You are on page 1of 8

TUNNELS & DEEP SPACE

\P

Developme,nt of Unlined Pressure Shafts


And Tunnels in Norway
Einar Broeh
Unlversity of Trondhelm

rñopo only to favorable tunneling conditions; leading to uncertain delivery and very

I n"¿
tric energy. More than 99Vo of a total
it is also the consequence of a support
philosophy whiçh acpepts some falling
rock during the operation peripd of a
high prices. As a result, four Norwe-
gian hydro power stations with unlined
pressure shafts were put into operation
annual production of 90 TWh of elec- water tunnel. As long as rockfalls in (Table l).
tric energy is generated from hydro certain parts of the tunnel don't de- As early as 1922, three pressure shafts
power. Figurç I
shows the installed velop considerably and increase the were {escribedin detail in a publica-
production capacity of Norwegian hy- head loss, a reasonable number of small tion from the Norwegian Geological
droelectric power stations. It is inter- blockages spread out along the tunrrel Survey (Vogt 1922). The Herlands-
esting to note that, since 1950, under- will not harm the tunnel or disturb the foss, Svelgen, and Toklev shafts were
ground powerhouses are predominant operation of the hydro power station. later investigated and described by
In fact, of the world's 300-500 under- Ifnecessary, they may be removed Broch and Christensen (1962), and
ground powerhouses almost one-half during later inspection and mainte- Herlandsfoss was discussed by Selmer-
are located in Norway, Another proof nance. Olsen (1970).
that the Norwegian electriciry industry The pressure shaft at Herlandsfoss
is an "underground industry" is that it is shown in Figure 2. According to the
Early Unllned Pressure Shafts
has approximately 2,500 km of tun- original design the penstock and the
nels. During and shortly after the First concrete plug were placed only 50 m
Through the design, construction, World War there wâs a shortage of steel from the turbine, leaving 150 m of the
and operation of all these tunnels and
underground powerhouses, valuable
experience has been gained, Aiso, spe- GW
cial techniques and design concepts have
been developed over the years. One
HYDRO'ELECTRIC POWER STATIONS
such Norwegian specialty is the un- IN NORWAY
lined, high-pressure tunnels and shafts
which this paper describes, 15
It should be mentioned as a prelim-
inary matter that the rock of Norway
is of Precambrian and Paleozoic age.
Although there is a wide variety of rock t0
types, highly metamorphic rocks pre-
dominate. From an engineering point
of view they may in general be classi-
fied as typical hard rock.
Most of our hydro power tunnels have
only 2-4% conçrete or shotcrete lin-
ing, Only in a few cases has it been
necessary to increase this to 30-60%.
The low percentage of lining is due not

Þ o o o
Einar Brr¡ch, a professor in the Department
of Geology, University of Trondheim,
lf!
ol
(f'
crì
t\
C'I
YEAR o

Trondheim, Norway, is a Vice President of
the Internati<¡nal Tunnelling Association. Figure l. The deaeloþment of hydroelectric þower þroduction in Noruay (Myset /,980).

Und*grouul Spacc, Vol. 8, pp. 177-184, 1984. 0362-0565/84 ¡3.00 + 0{J t77
Printed in the U S.A. All ri¡ghtr reserved. Copyright @ I'ergamon l'res¡ [,td.
Table 1. The frst unlined pressure shafts in Norutay- structed.
The new record shaft of 286 m at
Water Head Dlameter Rock
Experience
Tafiord K3, which was put into oper-
Name Year (m) (m) Tvæ
ation successfully in 1958, gave the in-
Herlandsfoss 1919 136 3.20 Mica-schist Partly failed dustry new confidence in unlined shafts.
Skar 1 920 129 Gneiss- Completely As Figure 4 shows, new unlined shafts
granite failed were constructed in the early 1960's.
Svelgen 1921 152 2.40 Sandstone Minor leakage Since 1965, unlined pressure shafts have
Toklev 1921 72 2.50 Monzonite No leakage
been the conventional solution for heads
up to 600 m. In 1981, the Tafiord
high-pressure tunnel unlined. During lined with concrete and grouted with Kraftselskap set its third world record
the first ñlling of the tunnel and the cement. Since then the shaft has op- by putting into operation an unlined
shaft, increasing leakage through the erated without problems. pressure shaft with a water head of
mica-schist layer was observed. The The Toklev pressure shaft has func- 780 m. However, plans are already
tunnel was then emptied and a 60-m- tioned without any reported problems completed for a new unlined pressure
long reinforced concrete lining was since it was put into operation. shaft with a water head of 1,000 m
placed inside the penstock. After two (Bergh-Christensen and Kjolberg I 982).
months of operation, rapidly increas- Altogether, by the end of 1982, 64 un-
Development of the lined pressure shafts with water heads
ing leakage was again observed. In- General Plant Layout
spection of the emptied tunnel re- between 150 and 780 m (with an av-
vealed open cracks in the concrete on Although three out of four pressure erage of 314 m) were in operation in
both sides of the tunnel near the shafts constructed around 1920 were Norway. Figure 4 clearly demonstrates
springline. After this failure the pen- that increasing water heads reflect an
stock was extended through the whole increasing confidence in unlined pres-
tunnel to the foot of the shaft (Fig. 2). sure shafts over the last 20 years,
No leakage from the shaft has been This confidence in the tightness of
observed since, and the power station at Svelgen to be beaten. Through 1958, the unlined rock mass increased in 1973
has operated without unplanned stops nine more unlined pressure shafts were when the first closed, unlined surge
for 60 years. constructed, but all had water heads chamber with an air cushion was suc-
The pressure shaft at Skar was, to below 100 m. Before 1950 the above- cessfully put into service at the Driva
make a long and miserable story short, ground powerhouse with PenstockÍ/as hydroelectric power plant. This inno-
a complete failure and was replaced by ihe conventional layout for hydro- vation in surge chamber design is de-
an ordinary penstock (except for the power plants (Fig. 3). scribed in detail by L. Rathe (1975).
upper part of the tunnel). The primary When the hydro power industry went The bottom sketch in Figure 3 shows
reason for the unacceptable leakage was underground in the early 1950's, they how the new design influences the gen-
the low overburden of rock, only 22 m brought steel pipes with them. Thus, eral layout of a hydro power plant. The
where the water head was I 16 m. for a decade or so most pressure shafts steeply inclined pressure shaft, nor-
At Svelgen, leakage of 3-5 Vsec was were steel-lined. During the period mally at 45o, is replaced by a slightly
observed as two small polluted streams 1950-65, a total of 36 steel-lined shafts inclined tunnel, l:10-l:15. Instead of
during the frrst filling of the pressure with heads varying from 50 to 967 m the conventional open surge chamber
shaft. A short section of the shaft was (with an average of 310 m) were con- near the top of the pressure shaft, a

HERLANDSFOSS
Hydro-electric power stotion
5colc in mclras
50 00

/ = 1,1 = bulk dcnsitY


h: nace3sofy ¡ock covet
H: woter prcssurc in sholl

Hornbl.ôd. !chrtl

Figtre 2. The Herlandsfoss hydroelectric þower station, in oþeralion since I919 (Selmer-Olsen 1970).

178 UnLrrtc;nou¡lo Sr¡r:s Volume 8, Number 3, 1984


Before l95O Surge Tonk

Supply Tunnel

ur9e
Chomber
Heodroce Tunnel

t950 - t960

:Jg.=
Toilroce Tunnel

From 1960 on

--____

From 1975 on
Closed, Unlined Surge
Chomber wilh Air Cushion

Tunnet
--___

'fhe deuebþmenl oJ the general


layout oJ hydroelectric þlants in Nonuay.
II
I
Ê4{vl II
I
Tafjord K5 f- .l
g UNLINED PRESSURE SHAFTS
o AND TUNNELS IN NORWAY
lr¡ 600
-
É.
lJ.,
l- Tafjord K4 ¡-
400
=
9
l- Taljord K3 ?- -
t-
(, 200
aa
x o

= ?1.' i.. i
a
No information col.tected

50 1960 I97O YEAR r980


Figure 4. Tlw dettelopm.ent of unlined. þressure sha.fß and tunnek in Norway. \6ii!
\rrun ç,

closed chamber is excavated some- plants used at that time (Fig. 3). For the uncommon inclination of 60". A
where along the high-pressure tunnel, construction reasons the inclination of revised rule of thumb which would also
preferably not too far from the pow- the unlined shafts varied between 3l' cover shafts steeper than the com-
erhouse. and 47", with 45" as the most common. monly-used 45" was presented by Sel-
After the tunnel system is filled with The rule was expressed as follows mer-Olsen (1970). It was expressed in
water, compressed air is pumped into (Fig. 5): a more general way as follows (Fig. 5):
the surge chamber. At Driva, where
the water head at the chamber is 425 m, h>c.H _l¿- "v"' H
the total volume of the chamber is 6,000 .y. . cosc.'
cu m, Of this, 3,000 m is filled with
for every point of the tunnel, where
where
compressed air. This compressed air h : vertical depth of the point
acts as a cushion to reduce the water studied (in m), 1* : density of water,
^y. : density of the rock mass, and
hammer effect on the hydraulic ma- H: static water head (in m) at the c. : the inclination of the shaft.
chinery and the waterways, and also point studied, and
ensures the stability of the hydraulic c : a constant, which was 0.6 for The failure of the Byrte shafr was also
system. Table 2 describes the air cush- valley sides with inclinations analyzed for the first time with a finite
ion surge chambers in service. up to 35o and increased 1.0 element model (Brekke et al. 1970),
for valley sides of 60o. In the fall of 1970 another failure
The F¡rst Deslgn Crlteria occurred at Åskora, where an unlined
In summarizing the experience from High valley sides steeper than 60o are tunnel in sandstone with a water head
early unlined pressure shafts, Vogt rather uncommon in Norway. This of approximately 200 m was hydraul-
( 1922) states that the first and foremost
simple rule was, of course, to be used ically split. The split followed sand-frlled,
requirement for a pressure shaft is that with care under special geological con- steeply dippingjoints with a srrike par-
leakage be avoided. He disagrees with
ditions. allel to the very steep valley side (55')
those who at that time claimed that an
In 1968, the unlined pressure shaft and normal to the tunnel. The failure
unlined pressure tunnel is safe when at Byrte, with a maximum static water is described in detail by Bergh-Chris-
head of 300 m, failed. The shaft had tensen (1975).
the weight of the rock overburden is
greater than the water pressure. (He
even says that to get this idea out of Table 2. Closed, unlined, surge chambers wilh air cushions in Nonaay.
the profession is one of his main rea-
sons for writing the report.) According Year Alr pressure Volume of
to Vogt, the main risk for unlined pres- Name Completed (bar) Chamber (m.)
sure tunnels and shafts is bad rock
masses with weathered zones, joints, etc. Driva 1 973 42.5 6,000
Hence, the best way of avoiding leak- Jukla 1974 24 6,200
a.ge is to place the tunnel as deep into
Oksla 1 980 46 17,300
the rock mass as possible, Sima 1 980 50 7,1 00
In the years before 1968 the rule of Kvilldal 1 981 43 100,000
thumb for planning unlined pressure Nye Osa 1 981 18 12,000
shafts in Norway Tafjord K5 1 981 75 2,000
was connecied with
the general layout for hydro power Brattset 1 982 26.5 3,000

180 UtnrrcrouNn Spncp Volume 8, Nunrber 3,


= 0.2, and ¡¡.9!91
('vert ratio ar a distance
of 5 d from the valley is 0.5 (d is rhe
depth of the valley ana H the maxi-
mum static head; as young,s modulus
E is kept constanr, it will nót influence
the results). To make the model di_
mensionless, the static water pressure
is expressed as the ratio H/d, where the
water head is expressed as a height in
the same units as-the valley depth"(e.g.,
in meters). The curved lines'rün
through points where the internal water
pressure- in a shaft equals the minor
prlncrpal stresses in the surrounding
I-igure 5. Defnitiorx for the rule of thumb
for tunnel design. rock mass (o, : H).
The use
After this failure a new rule of thumb The new design tool was put into use
was introduced by Bergh-Christensen .
in 197 l-72 and is describèd in detail
illustrared
tom of the
and Dannevig (1971), where the incli by Selmer-Olsen (1974). It is based on tion is loca
nation of the valley side was taken di- the use of computerized finite element and the top of the valley side 600 m.a.s.l.
rectly into accounr (Fig. 5): m_odels (rEu) and the concept rhat no- This makes d : 500 m. The maximum
where along an unlined prelsure shaft water level in the intake reservoir is
¡ ¡ "Y*'H
.
or tunnel should the internal water 390 m.a.s.l. This makes H : 290 and
1, cosB' pressure exceed the minor principal the H/d rario : 0.b8. At all points in_
where stress in the surrounding rock masi. side or below the 0.58 line tire minor
Very briefly, the rE¡r¡ mõdels are based principal stress in the ro:k mass ex_
L : shortest distance between the on plain strain analysis, Horizontal ceeds t
surface and the point studied unlined
(in m), and
stresses (tectonic plus gravitational) in- shaft; plitting
: average inclination ofthe valley
creasing linearly wirh depth are ap_ should åf.ty o?
B plied. Bending forces in th'e model aie 0.2 is i line'will
side. avoided by making the valley small in be the 1.2 0.58 : 0.7 line. As a
x
a diagram relation ro rhe whole modê|. If re- demonstration, a 45" inclined shaft is
ssure shafts quired, clay gouges (crushed zones plle{ in this po_sition in Figure Z.
presented. containing clay) may be introduced. Design charts for a numbe"r of vallev
with infor- In addition to real cases, a number side inclinations, p, are available. To Ât
mation by the Norwegian Geotechnical
Institute ( 1972) and is shown in a slightly
revised version in Figure 6. It is wãrth 1.0
noticing that the unlined pressure shafts trH< l00m ¡OA?
(#) O H = 100-200m Major teakage
where leakage is observed are, with rhe
exception of Bjerka, plotted below the
,nr:y AH = 269-396r Z
V > 300m
H Minor teakage
curves defined by the rule of thumb. 0.8
A o o Ír = 2,65
ô o
O¡ Ír = 3,00
0.6
o A
Deslgn Charts Based on
Flnlte Element Models
o 4 )-'
0.1 a7/\ ¿
Parallel wirh the revisions of the rule
of thumb, the search for
_- -J1
o -_T: á
JCOHertandsf oss
better and o
more general design criteria was inten- Z Svetgcn
sified at the Department of Geology of
I
the University of Trondheim, Tiese 0.2
S kar
criteria were to be valid for unlined OH er I an dsto s {before fa iture )
pressure shafts and tunnels, and also
for unlined surge chambers with com-
pressed air cushions. The frrst hydro
power plant with this new design, Driva, 0l02030 10 50 60
was already under construction. Figure 6. Unlined þressure shafts in uallE sides with uariou inclinatioru, p.
P'

Volume 8, Number 3, 1984


Urnrncnou¡lo Sp¡ce lgl
the actual valley side to one of these is 0.5 is used in the standard charts. An Geological Restrictlons
normally possible. In this process it is increase in Poisson's ratio, u, will give
necessary to simplify and idealize the o. : H lines that go deeper in the val- The reu-developed design charts are
valley side by smoothing out the actual ley side. For the standard charts, u : based on the assumption that the rock
profile and ignoring protruding parts. 0.2 is used. mass is homogeneous and continuous,
It is also possible to make interpola- The shape and width of the valley an assumption which cannot be abso-
tions between two standard design have a major influence on the stress lutely correct even for massive Precam-
charts.It is important that the profrles distribution near and under the bot- brian granites and gneisses. However,
be made at a right angle to the contour tom of the valley. The analyses, how- observations and investigations of stress-
lines of the map. In cases where the ever, have shown that the os : H lines induced stability problems such as rock
pressure shaft is placed in a part ofthe on levels above the bottom and at ac- bursts, popping rock, and spalling rock
valley side which is protruding in the tual distances from the valley side are in a large number of tunnels in lord
horizontal section, a series of profrles not influenced much. On the standard and valley sides clearly indicate that the
through the protruding part should be charts the width of the bottom of the naturaljointing of rock masses has only
studied. valley is normally % d. minor influence on the distribution of
Through a number of analyses, all So far only two-dimensional models the virgin stresses. The jointing may,
the factors influencing the results have have been used, and the stress perpen- however, have a strong influence on
been carefully evaluated within natural dicular to the model plane has been the final development of a stability
limits. For example, if a measured bulk assumed to be the intermediate prin- problem as well as on leakage through
density, 1., varies from the standard cipal stress, or. Stress measurements are the rock mass.
2.75, this can be compensated by a cor- sometimes carried out as a control, As the permeability of rock normally
rection of the overburden by the ratio mainly where there is reason to believe is negligible, it is the jointing and the
2.7\fi,. Also, an upper layer of topsoil that the tectonic stresses are not nor- faulting of the rock mass, and in par-
or weathered rock masses can be com- mal. Also, hydraulic splitting tests are ticular the type and amount of joint
pensated for by reducing the thickness sometimes used as a control of the o, inÍìlling material, that is of importance
of the overburden in accordance with : H lines. For such tests it is important when an area is being evaluated. Cal-
the bulk density of these masses. that the boreholes intersect natural cite is easily dissolved by cold, acid water,
Measurements as well as observa- joints with unfavorable directions with and gouge material like silt and swell-
tions indicate that the or"JÇ,.n ratio in regard to the possibility of leakage from ing clay are easily eroded. Crossing
topographically undisturbed areas in the unlined shaft. The splitting pres- crushed zones or faults containing these
Norway normally varies between 0.5 sure is raised to 2OVo al¡ove the esti- materials should preferably be avoided.
and 1.3, and very seldom exceeds 1.5. mated minor principal stress at the ac- If this is not possible, a careful sealing
As a conservative solution, a ratio of tual location. and groutingshould be carried out. The

p:40"
d

Urock = 2,75 H/d.


t,S
V = 0,20
K = lho, /q.., = 0,5
d = depth of valley
¡ = max. static water head

Figure 7. Design charl for unlined presntre shafß based on a fnite elemenl nodel. 'f he cur-ues run through þoints where th¿ inlernal uutn
þressurein the shaft equak lhe minor þrincipal sttess in the sunounding roch mass, H : o",

182 UNoercrouuo Slnce Volurne 8, Nurnber 3, l9fl4


CONCRETE PLUG
ACCESS TUNNEL
PR ES SURE
SHAF T

T RASH RACK
reTUNNEL
ÏURBINE

PLAN OF AN UNDERGROUND HYDROPOWER


PLANT WITH UNLINED WATERWAY

CROSS SECTION THROU6H THE WATERWAY

UNLINEO STEEL & CONCRETE UNLINED


LIN IN G LIN IN O
Figure 8. PIan and cross seclion of am underground hydroþouer plant with unlined walerways.

grouting is the more important the and Rjerka was caused by such unfa- Underground Hydropower Plants
closer leaking joints are to the power- vorably oriented joints and faults. A WIth Unllned Watenvays
house and access tunnels and thè more careful mapping of all types of discon-
their directions point roward these. The tinuities in the rock mass is therefore
same is also valid for zones or layers of an important part of the planning and
porous rock or rock that is heavily design of pressure shafts.
jointed or broken. During the construction period it is
.important- that changes in àll leakage
into the shaft or tunnel, even minór are given, as the intention is to show a
dri system rather than give details. Similar
ser la_youts can be found for Norwegian
stress distribution, If
they have a strike for plants with warer heads in the rangi of
nearly parallel to the valley side with a the 200-600 m.
steep or medium-steep dip towards the The figure is to some extent sel[-ex-
valley, they are especially dangerous. planatory. It
Not only may they change rhe stress however, tha
distribution; they may also often cause are used the
leakage during construction as well as point will no
during operation. The hydraulic split- lined pressure shaft ends and the steel
ting of the pressure tunnels at .{skora bers. lining starts, This is where the selecred

Volume 8, Number 3, 1984


U¡ruEncnoulo Sp,qce 183
os : H line should intersect the water- 197 | - I ngeniórgeologishe oerderinger uerdór- lined pressure shafts and tunnels in Nor-
way. The elevation of this point and ende uforet tryhhsjaht ued Mauranger hraft- way, Roch mechanics: cauerns anl, þressure
the length of the steel-lined section will uerh (Engineering geological eualuations of såalts (lVittke, editor). Rotterdam, The
the unlined þressure shu.ft at the Mauranger Netherlands A. A. Balkema. Pp. 545-554.
vary with the water head, the size and
hldroþouer þlant). Unpublished report. Broch, E. 1984. Design of unlined or con-
orientation of the powerhouse, and the Oslo, Norway: Geoteam A/S. crete lined high pressure tunnels in top-
geological conditions, in particuìar the Bergh-Christensen,J., 1975. Brudd i uforet ographically complicated areas. To be
character and orientation ofjoints and trykktunnel ved A,skora kraftverk lFail- published in Water Pouer and Dam Con-
fissures. Lengths in the range of 30- ure of the unlined pressure tunnel at the struclion 36:ll.
80 m are fairly common. A.skora hydropower plant). Fjelkþreng- Buen, 8., and Palmstróm, A. 1982. Design
The access tunnel to the foot of the 4 Broch,
ningstehnihh-B ergntehanihh I 97 and supervision oF unlined hydroporver
unlined pressure shaft is finally plugged Heltzen, and Johannessen, editors). shafts and tunnels with head up ro 590
Trondheim, Norway: Tapir. Pp l5.l-15.8. meters. Roch mechanics: caaeÍns and pres-
with concrete and a steel tube with a
Bergh-Christensen,J., and Kjolberg, R. 1982. sure shafx (Wittke, editor). Rorterdam, The
hatch cover. The length of this plug is Investigations for Norway's longest un- Netherlands 1982. A. A. Balkema. Pp.
normally l0-25 m, depending on the lined pressure shaft. Water Pouer and Datn 567 -57 4.
water head and geological conditions. Construt lion 34 :4, 3 l-35. Johansen, P. M., and Vik, G. Prediction of
Around the concrete plug and the up- Bergh-Christensen,J., and Kjolberg, R. 1982. air leakages from air cushion surge cham-
per part of the steel-lined shaft a thor- Investigations for a 1000 metres head un- bers. Ro¿å mech.anics: caaerns and, þressure
ough high-pressure grouting is carried lined pressure shaft at the Nyset/Steggje såals (Wittke, editor). Rouerdam, The
out. This avoids leakage into the pow- project, Norway. Roch mechanics: cauerrß Netherlands: A. A. Balkema, Pp.935-938.
erhouse and the access tunnels. and þressure såa/ts (Wittke, editor). Rot- Myrset, Ó. tsAo. Underground irydro-elec-
terdam, The Netherlands: A. A. Bat- tric power stations in Norway. Subsurface
kema. Pp 537-543. sþace (5. M. Bergman, editor). Vol. l. Ox-
Concluding Remarks Bergh-Christensen, J. 1982. Design of un- ford: Perganron Press. Pp. 69t-699.
Experience from a considerable lined pressure shaft at Mauranger pow- Myrset, O., and Lien, R. 1982. High pres-
number of pressure tunnels and shafts, erplant, Norway. Roch mechanics: carenß sure tunnel systems at Sima powerplant.
and þressure såalts (Wittke, editor). Ror- Roch mechanics: coûerrùs and, þressure shafß
as well as so-called air cushion surge
terdam, The Netherlands: A. A. Bal- (Wittke, editor). Rotterdam, The Neth-
chambers, have been gathered over a kema, Pp.53l-536. erlands: A. A. Balkema. Pp. 667-676.
long period of time in Norway. These Bergh-Christensen,J. 1982. Surge chamber Norwegian Ceotechnical Institute. Oue¡siht
show that, providing certain design rules design for Jukla. Water Pouer and Dam oaer norshe ufôrele tunneler og sjahter (A re-
are followed and certain geological and C or¿struc tion 34 : I 0, 39
- 41. ttieu of Norutegian unlined þressure lunnek
topographical conditions avoided, un- Brekke, T. L., Bjórlykke, S., and Blind- and shafts). Unpublished report.
lined rock masses are able to contain heim, O. T. 1970. Finite element anal- Rathe, L. 1975. An innovarion in surge-
water and air under pressures up to at ysis of the Byrte unlined pressure shaft chamber design. Water Power 27 ,244-248.
least 75 bars, equaling 750 m water failure. Large permanenl underground oþen- Se Imer-Olsen, R. 1970. Experience with un-

head. [n the future this experience may ings (Brekke and Jórstad, editors). Oslo, lined pressure shafts in Norway. Larga
Norway: Universitetsforlaget. Pp. 337- þermanent underground oþenings (Brekke
also be important outside the hydro
342. and Jórstad, editors). Oslo, Nonvay:
power industry, for instance in the Broch, E., and Bergh-Christensen,J. 1962. Universitetsforlaget. Pp. 327 -332.
construction of cheap, unlined storage Undersókelse verdrórende ulôrete Selmer-Olsen, R. 1974. Underground
facilities for different types of gas or try kksj akter (I nu e s ti g atiorx of un line d pr e s - openings frlled rvith high-pressure water
liquid under pressure. n sure shafß). Trondheim, Norway: Inst. for or air. BuLI. Int. Ass. Engineering Ceology g,
Bassbygging, NTH. I l-95.
Broch, E. 1982. Designing and excavating Vogt, J. H. L. 1522. Tryhhtunneler og geologi
underground powerplants. Water Pouer (Pressure lunnek and. geologl. Report no.
References and Dam Construction 34:4, 19-25. 93. Oslo, Norway: Norges Geol. Under-
Bergh-Christensen,J., and Dannevig, N. T. Broch, E. 1982. The development of un- sokelse.

184 Urur¡Encnoulo Sp.<:e Volunle 8, Nurnber 3, lg84

You might also like