Professional Documents
Culture Documents
Design Layout
Design Layout
s.]gR CAST as REG"D
ve
316 8.8.
“ANCHOR STUDS
|
1
1
|
TyPE-D
(ELEVATION
NOTE!
1. FOR .OCATION AND SIZE OF SEALS REFER
Iep d.2-1 PAGE 14 0F 16
2. FOR MATERIALS SELECTION REFER 70
Tgp 3-2-1 PAGE 3 OF 16 AND TABLE 4
Hep 31211 PAGE 16 OF 16.
0
ss0) IMPERIAL
BASIC PRACTICE
|
|
L
|
|
|
TYPICAL GAS SEALS
AT MANHOLE
2_| Nov 84
[pp 3.21 [onFROM TANK HEATERS:
1 — PRPASATE E
a
SEALED —
ter
i
5 ial
DETAIL
ONLY ONE SEWER
_—ineg_sveass
(SEE NOTE
ik
IS AVAILABLE
x INPS BYPASS:
SEALED,
TNLETS
CONTAMINATED WATER
DETAIL 2}
SEWERS (AR
WHERE SEGREGATED SE
OW POINT OF TANKLOT—
1:
|__N.0.-INPS BYPASS WITH
EXTENDED STEW
(SEE NOTE 3)
St
ro
¥
A
EXTENDED STEM SUPPORTED
By GUIDES ON FOUNDATIONS
GATE VALVE (RISING
STEM) TURNED TO
ANGLE_OF DIKE
FLANGED VALVES IN| BURIED LOCATIONS ARE IRON
BODY, BRASS MOUNTED WITH NON-RISING STEM.
PROVIDE SIONS INDICATING FUNCTION OF EACH
BRAN VALVE. AND. WHETHER NORMALLY KEBT OPEN OR CLOSED.
BY-PASS VALVE NORMALLY OPEN EXCEPT IN THE
EVENT OF PRODUCT SPILL.
FOR TERMINAL REQUIREMENTS REFER TO PARAGRAPH 6.7.1
TANK LOT TO BE GRADED TOWARDS THE CATCH BASIN
IMPERIAL
BASIC PRACTICE
TANK LOT DRAINAGE FOR
ATMOSPHERIC STORAGE
VESSEL,2-4"=20 X 1" LG.
Pu BO!
22 GA STEEL
OM
SLOTS CUT TO pe OM BRAN _
RECEIVE BOLTS ey tow A ont a
SPLIT HOSE
PACKING.
COVER
Ape
=
ao
eee
— —h_ ~U/G TANK
' DIA. HOLE FOR #" PIPE
DIA. HOLE FOR 1J" PIPE
FOR 1" PIPE
FOR 2" PIPE
IMPERIAL
BASIC PRACTICE
FUNNEL, & COVER DETAILS
FOR TERMINALS
D [nov ves /IBP 3.2.1 StBASIC PRACTICE
24
2.2
IMPERIAL
LOW AND HIGH BACK PRESSURE AIR FOAM | gp 3.2.2
SYSTEM FOR FIXED ROOF STORAGE TANKS | fege org?
SCOPE
‘This Basic Practice covers mandatory requirements governing the design and installation of air foam
systems using either a low back pressure system with foam makers located at the top of the tank riser
Or high back pressure system with foam makers located on a fire truck. The former is required for new
installations, and the latter for retrofits or repairs on existing high back pressure systems. The systems
are used on fixed roof tanks and covered floating roof tanks.
‘An asterisk (*) indicates that additional information is required. If a job is contracted, this additional
information is furnished in the Job Specification.
MATERIALS:
Pipe for risers and laterals shall be of carbon steel, schedule 40 min, wall thickness.
Frangible diaphragms, incorporated in the seal chamber of foam chambers, shall be 14 oz, (400 2)
(0.061 in, (1.55 mm) thick) of common soda lime glass scored to facilitate breakage under foam
pressure,
Foam chambers and makers shall be carbon steel.
DESIGN
+*Foam chamber requirements for flammable and combustible liquids. Foam chambers and makers shall be
provided for tanks 20 ft. (6.1 m) diameter and over in the following services:
a. Tanks containing stocks witha closed cup flash point of 130°F (55°C) and below. (This includes
low flash materials and most crude ois.)
bb. Tanks containing stocks with a closed cup flash point above 130° (55°C) if such stocks are stored
ata temperature above or within 15°F (8.5°C) of their flash point.
cc. Fixed roof tanks with internal floating covers of steel, aluminum, non-metallic, or combustible
construction shall be protected in a way similar to a cone roof tank.
d.* Where tankage spacing guidelines are not met.
cc. The number of foam chambers shall be as follows:
1) For low back pressure systems see Table 1
TABLE 1
Low Back Pressure Systems
‘Nominal Tank Diameter Number of Foam Chambers Required per tank
20to 80 ft. ( 61024 m)
81 to 110 ft. (24 t0 34 m)
111 to 130 ft. (34 t0 40 m)
131 to 150 ft. (40 to 46 m)
151 to 170 ft. (46 to 52 m)IMPERIAL
1B 3-2-2 LOW AND HIGH BACK PRESSURE AIR FOAM
pees on aan SYSTEM FOR FIXED ROOF STORAGE TANKS E59)
PAGE 2 OF 4
BASIC PRACTICE
2) For high back pressure systems see Table 2
TABLE 2
High Back Pressure Systems
Size of Tank Diameter Number of Foam Chambers |
2010 65 fi.(20m)
66 ft. to. 90 f.(20 to 27m)
91 ft: to 110 £1,027 to 34m)
111 ft. to 125 £8.34 to 38m)
126 ft: to 140 f1.(38 to 43m)
141 ft. to 150 ft.(43 to 46m)
ag og
35
‘The design and installation of foam chambers for flammable and combustible liquids shall be:
a. For low back pressure systems as per fig. 1.1, 1.2, and 2.1
b. For high back pressure systems as per Fig. 1.1, 1.2, and 3.1
‘The design and installation for water soluble solvents, i.e. alcohols, ketones, etc., shall be specified by
the Owner's Engineer.
Foam chambers shall be located to minimize length of lateral piping. If more than one chamber is
required, they shall be equally spaced around the tank, as per IBP 3-2-2 Fig. 1.1
‘Foam makers shall be provided and installed as follows:
a, For low back pressure systems
1) For tanks $5 ft. (16,8 m) diameter and smaller, foam makers with a capacity of 250 gpm
(56.9m’/h) at design inlet pressure.
2) For tanks larger than 5S ft. (17 m) diameter, foam makers with a capacity of 500 gpm
(115 m’/h) at design inlet pressure,
b. For high back pressure systems not applicable as foam makers are on fire trucks.
“Blanked foam chamber connections. When specified that flanged connections be provided for future
installation of foam chambers,such connections shall be blanked with a 1/4 in, (6 mm) thick blind
flange, installed as a gas tight connection.
Piping Layout.
a) Low back pressure systems
1) Each foam chamber shall be equipped with its own riser, foam maker and lateral.
2) Pipe risers shall be installed directly below the foam makers.
3). Pipe risers shall be spaced a minimum of 4 in, (102 mm) clear from the tank shell.
b. High back pressure systems
1) Each foam chamber shall be equipped with its own riser and lateral.
2) Pipe risers shall be installed directly below the foam chamber.
3) Pipe risers shall be spaced a minimum of 4 in, (102 mm) clear from the tank shell.
‘The riser pipe size to cither the foam maker in a low back pressure system or the foam chamber in a
high back pressure system shall be the same size as the lateral.IMPERIAL
LOW AND HIGH BACK PRESSURE AIR FOAM | gp 3.2.2
REV 6 JUNE'88
SYSTEM FOR FIXED ROOF STORAGE TANKS | faye JUNE
BASIC PRACTICE
3.8 Lateral Pipe Size
C a, For low back pressure systems. Laterals up to 350 ft. (110 m) in length shall be NPS 3 (88.9 mm
OD) for 250 gpm (57 m’/h) foam makers and NPS 4 (114.3 mm OD) for $00 gpm (115 m’/h)
foam makers. Where greater lengths of laterals are required, they shall be sized so that the lateral
pressure drop does not exceed 35 psig. (240 kPa gauge).
b. For high back pressure systems. The size of the laterals shall be as shown in Table 3. The length of
the laterals from the roadway to the tank, including the riser, shall not exceed the maximum length
shown in the table with allowances made for any fittings.
TABLE 3
Tanks 40 Ft, Dia. & Smaller ‘Tanks Over 40 Ft. (12 m) Dia.
Height
of Tank Lateral Size Max. Length* Lateral Size Max. Length
Ft. (Meters) NPS(OD mm) | in Feet (Meters) | NPS(OD mm) | in Feet (Meters)
32.0.8) aaa 215 4) 6 (168) 525 (160)
40 (12.2) 4cl4) 250 (76) 6 (168) 90 (149) |
48 (14.6) 44) 225 (69) 6 (168) 450 (137)
* Based on a roughness factor C of 120
3.8.1
‘Where existing chemical systems are converted to an air foam system, the following shall apply:
a. When the existing risers consist of dual NPS 3 (89 mm OD) lines, these may be retained in service
by manifolding them together at the base of the riser and installing a NPS 6 (168 mm) lateral.
b. The length of the lateral shall not exceed the length Table 4 after allowances are made for
any fittings which may be installed,
cc. Where the risers are smaller than NPS 3 (89 mm OD) they shall be replaced with NPS 4 or 6 inch.
TABLE 4
Tank Height Max. Length of NPS 6 (168 mm OD) Lateral*
in Feet (Meters) in Feet (Meters)
2 9.8) 375 (114)
4002.2) 300 (1)
48185) 2s (6)
* Based on roughness factor C of 120
3.9 Lateral Terminals. Laterals shall terminate on the road side of all pipelines and drainage ditches, The
terminals shall be from 2 to 4 ft. (0.6 to 1.2 m) above grade in accordance with IBP3-2-2 Fig. 1.2.
a. Low back pressure systems shall have their terminals located in relation to the fire hydrant so that
the total length of hose from the hydrant to the fire truck and from fire truck to terminal shall not
exceed 100 ft. (30 m).IMPERIAL, |
1Bp 3-2-2 LOW AND HIGH BACK PRESSURE AIR FOAM
paged peace SYSTEM FOR FIXED ROOF STORAGE TANKS
bb. High back pressure systems shall have their terminals located in relation to the fire hydrant so that
the length of hose from the hydrant to the fire truck or from the fire truck to terminal shall not
exceed 25 ft. (7.5 m). The terminals shall not be more than 15 ft. (4.5 m) from the roadway.
3.10. For tanks requiring two laterals, they shall be brought to a single location 4 ft. (0.6 m) apart. However,
not more than two laterals from any one tank shall be brought to the same location.
3.11 *Where prevailing winds exist, the lateral terminals shall be located upwind from the tanks.
3,12 The terminal connections on foam makers shall be as follows:
a. Low back pressure system
1. Laterals to 250 gpm (57 m’/h) foam makers shall terminate in one 2!/2 (92 mm OD) mating
hose coupling.
2. Laterals to 500 gpm (115 m’/h) foam makers shall terminate in two NPS 2!/2 (92 mm OD)
‘mating hose couplings.
3. Couplings shall be provided with dust caps or plugs
b. High back pressure system
1) NPS4(114 mm OD) terminals shall have Evertite hose adapter #992-2A and dust cap #992-5A
(or equal) installed.
2) NPS 6(168 mm OD) termina! shall ave Eerie hose adaper #92868 and du cap #928-38
(or equal) installed.
FIELD CONSTRUCTION
4.1 Riser supports shall be 1/2 in. (13 mm) thick plate, 12 in. (300 mm) length, with the width depending
on riser dimension. Each support shall be located on 8 ft, (2.5 m) centers and placed perpendicular to
the tank shell and centered on the riser pipe. The edges of the plate shall be continuously welded on all
sides, to both tank shell and pipe with 1/4 in. (6 mm) fillet welds.
4.2 Laterals shall be installed as follows:
a. Slope continuously toward the dike.
b. Shall not run through the dike area of any other tank or group of tanks. However, piping within a
‘group of tanks may cross intermediate toe walls within that group.
c. Shall extend outside the dike to points at least one tank diameter or 50 ft. (15.25 m), whichever is
‘eater, from the tank.
4d. A minimum of 1 ft. (300 mm) above finished grade.
‘A NPS 3/4 (26.7 mm OD) drain valve shall be provided inside the tanklot and at the lowest point of the
foam lateral near the dike.
Where the pipes pass through the dike, they shall be protected against external corrosion by using either
wrapped of extruded polyethylene or fusion bonded epoxy coatings.
A flange shall be used to join the foam riser and the foam lateral at the base of the tank.
Bog of
TESTING
5.1.1 Performance Test, All components of the air foam system shall be tested with foam by the Owner
before the tank is put in service. The foam generating truck discharge pressure shall be between 125
and 150 psig (860 and 1035 kPa gauge).
Last ERE BP Reviewed-Revision 3, January 1977| , FIREWALL
HOSE ADAPTOR
AND DUST caP——_1
(ONE CHAMBER?
, fuse .
4 yy Hose aparror
AND DUST CAP
(FIVE CHAMBER)
OSE ADAPTOR *
AND DUST cap —=
(TWO CHAMBER?
FIREWALL
FIREWALL
UW ose apartor
WAND DUST CAP
(THREE CHAMBER)
HOSE ADAPTOR
SY AND OUST CAP
(SIX CHAMBER?
IMPERIAL
BASIC PRACTICE
E_ADAPTOR LATERAL PIPING INSTALLATION
ae “AY ano oust car FOR LOW & HIGH BACK
PRESSURE SYSTEMS
crouR onAWBER [alBP Tl
Nov 783 |IBP Sean)wee ROE 2)
roaw cunwen sarery —You might also like