Professional Documents
Culture Documents
AN ARBITRATION BETWEEN:
THROUGH
AN ARBITRATION BETWEEN:
…CLAIMANT
AND
…RESPONDENT
SYNOPSIS OF SUBMISSIONS
seeing the good records of the Claimant who had earlier successfully
completed the 350 TPD DR Plant for the Respondent and their goodwill in
Erection Agreement. The present Contract was not the first project
between the parties and infact the prior agreement was entered on the
discharge its obligations as per the contract even before the formal
contract was signed but there was a gross delay in payments and the
schedule of the contract. As per the contracts signed between the parties
the time of signing of the agreement. This payment was necessary so that
andtook almost one year to release the advance payment. Despite the
good faith and even had to use their own manpower, train their own
people for the work to be done, pay the third parties from their own
about the overdue payments with respect to work done as per progress
Claimant Company stating about the payments made to the third parties in
1/6 Claimant Document Page 31) that payments have not been
released by the Respondent despite delivery of the items from the vendors
of steel, cement etc. Further similar reminders were also sent on 21st
2011 (Ex. CW 1/8 Claimant Document Page 35) and 7th April 2011
hardships being faced by the non release of the payments. The Claimant
5. The entire civil and structural work for the Power Plant was completed
availability of funds was delaying the supply of electrical goods and other
inputs. The Claimant had even deputed extra 25-30 operation staff for
was also called upon to enter into a proper agreement for continuous
operations and maintenance of the plant with the claimant which was later
declined and M/s Ensol was preferred over the Claimant by the
Respondent.
email was sent to the respondent stating that the work was heading for
Email to Respondent was sent stating that the Claimant had submitted
the commissioning and make available funds for expenses of the staff and
2011 and requesting the Respondent to release the payments. Details sent
respondent.In fact all the invoices raised by the claimant for the work done
were got verified by the respondent from its senior employees from time to
by the Claimant and the respondent was requested to smoothen the cash
Ensol who in fact did not have the expertise nor manpower to perform the
required task. The Claimant had infact forewarned the respondent about
the same. This was later realized by the respondent. Due to the
inspite of investing its own funds by the claimant their dues were not being
cleared. The contractors were sitting idle because of lack of funds. Inspite
of assurance given nothing was done by the respondent. Kindly see mail
which were incorrect and dehors the agreements and subsequent conduct
of the respondent.
Claimant Document Page 85), stating the service tax of Rs.97.86 Lakhs
of which the Respondent Company has already availed CENVAT was not
9
Claimant company, which makes total pending taxes & duties of Rs.1.50
10. As per the negotiations between the parties the Respondent had
agreed to source second hand turbines along with the Air cooled
condensers to cut down the cost of the project and the same has been
accepted by both the parties in interest of cost cutting of the project. The
project cost was reduced to Rs.2.8 Crores per MW by cutting the down the
Turbine along with Air Cooled Condensers would have cost around Rs. 5.5
Cr. per MW. Sourcing of second hand Turbines helped in making the
11. As per the terms of the Contract, it was the Claimant who had to
purchase the materials from well reputed third party vendors and was
required to make payments to all their vendors but this all was subject to
the timely payments and clearing of invoices on time which was already
between the parties because of which there was a delay which was
Respondent.
10
placed orders directly and settled all terms of supply with them. The
claimant was left with no say in the matter. It was precisely because of this
reason the respondent did not insist on the claimant furnishing any
various vendors/suppliers.
make any direct payment to any third party vendor. As per the clear terms
the vendors and the same had to be reimbursed by the Respondent. The
direct payments made by the Respondent later to the Third Party vendors
had resulted in loss of control of the Claimant over the vendors thus losing
the essence of the nature of the turnkey contract. Also the payments made
violating the terms of the agreements. One of the main reasons for the
company neither had the Steel Melt Shop ready, which would consume
power generated nor an agreement with the State Grid to export power in
increase in cost of the project for the Claimant and the claimant has
contract.
15. The Respondent arbitrarily stopped the entry of the Claimant into
project site in May-2015 without any prior notice and without terminating
the contract.The Claimant Company has been associated with this Project
in the most professional manner right from inception and hasmaintained its
manpower at site with accommodation and vehicles for such a long time
the Respondent has made some arrangement with the M/S Gulf Ispat for
taking over the project without the Claimant’s consent and barred the
Claimant from entering into the project site. All these facts were
Respondent Company, the Claimant was left with no other option but to
After constitution of the Tribunal the claimant has filed the Claim petition
12
SUBMISSIONS
of RW-1).
29.03.2010).
completed?
project has been delayed by more than one year for no fault
21.08.14)
and the only work left was the formal commissioning of the
along with air cooled condensers and all the vendors were
and the sources from which they were purchased for the
Ans.Yes}
aspect.
Thermax.
Respondent?
Ans.Yes}
commissioned.}
20
E- mail address.
into project site without and any prior notice and without
arrangement with the M/S Gulf Ispat for taking over the
you that Mr. Rohit Mittal from Gulf Ispat Power was handling
all the affairs of the Power Plant from the side of the
Ans. It is not Gulf Ispat Power but it was Gulf Petro Chem.
Yes, Mr. Rohit Mittal was looking after all affairs of the entire
of the work has been completed and the only work left was
2015. In any case, despite this all the three bollers were
stopped the entry of our staff and engineers into the plant
communication.”
into the Project site, without any prior written notice neither
witness.
Ans. No such Letter was written. (This belies the case of the
you that Mr. Rohit Mittal did not permit any employee of the
CLAIMS
the claimant has raised its demand for the outstanding balance payment of
16.27 Cr. This email is sent on the admitted email ID of the Respondent.
party directly against the total value of EPC Contract being Rs. 108 Crores
awarded to it on
The Hon’ble Supreme Court has held in Brij Paul & Bros. Vs. State of
work.
AIR2009Delhi 88. In this case, it was stated by the ld. arbitrator that the
law is well settled that if a breach has been committed by a party then the
compensated for the deprivation of his profit. The breach in this case was
the respondent who did not allow the claimant to perform his part
of the contract, while the claimant had been ready and willing to
carry out and to execute the contract. Therefore, the claimant was
held entitled to expect profit which he would have earned had the
for the compensation was 10% and the reasoning was approved and
(2006)11SCC181
In this case, the Hon’ble Supreme Court discussed three popular formulae
27
which calculate loss of profit along with loss of overhead. They are the
Hudson formula, the Emden formula and the Eichleay formula. It was
the facts and circumstances of a particular case, would eminently fall within
1972 SC 696
In this case, the Hon’ble Supreme Court held that the method used for
each case. The court held so following the landmark English judgement
mentioned that the project has been delayed with no fault of the Claimant
and that the overrun cost shall be 30% on the balance work.
28
The Respondent are also liable to pay liquidated damages for the loss
“By any reason the project gets delayed more than one month due to no
fault of PECL, TIL shall pay liquidated damages to PECL at the rate 2%
that:-
awarded not exceeding the amount so stated. Similarly, in cases where the
liquidated amount or penalty is the upper limit beyond which the court
are applicable to the law of contract, which are to be found inter alia in
a suit.
have been caused thereby" means that where it is possible to prove actual
damage or loss, such proof is not dispensed with. It is only in cases where
awarded.”
(Emails 7.04.11 & 23.04.11). The Claimants were burdened with salary and
respondent.
30
essence, breach by the promisor to perform its obligation at the fixed time
contract. However, it further states that where the intention of the parties
is that time should not be of the essence of the contract, the contract does
essential
Effect of such failure when time is not essential: If it was not the intention
of the parties that time should be of the essence of the contract, the
from the promisor for any loss occasioned to him by such failure.
his promise at the time agreed, the promisee accepts performance of such
31
promise at any time other than agree, the promisee cannot claim
Maharashtra AIR 1979 SC 720 has held that the question whether or
not time was of the essence of the contract would essentially be a question
contract. It was further held that even where the contract provides that
date later than that originally stipulated. Therefore, it could never have
been the intention of the parties that completion of the contract work by a
“8. It will be clear from the aforesaid statement of law that even where the
parties have expressly provided that time is of the essence of the contract
such a stipulation will have to be read along with other provisions of the
exclude the inference that the completion of the work by a particular date
for payment of fine or penalty for every day or week the work undertaken
remains unfinished on the expiry of the time provided in the contract such
of time it seems to us clear that time (12 months period) was never
The principle of law laid down in the Hind Construction Judgment was
(1999) 9 SCC 449, where the Hon’ble Supreme Court held as follows:
“14. Incidentally the law is well settled on this score on which no further
dilation is required in this judgment to the effect that when the contract
itself provides for extension of time, the same cannot be termed to be the
essence of the contract and default however, in such a case does not make
issue can be brought within the ambit of the first para of Section 55 and it
24. … The contract itself provides reciprocal obligations and in the event
continuing with the notion of the time being the essence of the contract
that time was not treated as of essence in the present Contract by the
Respondent.
In this regard, reliance may be placed on the Delhi High Court's decision
committed a patent illegality. The Court, while upholding the award, held
that as the claim was owing to delay and the delay in handing over the
construction site had been established, the threshold of evidence for the
"The AT referred to the Standard Data Book for Analysis of Rates (First
months' delay. It also referred to the Hudson formula. This was on the
handing over of the site to it by the Petitioner was concerned. The failure
circumstances."
34
was no record proving the same. The Tribunal noted that the monthly
to the respondent.
during the extended period of contract. The Tribunal noted the plea of the
Tribunal held that the said submissions of the petitioner are erroneous as
calculations based on Standard Data Book are accepted guidelines and are
being followed by the petitioner and its engineers extensively. Even the
rate analysis of various items is being worked out based on the format
given in the Standard Data Book. The Tribunal noted that the monthly
respondent did not suffer any loss during the extended period of contract
24. It may be noted that there can be no quarrel with the Arbitral Tribunal
"104. ........We may at this juncture notice the different formulas applicable
in this behalf.
23.10.2012.
High Court held observed that a claim for loss of earning capacity and
It means that the manpower, plant and machinery used at the site by the
use the same for another contract and it is loss of profit of that other
usually suffer a loss of the profit earning capacity of the particular contract
earned and without being free to move elsewhere to earn the profit which
respondent has defaulted in payment of taxes and that the same will have
respondent.
which the Respondent Company has already availed CENVAT was not
37
Claimant company, which makes total pending taxes & duties of Rs.1.50 Cr
claimed and Hon’ble Tribunal mayaward any other or further relief as the
Hon’ble Tribunal deems fit and proper in the facts and circumstances of the
case.
THROUGH