.ProjacsTraining.com 184
Primavera Project Management
The exception section of the Scheduling / Leveling reports shows the results of
the leveling calculations.
www.ProjacsTraining.com 185
Primavera Project Management
www.ProjacsTraining.com 186
Primavera Project Management
Managing Baselines
A baseline is a complete copy of a project plan that you can compare to the
current schedule to evaluate progress.
- You can compare up to three baselines at one time. For example, you might
want to create a baseline of the original project schedule, and then create
two additional baselines at different stages of the project.
www.ProjacsTraining.com 187
Primavera Project Management
- To create a baseline project, select the desired project and click Add.
- If multiple projects are open, you can create a baseline for the selected
projects. (To select a project Ctrl-click on its band.) Choose to save a copy of
the current project as a new baseline or convert another project to a new
baseline.
www.ProjacsTraining.com 188
Primavera Project Management
- Open the project for which you want to select a project baseline.
- In the Project field, select the project to which you want to assign a project
baseline. In the Project Baseline field, select the desired baseline or the
current project. If no baseline is designated as active, the current project is
used as the baseline project.
www.ProjacsTraining.com 189
Primavera Project Management
Examine updated project schedules using the many display and print options
available.
www.ProjacsTraining.com 191
Primavera Project Management
www.ProjacsTraining.com 192
Primavera Project Management
Using Spotlight
www.ProjacsTraining.com 193
Primavera Project Management
-Highlight the activities to be updated by dragging the data date to the desired date.
www.ProjacsTraining.com 194
Primavera Project Management
Entering Actuals
Once a project is underway, you must enter actual schedule and resource use at
regular intervals. You may need to update daily, weekly, or monthly,
depending on the timespan of your project and how frequently you want to
adjust your forecasts. Actual data is different than planned data- it is the real
time/cost associated with an activity.
www.ProjacsTraining.com 195
Primavera Project Management
Now that actuals have been entered, it is time to reschedule the project based on
the new data. Any activities that were delayed will delay their successor
activities.
www.ProjacsTraining.com 196
Primavera Project Management
www.ProjacsTraining.com 197
Primavera Project Management
Analyze the schedule to determine if milestone dates and project dates are
being achieved.
Compare your project finish date to the baseline finish date to see if you will complete
the project on time.
If the project finish date is behind schedule, analyze the critical activities causing the
delay.
Adjust the project to meet your project finish date.
If the calculated finish date is later than the Must Finish by date, you can use
several methods to shorten the project:
www.ProjacsTraining.com 198