Professional Documents
Culture Documents
Versus
INDEX
[NISHANT DATTA]
DATTA & CO.,
ADVOCATES FOR RESPONDENT
12, Lawyers’ Chamber Block-I,
Delhi High Court,
New Delhi 110003.
Email: dattacoadvocates@gmail.com
Tel: 011-23388305, 9811698993.
NEW DELHI
DATED: ___.04.2021.
1
Versus
respondent herein.
and all disputes arising from all three must be resolved in this arbitration
proceeding;
May 2015;
15. That it is submitted that the above That the contents of these paragraphs
Agreement all dated 12th August agreements are three different and
2009 are inter- related and part individual scope. It is submitted that
and parcel of one contract i.e. the claimant herein in its endeavor to
were signed on the same date; i.e. project in the prescribed duration and
parties at New Delhi. The three attempting to prove the three different
three are inter-linked and part of drafted in the form of one single
68. The Engineering Agreement and That the contents of the instant
the Supply Agreement provide for paragraph are admitted to the effect
mention herein that the Erection erection agreement does not contain
4
said agreements were entered into submitted that the issues relating to
on the same date, i.e., 12th the validity of the erection agreement
parties and are part of the same proceedings were adjudicated upon
of the same Power Plant and as whereby the Ld. Arbitrator was
under:
“17. For the afore stated reasons, I come to the conclusion that there
“The learned counsel appearing for the Claimant had submitted that in
view of the order passed by the Tribunal dated 13th December, 2017,
that the claim petition already filed and the supplementary claim
amending the entire statement of claim. The learned counsel for the
was decided that the Claimant shall file a supplementary claim petition
In view of the fact that a comprehensive reply has already been given
7. That the order dated 13th December 2017, insofar as the same
Tribunal vide it's order dated 9th June 2019, the claimant filed its
9. That what emerges from a perusal of the above is that the entire
that out of the 3 contracts executed, one contract did not have an
sake of convenience and that they are part of the same transaction.
8
that all the three agreements were interlinked and there was only
one contract.”
12.It is also the admitted case of the Claimant that the contract for
to the contract being novated - Rs. 60.14 Cr for supply and Rs.47.86
arbitration clause was provided for the said two contracts taken
of arbitration.
13.In the claim petition, the claimant has proceeded and has built up
its entire case on the presumption that all the 3 contracts being a
Claimant does not give any breakup of the outstanding dues and
supply agreement.
have been raised. It is further submitted that the invoices never see
the light of the day. The rule of best evidence must be applied and
Claimant.
over the vendors/sub vendors for the supply of the material. This
loose control over the suppliers and secondly, said loss of control
and the Claimant actually could not ensure compliance with the
timelines.
16.The claimant agreed to all these changes and in fact required them.
Further, no grievance can be raised at this stage about it. When the
contract terms are novated and such change would make the
agree. The plea of duress is completely false and baseless and the
for Respondent was in 2011 and 2012 and because of that the entire
basis of letter dt. 24.2.10 (alleging that it was done at the instance
of banks falls as the banks were not in the picture in 2010 even as
per claimant).
17.In view thereof, and keeping in mind the admitted case that the
payments for the supply of the goods was being made directly by
the claimant. Thus, the entire claim for the supply of the goods is
entail any presumption and the onus lay entirely on the Claimant
from the Respondent cannot shift the onus of proof in any manner.
20.The Claimant has not led any direct evidence whatsoever to show
the goods has been placed on record by the claimant. The claimant
21.In support of its claim, the claimant has filed various challan
at the relevant point of time was covered under the value added
tax mechanism and no challan for payment of any value added tax
at the site nor has any other evidence been produced by the
claimant to show that the alleged goods have been brought at the
site by the claimant. No proof of supplies has been filed, much less
proved and only progress reports are being relied upon, which at
the Evidence Act, 1872. Further, the Claimant has also not filed
the Claimant.
supplied by the claimant and for which payment has not been
could have been easily identified. The onus to produce the said
25.It is the admitted case that the supply contract is worth Rs. 60
Crores. The Claimant admits that Rs.59 crores have been paid to it.
15
98% of the work is done, which means, all supplies are complete
and paid for, only the erection part remains. 98% would constitute
done.
26.The claimant has laid great stress on the fact that Respondent has
settled law that the claimant has to prove his own case and cannot
28.The road was already there as the Claimant admits that a running
material and men and the same was done by it on the assumption
of being awarded the contract. This claim will also be beyond the
present agreement(s).
own funds by the claimant their dues were not being cleared:
On the one hand the Claimant says nothing could be done as there
was no money and on the other hand, the Claimant also says that
be believed, lack of funds could not have come in the way of work
being done.
be new, which was also supplied second hand, due to which the
repair work. They should tell the Hon’ble Tribunal that it the job of
Thermax and not the Claimant, then why would the Claimant do it
33.The Claimant’s claim for the overrun cost shall be 30% on the
allowed as the claimant has not proved any actual loss suffered by
Claimant has not led any evidence to show the extent of loss
only the outer limit. Actual loss has to be proved. The Claimant
has also relied upon judgment in case of KNA and as such must
as such must have been duly accounted for, which do not see the
light of the day. The Claimant’s has claimed amounts for allegedly
thereof.
Claim No.3:
amounts and figures and the same should have been furnished.
Rs.2 crores has again not been proved and no cost certificate has
been furnished. Lastly, the interest rates and duration claimed are
also not tenable and 18% is overly excessive. The Claimant has
failed to show its net profit percentage and/or cost of any alleged
In light of the above, the Hon’ble Tribunal may kindly reject the
merits the same are not tenable while the Respondent’s counter
[NISHANT DATTA]
DATTA & CO.,
ADVOCATES FOR RESPONDENT
12, Lawyers’ Chamber Block-I,
Delhi High Court,
New Delhi 110003.
Email: dattacoadvocates@gmail.com
Tel: 011-23388305, 9811698993.
NEW DELHI
DATED: ___.04.2021.