You are on page 1of 335
IMPERIAL \BP 3-2-1 SEWER SYSTEMS REV 7 JUNE 88 PAGE 1 OF 19 BASIC PRACTICE 1 € 1 2 Deleted. 3 Anasterisk (*) indicates that additional information is required. If a job is contracted, this additional information is furnished in the Job Specification. ‘SUMMARY OF ADDITIONAL REQUIREMENTS, 241 Table I lists the Basic Practices Standards and Publications which shall be used with this Basie Practice. Local codes and/or standards shall govern if they are more restrictive than this Basic Practice. SCOPE This Basic Practice covers mandatory requirements governing the design and installation of sanitary and industrial sewer systems FIGURE 1 Basic Practices 1BPO-0-1 General Conditions TBP3-18-1 Piping Fabrication TBP3-19-1 Piping Erection and Testing IBP20-1-2 Administrative Procedures for Obtaining Imperial Oil Engineering Approval Standards ASTM Standards dB Gray Iron Castings ASS Pipe, Steel, Black and Hot-Dipped, Zinc Coated Welded and Seamless A74 Cast Iron Soil Pipe and Fittings C14/C14M_—_Conerete Sewer, Storm Drain and Culvert Pipe Sewer and Manhole Brick C16/C16M_—_Reinforced Concrete Culvert, Storm Drain and Sewer C139 Concrete Masonry Units for Construction of Catch Basins and Manholes 279 CChemical-Resistant Masonry Units €361/C36IM Reinforced Concrete Low-Head Pressure Pipe cas ‘Compression Joints for Vitrified Clay Pipe and Fittings C700 Vitrified Clay Pipe, Extra Strength, Standard Strength and Perforated AWWA - American Water Works Association 203 Coal Tar Protective Coatings and Linings for Steel Water Pipelines Enamel and Tape — Hot Applied cu Gray-Iron and Ductile-Iron Fittings, 3 in. through 48 in. for Water and Other Liquids cist Ductile Iron Pipe, Centrifugally Cast in Metal Molds or Sand-Lined Molds, for ‘Water or Other Liguids Board of Transport Commissioners for Canada General Orders No. 812 and 900 _ | 2.2. ASTM C12 Installing Vitrified Clay Pipe Lines shall be used with this Basic Practice. IMPERIAL 1BP 3.2.1 REV 7 JUNE 88 ‘SEWER SYSTEMS PAGE 20F 19 BASIC PRACTICE DEFINITIONS 3.1 *Sanitary sewers shall form a separate system into which no oil or any other waste may be discharged. They shall only collect raw waste from toilet facilities, lavatories, showers and floor drains in rest, wash and locker rooms. There shall be no interconnection between the sanitary and industrial sewer system unless approved in writing by the Owner's Engineer. 3.1.1 If facilities for the treatment of raw sanitary waste in bulk are not available in a plant or municipal sewer system, sanitary sewers shall discharge into septic tanks. Approval shall be obtained from the local health authorities for the septic tank system by the contractor. 3.2 Industrial sewers collect normal oily or non oily waste water, chemical waste water, storm water or CC” firewater for delivery to appropriate waste treatment facilities. The sewers are classified as follows: a) Chemical sewer. b) Contaminated water sewer. ©) Once through water sewer. 4) Surface run-off sewer. 3.2.1 Chemical sewers shall carry only waste chemicals where their concentration, quantity and/or activity is such that they must be treated before being discharged into the contaminated water sewer. The following sources may be considered as chemical: a) Phenols. By Aca ©) Causties. 4d) Oils contaminated with chemicals. ©) Effluent from chemical cleaning operations. 3.2.2 Contaminated water sewers shall carry oily process water low in sulfides COD and BOD. The effluent shall be collected in an oil separator prior to water treatment. 3.2.3 The following sources may be considered as contaminated water run-offs. a) Barometic condensers and steam ejectors where the condensate may be contaminated with ubricating oil or condensed hydrocarbons. b) Effluent from the surface of box type coolers or condensers, ©) Drains and water drawoff devices on equipment and tanks, 4) Drains and pump glands and the cylinders and glands of reciprocating pumps. ©) Drains trom sample points. £) Floor drains from analyzer housings. 8) Skimmings from cooling towers. 1h) Water drawoff from atmospheric storage and other special tankage. ji) Surface run off from areas normally subject to oil contamination. 3.2.4 Once through water sewers shall carry cooling return water to be treated in a clean water separator prior to discharge to the receiving water body, 3.2.5 The following sources may be considered as once through water: a) Effluent from coolers and condensers irrespective of the relative pressures of the water and product sides. 'b) Water from box type coolers and condensers where the water drawoff is below the water surface and any oil on the surface can be run-off to the contaminated water sewer. ©) Condensate from steam traps where the condensate is not contaminated with lubricating oil or other hydrocarbons, 4) Effluent from drinking fountains and emergency showers. BASIC PRACTICE | IMPERIAL Bp 3-2-1 ‘SEWER SYSTEMS REV 7 JUNE ‘88, PAGE 3 OF 19 | 3.2.6 ‘Surface run-off sewers shall carry storm and firewater to a Separator from areas normally not subject to oil contamination, Steam turbine condensate, boilerplant blowdown, cooling house blowdown and tank lots are usually discharged into this system. Delete. Mains are sewers collecting effluent from laterals and sublaterals. Laterals are sewers, collecting the effluent from normally not more than two sublaterals, discharging to mains Sublaterals are sewer branches (min. NPS 6 (168 mm OD)) collecting effluents from catch basins, discharging into laterals or mains. Drains are small sewer connections (min, NPS 2 to 6 (60.3 to 168.3 mm OD) from points such as pump bases, equipment drips, low points in floors, etc. Delete. Catch basins are used to collect surface drainage and process wastes in individual drainage areas and to tap sediment at the point nearest the source. Manholes are used in sewer mains as jun ‘maintenance and inspection. 1A points and sediment traps, and to provide access for Seals (hydraulic) are used to isolate the various parts of a sewer system, preventing vapor travel and spread of fire or explosion. They are installed at catch basins (para 6.5) and manholes (para 7.2). ‘Toe walls are raised curbs which contro! spillage and drainage of storm, process and firewater. Vents are used for manholes to prevent blowing of seals by pressure buildup. Integrated plants. The term “integrated plants” used herein is defined as two or more individual process units located within a common process block and designed to be interdependent in operation (heat exchanger integration, lack of intermediate tankage, etc.) Plot subdivision (of process unit areas) is an area which is segregated by at least $0 ft. (15 m) of clear access on all sides’ by roadways or process-lo-process spacing, thereby providing unobstructed accessibility for firefighting operations. MATERIALS ‘Sewer piping materials shall be as follows, selected for the location given below, when not otherwise specified l IMPERIAL 18 3.2-1 REV 7 JUNE ‘88 ‘SEWER SYSTEMS PAGE 4 OF 19 BASIC PRACTICE Location And Service Pipe Materials Remarks a. Buildings: Sanitary Sewers Building Sewers Floor Drains b. Catch Basin Seals, Use ductile iron pipe to Ductile Iron building. a point 5 ft. outside Ductile Iron ¢. Areas Subject 10 | 7 Imposed Loads: Near Heavy Foundations Impact Loads Under Paved Areas Duetile Iron, Cast Iron ASTM A74 extra heavy for sizes 2” to 15” (5010 375 mm) Cast iron limitation: Reinforced Concrete Sewer Pipe Reinforced Conerete Culvert Pipe Internally coated with Coal Tar-Polymide Epoxy if used in dirty water (containing sulfur compounds) service Carbon steel Externally coated and wrapped, and internally lined per AWWA C203: *External coating to be ‘Single-Coat, Single Wrap or Double-Coat, Double-Wrap systems per AWWA C203, d. Areas Subject to Nominal Soil Loads (no impact loads) Ductile Iron Vitrified Clay Unreinforced Concrete, Reinforced Conerete Internally coated with Coal Tar-Polyamide Epoxy if used in dirty water containing sulfur compounds) service PYC or Glass Reinforced Plastic, Use and Material selection requires approval by ‘Owner's Engineer €. Chemical Sewers *Material selection to be developed with Owner's Engineer 41 Tabled 's materials normally used by Imperial Oil and shall be used as a guide only. IMPERIAL ‘SEWER SYSTEMS BASIC PRACTICE (BP 3-2-1 REV 7 JUNE 88, PAGE § OF 19 4.2.1 Minimal depth of cover shall be determined by the greater of freeze protection requirements or crushing loads, but shall not be less than the values shown below. ‘Min, Depth Of Cover Min. Depth Of Cover Location Refineries Terminals Location Refineries Terminals loco v0" 3m) | 4-07C.2m) | Sarnia 2.6"(.75m) | 4°-0"(1.2m) Strathcona s.0%(15m) | 6-07(.8m) | Toronto 4-0" Calgary 6-0"(1:8m) | Montreal 3'-6"(Im) 0 Regina 6-0"(1.8m) | Dartmouth x-0"(.9m) | 4-0". 2m) Winnipeg 6-07(1.8m) | St. John’s 4°.0"(1.2m) 4.2.2 *The depth of surface water drains in tank fields may be reduced when approved in writing by the Owner's Engineer. 4.2.3 Minimum cover depth of pipe in light traffic areas, if no pipe sleeves are used, based on strength considerations, shall be in accordance with the following table measured from grade to top of pipe. Line Material Reinforced Conerete Pipe Cast and Ductile Iron Pipes ‘and Mechanical Joints ‘Carbon Steel Pipe Depth In Ft. (m) 309) 26) 103) 4.2.4 For the purpose of this specification, plain and reinforced concrete pipes, and burnt clay pipes shall be ‘considered rigid, steel pipe (used as a pipe or a sleeve) and ductile iron shall be considered flexible. DESIGN 4.2.5 Mechanical design of sewer pipes a) Flexible pipes-shall be determined as per AWWA C150-81. Both earth loads and live loads shall be used. b) Rigid Pipe 1) Concrete, plain or reinforced-shall be determined from papa. 4.2.6 or by referring to “Design and Construction of concrete sewers, Portland Cement Association, 1968" 2) Other material-as per manufacturer's standard. 3) The crushing strength of commonly used sewer conduit is listed in Table 4 ) For design of pipe under highway or railway crossings, refer to API RP 1102, ANSI B31.3 and para. 4.2.7. 4) For both flexible and rigid pipe 1) Back fill is assumed to weigh 120 Ibs/ft' (190 kg/M) unless otherwise specified. 2) Live load due to impact is assumed to be 50% of the vehicle wheel load. IMPERIAL. BP 3.2.1 SEWERS SYSTEMS REV 7 JUNE "88 PAGE 6 OF 19 BASIC PRACTICE 4.2.6 Selection Guide for reinforced concrete sewer pipe. The classes shown below may be used when the vehicle wheel load does not exceed 16,000 Ibs (7250 kg). Class of Reinforced Depth of cover | Concrete Sewer Pipe xa) (ASTM C76) | 24(61.2) Vv | (1.22.4) iu G44.) Vv 14-20 (4.26.0) v 4.2.7 Sewer pipes crossing under railway tracks shall conform with the requirements of the Board of ‘Transport Commissioners for Canada General Order No. 812 and 900. (Drains or sewers within 20 feet (6 m) of the nearest rail shall have a minimum of 3°-0” (0.9 m) cover). 4.2.8 a) The top of any drain or sewer crossing under a road or driveway, or any area where mobile equipment may be expected to travel, shall not be less than 2'-0" (.6m) below the surface. b) Drains and sewers constructed of clay pipe or plain concrete shall be protected by culverts or pipe sleeves (IBP 3-7-1 fig. 7.1) at crossings under roads and driveways unless a minimum cover of 6 ft, (1.8 m)is provided. 4.2.9 *Drains and sewers shall not pass under foundations of heavy structures or buildings except where approved in writing by the Owner's Engineer, INSTALLATION SITE PARTICULARS, 4.2.10 *The Owner shall provide the Contractor with plans of the site showing ground elevations and surface obstructions. Underground lines and obstructions shall also be indicated, where known. EXCAVATION 4.2.11 *The Owner shall move any existing piping encountered where essential to the execution of the work. 4.2.12 *The use of trench-digging machinery is acceptable, except where its operation may cause damage to existing pipes or structures above or below ground and then hand methods shall be used. 4.2.13 The width of the trench shall be kept to a minimum consistent with providing adequate access for sealing joints and tamping underneath the pipe. Refer to Table 3, Recommended Trench Width, 4.2.14 Where it is necessary to dig a trench wider than was assumed in the design of the sewer or drain, the strength of the pipe material shall be rechecked on the basis of the actual trench width. 4.2.15 When shoring is withdrawn after partial backfilling, it shall be withdrawn in widths not exceeding 2 feet (600 mm). The void left shall be filled and compacted. 4.2.16 The Contractor shal shore any existing piping that is not removed. 4.2.17 Fences, poles and all other property shall be protected unless their removal is authorized by the Owner, ‘Any property damaged shall be restored to its original condition by the Contractor PIPE LAYING 4.2.18 *a) Irrespective of the nature of the soil and the location, pipe shall be laid on a bed of well tamped sand or pitran gravel with a maximum particle size of 3/4 inch (19 mm), b) The minimum thickness of the bed shall be 4 inches (100 mm) for pipes less than 12 inches diameter and 6 inches (150 mm) for pipe 12 inches diameter and larger. ©) Clay sewer pipes shall be installed in accordance with ASTM C-12. IMPERIAL BP 3-2-1 REV 7 JUNE ‘88 SEWER SYSTEMS PAGE 7 OF 19 BASIC PRACTICE 4.2.19 Pipes of the bell and spigot type shall be jointed in such a manner as to leave a smooth bore. The spigot 4.2.20 tend of each length shall point downstream. ‘The invert of each length of pipe shall be checked after it has been jointed. BACKFILL 4.2.21 a) The initial bach 4.2.22 4.2.23 ‘up to the mid point of the pipe shall be sand or pit-run gravel of the same quality as that used in the bottom of the trench. b) The material shall be tamped in 4 inch (100 mm) layers with particular care taken to ensure thorough compaction beneath and on each side of the pipe to provide support free from voids. ©) Temporary blocks and wedges, where used for positioning a length of pipe, shall be removed as soon as the weight of the pipe is taken by the backfill. 4) Concrete stub-ins at manholes shall have an initial backfill of slush conerete, supporting the length of the stub-in, poured to a minimum height of it’s centerline. ©) Ductile iron stub-ins at manholes shall be laid on a bed of welltamped sand or gravel. Any minor voids present between the stub-in and the compacted bed shall be filled with concrete TABLE 3 - RECOMMENDED TRENCH WIDTH inches (cm) AT TOP OF PIPE Clay And Pipe Size Ductile Iron Unreinforced Reinforced NPS (mm) Or Steel | Concrete Concrete 4 (100) 17 (43) 21 (53) = 6 (150) 19 (48) 2461) = 8 200) 22. (56) 26 (66) = 9 (225) = 27 69) = 10.250) 24 (61) 28.71) = 12.800) 26 (66) 30 (76) 32 @1) 14.50) 28 (71) A S 15 (380) = 34 (86) 36 1) 16 (410) 3076) = = 18 (460) 33 (84) 38 97) 39.09) 20 (510) 35 (89) = = 21 530) = | 41 (104) 43 (109) 24 (610) 40 (102) | 45 (114) 46 (117) 27 690) — = 49 (124) 30 (760) 45 (114) = 53 (135) 33 (840) = = 57 (145) 36 (910) | 51 (130) = 67 (170) 42 (1070) 58.(147) = 75 (190) 48 (1220) 64 (163) = 82 (208) $4 (1370) 70 (178) = 89 (226) Additional backfill to a depth at least 12 inches (300 mm) over the top of the pipe shall next be deposited by hand placing and be well tamped. This additional backfill shall be sand or pit-run gravel of the uality used in the bottom of the trench. The balance of the backfill shall be compacted excavated earth. INSPECTION ‘The work shall be subject to inspection at all stages. Sewers shall be inspected thoroughly before backfilling has commenced. If partial backfilling is necessary, all joints in the sewer shall be left exposed until they have been inspected. IMPERIAL ep 3-2-1 SEWERS SYSTEMS REV 7 JUNE ‘88, PAGE 8 OF 19 BASIC PRACTICE 4.2.24 *a) Gravity sewers shall be water tested before backfilling has commenced unless partial backfilling is required for anchoring the sewer. If partial backfilling is necessary, all joints in the sewer shall be Iefi exposed. The water test shall consist of filling the system with water to 15 ft. (5.48 m) above the highest point in the system by using a 4 in. diameter standpipe. The static head shall be maintained for a minimum of 1 hour. The leakage rate shall not exceed 3 USG/mile/inch of diam. /hour. )_ Pressure sewers shall be tested in accordance with IBP 3-18-1 and IBP 3-19-1 4.2.25 *A clay material shall be used as a backfill to form a plug around sewer pipes where effluent seepage would pollute environmentally sensitive areas (ex. a body of water, a third party’s property or sewer system). It shall be approved by the Owner's Engineer. 4.3, Rubber rings used for ductile iron or cast iron bell-and-spigot joints and reinforced conerete bell and. spigot joints shall be synthetic, oil resistant type per ASTM D1869. 4.4 Materials for manholes catch basins and other drainage facilities shall be as follows: Item Material Specie Specification Requirements a. Covers and Frames | Cast Iron, ASTM A 48, Class 25 b, Segmental ASTM C139 Concrete Blocks ©. Concrete Pipe ASTM C76 Catch basins and manholes for Sections, chemical sewers shall be lined with acid proof brick per ASTM C279 Type L using potassium silicate or equally chemically resistant mortar 4. Brick ASTM C32 e. Concrete +2500 psi (17.2 MPa) compressive strength. Cement lype as required for sulfate exposure. 4.5 Diked enclosures for refrigerated storage vessels. Materials for drain system piping, including the block valve (outside the enclosure), shall be suitable for the lowest temperature which may be encountered during a spi 4.6 Cement-sand ratio for mortar shall be as follows: a. For masonry joints: 1:2 b, Allother mortar: 1:3 4.7 Deleted, ‘SEWERS, PIPES AND DITCHES MEANS OF COLLECTION 5.1 Buried pipe shall be used for: a. Chemical sewers. b. Contaminated water sewers. IMPERIAL 1BP 3-2-1 REV 7-JUNE ‘88 SEWER SYSTEMS PAGE 9 OF 19 e | BASIC PRACTICE ©. Once-through water sewers. Alll sewers within process unit ara limits. . Waste stream collection in areas immediately adjacent to process units areas, where the possibility for oil or chemical spillage exists." f. Sanitary sewers. Note: (1) An example of such an_area is a shell and tube heat exchanger bundle pullout area immediately adjacent to “battery limits” 5.2 Open ditches are acceptable for 5.3 Pipe to oily water collection systems shall be used for tankage area deferred runoff and for runoff from utility areas. free storm water outside process unit area limits. 5.4 Pipe is used for the collection of recirculated cooling water blowdown outside process unit area limits. 5.5 Natural runoff is acceptable for runoff from unused plant areas. 5.6 Cleaning access shall be incorporated into the design of all sewers. Solid matter shall be trapped as close to its source as possible. 5.7. *The number of mechanical joints shall be mi potentially chronic hazard toxic materials, Pi Engineer. C)) emer 5.8 Capacity Requirements, Sewers shall be designed to flow at 70% depth at estimated maximum flow. 5.9 Maximum and minimum flow velocities. Sewers shall be designed to be free flowing with maximum and minimum velocities as follows: ized in sewer piping collecting waste streams contai ‘arrangements shall be reviewed with the Owner’s Flow Depth Velocity Maximum Design | 0.70 diam. 17 fps (2 m/s) ‘Minimum Design 0.30 2-1/2 fps (0.8 m/s) 5.9.1 *Sizing Guide Using 1.25 times the required capacity and assuming full bore flow charts 1° and 2 may be used as a guide to determine velocity, slope and capacity for pipes up to 24 inches diameter with flow ‘coefficients of 0.010 and 0.015 respectively (see Table 4). The flow in pipes over 24 inches diameter can be approximated using the formula shown below: IMPERIAL, BASIC PRACTICE (BP 3-2-1 SEWERS SYSTEMS REV 7 JUNE ‘88 PAGE 10 OF 19 Velocity for full bore flow is: Where v v LMR? Ss CRS)? a 1.25 x required capacity in cu ft/sec. (m’/s) cross sectional area of pipe in sq. ft. (m’) mean velocity in fps (maximum 7 fps) (2.1 m/s) Hydraulic radius in feet (m) cross sectional area of pipe in sq. ft. (nr?) ‘wetted perimeter in Feet (m) 1.486 Ri a coefficient Slope of sewer in feet per foot (meters per meter) ‘A coefficient whose value varies with various classes of pipe and is given in Table 4. The value ‘of “‘n” in the equation increases with decreasing. flow depth and shall be taken into account. Note 1) A check of critical depth, velocity, discharge and slope is required for both minimum and ‘maximum discharge. Critical flow shall be avoided. SLOPE IN FEET PER 100 FEET OF LENGTH IP 3-2-1 REV 7 JUNE ‘88 SEWER SYSTEMS PAGE 11 OF 19 cHaRT 1 FLOW IN US, GALSJMIN, Note: IMPERIAL BASIC PRACTICE Curves ate derived from the Manning formula for closed circular pipes flowing at full bore with n = 0,010 SLOPE IN FEET PER 100 FEET OF LENGTH IMPERIAL 19P3.2- Esso) ‘SEWERS SYSTEMS REV 7 JUNE ‘88 BASIC PRACTICE PAGE 12 0F 19 FLOW IN US. GALS/MIN Note: Curves are derived from the Manning formula for closed circular pipes flowing at full bore with n = 0.010 IMPERIAL. IBP 3-2-1 SEWER SYSTEMS REV 7 JUNE '88 PAGE 13 OF BASIC PRACTICE sani 5.9.2 Acall seal, the pressure drop allowance shall be less than the design velocity head (V'/28) 5.9.3. *Drains and sewers shall be sized to keep the inverts at the battery limits as high as possible. Battery limit invert elevation shall be specified by Owner's Engineer. 5.10 Storm Water. Estimated storm water quantities shall be cumulative throughout the system. Data for Co rainfall runoff is as follows: "REFINERY Area Run off “7 inJhe (mmibey” Toco 10 es Strathcona Xo 5, Sarnia 10 G3) Dartmouth 10 es, Montreal Ko 63, Note: (1) Design criteria since 1950 to be used instead of NBC data, *Unpaved areas designed “future paving” shall be considered as paved for sizing the process unit mains, 5.11 Drains shall be minimum NPS 2 to NPS 6 (60.3 to 168.3 mm OD). 5.12 Sublaterals and Laterals shall be minimum NPS 6 (168.3 mm OD), 13 Industrial sewers within process areas shall be designed as follows: 2) Chemical sewers, Contaminated Water sewers and Once Through Cooling Water sewers shall be sized according to process design flow rates ') The Surface Runoff sewers shall be sized to handle the greater of the storm water or firewater flow. ©) Contaminated Water sewers and Surface Runoff sewers shall be separate, unless otherwise specified by the Owner's Engineer. However, if permitted to be combined the sewer design flow shal be the greater of! 1) The sum of storm water and process design flow. ii) The sum of firewater and process design flow. 4) A sufficient number of catch basins shall be provided in any area to handle the design firewater rate ‘without flooding, Firewater quantities shall be included to the following extent 1. Sublaterals: $00 USGPM (110 m'/h) from each catch basin 2. Laterals: The cumulative flow from the catch basins served. 3. Process Unit Mains: The cumulative flow from the laterals and sublaterals but the upper limit of the firewater quantity in the main from any facility or process unit shall be 6000 USGPM (1360 m'7hp 5.14 ls and sublaterals serving equipment and facilities (such as loading stations, pumphouses, et.) C outside process areas shall be designed 2s follows: 1, Sublaterals: 300 USGPM (110 m’/h) from each catch basin. 2. Laterals: The cumulative flow from the catch basins served 3. Process Unit Mains: The cumulative flow from the laterals and sublaterals but the upper limit of the firevater quant nthe main from any Tacity o process unit shal be 600 USGPM (360 as 5.15 Industrial sewer mains outside process unit areas receiving the combined flow from tank areas, process units, street drains, etc, shall be sized as follows: a. Contaminated Water sewers and Once Through Cooling Water sewers shall be sized according to ‘cumulative process design flow rates. IMPERIAL. (ep 3.2.1 REV 7 JUNE ’88 SEWER SYSTEMS PAGE 14 0F 19 BASIC PRACTICE | b. The Surface Runoff sewers shall be sized for the larger of the estimated storm run-off, which shall bbe cumulative throughout the system or a single allowance for firewater. cc. Contaminated Water sewers and Surface Runoff sewers shall be separate, unless otherwise specified by the Owner's Engineer. However, if permitted to be combined, the sewer design flow shall be the sreater of: 1. The cumulative process design flow and the cumulative storm run-off flow. 2. The cumulative process design flow and a single allowance for firewater. d. The firewater allowance shall be the largest single quantity of firewater discharging into the main from any facility or process unit, but not less than 2000 gpm (450 m’/h). The maximum allowance for firewater is 6000 USGPM (1360 m’h) from process unit areas or 3000 USGPM (680 m’/h) from tank areas, whichever is applicable ‘The contaminated water sewer load in subpar. a.) above shall not include chemical sewer loads until after any neutralization. In addition, chemical sewer loads shall not be included if separate waste treatment is required. 16 Surface runoff, sewers from tankage ares to open ditches shal be as follows a. Water in unlined ditches shall have a maximum velocity of 2 ft. per second (0.6 m/sec). In lined ditches the water velocity is unlimited. b. Ditches from offsite areas shall carry the total estimated storm runoff from roads and open areas, ‘or 1000 gpm (230 m’/h) whichever is larger. The estimated storm runoff shall exclude the deferred runoff from the areas within the tankage dike. ¢. Deferred runoff from individual tank areas to the ditches shall be based on the following ‘requirements to provide for both firewater and storm water flow for each tank. ————— ‘Size Of Tank, Specific ‘Diameter Flow Requirements: | Requirements: fe [om gpm | m'/h <40 <12 500 | 110 _| Pipesize shall not 401065 | 121020 i000 230 | beless than NPS 8 6510130 | 201040 1500 350 | 219.1 mm OD). >130 | | >40 2000 | 460 J “Rainfall frequency and intensity shall be considered in establishing deferred runoff rates from ‘combustible liquid stock tankage areas (if enclosed in a single peripheral dike). Final runoff ratio shall bbe approved by Owner's Engineer. DRAINS AND CATCH BASINS 6.1 *Open channel floor or pavement drains shall be covered with grating unless otherwise specified. Proposals to use stich drains shall be reviewed with the Owner’s Engineer. 6.2.1 Drains shall be provided at each piece of equipment where waste liquids may be discharged during startup, shutdown or normal operation. 6.2.2 Drains from pump rows shall connect to drain headers, and the header shall connect to a manhole. 6.2.3 Drains from individual pumps, knock out drums or other equipment shall connect to manholes. They may be connected to catch basins within the same fire hazard area (20 ft max.) at the discretion of the (Owner's Engineer. 6.2.4 All drains entering manholes shall be sealed. 6.2.5 The length between a drain header and a manhole shall not exceed 75 ft. IMPERIAL lop 9.24 SEWER SYSTEMS REV 7 JUNE 88 PAGE i50F 18 BASIC PRACTICE 6.2.6 Seals shall be provided at the point of entry of waste liquid into the sanitary sewer system. 6.2.7 At intersection of drains ““Y” branches shall be used. At changes of direction elbows of maximum 45 shall be used 6.2.8 *For drains not identified the Owner's Engineer shall approve the type of disposal system to be used. 6.3 Floor drains shall not be installed in control rooms or electrical substations. They may be used in other buildings in floors where they handle only oily waste water, and shall be connected to a catch basin. 6.4 Sample rooms, laboratory sinks, and similar drains containing oils, but free of corrosive chemicals, may discharge to the contaminated sewer system. ‘A running trap with double hub vented to atmosphere shall be installed in the sewer line at a point where the drain or soil pipe leaves the building. 6.5 Catch basins within process areas shall be as follows: a. Catch basins shall not be located beneath equipment, stairways, ladders or pipeways. b. Inno case shall one catch basin be directly connected to another catch basin. ©. Process unit areas shall be subdivided into individual drainage areas containing a maximum of 3000 sq. ft. (280 m:) for paved areas and $000 sq. ft. (465 m) for unpaved areas. One catch basin shall be provided for each drainage area. The maximum open travel of liquid to the catch basin shall be 50 ft. (15 m). Final grading or paving shall slope to the catch basin at not less than 1:100, Figure | illustrates a typical process unit areas drainage arrangement. d, Hydrocarbons shall not accumulate within catch basins. Therefore, outlets at catch basins shall not be sealed, except as noted in paragraph 6.5.1 and 6.5.2. €. Catch basins may be connected by sublaterals to laterals provided they are within the same fire risk area and are no more than $0 ft. apart. 6.5.1 Where asphalt may enter, the sewer system catch basins shall include a normally closed, vertically sliding gate or equivalent which must prevent asphalt from entering the sewer system. Easy access to these catch basins is necessary to allow raising the sliding gate to permit drainage. 6.5.2 Where C3s and C 4s could enter the sewer system catch basins shall include a seal adequate to prevent these light hydrocarbons from entering the sewer system. Figure 1 671 6.50 BP 3-2-1 REV 7JUNE'88 | SEWER SYSTEMS | PAGE 18 OF 19 ] IMPERIAL |_BASIC PRACTICE Drainage around plant buildings. Final grading and paving around all plant buildings shall direct liquids away from the buildings Draining diked or toe wall enclosures. Where rain water will not percolate through the bottom of the enclosure within 24 hours, a drain sytem shall be installed to provide for rain run-off. The drain system shall be in accordance with Fig. 4.1 and either of the following: a. A catch basin within the diked area discharging to the surface runoff sewer system, or b. A pipe through the dike discharging to an open ditch drainage system outside the dike. For pressurized or refrigerated storage, either system in subpar. a or b above shall be provided with a gate valve or shear gate located in an accessible position outside of the enclosure. ‘The system in subpar. b shall be provided with a gate valve or shear gate ‘Terminal requirements for draining atmospheric storage tank lots are not met by Fig. 4.1. Terminals do ‘not permit drains from tankage water draw-offs or surface run-off to be connected to an outside main sewer system. Collection from tankage water draw-offs and surface run-off shall be handled by Separate systems, These collection sytems consist of: 1, Water Draw-off From Tanks This system requires an underground network of 3 inch (75 mm) PVC pipe, wth clean-outs at water draw-offs and all bends, to collect and transfer water draw-off from a group of tanks to a 5000 IMP. GAL. underground collection tank. The underground collection tank shall be located within the dyked enclosure convenient for discharge by truck or manually operated pump. Details for the tankage water draw-off funnels, the 3 inch (75 mm) PVC drain line clean-outs and the underground collection tank are provided on Figure 6.1 2. Surface Runoff Surface run-off for a group of tanks shall be provided by grading the area within the dyked enclosure (0 @ common sump convenient for discharge. Discharge over the dyke shall be accomplished by 2 syphon system or a manually operated pump. Local preference for the discharge system shall be provided in the Job Specification. Sump discharge shall be directed to the Terminal separator Catch basin shall have a 12 in. (300 mm) debris pocket located below the outlet invert. Construction of catch basins. Catch basins shall be sized to permit hand cleaning. Construction may be of concrete, or prefabricated concrete. Catch basin covers shall be flat slotted covers or grate type covers. Catch basins shall be installed so that the covers are set flush with the low points of grading or paving. For unpaved areas where considerable silt or debris is expected as in tank fileds a 3 inch (75 mm) 10 ft Bm) diameter, depressed area shall surround the catch basin. For Terminals, pure product drains are required from all equipment such as pumps and filtration vessels and shall discharge to an underground retention tank. Funnels as pet Figure 5.1 shall be installed at all equipment drains. In line flow indicators shall be installed on lines from air eliminators. MANHOLES, Mangal shall located Res eee PEE Brot and a ma ». At junetions of refinery mains with process unit mains and with mains or laterals from facilities outside of process unit areas, ¢. At dead ends of mains. 4. Manhole locations shall not exceed intervals of 300 ft (90 m) for sewers less than 24 in. (600 mm) diameter, or intervals of 500 ft (150 m) for sewers 24 in. diameter and larger. e. Where changes in direction and/or slope of more than 45° occur. IMPERIAL T BP 3-2-1 SEWER SYSTEMS REV 7 JUNE ’88 |_ BASIC PRACTICE PAGE 17 OF 19 ‘Sealed manholes shall be provided for the following requirements (see Figure 2 below): a. All mains or laterials from unsealed catch basins, storage areas, individual process units, integrated plants, or facilities outside process unit areas such as loading stations, pump houses, etc. shall pass through sealed and vented manholes when tying into the main sewer. bb. Large process unit areas and integrated plants shall be subdivided into individual areas of 40,000 to 60,000 sq. ft. (3700 to 5600 m') each separated by a sealed manhole. €. Am individual process unit or part of a process unit, located within an integrated plant, but designed to operate separately from the complete process, shall have a separate sewer, with a sealed manhole, that ties directly into the main plant sewer. d. The last manhole in a main plant sewer, before entering the separator, shall be sealed to prevent a separator fire from traveling back through the main. e. The depth of all seals shail be 6 in. (150 mm) minimum, Manhole vents shall be provided for the following requirements: All sealed sections of sewer systems shall be vented to prevent blowing of seals by pressure buildup. bb. Vents shall be provided on both sides of the seal in manholes equipped with baffle type seals. c. Where manhole seals are established by submerging inlet connections, a vent shall be provided on the sealed manhole and on a manhole upstream within the same sealed section. d, The highest manhole in each individually sealed section of the sewer system shall be vented. Vent piping shall be 4 in. NPS (100 mm) minimum size. BP 3.2.1 | REV 7 JUNE ‘88 SEWER SYSTEMS Pi 1 "AGE 18 OF 19 BASIC PRACTICE 1a 8.1 82 83 IMPERIAL £, Vent pipe location and discharge elevation shall be governed by the following: 1, Vents shall discharge at least 10 ft. (3m) above grade when in a safe and open area, 2. Vents shall extend above any equipment or pipeways located within a horizontal distance of 25 ft. (8m), Note: This may require an underground extension to a safe location and then attaching the vent to a pipe support or other structure. 3. Vents shall extend at least 10 ft, above any platform located within a horizontal distance of 25 ft 4. Vents shall not be located within a horizontal distance of 100 ft. (30 m) from a fired heater. When vents are elevated $0 ft (15 m) above grade, they may be located 50 ft (1S m) horizontally from a fired heater. g. Vents shall be identified as such with a sign or stencil lettering: and if specified, painted a distinctive color to aid visual identification. fh, Vent lines shall be cut horizontally to discharge upwards. i, Vent lines shall be protected against accidental damage by mobile equipment. i. Vent lines shall be self-draining, Construction of manholes, a, Manholes shall be sized to permit entrance for cleaning. Construction shall be of cast-in-place or prefabricated concrete. 3/4” (20 mm) galvanized rungs shall be provided for access, A 1 ft (.3 m) deep debris pocket shall be provided. b. Manhole top slabs shall be designed so that they can be removed to permit cleaning of the manhole, In addition, the slab shall be fitted with a 20 in. (500 mm) min. diameter cast iron solid cover and frame, for personnel access, and sealed to prevent the escape of vapors. Hot poured asphalt is an acceptable sealer for this purpose. A 4 in. (100 mm) diameter screwed brass plug shall be installed in the cover to permit sampling. Manholes shall be installed so that manhole covers are set flush with the pavement in paved areas, and approximately 2 in, (50 mm) above grade in unpaved areas. d, Top of the effluent fine at manholes shall be no higher than the top of the lowest inlet line. ADDITIONAL REQUIREMENTS FOR CHEMICAL SEWERS ‘Neutralization or other treatment of Chemical Sewer effluent will be specified Corrosive chemical drains shall consist of a vitrified clay elbow set flush in the conerete floor or paving and piped to an acid sump or chemical sewer. A strainer of acid resisting material shall be placed in the top of the elbow to prevent the drain from plugging with refuse, Installation of vitrified clay pipe shall be per ASTM C12, using Class A bedding suitable for 2 ‘minimum load factor of 3.4. Last ER&E BP Reviewed-Rev. 7, June, 1986 [Mperiat 1ap 3.24 SEWER SYSTEMS REV 7 JUNE ‘88. Fae 18 0F 18 | easic PRACTICE TABLE 4 MATERIALS NORMALLY USED FOR REFINERY SEWERS MATERIAL aroeaN TE ‘conceee | CENT buemue rena cuss Son” | stanoano| gouty rian —__| eetvromcen} stannaep ANSI ASTM Cid ASTM C13. emscmcmon | th | asrmca| astaca) stimman] erm | asrcrs | GSrasat Anh Srasnent| sree ‘SIZE = A wo | ww | oe | 200 aw ‘ cm) om | te oe | ko, te : ot... 6h6Llrrr Ll oe so] we] eo] a 7 Sheen | me | ue | Se | 25 | cmc | tao iH _ | tas ASIMTHREE [6 130 i800 | % oo fi _ 2 cstnearrn| | 90 ne 7 i a shown factor) 6 e |__| 7 ae] 0 _ 3 | a mo _| mm _ a ear ator eee eae orcas _ Base _ ee wes : _ te ‘Notes: (1) Ductile o cast iron pipe with push-on joints is acceptable providing suitable gasket material is available. Neoprene gaskets are good for most services, but in each case consideration must be given to the fluid handled and the corrosive materials in the surrounding soil in selecting the gasket ‘material. Selection of gasket material shall be approved by the Owner's Engineer. cerenn. pores: 7 SECTION A. oi PLAN SEPTIC AO SIPHON TANS name SEPTIC TANK SIPHON TANK STPHON OF CAPACITY | eNGTH| WIDTH DRAW ING] Serve | cations | nes | DEPTH Te] 300 7-10 | 550 wo reouineo | oT REQUIRED iis [800 1-20] 1000 Tore con 21-25] 1300 Dea Ee ape {P2es0—[ 1600 ao [ot0" 4 fenet 31-100 [1800 Eo foo apa 191-180 | 2000 sro fio spare si-200 | 2500 Sef spare ALU ITTINOS TO BE 4 WPS CAST IRON ‘he Tann. 18 cONaTRUOTED OF EITHER: Beer Soe one Te Herd motes ton seails ne pup ates SESE Re eat SEPTIC TANK DETAILS IMPERIA BASIC PRACTICE novar |IBP. SJorso! r A BisTRIBUTION Box WITH A 4 BisraisuT: or°8 So ere Biaasee te! wri Jor. ——— See hate tenant 280 hey Set note: “7 ELev.oF ouruets. PLAN OF FILTER BED fe WIN OF 1" pete THe THCET. TILE eM ORADE: VERT GAPS FROST O€PTH see THIS TEP section AW A- FIGURE 1. | FOR ABSORBENT TYPE SO1L-SAND.GRAVEL.ETC. | bp A Les PLAN OF FILTER BED * oRUBHED STONE 47 DIA.DISTRIBUTOR TILE san 7a CRUSHED STONE COLLECTOR THLE section A-A O ILE ENO VENT CAP. coutecton RADE ot 7 7 ae SOL\ECTOR PIT an ‘5/8 CRUSHED STONE 4{,DIA-COLLECTOR ‘ite section B-B aE. FOR CLAY SOL. NoTE! 1. THE FILTER BED SHALL NOT BE LOCATED UNDER ANY ROADWAY. ACCESSWAY OR PAVED AREA. 2. WEEPING TILE SHALL BE KEPT 10° FROM ANY FOUNDATION. 2. ASPHALT COATED PAPER SHALL BE PLACED DIRECTLY! QVER TOP OF JOINTS: OF RAIN TILE MIN. 6% BOTH TES. 4. DISTRIBUTION BOX SHALL BE DESIGNED TO SUIT LOCAL CONDITIONS AND CONSISTS OF = (a) A SOLID UNIT OF EITHER CAST-IN-PLACE OR PRECAST CONCRETE 3" THICK WITH A MINIMUM COMPRESSIVE STRENGTH OF 2000 PSI AT 28 DAYS AND 3° THICK. oR. (> 32,0A. TREATED STEEL WITH A REMOVABLE OP. 5. CLAY FILL SHALL NOT BE USED IN THE FILTER BED GRANULAR NATERIAL SUCH AS _CINDERS OR ASHES SHALL NOT BE PLACED ON TOP OF FILTER BED. IMPERIAL BASIC PRACTICE SEPTIC TANK FILTER BEDS we [S| wunevr >a opt ionaLy MAINTAIN 6 Chauid' SEAL. S| c/w BL CLEAN-puT |

s.]gR CAST as REG"D ve 316 8.8. “ANCHOR STUDS | 1 1 | TyPE-D (ELEVATION NOTE! 1. FOR .OCATION AND SIZE OF SEALS REFER Iep d.2-1 PAGE 14 0F 16 2. FOR MATERIALS SELECTION REFER 70 Tgp 3-2-1 PAGE 3 OF 16 AND TABLE 4 Hep 31211 PAGE 16 OF 16. 0 ss0) IMPERIAL BASIC PRACTICE | | L | | | TYPICAL GAS SEALS AT MANHOLE 2_| Nov 84 [pp 3.21 [on FROM TANK HEATERS: 1 — PRPASATE E a SEALED — ter i 5 ial DETAIL ONLY ONE SEWER _—ineg_sveass (SEE NOTE ik IS AVAILABLE x INPS BYPASS: SEALED, TNLETS CONTAMINATED WATER DETAIL 2} SEWERS (AR WHERE SEGREGATED SE OW POINT OF TANKLOT— 1: |__N.0.-INPS BYPASS WITH EXTENDED STEW (SEE NOTE 3) St ro ¥ A EXTENDED STEM SUPPORTED By GUIDES ON FOUNDATIONS GATE VALVE (RISING STEM) TURNED TO ANGLE_OF DIKE FLANGED VALVES IN| BURIED LOCATIONS ARE IRON BODY, BRASS MOUNTED WITH NON-RISING STEM. PROVIDE SIONS INDICATING FUNCTION OF EACH BRAN VALVE. AND. WHETHER NORMALLY KEBT OPEN OR CLOSED. BY-PASS VALVE NORMALLY OPEN EXCEPT IN THE EVENT OF PRODUCT SPILL. FOR TERMINAL REQUIREMENTS REFER TO PARAGRAPH 6.7.1 TANK LOT TO BE GRADED TOWARDS THE CATCH BASIN IMPERIAL BASIC PRACTICE TANK LOT DRAINAGE FOR ATMOSPHERIC STORAGE VESSEL, 2-4"=20 X 1" LG. Pu BO! 22 GA STEEL OM SLOTS CUT TO pe OM BRAN _ RECEIVE BOLTS ey tow A ont a SPLIT HOSE PACKING. COVER Ape = ao eee — —h_ ~U/G TANK ' DIA. HOLE FOR #" PIPE DIA. HOLE FOR 1J" PIPE FOR 1" PIPE FOR 2" PIPE IMPERIAL BASIC PRACTICE FUNNEL, & COVER DETAILS FOR TERMINALS D [nov ves /IBP 3.2.1 St BASIC PRACTICE 24 2.2 IMPERIAL LOW AND HIGH BACK PRESSURE AIR FOAM | gp 3.2.2 SYSTEM FOR FIXED ROOF STORAGE TANKS | fege org? SCOPE ‘This Basic Practice covers mandatory requirements governing the design and installation of air foam systems using either a low back pressure system with foam makers located at the top of the tank riser Or high back pressure system with foam makers located on a fire truck. The former is required for new installations, and the latter for retrofits or repairs on existing high back pressure systems. The systems are used on fixed roof tanks and covered floating roof tanks. ‘An asterisk (*) indicates that additional information is required. If a job is contracted, this additional information is furnished in the Job Specification. MATERIALS: Pipe for risers and laterals shall be of carbon steel, schedule 40 min, wall thickness. Frangible diaphragms, incorporated in the seal chamber of foam chambers, shall be 14 oz, (400 2) (0.061 in, (1.55 mm) thick) of common soda lime glass scored to facilitate breakage under foam pressure, Foam chambers and makers shall be carbon steel. DESIGN +*Foam chamber requirements for flammable and combustible liquids. Foam chambers and makers shall be provided for tanks 20 ft. (6.1 m) diameter and over in the following services: a. Tanks containing stocks witha closed cup flash point of 130°F (55°C) and below. (This includes low flash materials and most crude ois.) bb. Tanks containing stocks with a closed cup flash point above 130° (55°C) if such stocks are stored ata temperature above or within 15°F (8.5°C) of their flash point. cc. Fixed roof tanks with internal floating covers of steel, aluminum, non-metallic, or combustible construction shall be protected in a way similar to a cone roof tank. d.* Where tankage spacing guidelines are not met. cc. The number of foam chambers shall be as follows: 1) For low back pressure systems see Table 1 TABLE 1 Low Back Pressure Systems ‘Nominal Tank Diameter Number of Foam Chambers Required per tank 20to 80 ft. ( 61024 m) 81 to 110 ft. (24 t0 34 m) 111 to 130 ft. (34 t0 40 m) 131 to 150 ft. (40 to 46 m) 151 to 170 ft. (46 to 52 m) IMPERIAL 1B 3-2-2 LOW AND HIGH BACK PRESSURE AIR FOAM pees on aan SYSTEM FOR FIXED ROOF STORAGE TANKS E59) PAGE 2 OF 4 BASIC PRACTICE 2) For high back pressure systems see Table 2 TABLE 2 High Back Pressure Systems Size of Tank Diameter Number of Foam Chambers | 2010 65 fi.(20m) 66 ft. to. 90 f.(20 to 27m) 91 ft: to 110 £1,027 to 34m) 111 ft. to 125 £8.34 to 38m) 126 ft: to 140 f1.(38 to 43m) 141 ft. to 150 ft.(43 to 46m) ag og 35 ‘The design and installation of foam chambers for flammable and combustible liquids shall be: a. For low back pressure systems as per fig. 1.1, 1.2, and 2.1 b. For high back pressure systems as per Fig. 1.1, 1.2, and 3.1 ‘The design and installation for water soluble solvents, i.e. alcohols, ketones, etc., shall be specified by the Owner's Engineer. Foam chambers shall be located to minimize length of lateral piping. If more than one chamber is required, they shall be equally spaced around the tank, as per IBP 3-2-2 Fig. 1.1 ‘Foam makers shall be provided and installed as follows: a, For low back pressure systems 1) For tanks $5 ft. (16,8 m) diameter and smaller, foam makers with a capacity of 250 gpm (56.9m’/h) at design inlet pressure. 2) For tanks larger than 5S ft. (17 m) diameter, foam makers with a capacity of 500 gpm (115 m’/h) at design inlet pressure, b. For high back pressure systems not applicable as foam makers are on fire trucks. “Blanked foam chamber connections. When specified that flanged connections be provided for future installation of foam chambers,such connections shall be blanked with a 1/4 in, (6 mm) thick blind flange, installed as a gas tight connection. Piping Layout. a) Low back pressure systems 1) Each foam chamber shall be equipped with its own riser, foam maker and lateral. 2) Pipe risers shall be installed directly below the foam makers. 3). Pipe risers shall be spaced a minimum of 4 in, (102 mm) clear from the tank shell. b. High back pressure systems 1) Each foam chamber shall be equipped with its own riser and lateral. 2) Pipe risers shall be installed directly below the foam chamber. 3) Pipe risers shall be spaced a minimum of 4 in, (102 mm) clear from the tank shell. ‘The riser pipe size to cither the foam maker in a low back pressure system or the foam chamber in a high back pressure system shall be the same size as the lateral. IMPERIAL LOW AND HIGH BACK PRESSURE AIR FOAM | gp 3.2.2 REV 6 JUNE'88 SYSTEM FOR FIXED ROOF STORAGE TANKS | faye JUNE BASIC PRACTICE 3.8 Lateral Pipe Size C a, For low back pressure systems. Laterals up to 350 ft. (110 m) in length shall be NPS 3 (88.9 mm OD) for 250 gpm (57 m’/h) foam makers and NPS 4 (114.3 mm OD) for $00 gpm (115 m’/h) foam makers. Where greater lengths of laterals are required, they shall be sized so that the lateral pressure drop does not exceed 35 psig. (240 kPa gauge). b. For high back pressure systems. The size of the laterals shall be as shown in Table 3. The length of the laterals from the roadway to the tank, including the riser, shall not exceed the maximum length shown in the table with allowances made for any fittings. TABLE 3 Tanks 40 Ft, Dia. & Smaller ‘Tanks Over 40 Ft. (12 m) Dia. Height of Tank Lateral Size Max. Length* Lateral Size Max. Length Ft. (Meters) NPS(OD mm) | in Feet (Meters) | NPS(OD mm) | in Feet (Meters) 32.0.8) aaa 215 4) 6 (168) 525 (160) 40 (12.2) 4cl4) 250 (76) 6 (168) 90 (149) | 48 (14.6) 44) 225 (69) 6 (168) 450 (137) * Based on a roughness factor C of 120 3.8.1 ‘Where existing chemical systems are converted to an air foam system, the following shall apply: a. When the existing risers consist of dual NPS 3 (89 mm OD) lines, these may be retained in service by manifolding them together at the base of the riser and installing a NPS 6 (168 mm) lateral. b. The length of the lateral shall not exceed the length Table 4 after allowances are made for any fittings which may be installed, cc. Where the risers are smaller than NPS 3 (89 mm OD) they shall be replaced with NPS 4 or 6 inch. TABLE 4 Tank Height Max. Length of NPS 6 (168 mm OD) Lateral* in Feet (Meters) in Feet (Meters) 2 9.8) 375 (114) 4002.2) 300 (1) 48185) 2s (6) * Based on roughness factor C of 120 3.9 Lateral Terminals. Laterals shall terminate on the road side of all pipelines and drainage ditches, The terminals shall be from 2 to 4 ft. (0.6 to 1.2 m) above grade in accordance with IBP3-2-2 Fig. 1.2. a. Low back pressure systems shall have their terminals located in relation to the fire hydrant so that the total length of hose from the hydrant to the fire truck and from fire truck to terminal shall not exceed 100 ft. (30 m). IMPERIAL, | 1Bp 3-2-2 LOW AND HIGH BACK PRESSURE AIR FOAM paged peace SYSTEM FOR FIXED ROOF STORAGE TANKS bb. High back pressure systems shall have their terminals located in relation to the fire hydrant so that the length of hose from the hydrant to the fire truck or from the fire truck to terminal shall not exceed 25 ft. (7.5 m). The terminals shall not be more than 15 ft. (4.5 m) from the roadway. 3.10. For tanks requiring two laterals, they shall be brought to a single location 4 ft. (0.6 m) apart. However, not more than two laterals from any one tank shall be brought to the same location. 3.11 *Where prevailing winds exist, the lateral terminals shall be located upwind from the tanks. 3,12 The terminal connections on foam makers shall be as follows: a. Low back pressure system 1. Laterals to 250 gpm (57 m’/h) foam makers shall terminate in one 2!/2 (92 mm OD) mating hose coupling. 2. Laterals to 500 gpm (115 m’/h) foam makers shall terminate in two NPS 2!/2 (92 mm OD) ‘mating hose couplings. 3. Couplings shall be provided with dust caps or plugs b. High back pressure system 1) NPS4(114 mm OD) terminals shall have Evertite hose adapter #992-2A and dust cap #992-5A (or equal) installed. 2) NPS 6(168 mm OD) termina! shall ave Eerie hose adaper #92868 and du cap #928-38 (or equal) installed. FIELD CONSTRUCTION 4.1 Riser supports shall be 1/2 in. (13 mm) thick plate, 12 in. (300 mm) length, with the width depending on riser dimension. Each support shall be located on 8 ft, (2.5 m) centers and placed perpendicular to the tank shell and centered on the riser pipe. The edges of the plate shall be continuously welded on all sides, to both tank shell and pipe with 1/4 in. (6 mm) fillet welds. 4.2 Laterals shall be installed as follows: a. Slope continuously toward the dike. b. Shall not run through the dike area of any other tank or group of tanks. However, piping within a ‘group of tanks may cross intermediate toe walls within that group. c. Shall extend outside the dike to points at least one tank diameter or 50 ft. (15.25 m), whichever is ‘eater, from the tank. 4d. A minimum of 1 ft. (300 mm) above finished grade. ‘A NPS 3/4 (26.7 mm OD) drain valve shall be provided inside the tanklot and at the lowest point of the foam lateral near the dike. Where the pipes pass through the dike, they shall be protected against external corrosion by using either wrapped of extruded polyethylene or fusion bonded epoxy coatings. A flange shall be used to join the foam riser and the foam lateral at the base of the tank. Bog of TESTING 5.1.1 Performance Test, All components of the air foam system shall be tested with foam by the Owner before the tank is put in service. The foam generating truck discharge pressure shall be between 125 and 150 psig (860 and 1035 kPa gauge). Last ERE BP Reviewed-Revision 3, January 1977 | , FIREWALL HOSE ADAPTOR AND DUST caP——_1 (ONE CHAMBER? , fuse . 4 yy Hose aparror AND DUST CAP (FIVE CHAMBER) OSE ADAPTOR * AND DUST cap —= (TWO CHAMBER? FIREWALL FIREWALL UW ose apartor WAND DUST CAP (THREE CHAMBER) HOSE ADAPTOR SY AND OUST CAP (SIX CHAMBER? IMPERIAL BASIC PRACTICE E_ADAPTOR LATERAL PIPING INSTALLATION ae “AY ano oust car FOR LOW & HIGH BACK PRESSURE SYSTEMS crouR onAWBER [alBP Tl Nov 783 |IBP Sean) wee ROE 2) roaw cunwen sarery — SAFETY RAILING PER TBP 9.7.1 £16, B. FOAM MAKER DYER AND MILLER MODEL NATIONAL REFINERY FIRE MARSHALL, FOAM MODEL 02 EQUAL SHOULD BE CONSULTED 5. RISER PIPE TO BE SIZED AS PER IBP 3.2.2 IMPERTAL BASIC PRACTICE LOW BACK PRESSURE SYSTE! PARAGRAPII3.7/3.8. FOR TANKS WITH tout M INTERNAL FLOATER oR Notes: (1) DIAMETER D=14" FOR TANKS WITH 247 SHELL MANHOLE | Drie: FOR TANKS WITH 30° SHELL MANROLE (2) DLAPHRAGS SHALL BE INSTALLED PER RECOMMENDATIONS | OF THE MANUFACTURER. “THEY SHALL BE LOCATED ABOVE Fre "Nax'iwm Tank L1GU1D LEVEL | (3) HLL WELOS SHALL BE "VAPOUR TIGHT. INSPECTION HATCH : | | | i FOAM CHAMBER. NATIONAL AER-O-FOAW TyPE_McS-34-S OR EQUAL. WELDED OR BOLTED To {ANK SHELL WITH VAPOUR TIGHT CONNECT | ONS FRANGIBLE GLASS, DiaPHRAM (NOTE-2) 1/20 + 41/2" FOAM CHAMBER, FOAM DEFLECTOR 67-1508. RAF. THREADED OR WELDED FOR 6° Dia. RISER — Win IWOW IMPERIAL, BASIC PRACTICE HIGH BACK PRESSURE SYSTEM INSTALLATION OF FOAM CHAMBERS FOR TANKS WITH OR WITHOUT INTERNAL FLOATERS Ak Len | S--K oI SECTION A-A SECTION - NUMBER = 3-2-2 Fig. 4.1, 5.1 TITLE - Installation of Foam Chambers For Tanks Without Internal Floaters - Installation of Foam Chambers Mounted on Tank Roof for use With Internal FLTG. Covers REVISION - 2 This DRAWING has been deleted as of November, 1983. If you wish to see a copy of the DRAWING, contact the Strathcona Technical Information Centre. IMPERIAL. j (BP 3.2.3 Gss0) | FIREWATER SYSTEMS REV 8 JUNE'88 PAGE 1 OF 10 BASIC PRACTICE ‘SCOPE 1.1 This Basic Practice covers mandatory requirements governing the design and installation of firewater systems. }2 The contents ofthis Basc Practice are arranged as follows: Section ? Scope Summary of Additional Requirements System Design Design Basis Water Supply Pumps and Drivers Booster Pumps Pipe Materials Piping Layout Hydrants Location and Spacing Monitor Location Hose Reel Location Deluge Systems Hydrant Selection and Installation Monitor Selection and Installation Hose Reel Selection and Installation Valve Selection Spray System Design and Installation Deluge and Spray System Installation for Pressurized and Refrigerated Storage 1.3. Amasterisk (*) indicates that additional information is required. If a job is contracted, this additional information is furnished in the Job Specification. ‘SUMMARY OF ADDITIONAL REQUIREMENTS 2-1 Table Iss the Basic Practices and standard which shall be used with this Basie Practice, 2.1.1 Table 2 lists the Basic Practices which shall be used with this Basic Practice, as specified by the purchaser. TABLE 1 Basic Practices TBP 3-2-1 Sanitary and Industrial Sewer Systems IBP 3-7-1 Piping Flexibility, Supports and Layout IBP 3-12-1 Valve Selection Criteria Standard NFPA Standard AWWA Standard 13 Installations of Sprinkler Systems C $02 Dry Barrel Fire Hydrants CSA Standard 89.6 Fire Hydrants IMPERIAL gp 3-2-3 REV 8 JUNE’88 FIREWATER SYSTEMS PAGE GE 20F 10 I BASIC PRACTICE TABLE 2 Basic Prectc 1BP3-73 Thrust Blocks for Underground Cast Iron and Non Metallic Pressure Pipe 1BP3.10-3 Cement Lined Pipe and Fittings IBPI7-S-1 Miscellaneous Safety Equipment TBPID.1-1 Paint and Protective Costings TBPI9-1-2 ‘Acceptance Criteria, Paint and Protective Coatings TBP 19-5-1 Cathodic Protection 2.2 Deleted c 2.3. Fire house couplings selected for a particular plant location shall be compatible with mutual aid and local fire protection facilities. ‘SYSTEM DESIGN DESIGN BASIS 3.1 *Design conditions, water supply and rates, piping sizes, materials of construction, and type of hydrant couplings will be Specified. 3.2. *The system layout, including the general location and number of pumps, hydrants, monitors, hose reels, deluge sprays, sprinkler systems, block and flushing valves will be specified. ‘The final layout and location of equipment and facilities shall be approved by the Owner's Engineer, 3.3 Connections for permanent use of water other than for fire protection are not permitted. 5.4 *Underground carbon stee! piping, and above-ground portions of carbon stec! piping passing through a dike or dike sleeve shall be protected against external corrosion using a Single Coat-Single Wrap or Double Coat-Double Wrap Protective Coating system, as specified 3.5 “The use of reinforced plastic pipe (RTRP Grades) for firewater systems requires approval of the Owner's C Engineer. 3.5.1. *Piping below grade: C a. When approved for use, steel pipe shall be coated and wrapped as per IBP 19-1 Protection shall be per IBP 19 b, Ductile iron pipe shall have TYTON or mechanical joints. Cathodic WATER SUPPLY AND SYSTEM 3.6 Firewater source will normally be specified to be an unlimited supply of water such as sea water, a lake, or ariver. Alternatively, wells may be used if they are of suitable capacity to meet these requirements 3.6.1 Capacity of the firewater system shall be sized on a cumulative basis. The system shall be capable of supplying the sum of the following: a. Firewater to the deluge system of a vessel involved in an emergency, plus the deluge system of adjacent exposed vessels. b. A minimum of 1000 USGPM (0.063 m’/s) of firewater from hydrants, 3.6.2 Sectionalized systems. Where the requirements of par. 3.6.1 are impractical, piping may be arranged to sectionalize the control of individual deluge systems, or groups of deluge systems. For example, if ‘more than one deluge head is required on a vessel, the system may be segmented to cover only that half Of the vessel exposed to an adjacent fire IMPERIAL, IP 3-2-3 FIREWATER SYSTEMS REV 8 JUNE’88 BASIC PRACTICE PAGE 3 OF 10 | 3.7 Where the firewater supply from a given source is limited: a. Firewater storage shall be furnished, with a capacity equal to 6 hours supply at specified design flow rates, independent of other plant process water usage; and b. The firewater source must be capable of supplying water at one-half the specified maximum demand on a continuous basis. 3.8 A “break tank” is required where firewater is supplied from a potable water souree, or any municipal source. PUMPS AND DRIVERS 3.9 A minimum of two firewater pumps, each sized for 50% of the system design capacity are required ‘Design shall include the following: a. Each pump shall be designed for 125 psig (860 kPa) discharge pressure at rated capacity. The pressure rise at shut off should not exceed 20%, and at 150% of rated capacity the head shall not, be less than 65% of rated head. 1b. The system pressure shall be controlled at the pump discharge by a pressure controller, bypassing excess flow back to the source of supply. c. Am averaging-type pitot tube installation shall be provided to permit testing the capactity of each firewater pump. The instrument shall be located in the bypass piping (pump discharge to source of supply), or if specified, in the main firewater grid piping. 3.10 Drivers: C a, One firewater pump shall be diesel engine driven. If diesel engine driven, a fuel tank having a capacity of 6 hours of continuous operation shall be provided, ’. Alternate pumps shall be steam turbine, diesel engine driven or electric motor drive. ¢. ASTART-STOP button for one main firewater pump shall be located in the main control house, 3.11 Continuous positive pump suction shall be provided. Priming devices are not acceptable. Deep well pumps shall be used where positive pump suction is not available. 3.12 Suetion screens shall be provided where foreign material is present which could plug the suction line or pumps. Either traveling or double removable sereens, cleanable with the pump in service, shall be used. 3.13 *The firewater system shall be continuously pressurized (when the main firewater pumps are not in use) by one of the following means as specified fa. A separate, small pressurizing pump manifolded in parallel with the main firewater pumps. b. A ‘Sjumpover connection” from the plant cooling water or process water systems. ‘A low pressure cutin with alarm shall be provided to actuate the electric motor driven, main firewater pump at a specified pressure. The alarm shall be located in the main control house BOOSTER PUMPS: 3.14 Booster pumps, as required, shall take sucti pressure can build up to exceed the system design rating, a pressure relief valve discharging to.a safe location, shall be provided. Conditions requiring booster pumps are: a. Extended firewater systems, where hydrant pressure may be insufficient to provide required flow. ’b. Elevated structures within process unit areas where firewater system pressure may be insufficient to provide required flow. 3.15. *Drivers for booster pumps will be either electric motors, steam turbines, or diesel engines as specified. IMPERIAL ap 3.2.3 REV 8 JUNE’88 FIREWATER SYSTEMS PAGE OF 1 oo BASIC PRACTICE PIPE MATERIALS 3.15.1 Pipe Materials shall be in accordance with the line Service Classifications and the requirements of this Co" Basie Practice 3.15.2 *Other materials may be used if approved in writing by the Owner's Engineer. 3.15.3 Piping above grade: ‘a. Cast iron pipe and fittings shall not be used. b. Steel pipe in salt water service shall be extra strong. cc. Lines in buildings shall be in accordance with local codes. 3.15.4 *Piping below grade: a. When approved for use, steel pipe shall be coated and wrapped as per IBP 19-1-1. Cathodic Protection shall be per IBP 19-5-1. b. Ductile iron pipe shall have TYTON or mechanical joints. PIPING LAYOUT 3.16 *The firewater system shall be looped and shall be provided with isolation valves. Block valves shall be provided so that in the event of any piping failure: No more than 1000 ft (300 m of pipe containing hydrants, hose reels, monitors or sprays can be lost. b. The piping to only two adjacent sides of any process block or tankage area can be lost 3.17 *Firewater mains shall be installed a minimum of 1 ft. (300 mm) below the frost line, Firewater C connections to monitors, hose reels, sprays, etc., in freezing climates shall be winterized, 3.18 Firewater piping within process unit areas shall be underground. 3.19 Firewater piping within process unit areas feeding any combination of more than two monitors, hose reels, hydrants, or sprays, shall be connected to two separate sections of the fire main separated by a valve in the main. In addition, the line to the hose reels and monitors shall be valved at each end where it connects to the main. However, short sections of pipe, less than $0 ft. (15 m) long, feeding a single hose reel or monitor, need not be valved at the firewater main takeoff. 3.20. *Firewater piping to marine terminals shall be protected from direct exposure to a fire on the water by C™ installing the lines above the deck. Where itis necessary to locate the lines below the deck, they shal be fireprooied. In freezing climates, an MOV shall be iistalled in the main firewater supply line to the dock. The MOV shall be locally and remotely operated. Facilities shall be installed so the firewater line can be drained dry during freezing weather. Valved hose connections shall be provided to permit fireboats to pump into the main firewater system. Location to be specified by the Owner's Engineer. 3.21 *As specified, the firewater system shall extend to plant buildings used for operations and storage. 3.21.1 *Firewater lines and hose reels required on elevated structures and equipment shall be specified by the ‘Owner's Engineer. HYDRANTS LOCATION AND SPACING 3,22 Hydrant locations shall be established in accordance with the following: © a. Hydrants shall be installed to reach vessels from both sides. b. Hydrants shall be installed so that each vessel can be reached by not less than three streams of water, from hoses each not exceeding 300 ft. (90 m) in length, ‘Where vessels are arranged in rows two deep, the hydrants shall be located alongside the roads or accessways around the vessels, STRATHCONA General | | | FIREWATER SYSTEMS e ||Esso| Instructions ! | & Information IPE MATERIALS REF.: IBP 3-2-3, para 3.15.4 1.1 Carbon steel piping shall be used for underground firewater lines. 1986 08 18 [~IMPeriat BASIC PRACTICE FIREWATER SYSTEMS | REV 8 JUNE‘88 IBP 3-2-3, PAGE 5 OF 10, 3.23 Hydrants shall be located on the street or road side of all pipe lines or drainage ditches. The length of the 4 in. (100 mm) size suction hose required between the hydrants and fire truck shall not exceed 25 ft. (7.5 m). Where large pipe bands or dr 1age ditches may hinder access from hydrants to process areas co tank fields, hydrants shall be located near accessways or walkways across such obstructions. 3.24 Additional area requirements governing the spacing and location of hydrants are given below: Area Specific Requirements a. Process Unit Valves and hydrants shall be so spaced that in the event of any line failure, flow shall be provided to two adjacent sides of a process unit at half the design capacity through hose runs not to exceed 400 ft. (120 m) to reach all the equipment. b. Atmospheric Tank Storage: All tanks Where fixed air foam Taterals installed e (oye an ating Roo, and Fixed Roof with Internal Floating Covers) Floating Roof Tanks Valves and hydrants shall be located so that at least one hydrant is within 400 ft. of any tank n the event of a line failure. Hydrant shall be located in relation to terminals of air foam laterals so that the individual distance from hydrant to fire truck and from fire truck to foam lateral does not exceed 25 ff, (7.5 m). Hydrants shall be located such that the tank stairway is facing the hydrant. c. Pressurized and Refrigerated Storage: All vessels Vessels arranged two rows deep Hyédrants shall be located on at least two sides of each vessel, so that the vessel can be reached by not less than 3 streams of Water from hoses, each hose length not to exceed 300 fi. (0 m), Hydrants shall be located along roads or accessways around the vessels. 4. Cooling Tower {At least four hydrants shall be located within 100 to 200 ft. (30 to 60 m) of the cooling tower. MONITOR LOCATION 3.25. "Monitors shall have an effective nozzle range of atleast 100 ft. (30 m), and shall be located a follows: a. Fixed location, at-grade: Locate approximately 50 ft. (15 m) from the equipment being protected. e@ Where closer spacing is specified, the actuating valve shall be located at least 50 ft. (15 m) from the protected equipment. b. Fixed location, elevated: Locate approximately 50 ft, (1S m) horizontally from equipment being protected, and at an elevation to cover said equipment. The actuating valve shall be located at grade below the monitor. IMPERIAL lap 3.2.3 REV 8 JUNE'88 FIREWATER SYSTEMS | mae eo sasicpmcrce_| ‘Where closer monitor spacing is specified, the actuating valve shall be located at least $0 ft. (1S m) horizontally, from the protected equipment. ‘Where remote control of elevated monitors is specified, final designs shall be approved by the Owner's Engineer. c. Location of trailer mounted monitors will be specified. ‘d._All locations to be approved by Owner’s Engineer. 3:26 Cooling towers shall be protected by fixed location, a rade hydrants and monitors, in sufficient (min. 4) number to provide firewater coverage to all sides. 3.26.1 Sufficient 14/2 in. by 150 ft. (45 m) long hose reels and housings shall be located on the top deck of cooling towers to provide total deck area coverage. Supply line size to be approved by the Owner’s Engineer. 3.27 Drums shall be protected as follows: C a. If three or more drums are installed, each drum shall be fireproofed. *b. If only one or two drums are installed in the same area, provisions for cooling with water may be Substituted for Gireproofing. The water required for cooling shall be supplied by a fixed spray system or hydrants, hoses, or monitors. HOSE REEL LOCATION 3.28 *Hose reels shall be located per the following: C a. Within process unit areas: The minimum number of hose reel installations shall be based on providing coverage to the entire plot area with spacing at approximately 200 ft. (60 m) centers. b. Outside process unit areas: Hose ree! installations as required to provide protection to equipment, and facilities likely to be a source of hydrocarbon release, such as at pump areas, at tank ear or tank truck loading stations, and similar fire risk areas. DELUGE SYSTEMS 3.29 Top mounted deluge systems shall be provided for pressurized and refrigerated storage. The capacity of the firewater system in these areas shall be capable of supplying the sum of the following: a. Firewater to the deluge system of a vessel involved in an emergency, plus the deluge system of adjacent exposed vessels, and b. A minimum of 1000 gpm (227 m'/h) of cooling water from hydrants. Where the requirements of subpar. a. and b. above will exceed the specified firewater system capacity, piping may be arranged to sectionalize the control of individual deluge systems, or sroups of deluge systems. For example, if more than one deluge head is required on a vessel, the system may be segmented to cover only that half of the vessel exposed to an adjacent fire. HYDRANT SELECTION AND INSTALLATION. 41 *Hydrants with or without monitor connections shall be used as specified (See Fig. 2.1). 42 Hydrant hose connections shall be per Fig. 1.1. 4:3. Hidrants shall be provided with a 15* (380 mm) diameter handwheel. 4:4 Horrants shall met requirements per CSA Standard B89.6 latest revision. 4.4.1 Hydrants which are used to service 11/2 in. hose reels only shall be 2 in. in size. IMPERIAL ap 9.2.3 Esso) FIREWATER SYSTEMS REY 8uNe gs PAGE 7 OF 10 BASIC PRACTICE 4.4.2. *Hydrants in process areas, pump pad areas, loading rack areas and docks shall be equipped with fixed ‘monitors. Other areas requiring fixed monitors shall be specified by the Owner's Engineer. 4.43 Hydrant installation shall conform to Fig. 2.1. MONITOR SELECTION AND INSTALLATION 5.1 All monitors shall be brass or bronze construction, double swivel, ball bearing, universal motion. The €_ monitor shall have a locking device suitable for unattended operation. The monitor shall be the deck pipe type, lever operated, similar to Akron Brass style 508. ‘A constant flow, combination straight stream fog nozzle, similar to the NPS 2'/ (65 mm) size Akron 1750, shall be furnished instead of the normal tip and tube. Note: Akron Brass Company 1450 Spruce Sireet Wooster, Ohio U.S.A. *Construction features for elevated monitors will be specified, and shall include a feature to adjust the water spray pattern where movement of the monitor is controlled from grade. ixed location monitor installations shall be as shown below: 5.2 5.3 Trailer mounted type monitors shall have the nozzle assemblies mounted on a light weight wheeled inflated tire trailer capable of being handled by one person. The monitor-trailer assembly shall be designed to resist the nozzle reaction forces and be stable during operation. The monitors shall be furnished with two 21/2 in. (63 mm) hose connections and two 100 ft. (30.5 m) lenghts of 2'/2 in. (63 mm) hose. The hose shall be stored on the trailer with the hose arranged to play-out readily when the trailer is put into service. The hose to the monitor shall be permanently connected (o a valved outlet from the firewater system. (Note: This may be one outlet from an area fire hydrant.) Non trailer type portable monitors shall be equivalent to the “‘multiversal” type. Monitors shall be Installed in a housing with 100 feet of 21/2. (63 mm) hose, similar to that shown in IBP 323, ig. 7. Hose. The 21/2 in. (63 mm) hose shall be provided in 50 ft. (15.3 m) lengths and shall be rated for 400 psi (2750 kPa) design test pressure. It shall be neoprene rubber lined, single cotton nylon jacket, oil and abrasive resistant neoprene rubber or plastic coating. Couplings shall be 2'/2 in, (63 mm) pet Fig. 1.1. All hose shail be red in colour. IMPERIAL. (BP 3.2.3 REV 8 JUNE’88 FIREWATER SYSTEMS PAGE 8 OF 10 BASIC PRACTICE | e 5.3.1 Fixed type monitors shall be: a. Installed on hydrants as per Fig. 3.1 b, Connected to a NPS 3 gate valve, if not installed on hydrants. Drainage for lines leading to monitors must be provided. HOSE REEL SELECTION AND INSTALLATION Deleted. Deleted, a ae as a) Fixed hose reels connected to the firewater system shall be as shown in Fig. 4.1, suitable to handle 150 ft. (46 m) of 1/2 in. (63 mrn) firm type hose without kinking or collapsing. 'b)_ Firm type, rubber covered, rubber lined hose shall be used so that hose may be put in service without complete unwinding of hose from reel. The hose shall be furnished in 150 ft. (46 m) lengths and be Fated for 400 psi 2760 KPa) design tet pressure. It shal be good for operation at temperature of 40°F (-40°C). ©) 1'/2 in. couplings shall be provided with the hose. 4) Fog nozzles provided for these hose reels shall be Akron Brass style 1717 or equivalent. 6.2.2 Hose reel and housing installation shall be as shown in Fig. 5.1. 6.2.3. *Monitors and nozzles shall be as per Fig. 3.1 with positive monitor locking devices e 6.3 Hose reels shall be installed so that the hose can be pulled off in a clean accessway which is parallel to the equipment being protected, such as along a pump row. VALVE SELECTION 7.1 Block valves in underground firewater piping shall: a, Be operable from grade with the valve stem and packing permanently protected from contact with earth, rocks, ete, 'b. Be provided with a valve position indicator at grade to indicate full open and closed positions. c. Valve guards are required to protect valves located with 3 feet (I m) of roadways or accessways in areas of high vehicular traflic to avoid mechanical damage to valves. Guards shall be NPS 4 (114.3 mm OD) Sch. 40 pipe filled with conerete and set in a concrete foundation, 7.2, Butterfly valves are not permitted in firewater service. 7.3 Gate valves installed in aboveground firewater mains shall be OS&Y. 7.4 Ballvalves, in the firewater piping to monitors, shall be provided with manual gear operators to restrict closure to 10 to 15 seconds. 7.5 Manually operated ball valves in sizes NPS 21/2 and smaller are permitted in the firewater system without closure time restrictions. ‘SPRAY SYSTEM DESIGN AND INSTALLATION 8.1 Spray system design shall conform to NFPA 13 and the following: Spray systems, when specified for high risk fire areas, such as plant building for storage of low-flash products, or congested areas with restricted ‘access, shall incorporate the following e design features: a. When overall coverage is required an open head type system with a manually operated main valve shall be provided per the sketch below. Outdoor spray systems shall be provided with upright open deluge type heads. STRATHCONA |sso| Instructions & Information | I I | | I | General | FIREWATER SYSTEMS | | | | | | | | I ! I VALVE SELECTION REF.: IBP 3-2-3, para. 7.1 2.1 Cast steel valves (11-13% chromium trim) shall be used for underground firewater Lines. 1986 08 18 IMPERIAL 19 3.23 Esso) FIREWATER SYSTEMS REV 8 JUNE'8B PAGE 9 OF 10 BASIC PRACTICE 'b. The location of the main actuating valves for manually operated spray systems shall be at least 50 ft. (15 m) horizontally from the area under protection. The valves shall be identified by signs. c. Where an automated system is provided the design of the heat actuated devices, ultra violet detectors or other systems, shall be approved by the Owner’s Engineer. 8.2. Spray heads shall have a minimum orifice opening of 1/2 in. (13 mm). 8.3 Flushout connections shall be installed to permit flushing all sections of the system with fresh water. ‘They shall be capped or flanged. 8.4 Astrainer with a valved blowoff connection shall be installed in the main feeder pipe to the spray. The ‘maximum size openings of the strainer shall be 1/4 in. (6 mm) and the ratio of free screen area to pipe cross-sectional area shall be 3 to 1. Blowoff valve size and connection shall be NPS 2. 8.5 *Firewater application rate shall be 0.2 gpm per sq. ft. (0.48 m’/h per m') of area sprayed unless otherwise specified. 8.6 The spray system design shall be approved by the Owner’s Engineer. DELUGE AND SPRAY SYSTEM INSTALLATION FOR PRESSURIZED AND REFRIGERATED STORAGE COMMON REQUIREMENTS. 9.1 Deluge systems shall be as follows: ‘a, Deluge heads for the top system shall be as indicated in Fig. 6.1, detail A. Fig 6.1 also shows typical piping requirements for the top deluge system. b. Spray nozzles for tank shells and the bottom half of spheres shall be the non-clogging type, and shall have a minimum orifice opening of 1/2 in. (13 mm). Baffles or diverters shall be used to ensure coverage in areas shielded from direct water flow by appurtenances, platforms and toe plates. *The detailed design of all spray systems shall be approved by the Owner’s Engineer. 9.2 Operating and drain valves shall be provided for the cooling water deluge system of each vessel, as indicated in Fig. 6.1. The following requirements shall govern the installation: ‘a, Valves shall be installed in a valve box located outside the dike and be accessible in case of fire. b. The valve box shall be winterized. cc. Minimum spacing between the vessel and the valve box shall be one vessel diameter or 150 ft. (45 m) whichever is greater. d. The operating valve shall be identified by a sign located at the valve, ce. Piping layout to the deluge system shall permit complete draining at the single drain valve. PRESSURIZED STORAGE 9.3 Spheres and spheroids shall be provided with a top mounted firewater deluge system as shown in Figure 6.1. This will provide a minimum rate of 0.1 to 0.15 gpm per sq. ft. (0.24 to 0.37 m’/h per m'). The ‘water deluge shall cover the total vessel surface above the maximum equator. For vessels larger than 85 ft. (26 m) diameter, the system shall be sized to deliver 0.15 gpm per sa. ft. (0.37 m’/h per m. 9.4 Provisions for water flooding. Spheres not in refrigerated service (and spheroids) shall have a NPS 2'/2 C size hose connection installed in the product line to the bottom of the vessel to permit flooding of the vessel with water, as follows: ‘a, The connection shall be installed outside the dike, and at least 100 ft. (30 m) from the vessel. It shall be located between the vessel block valve and the manifold valve. The connection shall be made in the top of the lin, to prevent accumulation of water. . The connection shall include double block valves with drain, check valve and fire hose connection fitted with dust cap. (See IBP 9-2-1, Fig. 1.1). lap 3.2.3 IMPERIAL REV 8 JUNE’88 FIREWATER SYSTEMS PAGE 10 OF 10 BASIC PRACTICE REFRIGERATED STORAGE 95 96 97 9.8 ‘Spheres and speroids shall be provided with a top mounted firewater deluge system as shown in Fig. 6.1. This will provide a minimum rate of 0.1 t0 0.15 gpm per sq. ft. (0.24 to 0.37 m’/h per m’). The water deluge shall cover a total vessel surface above the maximum equator. For vessels larger than 85 ft. (26 m) diameter, the system shall be sized to deliver 0.15 gpm per sq. ft. (0.37 m’/h per m).. Double wall spheres using a granular type insulation in the annular space shall, in addition be provided ‘with a bottom spray system sized to deliver water at a rate of 0.15 epm per sq. ft. (0.37 m’/h per ni) to the under portion of the vessel within the vessel support legs. Dome roof tanks shall be provided with a top mounted firewater deluge system. The system shall be designed to deliver water at a rate of 0.1 gpm per sq. ft. (0.24 m’/h per m’) of roof surface. Baffles or deflectors shall be provided to direct roof water run off onto the shell ‘Dome roof tanks higher than 75 ft, (23 m) shall be provided with additional firewater at arate of 0.1 gpm per sq. ft. for the top half ofthe shell area. This water can be supplied through additional deluge heads ocated on the roof or through a spray ring system located at the top shell course. If compression rings ‘on the shell will obstruct the flow of water from the top deluge system, a spray ring system shall be installed below the compression ring for shell cooling. Last ERE BP Reviewed-Rev. 4, June 1982 HRDS. PER INCH SoREWED) 8 7 7 AUBERT MUTUAL AID THREAD G6 TAGLUDED ANGLE FULL VEE at | a rm 3 : a) ob ane asat WU PITCH DIA. 2.89" ERS a ALLTEL de 8 THREADS PER’ INCH ie ne ALL. IN ACCORDANCE WITH Bs Te Ue Doe eee AtbeRTA"ORDER'INcBuNCIL nic SAN 28. 19 | SCRENED 5 THRDS PER INCH | AMERICAN NATIONAL STRATHCONA ee STANDARD FORM yng 2 1/2" 29/64" ae 13/64" 33 13s is . st ol. i 2] lz 3] 3 S| * = <| § 1avat = 3 8 le [16] 2 335 4 76 a aie" 3 28 ag 7/8" = 28 ge MALE -TRUNCATED ONLY : FEMALE Suan, 60%" vee ” oan gS 3 TOLERANCE: $0.1 ALL IN ACCORDANCE WITH ee | G54 STANDARDS BED.2 (1954) se | ge NOTES: SARNIA REF INERY | GuTER wos oF ALE, 4x0 FEMALE, con's To JeRMINATE IN “MIOBEE CUT" ALL THREAD FORM i eocanines Se cee ant STEAM WE KEY Luss. 7 OPERATING NU 2 1/2" FOR HOSE CONNECT! ONS : PROVINCE OF NOVA SCOTIA STANDARD ee ae GONE NO. TY CHALIFAX) | | | f eA ||) | DARTMOUTH |REF INERY | FEREADS V fYeE Goro THREADS FER INCH Z ADS V_TYPE 60"2? THREA No Gr Sitene "FoR wecsos Taxon wiTH DEE ea eat Ihc ' THREADS Ti ~ RUBBER WASHER THREAD CALIPERS: FIRE HOSE COUPLINGS B74 Oro. x 174" THO 77 MONTREAL REG INERY nove: |IBP_ 3.2.3 1d Fiero REGARDLESS OF GROUND . XA | DEPTH OF TRENCH TO SUIT LOCAL CONDITIONS uv Lauaeat | TYPE _‘A‘ TYPE HYDRANT STANDARD LENE MARK_ON’ HYDRANT ~~ NOS 1/2 NPS HOSE CONNECTIONS: CK WARNING VALVE MUST BE FULLY OPEN 08 FULLY CLOSED MOUNT THIS SIGN ON HEAD OR HANDWHEEL VALVE STEM 70 ROTATE To OPEN COUNTER-CLOCKWISE 15" DTA. HANOWHEEL CAP WITH | 1/4 SQ. NUT WITH CAPS. THREAD. TO BE SPECIFIED AS PER STD. OWG TeP 3.2.3 FIG. 1.1 Lo& NPS PUMPER CONN. WITH EXTRA STRONG EVERTITE PART ‘A ADAPTER (FEMALE THREAD) AND CAP Sieouiews ANG. oft i EQUIPMENT CO. NONTREAL (or Eaaly CRORE saeT4 es SPECIFY DRAIN TO GRAVEL ss$ss BED. SEE NOTES 1 AND 2 a 6 NPS CLASS 125 ANST Far FLAN oR MECH. OTN MANUFACTURED 6 CANADA VALVE, CTD 4172" DARLIN E Wi Caps. lg tas! 2-2 1/2 NPS HOSE_CONN. WITH THREAD TO BE SPECTFIED AS PER IBP 3.2.3 FIG 1-1 Yr, NPS _CLASS 125 : FLANGE (icc REGARDLESS OF GROUND LINE MARK ON HYORANT BARREL DEPTH OF TRENCH TO SUIT LOCAL CONDITIONS MANUFACTURED AY CANADA. VALVE. ETD. eve SEE NOTE 3 DARLING 5-50-B-M Notes. 1. (A) GRAVEL BEDS SHALL CONSIST OF 3/4* STONE OR GRAVEL PLACED AROUND AND BELOW THE BOTTOM OF THE NYDRANT GRAVEL BED MUST BE_18” MIN. ALL ‘AROUND BARREL AND BASE JHE BED SHALL BE COVERED WITH HEAVY ASPHALT- IMPREGNATED BUILDING PAPER BEFORE BACKFILLING 2. HYDRANTS FOR DARTMOUTH TO HAVE DRAIN RING WITH ONE 3/4 IPS TAP. 3. SELECTION OF HYORANT_AND MANUFACTURER SHALL BE REVIEWED WITH REFINERY FIRE MARSHALL. @ o REFERENCE ORAWING: IBP 3.2.3 FIG. 1.1 THREAD DETAILS FOR FIRE HOSE COUPLINGS: IMPERTAL BASIC PRACTICE Ess9) HYDRANTS «| xov es [TBP APPROX. 4'-0% 1 178" OTA. NOZZLE DISCHARGE TIP th STANG Bb. 056! oR AKRON 2506 MONITOR (SEE ALSO NOTE 1) AKRON 1760 NOZZLE +4 & STANG Bb. 0561 OR AKRON" 9506 MONITOR, (SEE ALSO NOTE 1) ‘ABOVE GRADE — HIGH MONITOR (TYPE A) MOUNTED ON DARLING B-50-8-M HYDRANT SEE NOTE 2 APPROX, 4°-0" ‘ABOVE GRADE HIGH MONITOR (TYPE B) MOUNTED ON DARLING B-50-B-M_HYDRANT SEE NOTE 2 SNPS CLASS 125 ANSI THR'D FF. EUG. TACK WELD 7G SNPS NIPPLE HYDRANT SEE IBP 3.2.3 le : LJ LOW MONITOR MOUNTED ON DARLING B-50-8-M HYDRANT ‘SEE NOTE 2 = wontToR AKRON 508 08 STANG Bb. 0309) Ewin. co | f— svPs PIPE NIPPLE i AKRON 1780 NOZZLE | t SNPS CLASS, 125 ANSI FoF. FLG. TACK WEL 1G SNPS NIPPLE anes Gass. 25, ANSI at Gate vate” Shave On etal NOTES: |. SUITABLE BRACING MUST BE USED | ON ALL ELEVATED MONITORS. ('2. FINAL SELECTION, INCL. MANUFACTURER OF "HYDRANT AND MONTTOR SHALL BE REVIEWED WITH REFINERY FIRE MARSHALL. | | REFERENCE DRAWINGS: |IBP 3.2.3 FIG. 2.1 - HYDRANTS IMPERTAL BASIC PRACTICE HYDRANTS, SLOPE OUTER 3° CIP. DOWNWARD 4 END CORNERS: To BE ROUNDED @ ANCHOR BOLTS 3/87 THK. BASE R HOUSING DETA 14 GA. CARBON STEEL HOSE IReEL— (See NOTE 1) HOSE REEL & HOUSING INSTAL = LATION TO FIRE HYDRANT PER STD. TBP 3.2.3 FIG 8.1 1172 FyP.T. ? | | \ a yyuere,noues ror ve | |. Or | HOSE REEL, | (See NOTE 1) HOSE REEL SUPPORT REEL DETAILS 1. REEL MST BE OF SUFFICIENT SIZE TO HOLD OF 1 172" SINGLE JACKET FIRE HOSE. 1172" FiRW TYPE HOSE. THE TYPE OF HOSE REQUIRED WILL BE SPECIFIED 2. HOUSE TO BE PRIMED AND PAINTED FIRE RED. 3. HOUSE DIMENSIONS MAY VARY SOMEWHAT IF FIRM TYPE HOSE 1S SPECIFIED. Date van/75 |IBP. IMPERIAL BASIC PRACTICE HOSE REEL FOR 1 1/2" HOUS ING FIRE HOSE Fie. 4. SLOPE DOWN TO HYDRANT SECTION PLAN HOSE REEL AND HOUSING PER (BP 9.2.3 FIG 401 NoTEs: 1. LOCATION OF HOSE REEL HOUSING SHALL BE 4S SHOWN IN JOB SPEC 21/2 NPS THRD. HOSE our ING wiTH i 172 PLPING AS PER 2. WHEN HOSE REEL HOUSING 1S LocATED NPS FEMALE THRO. TPB 3-2-3 IN PAVED AREA. "CONCRETE PAD NAY BE DOWELLED TO EXISTING PAD. = 3. IF FIRM TYPE HOSE 1S USED. Hous ING WILL REQUIRE HEATER TO MAINTAIN SLOPE TEMPERATURE AT 40°F MINIMUM. ® | HYORANT AS PER (BP 3.2.3 ae 4 a 374 NPS DRAIN VALVE CONCRETE PAD I SEE NOTE 2 | GRADE Ls | €ss0) IMPERIAL. ELEVATION HOSE REEL AND HOUSING INSTALLATION AT FIRE HYDRANTS rev. | baTe Fo. | 1_| san 75 |IBP 3.2.3 Bal WIDTH DEPENDS ON APPURTENANCES. ‘ON TOP OF VESSEL 1/4" PLATE. —_l 1/2" 6 HOLES AT HEIGHT DEPENDS ON APPURTENANCES ON TOP OF VESSEL 2°70" CNTRS APPROX. DETAIL “¢ DELUGE WEIR DEFLECTION COLLAR. TROUGH es a | SHIELD FIREPROOF ING ‘COLUMN, 1/4" PLATE 2020 1/4" GAP BETHEEN SPHERE SURFACE, 2 COLLAR DELUGE FEED PIPE & NOZZLE DIMENSIONS ize or | OELUGE FEED [DELUGE NozZLE oe PIPE NOM, WELDING DiaN - ">" REDUCER 45, FT. DiaM. | 3° DIAMETER me ‘SMALLER | (SCHEDULE 40) 46.70 60 FT. | 4° DIAMETER | 4. y a+ DIAMETER" | (SCHEDULE 40) 61,70 85 FI. | 6° DIAMETER |g. 9 DIAMETER (2) | (SCHEDULE 40) WASHER SPHERE SEE DETAIL DETAIL NTS 150" i DELUGE FEED PIPE SEE CHART NOTE 6 1) justRUCTION SIGN Finematc| PAVING 4: 7 SLOPE N | = pz f f | ee a ! ' SLOPE J THE INTO ed = HiGH PRESSURE eel ane WRAPPED PIPE SS. FIREWATER MAIN A Losati: BR | DRAIN oan | DELUGE opeRaTine —/ DRAIN VALVE (DO. NOT INSTALL IN. ANY FIRE HAZARD AREA) ELEVATION NTS = FOR ADDITIONAL PIP. al THIS DIMENSION MAY BE VARIED TO PERMIT THE WATER TO_CLEAR OBSTACLES SUCH AS APPURTEN= ANCES 2 PLATFORMS. THE NOZZLE SHOULD BE LOCATED AT THE TOP DEAD CENTER OF THE Vessel). FOR LARGER DIAMETER VESSELS THAN THOSE INDICATED IN THE CHART A SPECIAL DESIGN WILL BE REQUIRED TO PROVIDE WATER AT A RATE OF 0.15 GPM PER SO. FT. OF THE TOTAL VESSEL ‘SURFACE. ING INFORMATION SEE 1BP 9.2.1 FIG. 1.1. WEIR REQUIRED AS PER DETAIL *C"- DELUGE MUST BE TESTED BEFORE SPHERE 1S PUT IN SERVICE, TO ENSURE THAT THERE ARE NO DRY SPOTS. INSTRUCTION SIGN TO INCLUDE SPHERE NUMBER AND OPERATING SEQUENCES FOR VALVES. SEE (SP 9.1.1 FIG1.1 FOR FIREBANK DETAILS AND_ALLOWABLE AREA’FOR BURN COND TIONS To PREVENT TOTAL ENGULFMENT OF SPHERE IN EVENT OF FIRE. STAIR TREADS SHOULD BE ATTACHED TO SHELL WITH CLIPS TO AVOID CAUS NG DRY SPOTS ON SURFACE OF VESSEL WHEN DELUGE IS OPERATING. IMPERIAL. BASIC PRACTICE FIRE & SAFETY : erate 3 somata IPT aan 1, rng 19 of, canson Sieh BRP t ' 2'-3 172" Le L25x25x5 A TYPICAL FOR_TOP PERIMETER OF “SHELTER ~veTa 1 SIDE | 174" PLYwoot ON 10 GAs SHEET STEEL > i \ 225x25%5 essxssxe! HINGE DETAIL 2 DCOR_ (SHOWN, 1-5 3/4" 2i-8 1a" : 1 ise" DETAIL 3 i CtoseD' = | | | | [-—SEE NOvE 4 | NOTCH TO SUIT IN) « 2. Ess0) MATER IAL FRAME TO BE 255X55X6 EXCEPT WHERE NOTED. TOP. SIDES, DOOR. BACK. SHELF AND FLOOR TO BE 10 GA CARBON STEEL SHEET. ALL WELDED CONSTRUCT ION. SHELF AND FLOOR TO BE COVERED WITH 174" PLYWOOD_AND HAVE 4-172" DIA. DRAINAGE HOLES IN’ EACH. DOOR HAROWARE : ST °-HINGE, DOOR PULL AND CASE BOLT 70 BE HEAVY DUTY STEEL CONSTRUCT ION. Finite *RED PAINT AS PER IBP 19.1.1 BOTTOM SECTION TO HOLD 100’ OF 2.1/2_NPS REDSKIN FIRE-HOSE CODE 774024 IN & DOUGHNUT ROLL. TOP SECTION TO HOLD AKRON PORTABLE MONITOR MULTIVERSAL STYLE 491 WITH “BLACK WIDOW 500°. ROUND ALL CORNERS. INSTALL SHELTER ON A CONCRETE SLAB HIGH ENOUGH TO ALLOW DOOR TO OPEN Tn SNOW. IMPERIAL FIRE-HOSE & MONITOR SHELTER BASIC PRACTICE DATE JAN/76 IBP Beier) THPERTAL IBP3-2-4 PRESSURE RELIEVING SYSTEMS Page 1 of 7 e BASIC PRACTICE Rev. 8 | Dec. 1990 a 12 24 224 222 223 224 225 cat "344 32 33 33.1 eo: : SCOPE This Basic Practice covers mandatory requirements governing the design, application, and instalation of pressure relieving systems comprising pressure relief devices and associated flare pipe headers. ‘An asterisk (*) indicates that adcitional information is required. Ifa job is contracted, this additional information is furnished in the Job Specification SUMMARY OF ADDITIONAL REQUIREMENTS. Table 1 lists the codes, publication, and standards which shall be used with this Basic Practice. TABLE 1 (CODES, PUBLICATION, AND STANDARDS ‘API Standards and Recommended Practices (RP) RP 520 Part 1. Design of Pressure-Raliaving Systems in Refineries RP 520 Part I instalation of Pressure-Reloving Systems in Flefnerios AP 521 Gude for Pressure Folie! and Depressuring Syste Sid 2000 Venting Atmospheric and Low-Pressure Storage Tanks ASME Codes Section | Power Boiler Section Vil Pressure Vessels, Division 1 ASTM Standard 84 ‘Surface Burning Characteristics of Buiding Materials ANSI Standards 8313 (Chemical Plant and Petroleum Retinery Piping 2351 Industnal Accident Prevention Signs Pressure reliet devices shall be provided as shown on the flow diagrams. Car-sealed open valves shall be numbered on the engineering flow plans and a ‘be supplied to the Owner. ‘A schedule showing the location, type, marking, size, flange rating, orfice identification, area and setting pressure of all pressure relist devices on each unit shall be supplied to the Owner. This shall also include the type of ud, gravity for molecular weight, maximum operating inlet pressure and temperature and relieving capacity as well as the presence of any corrosive agent. ‘A schedule shall be suppliod to the Owner's engineer showing the rate (Ib/t), composition or properties (e.g. gravity ‘or molecular weight), toxic material content, malodorous material content, temperature and pressure of the releases which occur from each PR valve on each contingency. This schedule should indicate which PR valves discharge to atmosphere and which to a closed system. {All bellows type PR valves shall be identified in the field in accordance with 1BP19-1-1 and painted yellow. All bellows bonnets shall be painted red. of numbers and locations shall DESIGN ‘The recommendations of API RP 520 shall be considered mandatory, ‘The recommendations of API RP 521 should be followed where practical. Any departures from this AP shall be approved by the Owner's Engineer. Pressure relief (PR) valve requirements for tired steam boller tumished to ASME Code Section 1 shail be per that code. ‘Waste heat bollers PR systems, shall be in accordance with the provisions of ASME Code Section Vil ‘The vendor shall comply withthe requirements of the proper authorities of the Province where the PR valve is to be installed. In order to ensure that the Refinery has certification for PR valve maintenancé approved by the Owner's Engineer. PR requirements for all other systems shall be per ASME Code Section Vill. the PR valve manufacturer shall be IBP3-2-4 TWPERTAL, Page 2 of 7 PRESSURE RELIEVING SYSTEMS Reva | Dec. 1990 BASIC PRACTICE PRESSURE RELIEF (PR) VALVE SELECTION AND INSTALLATION TYPES OF VALVES © "41 Acceptable types of PR valves are: conventional, balanced area bellows, or pilot-operated. The pilot-operated type PR valve is permitted only for clean services and its use shall be approved by the Owner's Engineer 4.1.1 The standard direct spring acting relief valve shall normally be used. 4.1.2 The bellows direct spring acting valve or the pilot operated type shall be used for the following conditions: ‘a. Where the valve is subjected toa back pressure greater than 10% of the set pressure, b. Where the back pressure is not constant and the range of variation may have an adverse ettect on the valve ‘operation. 4.1.3. The bellows type valve shall be used where necessary to protect the spring from corrosive or fouling material 4.1.4 The pilot operated type valve shall be limited to a maximum temperature of 450°F (232°O) and services which are rnor-fouling or have a gravity of 408API or higher. Pilot safety valves must be protected from freezing, ‘4.1.5 Installation of balanced area bellows and pilot operated safety vaives shall be approved by Owner's Engineer. VALVE SIZING © "42 Rupture discs (RO) may be used in conjunction with or as a substitute for PR valves only with the approval of the (Owner's Engineer. Acceptable types of RD's are: pre-scored conventional (forward acting) for both liquid and gas service; pre-scored reverse buckling for gas only service. The manufacturing range for all R's shall be the lowest available from the manufacturer, preferably zero. The full amount of the manufacturing range shall be applied below the design pressure of the equipment. Use of other types of AD's with larger manufacturing ranges shall be approved by the Owner's Engineer. © 49 The minimum size of pressure and thermal relief valves shall be NPS 3/4. 44 Deleted, “4.4.1 a. Inlet connections NPS 1-1/2 or larger shall be flanged. Inlet connections NPS 1 may be flanged or threaded, those smaller shall be threaded, Itt comer fa mab ged et tl Pra we Pats recs ‘CREDIT FOR THERMAL INSULATION © 45 Credit factors for insulation in determining the minimum PR device sizes for fire exposure shall be per API [AP 520 and subject to the following: ‘4. Credit shall be taken for the following insulation systems on steal vessels which are covered by galvanized or stainless steel jacket: 1. Cellular glass, rock cork, and high temperature mineral fibers. 2. All types of hot insulation. '. Credit can be taken for insulation systems on equipment constructed from low melting point material, such as aluminum, ©. Credit shall be allowed for plastic foam, ¢.g. polyurethane and similar types of materials, which melt or ‘decompose under fire exposure conditions if covered with materials such as high temperature mineral wool, and protected with a galvanized steel or stainless steo! jacket. Plastic foam insulation shall have a flame spread rating of 25 or less per ASTM E-84 and be approved by the Owner's Engineer. The covering shall prevent the plastic foam from decomposing or melting when the insulation system is exposed to a temperatura of 1000°F (640°C) for one hour. Credit may be taken also for the insulation property of mineral wool 4.6 Venting requirements for pressurized storage vessel installations. The following factors shall be analyzed in

You might also like