Professional Documents
Culture Documents
1. Hudson Formula:
Contract Profit % x [Contract Sum/ Contract Period] x Period of Delay
= NIL
(This would be applicable only in case of Cost plus contracts type contract where
some % of profit margin has already defined by the contractor in contract itself in
overall execution of the project which is over & above the actual project cost
incurred by the contractor)
2. Emden Formula:
Profit % x [Contract Sum/ Contract Period] x Period of Delay
= 9.91% x [108/12] x 57 Months
= 50.83 Cr ……This is the amount of Damages
3. Eichleay Formula:
Step 1:
Contract Billings Actual / Total Billing for Contract Period x Total OH for Contract
Period
Step 2:
Step 3: