Professional Documents
Culture Documents
Graduate School
Manila
I. ABSTRACT
The case of H.L. Construction Inc. vs. Marina Properties Corporation brings to
the forefront a complicated legal dispute between two prominent entities in the fields
of construction and real estate development. H.L. Construction Inc. (HLC), a reputable
construction company, alleges that Marina Properties Corporation (MPC), a renowned
real estate developer, breached the terms of their contractual agreement by failing to
make timely payments, thereby impeding the project's progress and putting HLC
under significant financial pressure. In contrast, MPC contends that the project delays
and setbacks were largely attributable to HLC's substandard craftsmanship,
inadequate oversight, and failure to adhere to agreed-upon schedules, which
prompted MPC to withhold payments to ensure satisfactory project completion.
This case seeks to examine the specifics of HLC and MPC's contractual
agreement, investigate the sequence of events that led to the dispute, and evaluate
the validity of the claims presented by both parties. The case highlights the potential
complexities inherent in commercial construction projects and emphasizes the
importance of clear communication, thorough documentation, and strict adherence to
contractual provisions in order to reduce the likelihood of disputes and costly litigation.
1
II. BACKGROUND OF THE STUDY
On December 15, 1989, HLC filed a lawsuit for monetary damages against
MPC and its alleged president, respondents Jesus K. Typoco, Sr. and Tan Yu, seeking
the payment of various sums totaling P14 million pesos.
a. P7,065,885.03 for labor price increases, change orders, and material price
increases;
b. P2,000,000.00 in additional compensatory damages, exclusive of court costs.
c. P3,147,992.00 representing retention funds allegedly withheld by MPC on HLC's
Progress Billings beginning in January 1990.
d. P2,000,000.00 representing the value of construction materials allegedly withheld
by MPC.
The respondents filed separate answers, denying the complaint's allegations and
claiming they are not parties to the Construction Contract and Amendatory Contract
and therefore not liable to HLC. MPC countered that HLC has no cause of action
against it and is not entitled to its claims. MPC counterclaimed for P68,296,227.14 in
actual, compensatory, liquidated, unliquidated advances, and attorney's fees.
2
On May 15, 1997, the trial court ruled in favor of HLC and ordered the following from
respondents MPC, Tan Yu, and Jesus K. Typoco, Sr.:
Due to a lack of evidence, the counterclaim for liquidated damages was dismissed.
Liquidated damages can only be awarded under paragraph 2 of the amended
construction contract that extended the completion date, and primarily based on the
finding that the project was 85% substantially complete, and that the delay and
stoppage of the project were caused by the respondent's failure to pay the progress
billings that would have allowed the petitioner to continue and complete the project.
The Court of Appeal ruled that Respondents were not liable for increases in
the cost of labor and construction materials on appeal. The CA based its decision on
the fact that the parties' contract was for a fixed sum of money and did not account
for inflation. Since there was no addendum covering change orders and extra work,
as stipulated in the primary Construction Contract, Respondents were also exempt
from such costs. Even though it appears that the petitioner performed additional
3
work as indicated by Progress Billing No. 24, this claim is not backed up by
adequate evidence.
The CA also came up empty when trying to justify waiving the 10% retention.
Petitioner did not meet the conditions set forth in the Construction Contract for
granting such a release, so no such release was granted. Since the petitioner
ultimately withdrew the construction materials, MPC was also not held liable for their
detention or withholding. There was no evidence in the files suggesting that Typoco
or Tan bore any legal responsibility. Furthermore, there was no liability for MPC to
assume toward the petitioner. The petitioner was found to be responsible for both
actual and liquidated damages by the CA. Since the latter had left the project
unfinished, MPC had to hire someone else to finish it and ended up paying more in
damages than the contract's remaining balance. In addition, the Construction
Contract called for liquidated damages to be paid at the rate of one thousandth of
the contract price for each day of delay.
CA agrees with petitioner that it is entitled to price escalation, but only for Progress
Billing No. 24's labor. The Contract only allows labor cost escalations, so material
cost escalations are prohibited. No provision in the original or amended contract
4
justifies billing for increased material costs. Petitioner provided no evidence of
material cost increases, such as official economic data on construction material price
indexes. Petitioner claims these cost escalations are damages due to billing delays
and claims for additional work. Respondents are liable for damages under Article
2201 of the Civil Code for their baseless and malicious refusal to pay those claims.
Retention Money
The claim for the 10% retention money was denied by the CA because the petitioner
failed to comply with the conditions set forth in paragraph 6.3 of the Construction
Contract. On the other hand, the latter claims that these conditions were deemed
fulfilled under Article 1186 of the Civil Code because MPC prevented the fulfillment
of those conditions when its contract was terminated. It would be allegedly unfair
and unreasonable for petitioner to guarantee the completion of a project by another
contractor. The simple fact is that by failing to complete the project, the former failed
to meet a requirement for the release of the retention money.
5
Detained Materials
After two years, petitioner was allowed to remove illegally detained materials from
the site. Only 30% of detained materials were salvageable by 1992. Not true. The
CA ruled that MPC detained petitioner's materials only because it denied the
February 1990 letter's request for used form lumber. However, petitioner only
attempted to obtain its request in that letter. It should have tried again before
claiming respondents unreasonably prevented it from removing its construction
materials from the premises. The other materials were never removed from the
construction site. Thus, petitioner was never denied these.
Petitioner also had a warehouse in a construction site yard that was guarded by its
own security and inaccessible to MPC personnel. Therefore, it should have
protected those materials from the elements and theft.
Attorney’s Fees
Petitioner claims attorney's fees under Article 2208 of the Civil Code because
respondents' act or omission forced it to litigate with third parties or incur expenses
to protect its interest, and respondents acted in gross and evident bad faith in
refusing to satisfy its plainly valid, just, and demandable claim. The project was not
completed despite petitioner's claims being granted. Because the right to litigate
should not be monetized, attorney's fees are not awarded to winning parties.
Petitioner is not blameless in this dispute. MPC's withholding of petitioner's
payments does not indicate gross or evident bad faith. MPC had counterclaims.
Typoco did not act in bad faith, gross negligence, or outside his authority as
company president, according to the records. MPC should have been cited for
contempt of court for unilaterally terminating the Contract during the TRO, and a
6
preliminary injunction would have stopped the second contractor from working.
There is no evidence that the unilateral Contract termination was void.
Tan is not an MPC officer or director. He only spoke to petitioner's project manager,
Engineer Mario Cornista. The former allegedly verbally guaranteed the latter's
progress billings. Respondent's solidary liability to petitioner is unproven.
Petitioner claims that respondents' actions caused its project's failure, exonerating it
from counterclaims for actual and liquidated damages. Petitioner breached contract.
Since MPC was allowed to fire the contractor, it could not blame MPC for hiring a
second contractor. Petitioner completed about 80% of the project by November 30,
1989. It was already delayed. Respondents suspected it would not finish the project
after Engineer Miranda testified that it would lose money even if it did.
Petitioner delayed and breached contract. The obligor must pay damages that result
from its breach. MPC paid petitioner P31,435,187 of the P38,580,609 contract price,
leaving P7,145,422. The latter paid P11,750,000 to a second construction firm to
finish the project. Thus, MPC lost P4,604,579 for project completion.
Contract liquidated damages apply to petitioner.
Liquidated damages are agreed-upon penalties for breach. The agreed amount
compensates the owner for project delays. Philippine law considers these damages
penalties. Penal clauses increase liability in case of breach. It is attached to an
obligation to ensure performance. According to the CA, petitioner must pay
liquidated damages for 92 days, from the grace period in the Amended Contract's
expiration to February 1, 1990, when it abandoned the project.
7
VI. CONCLUSION
VII. RECOMMENDATIONS
8
protected and their interests are represented. Overall, adhering to these suggestions
can aid in avoiding legal conflicts similar to H.L. Construction vs. Marina Properties
Corporation and ensuring the successful completion of construction projects.