PROJECT : REPAIR WORKS FOR TWO-DTOREY RESIDENTIAL BUILDING

LOCATION : MARINA HEIGHTS SUBDIVISION PARANAQUE CITY


SUBJECT : COST PROPOSAL - REPAIR WORKS DUE TO LEAKS

Item No. ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

I. GENERAL REQUIREMENTS
1.0 Mobilization & Demobilization 1.00 lot 3,000.00 3,000.00
2.0 Cleaning, Hauling and Disposal 1.00 lot 1,500.00 1,500.00
3.0 Temporary Facilities (Barracks, Water and Power) by owner
SUBTOTAL I. GENERAL REQUIREMENTS 4,500.00

II. GROUND FLOOR


1.0 Ceiling works
a. Maid's Room
- Dismantling of ceiling 4.00 sqm 200.00 800.00
- Installation of ceiling 5.00 sqm 980.00 4,900.00
- Painting of ceiling 4.00 sqm 360.00 1,440.00
b. T&B
- Dismantling of ceiling 3.00 sqm 200.00 600.00
- Installation of ceiling 4.00 sqm 980.00 3,920.00
- Painting of ceiling 3.00 sqm 360.00 1,080.00
SUBTOTAL II. GROUND FLOOR 12,740.00

III. SECOND FLOOR


1.0 Removal of existing tiles 1.00 lot 1,200.00 1,200.00
2.0 Tracing and repair of leaks 1.00 lot 5,000.00 5,000.00
3.0 Installation of new tiles 1.00 lot 18,000.00 18,000.00
4.0 Waterproofing of floor (Bathroom area) 1.00 lot 8,000.00 8,000.00
SUBTOTAL III. SECOND FLOOR 32,200.00

IV. PLUMBING WORKS


Tracing, declogging and repair of sanitary pipe line
1.0 from ground floor to septic tank 1.00 lot 20,000.00 20,000.00
SUBTOTAL IV. PLUMBING WORKS 20,000.00
DIRECT COST, PHP (VAT EXCLUDED) 69,440.00

Terms and conditions:

1. All works not included above will be subject to additional


works and will be charged accordingly.
2. Terms of payment - 50% Down payment, 50% balance by progress billing
3. Mobilization - 3 days upon receipt of down payment

SUBMITTED BY: CONFORME:

_____________________________ ___________________
RIO GRACE G. ILAGAN OWNER
OPERATIONS MANAGER
DATE: __________________________________