Professional Documents
Culture Documents
1-56 GARDINER
010
Prepared for
MANALTA COAL LTD.
Calgary, Alberta
by
TECHMAN LTD.
Engineers s Consultants
9th Floor - 320 - 9th Avenue S.W,
CALGARY, ALBERTA
t '
December 1975
TM 110
Kev. 3
l PHONE (403) 261-8710 9th FLOOR
320 - 9th AVENUE S.W.
TELEX: 038-2)733
CALGARY, ALBERTA
T2P 1K6
l
Mr. J.A. McDonald
Manalta Coal Ltd.
l Box 2880
Calgary, Alberta
l (Cont'd
l
l
l Ir. J.A. McDonald -2- November 14. 1975
l the basis of moisture removal capacity., and the flash dryer, the perfor
mance of which on German brown coal is well-documented and which is assumed
to offer parallel performance on Onakawana lignite.
l TECHMAN
l JGB/dc
Encls.
l
l
l
l
l
l
l
l
l TABLE OF CONTENTS
421! 2NE8302 83. 1 -56 GARD l NER (7110JO
l
l INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . l
l CONCLUSIONS S RECOMMENDATIONS . . . . . . . . . . . . . . . . . . . . .
SUMMARIZED FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
BENEFICIATION ALTERNATIVES . . . . . . . . . . . . . . . . . . . . .
3
5
7
l Gasification . . . . . . . . . . . . . .. .. .
Solvent Refining . .. .......... .
. . ... . . . .. . . . . 7
........ .... .. 8
l SELECTED ALTERNATIVES . . . . . . . . . . . . . . . . . . . . . . . . . .
Drying Methods ........ .. ..... . . ... ... ... .. ..
13
13
l General . .. . .. . . . . . . .. . . . . . . .. . .. . . . . . . .
Material Balances ..... .. ..... .... ...
47
47
l SUMMARIZING COMMENTS . . . . . . . . . . . . . . , . . . . . . . . . . . . . . .
REFERENCES . . . . . . . . . . . . . . . . . . . ......... . . . . . . . . . . . .
51
57
l
l
1 . '
1 *
1 APPENDIX
1
1 LIST OF TABLES
1 TABLE IV -
Briquetting.
Estimated Capital arid Operating Costs.
22
35
1 TABLE V
TABLE VI
-
-
Energy Consumption for Schemes Proposed.
Energy Balance for Schemes Proposed:
36
1 TABLE VII -
Case I and Case II.
Product Unit Costs for Alternative
Schemes.
42
50
1 LIST OF FIGURES
1 FIGURE 2
FIGURE 3
-
-
Typical Plant Layout.
Typical Material Balance Flow Sheet.
53
54
1
1
1
1
1
l
I Page l
*,
l INTRODUCTION
l
l A number of beneficiation schemes are technically
possible, but the primary purpose of any beneficiation plan
for the Onakawana lignite must be to reduce substantially
l its moisture level. Hence, this report, while presenting
order-of-magnitude capital costs for gasification and
l .*
various drying and briquetting processes.
l
l Page 2
I
l Study guidelines setting the upper limit of capital
cost for any scheme proposed at $50 MM-^75 MM have been
imposed following discussions with consultants in the
l field of solid fuels beneficiation.
l
l
l Page 3
l
l CONCLUSIONS AND RECOMMENDATIONS
I Conclusions
l It is concluded that:
I
l Recommendations
l 1.
It is recommended that:
l
l
l Page 4
l *
l are estimated to be in the order of $35,000, exclusive
of the costs of a sampling program.
l
l
l
l
l
l
l
l
l
l Page 5
l SUMMARIZED FINDINGS
l
l The reserves have been examined a number of times,
most notably by the Ontario Research Foundation between
l 1928 and 1932 (1) (2) and by Alberta Coal (now Manalta Coal)
between 1967 and 1970, and in 1972. The in-situ properties
l
l TABLE I
PROXIMATE ANALYSIS OF ONAKAWANA LIGNITE
l Moisture
Ash
46.001
13.28
l Volatiles
Fixed Carbon
21.50
21.22
100.00
l Carbon
Hydrogen
Sulphur
Nitrogen
32.23%
2.20
0.51
0.23
l Ash
Oxygen
Chlorine
8.37
10.37
0.09
l Moisture 46.00
100.00
l
l
l Page 6
l
l
l
l
l
l
l
l Page 7
l BENEFICIATION ALTERNATIVES
l Gasification
l
l A conservative estimate of economically recoverable
Onakawana lignite reserves places them at 145 MM tons.
Experts in the field of gasification state that, at an
l
l
l Page
^
8
l Solvent Refining
l
l Factors similar to those which disadvantage central
ized gasification exist in the consideration of any pro
l
l In addition, no commercial-scale operation has been
built to date, even within a highly industrialized,
l Drying S Briquetting
l
l Removal of moisture from the lignite may be the
single most effective beneficiation measure possible,
l
l Page 10
l contacting with fast-moving drying gases. Fines in them
^
l
l To eliminate most of the hazards and inconvenience of
handling particulate lignite, the raw lignite must either
l
l
l
l Page 11
^
l plant feed.
l Selection of Alternatives
l
l The sections above have reviewed several beneficia
tion measures which might be applied in the development
l
l
l
l W Page 12
l
l
l
l
l
l
l
l
l
l
l
l
l
l
l
l
l Page 13
^
l SELECTED ALTERNATIVES
l Drying Methods
l
l
l
l Page 14
^
l
l Five methods of drying lignite by applying heat
either directly or indirectly have been examined, and these
are as follows:
l
l (1)
(2)
Rotary Steam-tube Dryer (indirect heating)
Fluidized Bed Dryer (direct heating)
l (3)
(4)
Indirect Heat Calciner (indirect heating)
Indirect-Direct Heat Calciner (indirect and
l (5)
direct heating)
Flash Dryer (direct heating)
l
l A discussion of the features and relative merits of
each method is included in the following sections. It must
l
l
l
l Page 15
*
l material and hence the "fill volume" are set for a partic
ular installation by adjusting the slope at which the
dryer rests. Typical "fill volumes" for efficient opera
l tion range between 10 and 20 percent; slopes may be up to
3/4 inch per foot, depending on the time of passage and
l most applications.
l
l
l Page 16
^
l particles", and this has been the main reason for its
inclusion here. In addition, heat fluxes are relatively
l appendix.
l
l Fluidized bed dryers enjoy widespread use throughout
the North American coal industry. Several companies includ
ing McNally-Pittsburg, Dorr-Oliver, Heyl S Patterson, and
l
l Essentially, wet coal is fed onto a grate through
which hot gases (from a combustion chamber just below) pass
l tary fuel.
l
l
l Page 17
^
l
l Indirect heat rotary calciners are used for heat-
treating and drying at higher temperatures than are
obtained in steam-tube rotating dryers. Heat transfer
l coefficients are roughly the same; however, total surface
area for heat transfer is much reduced. CalculaLions
l were increased.
l
l
l Page 18
^
l
l The indirect-heat calciner differs from other rotat
ing drying equipment in that it is, in effect, contained
within the furnace supplying the heat. Like the steam-tube
l dryer, it requires "a minimum flow of gas to purge the
cylinder which, when handling granular solids, reduces
l dusting"
(8)
, and this is the primary reason it has been
included for consideration in the present study. A quan
l heat calciner.
l
l The indirect-direct heat calciner is similar to the
indirect-heat type except that, as its name suggests, the
material is dried by direct heat as well as by heat trans
l fer through vessel walls. VThereas the principal'mechanisms
of drying in the indirect-heat calciner are that of
l
l
l Page 19
^
l Flash Dryer
l
l
l Page 20
l Discussion
l
l Several drying methods have been reviewed. In each
case it has been assumed that the method is applicable to
l
l
l
l Page 21
^
l Briquetting Methods
l
l Two types of briquetting are applicable to the
Onakawana lignite: (1) with a binder, and (2) without a
binder. However, tests have been performed on the Onak
l awana lignite which show that a high proportion (some
101 by weight) of binder is required for successful
l ting techniques.
l
l
l
l
l
l
l Page 22
l TABLE III
l Extrusion
Press 12 - 2C^ 1400 kg./cm 2
l Double Roll
Press
Ring Roll
Press
*20 - 24%
6 - 151
1000 kg./cnT
5
l
l Three types of presses may be used, as noted above.
The double-roll press, while designed to be used for
l f Q\
handling l '. While extrapolation of this experience to
the Onakawana application should be done carefully, it is
l
l
l
l Page 23
i
l 1000 tons per day, and (2) ring-roll presses, with pressures
l
l
l Page 24
m
l little.
I
l
l
l
l
l
Page 25
EXTER PRESS
(INTERPOLATED)
FIG. l
TECH M AW LTD.
MO*" l **-
AS SHOWN ' l.C. HGUkf
TM-MO
PEC., 1974
RELATIONSHIP Of RRIQUETTING PRESSURE
TO PRODUCTION RATt
VI 56-00
l
l Page 26
l Simplifying Assumptions
l
l Raw Lignite Production
l Fuel Quality
l
l
l Briquetting Feed Quality
Page 27
l Operating Bases
l CASE I CASE II
l Briquette Production
l
l Capital Cost Escalation Rates
l 1971
1972
5*
S.5%
l 1973
1974
G.8%
12.0%
l Estimating Procedures
l
l
l Page 29
*,
l scheme.
l
l Silos St Car Loading Facilities
l
l
l 30
l -10% to +30% of the lump sum stated, given that 2Jj days 1
production storage is indeed required.
l Electro-Static Precipitators
l
l Electro-static precipitators are impossible to size
without some idea of dust loading and gas velocities to be
l
l Buildings
l
l The costs of heating and electrical distribution sys
tems have been assumed to be included in the 30% contin-
l
l
l Page
^
31
l Major Equipment
l
l Rotary steam-tube dryers, indirect-heat calciners,
and indirect-direct heat calciners have all been priced
l dryers.
l
l A "probable value" guesstimate has been used in the
pricing of briquetting equipment, given the time constraints
l
l
l Page 32
l
l
l Page
t
33
l below:
l Carbonizers;
Presses; 6 ring-roll presses*
2 Lurgi carbonizers
4 double-roll presses
l
l An estimated maximum of $40 MM is projected for the
Onakawana application on the basis of this comparison with
l
l
l Page 34
H*
l
l Capital and operating costs are summarized in Table IV
on the following page, and have been developed from cost
l estimate calculations.
l
l
l
l
l
l
l
l
l
l
l
l
ESTIMATED CAPITAL S OPERATING COSTS
IV A. CAPITAL COSTS
(dollars x 106)
Case I: 1.0 MMTPY Mined
Drying Scheme Briquetting Method
Type Capital Cost Type DR Press EX Press RR Press
Capital Cost 2.28 OF 4.11
Rotary Steam Tube Dryer 11.72 Combined 14.00 14.53 15.83
Fluidized Bed Dryer 4.28 coste 6.56 7.09 8.39
Indirect Heat Calciner 4.89 dhown 7.17 7.70 9.00
Indirect-Direct Heat Calciner 7.94 fct 10.22 10,75 12.05
Flash Dryer 14.11 right . 16.39 16.92 18.22
Case II: 1.5 MMTPY Mined Capital Cost 2.89 3.42 5.25
Rotary Steam Tube Dryer 15.70 Combined 18.59 19.12 20.95
Fluidized Bed Dryer 7.05 costs 9.94 10.47 12.30
. . Indirect Heat Calciner 7.01 frhown 9,90 10.43 12.26
Indirect-Direct Heat Calciner 10.30 it 13.19 13.72 15.55
Flash Dryer 23.05 right 25.94 26.47 28.30
IV B. OPERATING COSTS
(dollars x 106)
Case I: 1.0 MMTPY Mined
Operating Cost
Operating Cost 0.36 0.39 0.46
1 . Rotary Steam Tube Dryer 2.89 Combined 3.25 3.28 3.35
Fluidized Bed Dryer 1.95 costs 2.31 2.34 2.41
Indirect Heat Calciner 1.75 shown 2.11 2.14 2.21
Indirect-Direct Heat Calciner 1.63 at 1.99 2.02 2.09
Flash Dryer 1.84 right. 2.20 2.23 2.30
"0^7"
Case II: 1.5 MMTPY Mined Operating Coat "oT43 "oTsT
Rotary Steam Tube Dryer 3.65 Combined 4.08 4.12 4.22
Fluidized Bed Dryer 2.47 costs 2.90 2.94 3.04 DI
•Q
Indirect Heat Calciner 2.60
to
2.13 shown 2.56 2.70 W
01
Indirect-Direct Heat Calciner 1.91 at 2.34 2.38 2.48
Flash Dryer 2.35 right. 2.78 2.82 2.92
-Tj r
" "" ~ "" M M M jim "" ** "*l i mt wm H "
^'
Case I:
f
B)
iQ
Q
U)
O
l Page 37
l DISCUSSION
l CAPITAL COSTS
l OPERATING COSTS
l Scheme Using
1.99 to 2.09
l 2. Indirect-Heat Calciner
3. Flash Dryer
2.11 to 2.21
2.20 to 2.30
l
l
l
l ENERGY CONSUMPTION
Page 38
*
l array is
Annual Energy
l 1. Plash Dryer
2. Indirect-Direct Heat Calciner
3. Fluidized Bed Dryer
818.0 to
844.0 to
826.0
852.0
1,134.0 to 1,142.0
l 4. Indirect-Heat Calciner
5. Rotary Steam Tube Dryer
1,342.0 to 1,350.0
2,792.0 to 2,800.0
l
l On a position-weighted basis, the various schemes can be
arranged in order of decreasing benefit, as follows:
l consumption.
l
l
l Page 39
l Capital Costs
n
l
l Operating Costs
l
l
l Page 40
l Fuel costs have been assumed at $4.00 per ton for lignite
burned in the plant; feedstock lignite has been valued at
l $6.75 per ton. These are assumed direct mining cost fig
ures only and with field overheads assigned only to the
lignite available for sale. These costs may be substan
l tially increased when mining equipment amortization costs
and other indirect costs are added.
l shown below:
l Total
Annual
Raw Lignite
Fuel
Lignite
Used
Residual
For
l .Scheme Using Available as Fuel Sale
l
l Energy Consumption
l
TABLE VI
OVERALL ENERGY BALANCE FOR SCHEMES PROPOSED
Case I: 1.0 MMTPY Mined
Drying Scheme 'ress Energy Input Energy Consumed Net Energy Output Efficiency,
Type ype Btu/yr x 109 Btu/yr x 109 Btu/yr x 109 X
DR 10015 2792 7223 72.12
Rotary Steam Tube Dryer EX 10018 2795 7223 72.10
RR 10023 2800 7223 72.06
DR 10072 1134 8938 88.74
Fluidized Bed Dryer EX 10076 1138 8938 88.71
RR 10080 1142 8938 88.67
DR 10011 1342 8669 86.59
Indirect Heat Calcitier EX 10014 1345 8669 86.57
RR 10019 1350 8669 86.53
Indirect-Direct DR 10011 844 9167 91.57
Heat Calciner EX 10014 847 9167 91.54
RR 10019 . 852 9167 91.50
DR 10015 818 9197 91.83
Flash Dryer EX 10018 821 9197 91.80
RR 10023 826 9197 91.76
l "As-mined"
l
l
l CASE II; 1.5 MMTPY raw lignite mined
l CAPITAL COSTS
l 1. Indirect-Heat Calciner
2. Fluidized-Bed Dryer
9.90
9.94
to
to
12.26
12.30
l
l
l Page 44
l OPERATING COSTS
l 3. Flash Dryer
4. Fluidized Bed Dryer
5. Rotary Steam Tube Dryer
2.78 to 2.92
2.90 to 3.04
4.08 to 4.22
l
l depending on the briquetting method chosen.
l ENERGY CONSUMPTION
l array is
Scheme Using
Annual Energy
Consumption Btu x
l 4. Indirect-Heat Calciner
5. Rotary Steam Tube Dryer
1,986.0 to 1,998.0
4,147.0 to 4,159.0
l
l On a position-weighted basis, the schemes can be arranged
in order of decreasing benefit, as follows:
l
l
l Scheme Using
Page 45
^
Position-Weighted Score
l Indirect-Direct Heat Calciner 6
\
l Indirect-Heat Calciner
Fluidized-Bed Dryer
7
9
l Plash Dryer
Rotary Steam Tube Dryer
9
14
l
l Again, as in Case I above, only the rotary steam tube
drying scheme can be eliminated from further considera
tion at this time; some evaluation of the remaining
l
l Capital Costs
l OPERATING COSTS
l
l
l
l Page 46
l Annual
Fuel
Lignite
Raw Lignite Used
As
Residual
for
l Scheme Using Available
(tons)
Fuel
(tons)
Sale
(tons)
l Energy Consumption
l Scheme Using
"As-mined"
l Briquettes
(tons)
Surplus
(tons)
l (a)
(b)
Indirect-Direct Heat Calciner
Indirect-Heat Calciner
656,250
656,250
315,200
234,300
l (c)
(d)
Fluidized-Bed Dryer
Flash Dryer
656,250
656,250
277,200
320,200
l
l
l
l
l Page 47
l
GENERAL
l l
Indirect-Direct
l Heat Calciner 437,500 262,500 90,400 209,600 1,000,000
b)
l Fluidized Bed
Dryer 437,500 262,500 116,000 184,000 1,000,000
l Indirect-Heat
Calciner 437,500 262,500 146,000 154,000 1,000,000
I d)
- Flash Dryer 437,500 262,500 87,000 213,000 1,000,000
l a)
p Indirect-Direct
Heat Calciner 656,250 393,750 134,800 315,200 1,500,000
l Fluidized-Bed
l Dryer 656,250 393,750 172,800 277,200 1,500,000
* c)
Indirect-Heat
I Calciner 656,250 393,750 215,700 234,300 1,500,000
d)
l Flash Dryer 656,250 393,750 129,800 320,200 1,500,000
1
l Page 48
l
THERMAL VALUE OF R.O.M. SURPLUS St BRIQUETTED PRODUCTS
l
l R.O.M.
Briquettes Surplus Total
Operation . Btu .x 10* ...)
l
l CASE l: 1.0 MMTPY raw lignite mined
l a)
b)
Indirect-Direct Heat Calciner
Fluidized Bed Dryer
10, 920
10, 920
2 ,837
2 ,495
13 ,757
13 ,415
c) Indirect-Heat Calciner 10, 920 2 ,109 13 ,029
l d) Flash Dryer 10, 920 2 ,882 13 ,802
l
l
l
l
l
l
l
1 Page 49
1 *
1 SAMPLE CALCULATION OF PRODUCT COST
Processes Selected: Flash Drying 6 Ring Roll Briquetting
1 Plant Production:
Briquettes (656,250 s. t.) Btu.- 10,920 x 10 9
1 Operating
H.O. Ohd. 6 Admin @ 1552
Depreciation 25 yr . S.L.
- $ 2,920,000
438,000
1,132,000
1 Product Cost:
$14,429,399
1 f .0 .b .
stockpile
1
1
1
Flash Dryer
Press Type
Double Roll 1.31 0.75 1.20 1.28 0.75 1.17
Extrusion 1.33 0.75 1.2) 1.29 0.75 1.18
Ring Roll , 1.37 0.75 1.24 1.32 0.75 1.20 Jji
00
(t
Ul
o
' * R.O.M. lignite @ 9 x 106 Btu/s.t.
Dried and Briquetted lignite @ 16.64 x 106 Btu/s.t.
li
l
l Page 51
t
l SUMMARIZING COMMENTS
l b)
c)
Indirect-direct-heat drying
Flash drying
l d) Indirect-heat drying
l The fifth, that using rotary steam tube dryers, was removed
from consideration because of relatively high capital costs,
l high operating costs, and poor overall energy utilization.
l Both the flash dryer and the indirect-direct heat dryer have
l
l
l Page 52
*
l lower than those of a fluidized bed dryer when the units are
installed in comparable plants.
l Conclusions
l
l It is concluded that four of the five drying methods con
sidered in this studv should be evaluated further.
l
l These conclusions are qualified, in that certain assumptions
have been made concerning the suitability of the methods
for the Onakawana application, and these assumptions may or
l this.
.Page S3
FURNACES
t l l l i 4 l l l M l l l l l
BRIQUETTE STORAGE
i LOAD'OUT
FIG. 2
TECH M AIM LTD.
fcONI ___l"*"*" t 6. I'O-iH t
TM-KC
320,200
R.O.M. SALES
TPY
R.O.M.
450,000 TPY
129JOO————— T0 0|
?YERS AS FUEL -|
TPY
|
1
FI ASH DRYING
R.O.M. 1,050,000 i 656,250 "*". TO "DRIED" AND/OR
1,500,000 TPY TPY BRIQUETTING TPY "DRIED A BRrOUETTED"
PLANT -** SALES
IQ
Q
tn
1 '
393,750 TPY
H eO Removed J^PI TECHMAN LTD.
•c"" NONE MAWN " L.G. FIGURE ~—— TM-110
*w June , 7S *movw
l application.
l
l
l
l
11 ' Page 57
*
REFERENCES
1
1 ( 1) Ontario Research Foundation, A Technical 6 Economic
Investigation of Northern Ontario Lignite, Ontario
1 ( 6) loc.cit. p. 20-27.
I
1
W Page 58
* REFERENCES (cont'd.)
l
l (11) Landers, W.S., Binderless Briquetting of Indian Lignite,
Proc. Internat. Briquetting Assoc., Univ. of Wyoming
M Nat. Resources Res. Inst. Info. Circular Dec. 1959,
pp.30-37 (contained in U.S. Bureau of Mines OP 460).
l
l
l
l
l
APPENDIX
l
l
l \
l
l
--Dutt drum
Section at 'A-A* Section through ittom monlfold
rSteaai
l i•* '
WU rf *"*j ft ,-aJ
material .
ttil In hert atet
J^
' :rs "*"m-— '
l material
dltctiorgt conveyor
l
QiMio-tub* roUty diyw. (Oowral Antriet* JVan*perlaKm Ctrp.)
Figure l
Rotary Steam Tube Dryer
l
l
l
l
Start-up flock-
l
l
l
l Fluldiied-bed coil drytr. (Cevrttty tf Dtrr-Oltitr, /M.)
l Figure 2
DORR-OLIVER
Fluidized Bed Dryer
l
l
l
l
l \
l
l FAN STACKv r F AN FEED
l
l
l
DUST
COLLECTOR f FLUID BED
-y. DRYING
CHAMBER .FEED
BIN
l
DUST
BIN
l
, SETTLING
CHAMBER
l
DUST SCREW
CONVEYOR
l
AUTOMATICALLY
CONTROLLED FEED
AND DISCHARGE GATES
l
DISCHARGE VALVE
l
l BY-PASS
l
STACK
l
l Figure 3
l
HEYL k PATTERSON
Fluid Bed Dryer
l
l
l \
l
l
l
l
l
l
l
l
l
l
l
l Figure 4
McNALLY-PITTSBURG
Fluid Bed Dryer
l
l
l
l
l
l Furnoc* Wng
l
l
l
l Motor drive Burners Discharge chute
. Oai-fired Indirect-beat rotary ealeiner with a water-ipray extended cooler and feeder auembly. {CourHty ef BariltU-
l Figure 5
Indirect-Heat Calciner
l
l
l
l
l
l argt Crots MCtten
ifcowtag fligM*
l Figure 6
Double^bell iodirect-Ulrect rotary dryer. (Hording C*.)
l Indirect-Diroct-Heat Dryer
l
l
l
l
l
1 \
1
1 iH
j
-
1 c
J 1
h
^^^- -—^^•^.
^?
1 ^ j^^-**
***
i**1*~
4tr ^ M
— cod hid mtcKonlim
yy *
^y*2 r *" — (had Itirnoci tor dryinf cod
1 ^^
-- X
**
^
— f o humin o( dritr
\
w
?
— crctoni
\
— tlKlrotlolle dull •riciftllcior
1 l"Nt; M*
— cooling *iii*l lor culviriud (*o)
^
*-.
— sulvirlMd cool hetoir
^ a/
f\
10— •wlvirisid coal hidir
-
A
s. tt *^ finn*! wu vri^wvfiing privi
11 ^M rUlA^PAll brlAUAHtlkA Afm**
c ^
•** •^ ^ ^ It — fcrlavift* coAviyor
* f'
a
r
V V" 4/
f X
1
p
^^
^H P"
y
^^ ~
^
S.V W ,
'' 1 ~-^ ^^y
1 u" 1 *v1
1 f^^***^ m. lmm
Diagram ofx. Lurei flaih-dryine. pulverizing, and ring-roll briquetting plant for brown coal.
•J '
* Figure
LURGI
1 Flash Dryer in conjunction with Ring-roll briquetting press)
1
1
1
1
1
C-E RAYMOND FI^^SH DRYNQ
SYSTEM rt* COAL.
Figure 8
C-E RAYMOND
Flash Dryer
l APPENDIX
l 2.
Tel: 312 - 621-6200
Dorr-Oliver, Inc.
l Havemayer Lane
Stamford, Connecticut
Tel: 203 - 348-5871
06904
l 7.
Telex; 06-23227_^________
Combustion Engineering, Inc.
900 Long Ridge Road
l Stamford, Connecticut
Tel: 203 - 329-8771
06902
KG Industries, Inc.
l
l
l
l December 15/75
l LIST OF REVISIONS
l (REVISION #3)
l follows: "Moisture
Ash
46.00!?
11.28
l Volatiles 21.50
Fixed Carbon 21.22
100.00
ONTARIO
DIVISION OF MINES
GEOLOGICAL BRANCH
1974
Drill Records
SECTION C
Correspondence, Documents, and Drill Hole Logs
SECTION D
SECTION A
Progress Report on Onakawana Lignite-Fireclay Deposits,
District of Cochrane, 1973, by J.R. Trusler
Page
Summary l
Introduction 2
Tonnage Calculations 3
Recommendations 7
List of Maps (not included in OFR 5111) 8
SECTION B
Drill Records
"C" - Series, Drill Hole C-l to C-20 1-29
"B" - Series, Bore Hole No.l to B-182 30-211
Total 211 pages
SECTION C
Correspondence, Documents, and Drill Hole Logs
Correspondence, Statements of Expenses, Statements
of Work Performed 1-27
Samples and Testing 28
Report of Analyses 31
Key Map 42
Plan Showing Location of Drill Holes 43
Drill Hole Logs 44
Total 61 pages
- 111-
SECTION D
~ IV-
List of Maps
Master Explorations Limited, Onakawana Lignite Deposit.
2 Maps, scale l inch to 800 feet.
Onakawana Lignite Development, East and South-West Fields,
Surface Plan. Scale l inch to 200 feet.
Onakawana Lignite Field, Eastern Section, Ratio Map.
Scale l inch to 200 feet.
Onakawana Lignite Deposit, Drill Hole Location Map. Scale
l inch to 800 feet.
Onakawana Lignite Development, District of Cochrane, Ontario.
Scale l inch to 400 feet. To accompany Ontario Fuel
Commission Report.
Location Plan, scale l inch to 60 miles. To accompany Ontario
Fuel Commission Report.
- V-
Progress Report on
Onakawana Lignite-Fireclay Deposits
District of Cochrane
by
J.R. Trusler
1973
l
l 42 1 1 2NEe382 83 . 1 -56 GARD l NER
030
l
l
l
ONAKAWANA DEVELOPMENT LIMITED
l ONAKAWANA PROJECT
l VOLUME I SUMMARY
l
l Signed:
D ,4 Clarke ^""
D. Creamer
l H. W. S. Marshall
lI Vice-President and
Manager, Engineering Division
l Report 5366-4-73
l
October 1973
l
l
l 42M2NE0302 63. l-56 GARDINER
Volume l
030C
t Report 5366-4-73
l TABLE OF CONTENTS
l 4
METHODOLOGY AND ACKNOWLEDGEMENTS
5. l Plant Capacity
l 5. 2 Type of Power Plant
5. 3 Environmental Effects
5.4 The Construction Schedule
l
6 SPECIAL CONSIDERATIONS
l DRAWINGS
l
l
l Volume l
l
Report 5366-4-7^
l the 18th century, and was officially confirmed by the Geological Survey
of Canada and the Ontario Bureau of Mines by the end of the 19th century.
Lignite is a type of coal, and initially interest was directed towards mining
l 1928 and 1932. This investigation concluded that with the mining tech
nology then available, and in the economic conditions prevailing, mining
of the lignite was not commercially viable. The scale of operation
t
envisaged in 1932 was an annual production of 300,000 tons of lignite.
The scale of operation under consideration at this time calls for an
annual production of the order of 4, 000, 000 to 7, 000, 000 tons of lignite.
l area of about 400 square miles, which included the Onakawana lignite
deposits. This Company carried out a program of exploratory drilling,
sample testing and a test pit excavation between 1967 and 1970 to
l
l
l
l
l Volume I
l Report 5366-4-73
Page 2
l The coals at the top of this range are generally described as high
quality coal; and coals and lignites at the bottom of the range as low
quality coal.
l techniques are used to burn it. The major disadvantage of low quality
coal is that is is expensive to transport. For example, for the same
l
heat content, it would be necessary to transport more than twice as
much Onakawana lignite by weight as would be necessary with the
American bituminous coals presently used by Ontario Hydro in their
existing thermal power plants.
t
content. North American lignites have heat contents of the order of
6000 to 7000 Btu/lb. This ranks them as high quality lignite, almost
equivalent on the coal quality ranking scale to sub-bituminous coal.
European and other overseas lignites, however, are generally of
i
t
l
i
l
l Volume I
t Report 5366-4-73
Page 3
t Over the last two decades, the use of lignite in North America
l b)
they can burn the lower grade fuel at all.
i
i
l
l Volume I
Report 5366-4-73
M Page 4
t
Onakawana Project is:
l
will never be able to use successfully lignite as fuel,
whether this should be Onakawana lignite or any other
Canadian lignite:
f
any other Canadian lignite if required to do so.
l
f
i
t
l
l
l
i
l
l
f
Volume I
Report 5366-4-73
Page 5
l
Report 5366-4-73
Page 6
l
item a) above, was undertaken by Boyd, acting in the capacity of sub-
consultant to SECO.
l The study terms of reference are specific, and confine the scope
of work to producing:
f
l
t
t
l
f
t
l
l
t
Volume I
Report 5366-4-73
Page 7
Ontario Northland
l
l
The contents of this report are the considered opinions of
SECO and Boyd and, except where specifically noted, are not
necessarily shared by the parties acknowledged above.
l
Volume I - Summary, this volume is complete in itself and
contains a brief description of the Onakawana Project and the
principal conclusions reached by the study.
l 1 Introduction
t
2 The Mine (summary only)
A 6 Costs
7 Discussion
l
information accompanying the technical report.
l
prepared by John T. Boyd Company.
l
l
l
Volume l
Report 5366-4-73
Page 9
Two main seams of lignite are present, the lower over the
whole mineable area, and the upper in a lesser area. Both seams
vary widely in thickness between four feet {assumed as the minimum
recoverable thickness) and as much as 58 feet. The average thick
ness is about 15 feet. The lignite.outcrops in the bank of the
Abitibi River. Overburden thickness varies from 66 feet to 160
feet.
t
Report 5366-4-73
Page 10
l surface water run-off and pit water from the mine area, for routing
to sedimentation ponds for treatment before discharge into adjacent
rivers. The plans also call for continuous reclamation of mined-out
l that which exists at present. This is because the area will then have
topographical relief, be better drained, and because the planned
mixing of overburden and organic material will provide a better
l growth medium for trees and other vegetation than the present
muskeg.
t
l
f
l
l
l
t
l
l
1
Volume I
Report 5366-4-73
Page ll
5. l Plant Capacity
l Report 5366-4-73
Page 12
l the existing line, and the new line, from Pinard to Onakawana. These
two 500 kV circuits from Hanmer to Pinard and Onakawana would be
adequate to cope with the hydro generation in the area plus a 1000 MW
l
utilized unless the thermal power station capacity was increased to
an extent that the estimated lignite reserves would not be adequate to
support.
l
auxiliary loads of the power plant itself, and possible other local
loads in the area, this plant would generate 900 MW for transmission
south from the area.
t
(a) Boiler Selection
As with the mine, the concept of the power plant has been
l
based upon using only plant and equipment already fully proven in
commercial operation. This constraint posed no particular problems
except in the related cases of boiler selection and unit size.
l
combustion techniques successfully developed to burn bituminous
and semi-bituminous coals. These extrapolated combustion tech
niques have been applied with reasonable success to burning North
l
American lignites. It is a matter of opinion at this time whether
these techniques can be still further extrapolated to burn successfully
Onakawana lignite, which has a moisture content about lO^o greater
l
than the highest moisture content of North American lignites.
t
were consulted on this point. Two agreed with the authors of this
l
l
l
Volume I
Report 5366-4-73
Page 13
l
encompass burning Onakawana lignite would likely result in a boiler
expensive and difficult to maintain, and unreliable in operation. The
third contended that that extrapolation of existing North American
l
techniques could be used successfully to burn Onakawana lignite.
However, this contention could not be supported by direct evidence
such as actual operating experience.
t
tending that any attempts to extrapolate North American combustion
techniques to burn Onakawana lignite would not be successful.
l
The point at issue was an important one, because the cost
of a boiler using an extrapolation of North American combustion
techniques was estimated at only about 607o of the cost of a boiler
l
using the combustion techniques developed in Europe to burn lignite.
This difference in cost could amount to over $30 million in the case
of the proposed Onakawana power plant. However, to satisfy the
l
criteria of avoiding the use of any unproven equipment designs or
techniques in the concept of the power plant, the decision was made
to base the design concept upon a boiler using the European design
l
approach. Although the European design approach was selected,
manufacture of the boiler would still be done in Canada since commer
cial arrangements can be made by the manufacturers involved to
t
gain access to European technology.
l
Onakawana lignite compared to North American lignites. North
American combustion techniques for burning coal use air to dry the
coal or lignite in the pulverizing mills before it is fed to the burners.
l does result in a much larger and more expensive boiler, but equally
appears to offer an availability and reliability in operation on low
grade coals such as lignite fully equal, if not superior, to that offered
l
l
l
l Volume I
l Report 5366-4-73
Page 14
l
of a boiler led to consideration of appropriate unit size. The choice
lay between two units, each of about 500 MW net output, or three
units, each of about 300 MW net output. Two units would be less
l costly than three units. However, it was ascertained that while many
600 MW units were on order or under construction to the European
design, there was as yet no proven operating experience with units of
l this capacity. On the other hand, there are many units to the
European design in the 300 MW size class with many years of proven
satisfactory operation.
t in the concept of the power plant for Onakawana. This has the added
advantages that the overall availability of a 3-unit station can be
expected to be better than that of a 2-unit station, and the smaller
l units may be easier to transport to, and erect at, a relatively remote
site such as Onakawana.
l The first was the irregular flow of this river due to operation
of the Otter Rapids hydro plant upstream. To ensure adequate supply
t latter was preferred, and the probable cost penalty, which appears
small, was evaluated. Incidentally, the regulation of the Otter Rapids
plant discharge that would be required would improve the environment
l river, and lack of data on this point. There are rapids situated in
the Abitibi River some 15 miles upstream from Onakawana.
l
l
l
l Volume i
l Report 5366-4-73
Page 15
l blocking the inlets of any pump station providing cooling water for
a power plant at Onakawana.
t to make the base concept of the power plant include the use of a
cooling pond. This was done because such a concept could be
designed and costed without the uncertainties attendant upon the
l alternative of direct cooling from the river, even though the cooling
pond concept is more expensive in capital cost and slightly reduces
the thermal efficiency of the power plant.
l
flexibility of operation comparable to that associated with a conven
tional bituminous coal-fired power plant.
l
5. 3 Environmental Effects
l
or potential effects on the environment of the project. This description
should not be interpreted as comprising a complete "Environmental
Impact Statement". As commonly used, this term implies a more
l
detailed and exhaustive study of the ecology of the area than was
included in the terms of reference for this study. The recommenda
tions of Task Force Onakawana in this field have been noted and, in
l
most aspects accepted.
l
l
l
l
Volume I
Report 5366-4-73
Page 16
l mittent trapping, fishing and canoeing parties ever visit the site.
Therefore the immediate physical, as opposed to socio-economic,
effect of the project on man should be minimal.
l (to trap fly ash or dust emitted), and a high plant stack
results in adequate control of the plant emissions.
The resulting effect on local air quality is considered
l
(b) Water Quality - the adoption of a cooling pond reduces
the effect of thermal pollution to an insignificant level.
Potentially harmful effluents from both the power plant
and mine will be treated to an acceptable quality
l
lower ten miles of the Onakawana River will be lost
through diversion since both rivers flow through the
mine area. This is virtually unavoidable if mining
operations are not to be severely limited and was so
l (c)
considered by Task Force Onakawana.
l
miles of land area will be mined-out, it is considered
that, after reclamation, the land surface is likely to
offer a superior environmental habitat than that
l
presently existing.
l
l
l
l
l Volume I
l
Report 536()-4-73
Page 17
l
study. These were: -
l
the project would be made by June, 1974;
l
l
l
l
l
l
l
l
l
l Volume I
l
Report 5366-4-73
Page 18
l 6_____SPECIAL CONSIDERATIONS
l
The ownership and management organization of the overall
project is conjecture at this time. However, because of the
remoteness of the site area from any established communities,
l
because of the limited transport facilities to the site area (rail
but no roads), and because of the lack of any existing facilities
at the site (other than a rail siding), a somewhat unusual con
l
struction plan has been assumed. This calls for the owner
organizations to be responsible for the provision of the major
temporary on-site facilities and services that will be necessary
l
during development of the mine and construction of the power
plant. These in turn would be made available at no cost (or for
a nominal fixed sum) to the various contractors who would be
l
working on site during the construction period. This organizational
concept has many advantages in a situation of this kind, and is the
same as that adopted for other projects such as the Churchill Falls
l intervals.
l
l
l
l Volume I
l Report 5366-4-73
Page 19
l
employees, visitors, etc. , a 1200 man camp has been considered
necessary. A portion of this construction camp, with associated
catering, recreational and other facilities would be designed and
l
constructed to be converted, as construction draws to a close, to
become permanent facilities at the site for the overnight accommo
dation of operating staff.
l
The labour force required to operate the mine is estimated
at 250 to 340, and for the power plant at 200 to 210, depending upon
the mode of operation assigned to the plant. Add a labour force of
l
40 to 50 to operate the permanent accommodation and messing
facilities at the plant, and the total on-site labour force estimated
for the project is between 500 and 600. Depending upon the employ
l
ment policies and training programs adopted, it is possible that up
to half the labour force required might ultimately come from
Moosonee, the remainder from the Cochrane area. The Moosonee
l
Education Centre is already providing a reservoir of trained staff
suitable for many of the jobs that would be created by the Onakawana
project.
l
and these have been adopted in-toto: '
l
be established at Onakawana, and working conditions
should be such as to permit the labour force to
reside in established communities of their own choice,
l
regular scheduled commuter rail service should be
provided to carry workers between Onakawana and
their place of residence.
l
l
l Volume I
Report 5366-4-73
l Page 20
l on the site during their series of shifts would use the permanent site
accommodation and messing facilities mentioned earlier.
l TRAIN A
l leave Moosonee
arrive Onakawana
6: 15
7:30
p. m.
p.m.
leave Cochrane
arrive Onakawana
4:30
7: 30
p.
p.
m.
m.
l leave Onakawana
arrive Cochrane
8:30
11: 30
p.m.
p. m.
leave Onakawana
arrive Moosonee
8: 30
9:45
p.
p.
m.
m.
l
l
l
l Volume I
l Report 5366-4-73
Page 21
l this might have on the economic and social well-being of the local
people, many of whom are people of Indian ancestry. " Based on
the overall job multiplier as used in the Task Force Onakawana
l Report, for every two jobs created by the complex, one additional
job should be created in local established communities, such as
Moosonee and Cochrane, serving the complex. As a result, the
l of the new work force are obtained from within the area, by absorb
ing unemployment or under employment, and this in turn will depend
upon employment policies and training programs adopted. But the
l
l
l
l
l Volume
l
Report
Pago ^^
l COSTS
l c)
required between the site, and Cochrane and Moosonee.
l
equipment and services.
l
l
l Volume
l
Report
Pago 23
l construction, etc.
7. 3 Mining Costs
l move into areas of deeper overburden more remote from the power
plant. The resulting annual costs are quoted in the Mining Study
Report. The average cash production cost over the life of the project
l
l
l
l Volume I
l Report 5366-4-73
Page 24
40.6 cents
|4. 31/ton
44 cents
l
Total expenditure on fuel $750 million |484 million
(by the power plant) over
the life of the project
l
The cost of power at the exit of the power plant switchyard,
i. e, available for transmission southwards is quoted in mills/kwh
and has been calculated for the two assumed operating patterns.
l
Several power cost figures have been calculated based on various
economic assumptions regarding escalation, price structure
between the mine and the power plant, etc. The most straight
l
forward cost is one based on mid-1973 dollars with no allowance
for future escalation and this produces the following results:-
l
l
l
l
Ijt
l
l Vohime I
l Report 5366-4-73
Page 25
l Case l Case 2
(power cost in mills/kwh)
l Capacity Factor
l These are average figures for the life of the project. Comparable
l power costs based on dollars escalated over the life of the project
are, for Case l, 17. 64 mills/kwh, and for Case 2, 28. 38 mills/kwh.
Costs are derived on the basis of the mixture of private and public
l
l
l
l
l
l
l
l Volume
l Report
Page 26
l c)
techniques are used in the design of the plant boilers.
l f)
environmental guidelines and public opinion.
l
l
l
l Voltune I
l
Report 5^.6-4-7^
PaRo 27
l power plant would fill in the Ontario Hydro system was outside
the scope of this study. It is considered likely, however, that the
plant would operate initially as a base load plant but at a gradually
l result.
l
l
l
l
l
l
l
l
l
l ONAKAWANA DEVELOPMENT LIMITED
l
ONAKAWANA PROJECT
LIGNITE MINE AND POWER PLANT DEVELOPMENT
Engineering Feasibility Study and Economic Analysis
l
m VOLUME II - TECHNICAL REPORT
l Signed:
D. G^Clarke .x-""""'
m Thermal Power Consultant
D. Creamer
Senior Studies Specialist
l
l
H. W. S. Marshall
Vice-President and
l Manager, Engineering Division
l Report 5366-4-73
October 1973
l
Volume II
Report 5366-1-73
TABLE OF CONTENTS
1. INTRODUCTION
1*1 Location
1.2 Background History
1.3 Study Authorization
1.4 Purpose of the Study
1.5 Study Outline
1.6 Report Format
1.7 Acknowledgements
2. THE MINE
2.1 General
2.2 Geology and Field Description
2.3 Recoverable Reserves
2.4 Lignite Quality Characteristics
2.5, Mine Development Plans
2.6 Mining Costs
2.7 Discussion
l 3.U
3.5
3.3.2
3.3.3
Site Layout
Onakawana Pond Site
Summary
.^team Cycle Design
l 3.6 Schedule and Cost Assumptions
l 4.2
4.3
Turbo-Generators
General Mechanical Plant
4.3*1
4.3.2
Condenser Circulating Water System
Condensing Plant
l 4.3.3
4.3.4
4.3.5
Feed-Water Heating Train
Boiler Feed Pumps
Make-Up Water Treatment Plant
l 4.3.6
4.3.7
4.3.8
Service Water System
Fire Protection System
Plant General Arrangement
l 4.3.9
4.3.10
4.3.11
Auxiliary Bay
Administration Building Annex
Air-Conditioning, Heating, Ventilation and
Combustion Make-Up Air Units
l 1.4
4.3.12 Control Room and Office
Cooling Water Supply
l 4.4.1
4.4.2
4.4.3
4.4.4
General
Cooling Water Requirements
Once-Through Cooling on the Abitibi River
Onakawana Cooling Pond
l 4.5
4.4.5 Summary of Alternatives
Licrnite Handling System
l 4.5.1
4.5.2
4.5.3
Plant Fuel Consumption
Lignite Handling Characteristics
Operating Hours and Delivery Rates
l 4.5.4
4.5.5
4.5.6
Stock pile Requirements
Alternative Handling Systems
Description of Selected System
l 4.6.3
4.6.4
4.6.5
Bottom Ash System
Fly Ash System
Design Considerations
l
l
TABLE OF CONTENTS (continued)
7. DISCUSSION
l
7.1 Conclusions
7.2 Review
l 7.3 Discussion
REFERENCES
l DRAWINGS
l
l
l Report 5366-1-73
l INTRODUCTION
l 1.1 Location
The Onakawana site area is located in the Cochrane
l Onakawana.
1.2 Background History
l
l
l Report 5366-4-73
Page 1-2
l
l
commentary on the changes that have occurred in the last forty
years.
Further exploration and investigation work was
l
Company Limited (now known as Manalta Coal Limited) was issued an
exploratory licence covering an area of 375 square miles
including the Onakawana lignite deposits. The company carried
l
out a program of exploratory drilling, sample testing and a test
pit excavation between 1967 and 1970 to establish field limits,
reserve quantities, and lignite quality characteristics.
l
Coal (and subsequently its affiliated company, Onakawana
Development Limited), the Ontario Government, and Ontario Hydro
on the prospects for developing the Onakawana lignite field.
l
These discussions were primarily orientated towards the
construction of a lignite-fuelled electric power plant at
Onakawana with power transmitted southwards for use within the
Ontario Hydro system.
l
feasibility study of the proposed Onakawana Project, encompassing
both lignite mining and power generation. The Shawinigan
Engineering Company Limited, Montreal (SECo), in conjunction with
l
John T. Boyd Company, Mining Engineers, Pittsburgh (Boyd) were
requested to submit a proposal for the study. The proposal was
submitted by SECo in October 1972 and formally accepted in
December 1972. By agreement between the three contracting
l
parties, (Onakawana Development Limited, the Government 6 Ontario
Hydro) Onakawana Development Limited were designated as Project
Managers for the study and it is to them that this report is
l
directed.
1.4 Purpose of the Study
l
available as fuel for a power plant situated on or
adjacent to the lignite field.
l
l
l Report 5366-4-73
Page 1-3
l
l b)
c)
To determine the capacity and type of power plant
best suited to utilize this lignite as fuel*
To determine the effect upon the environment of
l the construction and operation of the mining
facilities and power plant, if built*
t ii)
generate electricity in a power plant at the mine
site;
an assessment of the effects upon the environment
l of such a mine and power complex, if constructed;
iii) an estimate of the cost of electrical power that
l 1.5
could be produced by such a power plant
Study Outline
l
l
l . Report 5366-a-73
Page 1-U
l
l Preliminary work by SECo and Boyd began in September
1972 with visits by staff to the site area during the latter
stages of the exploration program. Mining studies concentrated
l availability.
Progress meetings were held in Toronto on January 25th,
ripril 6th, and May 29th, at which SECo and Boyd reported on the
l The main
volume II - Technical Report
technical report volume is arranged in seven
l major sections:
1. Introduction
l
l
l
l Report 5366-4-73
rage 1-5
l
l 2. The Mine - a brief summary prepared by SECo of the
Mining Study Report with specific reference to the
interface with the power plant.
l 5. Supplementary
construction
requirements
Studies - on such subjects as
methods
and
and schedule,
availability,
effects, plant reliability, etc.
labour
environment
l 7.
the cost of energy.
Discussion - A review and discussion on the study
and statement of conclusions.
l References and Drawings follow.
l report including:
A. Combustion Technology and Boiler Design
l B.
C.
Cooling Water Supply Studies
Detailed Presentation of Capital Costs.
l Volume IV
The complete mining study report by John T. Boyd
Company entitled "Lignite Reserves and Mining Program - Onakawana
l Lignite Deposit".
l
l
l Report 5366-4-73
l Page 1-6
l 1.7 Acknowledgements
l
l
l
l
l
l
l
l Reoort 5366-4-73
l
l This section of the report describes the interface
l between the study work undertaken by SECo and Boyd and summarizes
the contents of the Mining Study Report which is reproduced in
full as Volume IV. A brief discussion of the impact of the
mining study on the power plant and particularly the cost of
l delivered lignite is also included.
2.1 General
l '
appropriate reserve categories, and supplied a key
input to the selection of the
caoacity.
power plant
l c)
Boyd, were also used in the design of the plant
lignite handling system.
Mining Plans - selection of plant capacity and
l operating pattern enabled SECo to calculate the
required annual lignite consumption for the plant,
and this was used as the basis for Boyd to
l
Report 5366-4-73
Page 2-2
l
l 2.3 Recoverable Reserves
l
The total recoverable lignite reserves are summarized
in the following table showing tonnages by field, seam, reserve
category, and overburden depth:
l Field
RECOVERABLE RESERVES (millions of short tons)
No. l Seam No. 2 Seam Total
l East
Main
3.1
41.5
8.6
121.5
11.7
163.0
l
Portage 5.4 8.9 14.3
Total: 50.0 139.0 189.0
l Proven ( 5%)
Partially Proven (± 2(H)
Probable (± 50 %)
101.1
69.5
18.4
96.0
55.6
9.2
106.2
83.4
27.6
l
Overburden *
Overburden Depth (feet) Reserves Strip Ratio (Bey/ ton)
0-60
l
6.9 2.8
60 - 100 45.7 4.7
100 - 140 92.5 6.2
4- 140
l
-43?-?. -9-JL
Total 189.0 6.56
l
* TnrO nrH nrj ti;**"i-ino ^ rvhftTval hat-WAAn seams, but Axcludino
rehandling of overburden.
l
The total in-place reserves are estimated as 221
Million tons on the basis of an in-situ density of.75 pounds per
cubic foot, and an allowance of 5% for out-of-seam dilution. Pit
recovery was considered variable depending on in-situ conditions,
l
but averaged about 85% over the entire field, i.e., 189 million
recoverable tons from 221 million in-place tons. The maximum
quantity of lignite available to the power plant was assumed to
l
be the average recoverable tonnage of 189 million. The total
aroa of the mineable field is approximately 6400 acres.
l
Report 5366-4-73
Page 2-4
l (millions tons/year)
Total Production-30 year life,
(millions tons)
overall Average Stripping Ratio
187.9 112.0
l including rehandling
(BCY/ton)
lumber of Pits in simultaneous
8.6 6.1
l operation
Principal Equipment:
Stripping Draglines
3
2 at 75 cy
2
2 at 54 cy
l Loading Shovels
Goal Haulers
Typical Total Ho. of Employees
l at 85 cy
3 at 11 cy
19 at 120 ton
255
l at 24 cy
2 at 11 cy
12 at 120 ton
150
l Average Labour Productivity
(tons/manhour)
Approximate Area of Mine Exausted
11
6,500
10
4,500
l (acres)
Both olans anticipate the maintenance of a reserve of
l
l
Keport 5366-4-73
Paqe 2-6
l
l The total cost of fuel at the power plant based on an
rate of return including interest and income taxes is:
l investment return
s. taxes
Eauivalent Cost at
$4.00/ton $4.35/ton
l 2.7 Discussion
The following comments express the opinion of SECo and
l are not necessarily shared in full by Boyd whose views are
expressed in the text of the mining studyf particularly on pages
6r, 6s and 6t.
l The proposed Onakawana mine requires a greater
production rate (for Case 1) and a more adverse combination of
l
l
Report 5366-4-73
Page 2-8
l
l a very heavy initial capital expenditure. From
the point of view of mining economics an alternate
solution is to maintain a relatively constant
l studies
ns a general conclusion it is important to recognize
that the circumstances under which the two (riine and Power Plant)
xvere conducted has prevented a thorough economic
l optimization of the combined project. In this regard, it seems
clear at the conclusion of the study work that the optimum size
of the mine recoverable reserves should be of the order of 145
i
i Annual Net Energy Generated - 61.9 x 10
11,000
12
5627 GKh
i factors are:
Equivalent Net Heat Rate
i Capacity Factor
ff
t-
100
Hours/Year
at full Output
8760
Btu/kWh
10,800
Installed Capacitv
_____MW,-
710
-B iiiii
i 77
60
50
6750
5250
4380
11,000
11,100
11,750
900
1120
1300
i 39 3420 12,300
The actual life-time capacity factor for a
1600
i lower incremental fuel costs than any other thermal plant within
Ontario, and would, therefore, be dispatched in preference to
them, and thus operate at a higher capacity factor. The plant
i
Ueport 5366-a-73
Page 3-3
NORTHERN ONTARIO
EXISTING 60Hz LINES
500KV
230KV ft LOWER
20 40 60
SCALE OF MILES
l
l Report 5366-tl-73
Pare 3-5
l
l Po'-.'er from these slants, a total of! sone 550
T, is collected 'r* 230 kV lines to a au):station at Pinard.
l
v itarir yy'-dro supplier; the following guidelines on transmission
line caoQcitv: ov.'cr to the Hanger substation in the Sudbury
-'rea -/.-hore the r^ain transmission qrid is joined. The addition of
-. -lajor oower -)lant at onakawana v.'ill require construction of
l
..o. of '.iQO kV Circuit? Total Line Capacity Available for Onakawana*
(figures are in net Ml: at n inard sub-station).
l 1 (existing)
2 (1 additional)
')
(1 additional)
850
1150
1U50
(maxiuuri)
(preferred)
(iraximum)
300
600
900
l
j^
t
* Capacity available for Onakawana is total
line capacity less existing hydro plant capacity using this line,
i.o., 550 'r .'.
t
capacity which uses the available transmission potential to the
fullest. The existing single-circuit line does have surplus
load-carrying potential. This is partly fortuitous, and in part
1
due to the fact that present Ontario Hydro planning envisages a
substantial increase in the future to the installed capacity of
the "atagani ^iver hydro plants. This extra capacity, of the
order of 300 -IK, must also use the 500 kV line and provision for
l
considerable nunber of factors. One significant consideration is
the reliabilit" of supply maintained during an outage of one of
the 500 kV circuits. The maximum line loading under emergency
l
conditions of a single-circuit is about 1100 MW. In the case
.'here two circuits were carrying a total of 1150 MW, if one of
the circuits were to trip out, it would be necessary immediately
and automatically to shed some 350 MW of generation at the
t
existing hydro plants.
3.1.3 Cooling Water Supply
l
l
l r'.eport 5366-4-73
Page 3-6
l
l pond on the Onakawana River. Both alternatives have fairly
definite economic limits to their cooling potential.
t 3.1.4 Conclusion
A review of the three prime factors leads to
t reserves
fully utilizes one additional 500 kV
l transmission circuit
can be cooled at reasonable cost by either
cooling water supply alternative considered.
l
Report 5306-4-73
Paao 3-7
l Paqo 3-8
l Pio
Mineral 7\nalvsis
37.46
l A.I 0
2 3
2
17.95
t J1 'e O
r:'iO
2 3
9.32
0.97
l ^
2 5
CaO
0
2
0.43
17.65
l f'.aO
P6
3
4.40
14.51
l i'iSL
K 0
2
O 1.53
1.07
l fusibility
2
Reducing (decj.F) Oxidizing (deg^.F)
t al Deformation Tenp.
ninq Tarr.perature
Temperature
2075
2175
2280
2145
2255
2360
l Relative characteristics
lignite are contrasted with those of lignites from various
of the world, in the following figures.
of the Onakawana
parts
t
l
l
FIGURE l
REPORT 5366-H-73
PAGE 3-6
l UJ
tO W 60 70
VOLATILE MATTER VM
ONAKAWANA LIGNITE
CLASSIFICATION OF
VARIOUS SOLID FUELS
MOISTURE CONTENT OF RAW-COAL
tst
i *"
i
s
O*
l
l In Europe and Australia, where many lignites
are of even noorer quality than Onakawana lignite, other
corobustion methods have been used with a high degree of success.
l proven performance, )
)
)
These two
items were
considered
l reliability,
)
)
the most
important
l flexibility of operation,
availability in suitable size,
l Canadian manufacture,
operational costs,
l
l
Report 5366-U-73
Page 3-13
boiler efficiency,
capital costs.
3.2.5 Boiler Proposals
The designs offered followed two different
approaches, the North American approach and the European
approach. The nain design parameters and layout drawings are
given in Appendix A. The basic comparison of the approaches is
shown below.
BASIC BOILER DESIGN
l level.
The boiler is equipped with eight Raymond
bowl-tyoa pulverizing mills, each supplying four burners on one
Corner firing is used. Eight levels of burners are
supplied. Exhauster fans withdraw the lignite/air mixture from
l '-..n'-.en via six seoarate refractor^' lined ducts to the mill inlets.
l
l
l 'Mn o
5366-4-73
3-15
l "-H.litir-' rxi^t ^or teroeratinn this ras with cold air. 'i'he
l li' nite ir. f od into the hot gas ducts prior to the rill inlets
n corijmsnces to dry out at this point. By the time the lignite
.an reached the nil l inlet, temperatures are in the order of 500
l decrees? r or so. The hanmer mills are very robust and repairs
p.nd inspection are facilitated by large access doors.
consumption is relatively low.
Power
New hammers are required
approximately every 2,000-3,000 hours, and replacement consists
l of welclina in carbon steel replacement pieces. Fuel line
temperature to the burners was given as 218-284 degrees F by one
supplier and 265-355 degrees F by another.
l groups of burners.
three levels.
Each burner group is supplied with air at
l the reheater and the economizer in the rear (downward) gas pass).
The European designs have been developed
l
l
l Report 5366-4-73
Page 3-16
l particular des inn also incorporates a wet pit bottom ar.h hopper
l ami separate airheaters for urimary and secondary air - these
features are less desirable than other alternatives.
l budget price for the European designs, In fact the price quoted
for the North American design was about the same as prices quoted
recently for bituninous coal fired boilers. A lignite boiler
should be ^ore expensive due to the low calorific value and
l the other.
Bottom ash is collected by twin Rotograte
stokers in one design and by a submerged drag-link conveyor in
The Rotogrates were included to allow for the burn-
off of combustibles. The other supplier of a European design
l It
The three designs were carefully examined in
relation to the background of experience of each manufacturer.
is clear that the only place where proven successful
combustion of lignite of the required quality exists is in
l Europe. In particular. German nanufacturers lead the field
l
l
l Paqe
53G6-U-73
3-17
l reasons:
(a) The North American designed boiler budget
price is considered unrealistically low.
l (b) The European design is based on proven
operation on similar fuels and similar size
l (c)
units.
The European design is considerably more
l (d)
efficient.
The Worth Aiaericaning furnace is small, and
the gas exit temperatures are considered too
l (e)
adverse!" affected.
The North American boiler uses hot air to dry
and transport the lignite. This does not
l allow maximum use of secondary air in the
form of intermediate, overfire or underfire
air - an essential . "actor in reducing burner
l profile;
l
l
l i'ncre
!J366-U-73
3-1 Q
l
l less wear due. to retardation of fly ash;
easier removal of deposits by soot-
l blowing.
However, vrith a noderate ash percentage and
good furnace and burner design, these
l (c)
two-pass design.
The "tower" design aopears to offer no price
advantage over tne two-pass design.
l (d) The two-pass design was considered superior
in the design of the air supply, choice of
l designed boiler.
The capital cost of the selected boiler is
hiah compared with the price quoted for the North American
The fuol savings, however, with the more
efficient European design chosen counter balance this to some
l Price Quoted
Difference
949.5 Million
$35.5 Million
l Rate Penalty
let Additional cost
$13.0 Million
l 935.5 M - $13,0 M
" 922,500,000
l
l
l Report 5366-1-73
Page 3-19
l
l reliability,
In summarizing, the boiler selected is the
one considered most likely to give good performance and high
based on actual operating experience. German
statistics quoted below* indicate, in fact, that the availability
l of lignite-fired boilers in West Germany is higher than that of
bituminous coal-fired boilers.
l Bituminous
Coal
Lignite
_____
Oil/Natural Gas
^——-——————.
l Boiler Availability
*Source
95 - 96)5 96 - 98X 97 - 100X
- West German statistics for 18 power units of 300 - UOO
MV7 capacity, year ending March 31, 1972.
l on lignite are in the 250 and 350 MW range, although units of 600
:"V7 are under construction in West Germany and two units of 450 MW
are under construction in the United States. Although there is
l
l
l Report 5366-4-73
l Paqe 3-20
l The principal
suitable power plant site are:
factors influencing the selection of a
l Hence a site on the west bank of the river was preferred and a
site visit v/as made at the end of September 1972 with this
objective; the report on this site visit is included in Appendix
Access to relatively deep water in the river channel was the
l main criterion, and on this basis, two potential sites were
identified. The site visit report refers to these as sites 1 and
3, subsequently re-named as South and North Abitibi sites
l Section 4.4, the main difference between the Pond and Abitibi
sites is their respective relationship to the mine and its
operations. The Mining Study Report includes a list of the
comparative features of the Pond and North Sites on Page 67. The
l rine haul road pattern adopted). The Pond Site however being
located on the same side of the railv/ay as 958 of the lignite
reserves needs only a temporary crossing (probably at grade) to
provide access to that portion of the East Field east of the
l railway.
3.3.3 Summary
l
l
l Report 5366- H- 73
Page 3-22
l
l The coolinn nond has been located at a convenient point
on the Onakawana niver and the power plant is located at its
northeast corner. The cooling water intake and discharge have
been positioned to minimize the length of cooling water piping,
l ' ut at the sate tii^e the use of a discharge canal gives the
facility cf separation of the discharge from the intake, thus
minimizing recirculation. By the use of single pass condensers,
l i.~, sho'/n to the east of the site. This consists of a large dyked
ares which "ill be utilized for any effluents from the plant
hich can not bo disposed of via normal drainage processes, due*
l
l
l Report 5366-ft-73
Page 3-23
l
l ' system of site roads is shown connecting all
i'Vortant operating areas and the construction and permanent camp
l -)
b)
operating reliability and flexibility;
manufacturer's standard designs for units of the
l c)
selected size;
two-shifting capability, even when considering the
base load design;
l d)
operation during the ensuing two months."
economic assessment relating capital cost and
l e)
efficiency;
requirement to minimize staffing,
l
l
l
l Report 53(i6-4-73
Page 3-24
l
l and
2,400 p.s.i.g./1 ,000 deg.F/1,000 deg. F Reheat
1,800 p.s.i.g./1,O00 deg.F/1,000 deg. F Reheat
l less than this figure, and the higher pressure can be justified
on this basis alone.
l was noted that there has been considerable trouble with some of
the 500 "lw unit turbines in the UK, but manufacturers pointed out
that this was mainly due to the very fine turbine blade
clearances used for the purpose of achieving maximum efficiency.
l (A CEGB policy occasioned by high fuel costs.)
The 2,400 p.s.i. cycle is more of a manufacturer's
l standard for this unit size and has the advantage, therefore, of
allowing major components to be relatively "off the shelf. More
data is available on the higher pressure cycle, due to it being
l more standard.
l
l
l Report 5366-4-73
Page 3-23
l
l There is also some advantage from the operational
"know-how" angle since all the latest Ontario Hydro plants are
designed for the 2,400 p.s.i, cycle.
l After considering all these factors, the 2,400
p.s.i./1,000 deg.F/1,000 deg. F reheat cycle was selected as a
l capacity factors.
3.6 Schedule and Cost Assumptions
l (b)
with subsequent units following at 6 monthly
intervals.
The planned operating life for the mine and power
l plant for economic calculations would be 30 years,
beginning in 1979.
l
l
Report 5 36 6- U- 73
Paqe 3-26
l
l services reauirecl nt the permanent
communities would be excluded.
residence
l
l
l
l
l
l
l
l
l
l
l
l
l Report 5366-U-73
l
l 4________PLAN? SYSTEMS DESIGN
l tempering the hot gas with cold air. About 2/3 of the way down
the gas duct, the lignite is fed into the hot gas stream, thus
allowing some of the moisture to crack off. The removal of the
moisture from the lignite lowers the temperature of the
l transporting gas, and at the inlet to the hammer compartment of
the mills the temperature is reduced to approximately 500 degrees
r. TO prevent overheating of the mill in the event of a fuel
l
l
l Report 5366-4-73
Page 4-2
l
l with large, easily removable inspection doors, for the purpose of
inspection and maintenance. These mills have a low power
consumption and a moderate noise level. Maximum coal size
required at the inlet is 4". Mill power consumption is estimated
l
l
l Report 5366-4-73
Page 4-3
l
l Bottom ash is collected by a water submerged drag-link
conveyor. Bottom ash is not expected to exceed 8?6 of total ash.
All superheater, reheater and economizer surfaces are equipped
I with steam operated soot blowers. Forced draft and induced draft
fans are not included in the boiler supply, but axial flow fans
have been selected for these duties and have operating
l characteristics as follows:
Forced(Draft) Induced
3,040
320
3,620
l to 15"fc MCR. Auxiliary fuel is No. 2 oil and burners are provided
sufficient for 30 to 3596 of total boiler heat input.
l
l
l
l
l I'oport 53G6-4-73
"ane H-i\
l
l Iloat lorsra in dry '"lue gas 5.3
l
Radiation 0.25
Unaccounted and manufacturer's margin 1.25
l Efficiency 77.6
l
\rection to boil-out/aoid clean
tir^e between units
l
'uring the final ^reparation of this Report,
information v/as received indicating that the pulverizing mill
-otor horr.eoower and the dust loading at precipitator inlet may
l
both be greater than the fiqures oreviously given and used as a
tarsia for this Report. However, as these parameters will vary
';ith the iranufacturer, it was not considered necessary to adjust
l
results at the study stage.
l
l
l
l
l
l
l Report 53G6-U-73
Paae 1-5
l
l ".2 Turbo-Generators
Quotations received from different turbo-generator
l months of June, July and August, during the greater part of the
year the vacuum will be better than the design condition with a
consequent improvement in heat rate for the plant.
l
l
1
1 0 Report 5366-4-73
Page 4-6
1 iUl
conpound machines.
Turbo-Generator manufacturers offered
Particulars are shown in the following table:
tandem
1
TURBO GENERATORS - TECHNICAL DETAILS
1
Supplier I II III IV
1 1. Gross generator out- 340,000 340,000 340,000 340,000
put (kW)
1 2. Generator voltage (kV) 18 19 22 22
3. Power factor 0.85 0.9 0.9 0.9
1 4. Steain pressure at MEV 2115 2415 2400 2415
(FSIA)
1 5. Jesign Condenser back 1.5" 1.5" 1.5" 1.8"
pressure (inch Hq
1 Abs )
fi. Type of B. F. P. in- Electric Steam Electric Steam
eluded in heat ba
1 lance
7. Main steam flow (PPH) 2,191,839 2,253,440 NA 2,284,305
1 at 1000 deg.F
3. Reheat steam flow PPH 1,973,822 2,005,294 NA. 2,036,701
1 at 1000 deg.F
9. Reheat steam pressure 545 528 NA 541
FSIA
1 10. Number of f .w. Heater s
Low pressure 4 4 4 4
1 High pressure 2 2 2 2
1
1
l
l Page
5366-4-73
4-7
l
l 13.Heat rate (1.5 Ins.
Hg Cond. Pressure)
7594 7632 7735 7913
l 15.Machine dimension
length
119*0" 105*0" 91 110*0'
l
l
l
l
l
l
l
l
l
l
l
l
l Report 5366-4-73
Page 4-8
l
l Information was relayed to all manufacturers to submit
revised figures for a 2" Hg absolute back pressure when a
decision was taken to use a cooling pond for cooling water.
l SUPPLIER I
1. The worsening of the vacuum form 1.5" to 2" will
give a Q.7% worse heat rate.
l SUPPLIER III
1. If constant output is maintained in going from
1.5" Hg absolute to 2.0" Hg absolute, the throttle
l
l
l
l
l
l
l
l Report 5366-4-73
Page 4-9
l algae build-up.
l
l
l Report 5366-4-73
Page 4-10
l
l Admiralty brass tubes are 39'O" long, l" in diameter and of 18
gauge construction. The cooling water temperature through the
condenser is designed for a rise of 15 degrees F. Heat rejected
l 196,000 US gpm per unit for full unit load. The design cooling
water velocity has been taken as 7 ft./sec. and a cleanliness
factor of 85%. Design back pressure is 2.0" Hg.
l 2)
3)
Less cooling water piping and fittings.
Less excavation.
l 4)
5)
Less pumping head and pumping costs.
Less overall capital cost.
l are pumped to the deaerating heater from the No. 6 high pressure
heater. Drains from the low pressure heaters are cascaded to the
next lowest heater and finally to the condenser. By-pass lines
and control valves are provided in the heater drain lines which
l
l
l Report 5366-4-73
Page 4-11
l
l is provided from the demineralized water-storage tank.
Demineralized water can be fed to each condenser hotwell at a
rate of 150 US gpm to make up for boiler blowdown and
miscellaneous losses.
l Low pressure feed-water heater tubes are
stainless steel construction. High pressure feed-water heater
l is included.
A condensate polishing unit of 2596 capacity
l Drawing 8.
A simplified steam flow diagram is shown in
l 3.
4.
Turbine shaft mounted pump.
Variable speed electric motor driven pumps of
l 5096 nominal capacity.
The evaluation should consider the following
l factors;
(a) Capital Cost.
l
l
l Ueport 5366-'l-73
Paqe a-12
l
l (c)
(d)
Flexibility in Operation.
Reliability.
l (e)
(f)
Operating Cost.
Maintenance.
l chemical feeds,
The plant includes a clarifier, filters,
clearwell pumping station, two-bed
denineralization train followed by mixed beds. Equipment and
l controls furnished allow semi-automatic operation of the water
treatment plant from a local control panel.
l
l
l Report 5366-4-73
Page a-13
l
l river-water pumphouse is installed on the Abitibi River with one
pump initially, to supply water for fire protection requirements.
This pumphouse will ultimately have four pumps to supply the
l cooling pond.
4.3.7 Fire Protection System
l
l
l
l Report 5366-1-73
Page 4-1
l
l Protection of unit auxiliary and main power
transformers is by means of a dry type deluge sytem. Deluge
valves located inside the building are electrically operated.
l 4.3.8 Plant General Arrangement
l and 5.
The arrangement of major equipment and
auxiliaries selected for the power plant is shown in Drawings H
The turbo-generators are arranged in line along the
l The boiler
vidth and 250*0" in height.
house is 516* in length, 180* in
l
l
l Report 5366-U-73
Page H-15
l
l 4.3.9 Auxiliary Bay
On the grade floor of the auxiliary bay the
l boiler feed pumps, condensate polishing units, bearing cooling
v;ater heat exchangers and pumps, battery room, etc., are
accomodated.
i
l
l Report 5366-4-73
Page 4-16
l
l t*.3.11 Air-Conditioning, Heating, Ventilation, and
Combustion Make-Up Air Units^.^^.^..^^^.^
l
l
l uoport 5306-1-73
Paqe 1-17
l
l feasibility study of a thermal power plant, and a considerable
portion of the overall study effort was devoted to this problem.
The increasing public awareness of the potentially harmful
l h) Closed-Circuit Cooling
with this approach the cooling water flows in
r. closed cycle. Leaving the plant condensers at an elevated
l temperature, it then passes through an artificial cooling medium
(cooling pond or towers) which lowers the temperature before the
water is returned to the plant. Ultimate heat dispersal is to
l
l
l Report 5366- H- 73
Page 4-18
l
l modifications and combinations of the two general approaches
used.
are
l
l
l
l Report 5366-4-73
l Page 4-19
l rhich is governed by the total heat rejected by the plant and the
river flow.
l
l
l
l
l Report 5366-1-73
Page 4-20
l
l assumed Total River Flow 2000 4000 6000 10000
l 10 dag. F
15 clog. F
iTA
HA
49
32.5
32.5
22
19.5
13
l 20 deq. P 49 2l\ 16 10
l (1)
(2)
At full plant output .
Remaining flow remains for mixing at the discharge
l
l
l Report 5366-1-73
Page 4-21
l
l This means that under minimum flow conditions
approximately 1/3 of the river flow would be extracted as cooling
water, the remaining 2/3 acting to mix with the discharge water.
l alternative.
b) Storage Pond at Onakavjana - a control
\an located immediately downstream of the proposed Onakawana
t plant site would create a storage pond which would regulate river
'Discharges and could also act as a "heat sink" or cooling pond in
the area of the cooling water intake and outfall. However, flow
l
l
l Report 5366-4-73
Page 4-22
l apart from the minor river valleys of the Onakawana River and
Medicine Creek. A cooling pond location adjacent to the mine
area was desirable and the Onakawana River Valley upstream of the
mine area is suitable. This stream is a tributary of the Abitibi
t River and flows parallel to the main river through its lower
reaches. It also traverses the eastern margin of the lignite
deposit and would thus be diverted into the Abitibi River in
l
l
l Report 5366-4-73
Page 4-23
l
l cooling pond.
No. 2.
The general area of the pond is shown in Drawing
l pond was evaluated by considering the fuel cost savings which are
realized when a larger pond (with lower cooling water
temperatures) is used. The relatively adverse topographical and
l F and a cooling water flow of 1300 cfs (as for the once-through
cooling system).
l
l
l Report 5366-4-73
t Page 4-24
l - subtract -
value of Otter Rapids alterations
$120,000
l through cooling:
Expressed as a present worth cost
f 31,000
l
l
l Report 53G6-4-73
Pace 4-25
l
l Hence the total economic penalty for the
adoption of a cooling pond is of the order of $8,050,000.
l (a)
{b)
Handling characteristics of the lignite,
Delivery schedule and rate from the mine.
l (c)
(d)
Shift cycle adopted for plant fuelling staff.
Climatic conditions.
l The required production rates, stockpile
handlincj method reflect consideration of these items.
sizes and
l ^onthly at 100?i CF
Rally at 100^ CF
770 x 10
25,300
3
860 x 10
28,300
3
N/A
33,000
l
l
l Report 5366-4-73
Page 4-26
l
l 3) i'or base load operation at 775 cpaapcity factor, this gives,
a net annual energy production of 6,330 GWh and an annual
fuel heat requirement of 69,600 billion Btu.
l
l
l Report 5366-H-73
Pnqe 1-27
l
l (case 1) has a basic output of some 750 tons/hour - a total of
2,250 tons/hour. In order to accomodate delivery surges, in
addition to the receiving hopper capacity, a stocking out rate of
l cost through the use of smaller bunkers and a lower reclaim rate.
Design parameter include:
l Bunker Capacity:
6 at 150 tons per boiler - 8,100 tons
total
l Equivalent Pover
Full Output:
Plant Operating Times at
l nine and power plant, and the fact that lignite delivery from the
vnine will be on a year-round basis, a very large annual plant
stockpile is not considered necessary. The mine development plan
calls for the maintenance of an in-mine reserve of stripped coal
l ready for loading of approximately 750,000 tonsf i.e., one to two
months plant consumption. This reserve is planned to cover a
major breakdown to the stripping draglines. Ample spare lignite
l loading and hauling capacity has been allowed for in the mine,
and apart from temporary short-term interruptions, lignite
l
l
l Report 53G6-4-73
l Page 4-28
l to 100J? output for some months during the winter and at lesser
output during the summer. It is conceivable that the annual
naintenance shutdown at the power plant could be planned to
l Brief consideration
following alternative systems:
(a) Underground reclaim
was
tunnels
given to the
v'ith a surface
l ('.)
stacker or trestle.
Bucket vheel stacker-reclaimer.
l was ruled out primarily because of its high capital cost, need
for top-grade operation and maintenance under the
operating conditions likely at Onakawana, and the inherent
arduous
l
l
l Report 5366-4-73
l Page U-29
l
l
l Report 5366-H-73
l Page 4-30
l scavenging out all rock over 4". This reduces the ash content of
the lignite and protects the conveyors, pulverizers, etc.-, from
damage. The average maintenance cost of this equipment is very
l 48" conveyors, from the reclaim tunnels, and the main conveyor
by-passing the stacker, are protected by suspended magnets.
The station bunker feed system is made up of
l a 48" main belt with four transfer points and three fixed
trippers. The fixed trippers and the end of the belt feed onto
48" conveyors with travelling trippers which supply the 18
l collectors which discharge the dust back into the bunkers. The
four transfer points on the main bunker feed conveyors are vented
into the bunkers to prevent dusting in the main lignite gallery.
l (b)
(c)
Lignite consumption - 1,180 tons/hour.
Ash percentage - 14J! as fired.
l (d) Bottom ash - 10J5 of total ash produced.
l
l
l Report 5366-1-73
l Page a-31
l Btu/lb.
Item (c) above is based on the highest ash
l
l
l Report 5366-4-73
Page 4-32
l
l This length of pipe would also entail the use
stages of pumpinq.
of at least two
l Other factors
pipeline disposal for ash are:
militating against the use of
l (d)
(e)
High
ash.
friction
"Visual"
factor with this type of
l water and which houses the initial (horizontal) part of the drag
link conveyor. The ash is taken automatically from the trough by
the continually moving drag link conveyor in the bottom of the
hopper. It elevates the ash up a slope to a discharge point
l outside the building, dewatering the ash in the process. The
three drag link conveyors (1 per boiler) deposit the ash on to a
36" rubber belt, which delivers all ash from the three boilers to
l two 200-ton truck hoppers. The truck hoppers provide storage for
approximately one day's output of bottom ash for the plant.
l
l
l Ueport 53o6-4-73
l Page 1-33
l discharge.
Three sets of dust collectors per system are
provided to ensure removal of all dust from the vacuum pump
A vacuum system was selected as it eliminates the
inherent dusting from piping used in a pressure system. Its
l
l
l Report 5366-li-73
Page U-34
l
l cost, both in purchase and operation, is lower than that of a
pressurized system, the alternative system which could be
l provided. Two fly ash silos are provided with a total capacity
of approximately 1 day's fly ash production. Because of the
normal ease of loading fly ash, one day's capacity is considered
sufficient to provide for efficient operation of the haulage
l truck.
4.6.6 Ash Disposal and Haulage
l 4.7.1 General
The following table shows the principal
corbustion products and their effect on environmental quality:
l
l
l
l
l
l
l
l Report 5366-4-73
l Page a-35
l Product Effect
l Gaseous:
Sulphur Dixoide SO t Above certain concen
l Nitrogen Oxide NO
2
trations, potentially
harmful effects on all
life forms.
l Particulate Katter
(dust or fly ash)
)
)
Visual as a "dirty" stack
plume, and physical on
ground contact.
l Treatment of
classified under three headings:
combustion products can be
l 1.
2.
Minimizing, by careful
combustion techniques.
Removal, by physical or chemical means,
control of
l electrostatic
example.
precipitators are .an
l 3. Dispersal, to
concentrations -
design.
avoide harmful
by appropriate
local
stack
l All three
application at Onakawana.
of these techniques have some
l
l
l
l Report 5366-4-73
l Page a-36
l
l
l Report 5366-4-73
Page 4-37
l
l breaks down readily to form N02. Research has shown that N02
will undergo reactions with a number of organic compounds in the
presence of sunlight, resulting in the effect of photochemical
l (b)
in a lower peak flame temperature.
Lowering the temperature of the
l (c)
combustion air.
The use of two-stage combustion. In
this process the amount of air
l introduced into the primary combustion
zone with the fuel is reduced to below
the theoretical value. Following this,
l lowering of the
combustion-gas
furnace.
peak and
temperatures
average
in the
l this and has been applied in the Onakawana boiler design to give
acceptable MOx figures.
l
l
Report 5366-4-73
Page H-38
l
l 1.7.4 Particle Emission and Electrostatic Precipitators
It is estimated that the dust concentration
l in the boiler flue gases from the Onakawana plant would be in the
neighbourhood, of 6.6 grains/cu.ft. at the air preheater outlet.
The Air Pollution Control Act, 1967, refers only to ground level
concentrations and these are not easily co-related to stack gas
l dust concentration. However, the standard used by Ontario Hydro
is a figure of 0.02 grains/cu.ft. at dust arrestor outlet,
corresponding to a dust arrestor (electrostatic precipitator)
l efficiency of 99.755. This standard is also designed to ensure
"no visible stack plume" in as far as plume discolouration is
concerned.
l Because of its low sulphur and sodium
content, the Onakawana dust is expected to have high electrical
resistivity making it difficult to collect. However, experience
l with similar fuels has shown that good efficiencies can be
achieved if the electrostatic precipitator is designed with extra
large collecting surfaces and low particle migration velocities.
l It is not possible to predict accurately the sizing of the dust
collector without establishing the resistivity of the dust by
burning and testing the fuel under conditions as close as
possible to actual operation. It is therefore recommended that
l before any engineering design commenced, a test should be,
conducted on an existing boiler of similar size range with a full
size precipitator on line. This test would establish the
l parameters for proper selection of the Onakawana electrostatic
precipitators. It would also determine if SO3 conditioning is
required, or if consideration should be given to locating the
l precipitator on the hot side of the preheaters. At this stage
the precipitator has been located after the air preheaters - the
normal procedure.
i
l In the absence of reliable dust resistivity
tests, in sizing the precipitators, the highest ash resistivity
at which electrostatic precipitators can collect consistently has
l been assumed. To obtain a collection efficiency of 99.7JS, two
precipitators are provided per boiler, each with 4 chambers, 6
fields, 9'x30* collecting curtains, and 25 gas passages at 9"
l spacing. This design is expected to reduce the stack emissions
to 0.02 gr. per cu. ft.
U.7.5 Stack Emissions and Design
l On the basis of the proposed combustion
techniques and electrostatic precipitator design, stack emissions
l with the oower plant at full output are estimated as follows:
l
l
l Report 5366-a-73
Page U-39
l
l Compound
Concentration
____(ppm)
Mass Flow
(Tons/Day)
l C02
H20
02
132,000
188,000
28,900
20,000
11,600
3,150
l H2
S02
S02
NOx
650,000
780
200
62,500
173
31
l CO
Particulate
50
0.02(gr./cu.ft.)
5
8
l conditions.
Stack height has been selected at 500 ft.
l
l
l
l
l
l Report 5366-4-73
l Page 4-40
l Height
Number of Flues
500 ft.
3
l Efflux Velocity
Internal dia. of Outer Shell
External dia. of Outer Shell
80 ft./sec.
28 ft.(top),
30 ft.(bottom)
30 ft.(top),
l fibreglass and protrude approx. 12-15 ft. above the top of the
concrete shell tp give the optimum aerodynamic effect on the
plume.
l 4.8 Switchyard
The single-line diagram for the Onakawana switchyard is
l 138 kV. The 500 kV ring bus accommodates the three incoming
generating units and provides for two line circuits to the Pinard
Station; 500 kV air blast circuit breakers are assumed used. The
l 138 kV rinq bus accommodates the incoming line from Otter Rapids,
•i circuit to the f line, and supply to the reserve station service
transformer; 138 kV bulk oil circuit breakers are assumed used,
l
l
l Report 5366-4-73
l Paoe 4-'
l from Pinard via a microwave link. The cost of a 300 ft. self-
supporting
estimate.
microwave tower has been included in the cost
l
l (c) compared with the provision of synchronizing
breakers at 500 kV, the breakers at machine
voltage provide faster clearance of faults
i provided to:
1. Unit auxiliary transformer, 20-4.16/4.16 kV, 40
i 2.
MVA, water cooled.
Metal-enclosed switchgear containing surge
protection, potential transformers for metering
i 3.
and control, etc.
Rectifier transformer for excitation system.
i off-load taps and are water cooled. They are rated at 375 MVA
for a temperature rise of 65 deg. C. A spare main unit
transformer is provided.
i
l
l .Report 5366-4-73
Page 4-43
l
l The station auxiliary load is high by virtue of the
type of fuel being burnt and the physical size of the boilers.
The unit auxiliary transformers are correspondingly large, being
l secondaries.
No auxiliary generation has been allowed for "black
start". Instead, as mentioned in Section 4.8, the 138 kV line
l Controls for fuel and ash handling are housed in a single special
section.
l generators.
Automatic run-up equipment is provided for the turbo
l
l
l Report 5366-1-73
Page 4-44
l
l A computer-type scanning, alarming, and data logging
systerc is provided as an operating aid. This incorporates analog
and digital inputs, and is provided with tele-typewriters and
i r.amples.
An enclosed test station is provided for the automatic
conditioning, monitoring, and recording of boiler water and steam
Samples are monitored for conductivity, pH and
i
i
i
i
i
l
i
i
t
l
i
l
l Report 5306-a-73
Pnqe 4-tl
l
l 4.11 Civil Works
l profile:
3' to 4' of muskeg material on the surface
l 5 1 to
clay)
15' (averaging less than 10') of marine
l
t 4.12 Plant Modifications for 2-Shift Design
l
l
l Report 5366-4-73
l
l Care has to bo exercised in the selection of condenser
tubo materials, to avoid tube erosion at low cooling water
l superheat and reheat control ranges are increased. For the base
load unit, full superheat-reheat temnerature is available down to
7O-75f, full load. To extend this range downwards, for a 2-shift
l
l
l Report 5366-4-73
Page t- HB
l
l Summing up, the modifications required are few and
relatively inexpensive compared with the over-all plant cost.
They includes
l (a) Attention to turbine design and blading clearances
l (b)
(c)
Possible nozzle control on turbine inlet
Larger superheater and reheater surfaces and
l (d)
increased attemperation
Possible speed control on boiler fan motors
l (e)
(f)
Possible alternative pulverizer gas tap-off point
Control dampers on stack flues
l
l
l
l
l
l
l
l
l
l
l
l Report 5366-4-73
l
l 5________SUPPLEMENTARY STUDIES
5* ^ Construction Plan
l contractor.
5.1.1 Transportation Access
l earlier include
The temporary site .facilities referred to
camp-site accommodation, supply of electric
l
l
l Report 5366-4-73
Page 5-2
l
l power, water supply, sewerage treatment, preparation of
construction storage and working areas, and the airstrip. During
construction these will be shared by the power plant and the mine
l and used by all contractors working on-site.
The major proportion of the construction
l
l
l Report 5366-4-73
l Page 5-3
l
l
l
l
l Report 5366-4-73
Page 5-4
l
l A list of the key schedule dates assumed for
the purpose of the study and incorporated in the construction
schedule is:
l Start Engineering February 1974
l Decision to proceed
Issue first tender documents (turbines)
June 1974
September 1974
l Otter Rapids
Award boiler supply contract
July 1975
August 1975
l (Units l and 2)
Close in building (Units l and 2) and
April 1977
October 1978
l Start boil-out and testing boiler
(Unit 1) April 1979
l
l
l
l
l Report 5366-4-73
l Page 5-5
l
l
l
l
l
l
l
l
l
l Report 5366-4-73
Page 5-6
l
l 5-2 Plant Operation
The plan proposed for operation of the power plant and
l the mine was developed to provide adequately attractive working
conditions for the project work force, and to encourage the
employment of people resident in the region. In line with this
l b)
required on the majority of duties.
Maintenance - can be covered by day work
(with overtime as required for contingent
l maintenance), or shift work or a combination
of the two.
l one day.
Probably the most important factor governing
l staffing
A practical solution to the operation
requirement would be to staff the plant for all
l
l
l Report 5366-4-73
l Paae 5-7
l labour
5.2.2 Labour Requirements
The
requirements
following table lists the estimated
for administration, operation, and
l maintenance of the power plant when operated at base load, 77
percent annual capacity factor - unit figures refer to total
plant staff after each unit is on-powerj
l
l
l
l Report 5366-4-73
Page 5-8
l
l At Supervision A Engineering
l Unit 2 Units 3 Units
l Station Manager
Assistant Manager
1
1
1
1
1
1
l Operation Engineer
Maintenance Engineer
Chemist-Engineer
Station Administrator
1
0*
1
1
1
1
1
1
1
l Subtotal
1
5
1
6
1
6
l 3. Operation Staff
Shift Supervisor 5 5 5
l Senior Operator
Unit Assistant (TG)
Unit Assistant (Boiler)
Plant Attendant
5
5
5
10
10
10
10
15
15
15
15
l Lignite Plant Supervisor
Mobile Equipment Operator
Lignite Plant Attendant
5
5
5
10
5
5
10
5
5
10
l Chemical Technician
Subtotal
5
50
5
70
5
90
l C. Clerical Staff
Stenographer - Typist 1 2 2
l Pay Clerk
Stores Clerk
Store Keeper (shift) 5
1
1
1
1
5
1
1
5
l Subtotal 8 9 9
l Maintenance Staff
Mechanical Maintenance Foreman
Mechanics
5
10
5
15
5
20
l Helpers
Electrical 6 Instrument Foreman
Mechanics (electrical)
5
5
5
10
5
10
15
15
5
l Helpers
Mechanics (instruments)
Helpers
Janitors/Labourers
5
5
5
5
5
5
5
5
10
10
5
5
l Subtotal 50 70 95
l
l
l Report 5366-4-73
Page 5-9
l
l E. Ash Disposal* 5 8 10
l 39?; annual capacity factor, the only changes to this staff list
are a reduction in the lignite handling plant and ash disposal
staff, the revised total for all three units being 200 men.
l policy,
automation
a trend
of
towards
plant
maximum
operation was
assumed, and the staff list for the
l
l
l Report 5366-4-73
Page 5-10
l
l (e) Maintenance is organized on a shift
basis and reflects the assumption that
major maintenance tasks would be handled
l by bringing in outside labour on an "as
required" basis.
l olant, labour requirements for the mine total about 340 and 250
men for Cases l and 2, respectively.
Additional labour is required at Onakawana to
l operate the camp site and catering facilities provided during the
operating life of the project. The total demand on these
services depends on the proportion of the total labour which
l
l
l
l
l
l Report 5366-4-73
Page 5-11
l
l Case l Case 2
(base load plant) (two-shift plant
l Power Plant
:line*
Camp
210
340
50
200
250
40
l Power Ash
Plant Disposal Mine Camp Total
l Management (supervisory,
engineering St office staff) 25 - 50 5 80
l Maintenance (mechanics,
welders, electricians,etc)
lobile equipment operators
40
5
5
5
80
130 -
125
140
l General labour (pumpmen,
cleaners,cooks,storemen,etc) 10 - 80 45 135
l Onakawana Report.
The availability of local labour in the
Cochrane District is discussed in some detail in the Task Force
The tentative conclusions reached include an
opinion that the whole of the required labour force might be
l drawn from Northeastern Ontario. The Report also notes that up
to 300 workers with vthe kind of skills required are located in
the Moosonee general area, many of whom are presently unemployed.
l
l
l Report 5366-4-73
Page 5-12
l
l .skills available within the toosonee local labour force and
indicate that this source can supply workers for jobs up to the
level of skilled tradesmen (electricians, etc)* For work above
l this figure would be too low and upwards of half the total labour
force (600 in Case 1) might be drawn from the Moosonee area.
5.2.3 Rail Commuter Service
l As described above, a rail commuter service
operated by Ontario Northland was devised to meet the following
l conditions:
1. Offer the alternative to project workers of
l
l the rail cars required are not owned by
Ontario Northland and are not presently being
manufactured.
l rail cars would probably be usable only for
this specific service, whereas the
l levels.
The annual cost of operating this service was
estimated by Ontario Northland as $90Q,900 at present cost
It was assumed that this rail service would be supplied
free to the project labour force and as a result this annual cost
l is an operating charge to the project*
In conclusion, the rail commuter service
l
l
l
l
l
l
Report 5366-4-73
Page 5-15
l
l
l Report 5366-4-73
Page 5-16
l
l (d) Ash and Dust Handling System
A trucking disposal system has been adopted in
i
l
l Report 5366-'!-73
Pay e 3-1.7
l
l Therefore the immediate physical, as opposed to socio-economic,
effect of the project on man should be minimal.
l of the lignite burnt, but the mining plan and stockpile system
adopted should minimize these variations. A full-scale study
considering such factors as: stack design, plant building height
l
l
l Report 5366-4-73
Page 5-18
l
l conditions.
Water vapour,
form of fog, will also be present
from
under
the cooling pond in the
certain cold weather
l July (hottest)
(approximate only)
75 93 108
l
l
l Report 5366-4-73
Page 5-19
l
l should be of the order of 20 deg. F. above natural
ambient temperature, and in winter, a major
l In
River.
the case of the Aoitihi River once-through cooling
i
l
l Report 5366-4-73
Page 5-20
l
l ambient when the plant shuts down. A variable
operating pattern for the plant, as in the case of
two-shift operation for example, will produce
l b) Waste Effluents
The water quality of the rivers in the area will
be affected to some degree by the discharge of
l waste effluents from the plant and the mine.
Waste water from the mine comprises
drainage and pit water.
surface
The drainage plans
l described in the
comprehensive and
Mining Study Report
generally provide for the
are
collection of all surface run-off and water pumped
l
l
l Report 5366-4-73
Page 5-21
l
l miles of the Onakawana River. The downstream
reach of Medicine Creek and the upstream reach of
the Onakawana River will not be affected. The
l Task Force Onakawana Report expresses some concern
that restoration of the lower reach of
Onakawana River might be desirable after the
the
i fauna.
If a once-through cooling system on the Abitibi
River were adopted, additional river flow changes
i will be made to the Abitibi. Due to the proposed
alterations to Otter Rapids discharges, daily flow
variations (refer to Appendix Bl) in the Abitibi
i
l
l Report 5366-4-73
Page 5-22
l
l dine area exploited and subsequently
reclaimed - Case l - 6500 acres, Case 2
- 4500 acres.
i adopted:
i
l
l Report 5366-4-73
l Page 5-23
t choosing.
In line with the above, the Onakawana site
l place of residence.
Preference should be given for employment on
l report.
a) Employment Created and Population Increase
l 1):
Operation of the mine - 340
l
l
l
l Report 5366-4-73
Page 5-24
l
l Secondary employment created in local
established communities for services, Ontario
Northland etc., due to population increases
l etc:
300*
l * Based on an
Grand Total
overall
- 900
job multiplier of 1.5 as used in The
l Task Force Report.
The total population increase resulting from
l b) Economic Impact
The primary economic impact during the
operating life of the project is the
l disposable income received by the new work
force at the site in wages and salaries.
Based on 1973 assumed wage levels, this is
l
l
l Report 5366-4-73
l COSTS
l This section of the report describes the estimates
prepared for the capital and operating costs of the power plant
l and collates these with the costs of mining. The net energy
generated at the plant and available for transmission is
calculated, and an economic analysis gives the effective cost of
l the power plant were estimated by SECo, and the mine by Boyd.
The cost of certain supporting services common to the project as
a whole, such as the camp and rail commuter service, were
l estimated by SECo.
All cost estimates were prepared intially on the basis
of cost levels prevailing as at mid- 1973 (July 1st). The
l estimates were based on the assumptions listed in Section 3.6,
specifically:
l Estimates include
facilities required
the
at
cost of all on-site
Onakawana with the
exception only of the 500 kV transmission line
from the power plant. The cost of the plant
l switchyard and the 138 kV line from Otter Rapids
are included.
l such allowance was included in the mine costs but this deficiency
should have an insignificant effect on the quoted costs.
A cash flow forecast was prepared on the basis of the
l proposed construction schedule (Drawing 12) with appropriate
allowances for normal contractor payment provisions. Escalation
l
l
l Report 5366-4-73
Paqe 6-2
l
l of the cash flow amounts was calculated on the basis of an
Escalation Forecast dated April 1972 and supplied by Ontario
Hydro and used for both power plant and mine costs. In order to
l olant is;
In round figures, the total capital cost for the power
l personnel etc.
(certain of these facilities are
also used by the mine, the total
$ 18.4 million
____^_:___________
l 3.
cost is as quoted)
Sub-Total $257.9 million
l
l
l
l Report 5366-4-73
Page 6-3
l
l 4. Engineering (office and field
supervision), administration, ex
pediting, owners costs, and start
l up expenses - at J.0% of line 3 $ 25.8 million
l 5.
6.
Sub-Total basic plant cost
Allowance for contingencies -
5283.7 million
l 7.
at m of Line 5
5312.1 million
l 8. Cost of escalation during con
struction (until the end of 1980 74.9 million
l 9.
based on line 7)
Cost of interest during con
l struction - at 8%
until Oct. l, 1979, based
on escalated costs, line 7
plus line 8
53.8 million
l insignificant.
The total estimated cost before the addition of
l
l
l Report 5366-4-73
Page 6-4
l
l Year
A summarized cash flow during construction follows:
Cost in 1973 $ Escalation Interest Total
l 1978
1979
1980
78.0
68.7
15.6
19.9
20.8
5.7
19.3
20.6
——
117.2
110.1
21.3
l
l
l
l
l Keport. S.V.n-.l-
raq i
l
l In total, the annual operating and maintenance cost for
the tvo plant operating cases is summarized as:
l Case l - -- .
(in thousands of 1973 dollar;
l 1.
2.
Basic Staff payroll
Routine maintenance materials
3,500 3,400
l 3.
and contract or pool labour
Sub-Total
3,000
6,500
2,000
5,400
l 5.
*i.
Sub-Total
Ash disposal (by the mine)
7,800
700
6,480
390
l 8.
9.
Sub-Total
Operation of camp accommoda
8,600 6,950
l 11.
force)
Sub-Total
900
10,600
900
8,800
l 13.
(Case 2') of capital cost
Grand Total Annual Cost
2,200
12,800
1,800
10,600
l
l
l Report 5366-4-73
Page 6-6
l
l ash storage is included at the plant to enable ash to be handled
on day shift only, not on a 24 hour basis as assumed by Boyd.
l Mine Capital
Mine Operating
Power Plant Capital
89.7
446.4
312.1
58.7
263.4
312.1
l investment
The total
return
true
escalation, interest during
costs after due allowance for
construction for the plant,
and corporate taxes for the mine, are
l substantially higher.
6.5 Cost of Energy
l
l
l
l
l
l Report 5366-4-73
Page 6-7
l
l Annual Lignite Consumption
Case l_________Case 2
6,900,000 tons 3,800,000 tons
l Net Plant Heat Rate 11,000 Btu/kWh 12,300 Btu/kVfr
l Capacity
Energy
Resulting Capacity
911.3 MW
6,063 GWh
917.3 MW
2,986 GWh
l calculation on the cash flows for both the mine and power plant
costs; a sample calculation follows s
Case l escalation ignored, all cash costs quoted in
l 1973 dollars, present worth calculated as at
1979 {on power date for first unit),
appropriate conversion factor for 1979 cash
l costs is therefore
millions of dollars:
unity. Figures in
l
l
l
l
l
l
l Report 5366-4-73
Page 6-8
l
l Mine Costs
1. Total cash costs (Capital s. Operation) - 536.1
l 3.
4.
Total lignite delivered to the plant
PW of lignite at m
"
-
187.9
million tons
38.4
l *5. Net price of delivered lignite (2t4)
million tons
" $3.98/ton
l 6.
7.
Total cash capital cost
PW of capital at 81
-
-
312.1
349.6
l 9.
10.
PW of operation at 8*
Total cash fuel cost (3 x 5)
-
"
139.6
747.2
l 11.
12.
PW of fuel at 8%
Total PW of plant costs, capital,
- 303.0
l 13.
operation and fuel (7 + 94- 11)
Total energy sent out by the plant
792.2
163,420 GWh
l 14.
15.
PW of energy at 8i
Net cost of energy sent out (12 t 14)
65,640 GWh
l *
(constant cost for 30 years) 12.07 mills/kWh
Minor difference from Mining Study Report cost is
l
l
l
l Report 5366-4-73
Page 6-9
l
l 1. Annual fixed charges for the plant:
Cost of money - S.000%
l Depreciation (sinking fund for
30 years @ - Q.8831
l 2.
8.8831
Plant capital cost (including interest) - 3356.9 million
l 4.
5.
Annual fixed capacity cost (3x1)
Annual operating cost
- $ 34.79/kW
- $ 12.8 million
l 7.
8.
Total fixed cost (4+6)
Equivalent to 48. 84
8760 x 0.759CCF)
48.84/kW
7.35 kWh
mills/
l 10.
67.62 x 10
l costs is due primarily to the fact that the second method assumes
that the plant operates at a constant output for exactly 30
/ears. In reality, there is a start-uo period in 1979 and 1980
l
Report 5366-4-73
Page 6-10
Case l Case 2
(mills/kWh)
(a) Constant energy cost r no
escalation, in 1973 dollars 12.07 19.69
(b) Constant energy cost, allow
ing for cash cost escalation
throughout the life of the
project, constant lignite
price ex. mine. 17.64 28.38
Detailed calculations are included in Appendix C.
l
l Report 5366-4-73
l DISCUSSION
i c)
appropriate techniques are used in the design of
the plant boilers.
There are no undue technical difficulties in the
i preparation of a design concept for either the
mine or the power plant, and the overall project
is regarded as technically feasible.
i f)
and public opinion.
If managed and developed as described in this
report, the project should generate a net social
i and economic benefit for the inhabitants of
Northern Ontario.
i
l
l Report 5366-4-73
Page 7-2
l
l 7.2 Review
Because of the considerable time constraints under
l which the study was completed and in order to emphasise the most
significant areas, the study effort was concentrated on the
following subjects (in general order of importance):
l Design and selection of suitable boilers to burn
the Onakawana lignite
l Mining: assessment
plan for development
of recoverable reserves and
l Selection of a suitable
source and system
cooling water supply
l energy as generated.
other subjects of less critical importance were
considered to be the selection of t'ie lignite and ash handling
l \yst9ms, and the assessment of the effect of the project on the
anvironment. other areas in respect to the conceptual design of
the pover plant were given a more cursory examination.
l
l
l Report 5366-4-73
Page 7-3
l
l The labour wage rates used in estimating mine
operating costs (derived in Appendix A of the Mining Study
Report) reflect conservative cost assumptions. Starting with a
l wage rate based on that used in Timmins, the following amounts
were added to obtain the wage rate used for mining at Onakawana:
l a 12 percent premium
increases (now in effect)
for
l The overtime
The overtime allowance
final form of the labour contract.
may change depending on the
l considered
The assumption that the project can be developed to
begin commercial delivery of power by October l, 1979, is
valid, but it does require a relatively fast
l
l Report 5366-4-73
Page 7-4
l
l 1. A survey in the winter of 1973-74 of icing
conditions in the Abitibi River, together with a
more detailed review of the feasibility of
l 2.
altering Otter Rapids discharges.
Confirmation of the acceptable environmental
l effect of thermal discharge of cooling water to
the Abitibi.
l 6.
concept for the plant foundations and cooling pond
(if required).
Adequate samples of lignite should be obtained by
l 1974 to permit boiler suppliers to prepare design
proposals for tendering.
l
l
l
l
l
l
l
l
l
l Report 5366-1-73
l
l 1.
REFERENCES
Report of Task Force Onakawana, January 1973.
l Paper No. 3)
Economic and Social Impact of the Development of
l 2.
the Lignite Deposit at Onakawana (Working Paper
No. H)
The Air Pollution Control Act 1967 - Government of
l 3.
Ontario
Relative importance of initial velocity and buoyancy of
l 6.
7.
"Environmental Control in an Age of Change", Heat
Engineering, Foster-Wheeler, March-April 1971.
British Experience with Tall Stacks for Air Pollution
l Control on large Fossil-Fuelled Power Plants, G. N.
Stone and A. J. Clarke, C. E.G. 6., London, England, 1967
l
1
Ontario
1
The Government of Ontario, Ontario Hydro, and Onakawana
Development Limited (Manalta Coal) , entered into an agree
1 ment in 1972 to undertake a feasibility study on develop
ment of the Onakawana lignite deposit, which was covered
by an Exploratory Licence of Occupation held originally by
1 Manalta. Such an approach was necessary in order to integrate
the resource planning responsibilities of the three parties as
it was felt that all three would have considerable interest if
1 the economics of power generation using Onakawana lignite could
be established.
A preliminary investigation of the environmental effects
1 of the development of the project was undertaken in 1972
by Task Force Onakawana; their conclusions were submitted
in January 1973.
1 The engineering cost study conducted by Shawinigan Engineering
has been received and studied by the three parties. While not
1 definitive, it does provide a sound basis for analysis of the
economics of the project. Integration of the economics of the
study with those of transmission and of alternative generation
concepts has been made by Ontario Hydro. While the concept
1 appears more expensive than nuclear plants, it compares
favourably with other fossil fuel projects under certain
conditions.
1 In view of this encouraging situation the government must examine,
in further detail with the other parties, the possibilities for
development of this important resource. The economics of this
1 and of alternative systems for use of the resource will of
course be reviewed, and if a favourable decision can be reached
on the power development concept, further engineering studies
1 and environmental impact studies will be required before the
project can be definitively outlined, and financing arrangements
f1 concluded.
1 ^
-S^l J
Leo Bernier
1 Minister
1
-I3000N
-HOWE
-9000E
-7000E
-5000E
-3000E
-IOOOE
COE
IOOOE
3000E
5000E
7000E
9000E
l IOOOE
"
® l 8
en
i
8 8
DRAWING 2
REPORT 5366-^-73
PORTAGE FIELD
51
75
50 82
FRASERDALE
/\ \
KAPUSKASING
50
COCHRANE
OHAKAWAKA K.
so0
LAKE ONTARIO ;; /-
:?V-'v:-.-.. -/' /•••'.
.•'•..•:
MILES
DRAfMNG 1
51 REPORT 5366-1-73
82
ONAKAWANA K.
50"
i -HOOOE
-9000E
-7000E
-5000E
-3000E
-IOOOE
COE
IOOOE
\.
\
\
3000E \
JRIVER WATER o
*C PUMPHOUSE -*ty
5000E
7000E
9000E
IIOOOE
g g 8o
"l
® i o
CO
DRAWING 2
REPORT 5366-H-73
PORTAGE FIELD
BY
BY
TABLE OF CONTENTS
North End. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
South End. . . . .. . ... . . .. ... . .. .. ... . .. .. .. . . .. .. .. . . .. .. 3
West End . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . .. 4
SAMPLE PREPARATION
Introduction:
lignite field.
a line was pushed north to location 54,000 N and -1,000 E. P-7-72 drill
field. Drill holes P-l-72, P-3-72 through P-6-72, were all drilled
exist to the west of the Portage Field and east of the Mattagami
River.
in the 1930's and located near the mouth of the Onakawana River -
Devonian beds at depths greater than 150'. This fact suggests that
the beds are probably dipping consistently and gently to the West
and that a change in dip opposite the lignite outcrop on the west
bank of the Abitibi River did not occur, thus lignite east of the
River it did greatly reduce the probability thereof, and eliminated any,
North End
might connect with the known field in the vicinity of drill hole
South End
potential of the south end of the known lignite field. Five of the ten
West End
of the lignite field 21 drill holes were located throughout the known
lignite field and chip samples were collected every 5' - interval in
average values.
was proposed in July and August and analysis results with hole log
However no bulk sample was taken and two holes with analysis results
were incorporated with the quality hole program including drill hole
drilled throughout the eastern 2/3 of the known lignite field, some
drill holes .
than averages over the known field. It is likely that these high
values are reasonable and the Portage Field is higher in ash and
Exploration
Quality Testing
One hole could be drilled and sampled every two days. Using
a large dia bit a hole was drilled to the top of the lignite coal and casing
inserted in the hole. The hole was flushed and a 5 1 long V.T.fvl. core
barrel replaced the large dia bit. Rods were pulled each 5' run.
Core was shaken from the inner core tube into a wooden holding-trough.
When coring with mud took place the core was washed in clean water.
The core was then placed in a 3' long wax-coated cardboard core box,
holes P-7-72 and P-16-72. Water was passed downward between the
two tubes and both water and all hole cuttings were forced upward
Page 7
SAMPLE PREPARATION
Chip Samples
A measuring cylinder was used to take portions from the 5' - interval
seam composite. This composite sample was split into three sections,
one sent for analysis, one sent for storage with Ontario Hydro in
Toronto and one sent for storage with Manalta Coal Ltd. in Calgary.
Core Samples
Each core box was logged and where core recovery was poor
site notes and observations were used to complete the hole log.
In some cases grey muddy clay coated the outside of the lignite core
and had to be washed away. The core was then split, lengthwise,
placed in a plastic bag for analysis, the other half being placed back
ANALYSIS
SURVEYING
NOTE:
BRIEF
JANUARY 1972
l
l 431 12NE030a 83.1-56 GARDINER
TABLE OF CONTENTS
050C
l i.
Page No.
l
SUMMARY
1.1 The Onakawana Power Project l
l 1.2
1.3
Size of project
Project timing
l
l
l
1.5 Advantages to Ontario 2
1.6 History 3
l
THE NATURAL RESOURCE CONCERNED 5
l 2.2
2.3
Location
Coal characteristics
5
5
l 2.4 Utilization 7
l
3.3 Water pollution 10
3.4 Use of land 11
13
i
4.3 The economic picture 14
4.4 Finance 15
i
Page No,
6. CONCLUSION
l
1.2 Size of the Project
The presently known and inferred reserves
l
The total capital investment required would be of the order
of $290 million. Construction would take 4 to 5 years;
l
would employ a peak working force of about 700 men; and
would generate more than $4 million in revenue for the
Ontario Northland Railway during the construction period.
i
units large enough to suit Ontario's power market did not
exist.
i
A power plant of the type proposed has a normal
economic life of about 30 years. Over this period, if the
period starts soon, the power produced should be significant
i - l -
1.3 Project Timing (cont'd)
market, and eventual competition of nuclear power, as the
nuclear gap closes, may prevent the project from ever being
initiated. This could mean that this major Ontario natural
resource might then never be developed.
— 2 —
l 1.5 Advantages (cont'd) *
i 1.6 History
i
decision to proceed has been negative because it appeared
that power from Onakawana coal would not be less costly than
i
alternative sources of power. However, these decisions, when
made, do not appear to have been anticipated:
i
(a) The delays and increased costs associated
with the introduction of nuclear power.
(b) The escalating costs and increasing scarcity
t Ontario.
(c) The development of a proven technology to
i technically feasible.
(b) That there is a market for the power that
i
would be produced.
t - 3 -
1.6 History (cont'd)
(c) That the cost of this power would be
competitive with the cost of the power
that it could displace.
. 4 -
jtntt
ONAKAWANA
PLANT SITE
HYDRO-ELECTRIC
B E C
R co LTD ^ Q U
POWER COMMISSION
OF ONTARIO
2.2 Location
These coal deposits are in Northern Ontario in
the region of Onakawana, about 60 miles south of Moosonee on
the southern coast of James Bay. The Ontario Northland Rail
way, which runs from Southern Ontario to Moosonee, passes
through the coalfield and provides ready access to the area.
- 5 -
2.3 Characteristics (cont'd)
of natural gas, and to the best methods of burning it in
boilers to raise steam to generate electricity. As yet, a
practicable and sufficiently cheap method of drying lignite
to make it economical to transport it long distances has
not been discovered. There are proposals to gasify Canadian
lignite, but the estimated cost of the gas produced does
not yet look competitive with natural gas. However, consid
erable advances have been made, especially recently, in
discovering how to burn lignite successfully and efficiently
in large boilers for power generation.
Therefore, large scale commercial use of lignite
is presently confined almost entirely to the generation of
electricity. Also, almost all lignite fuel power plants
are situated adjacent to the mine producing the lignite. Such
plants have been increasing rapidly in number and size during
the last decade. Appendix I attached contains a list of
thermal generating stations in various parts of the world
which use lignite coal for fuel.
Lignites themselves vary in their suitability as
fuel for boilers. The two most important characteristics,
disregarding air pollution problems which are dealt with below,
are the moisture content and the fouling characteristics. The
moisture content affects the handling characteristics of the
lignite, its heat content and the boiler efficiency. The
fouling characteristics of the lignite affect the operational
availability of the boiler and its maintenance costs.
Onakawana lignite has a high moisture content,
and therefore, a low heat content. On the other hand, it is
generally accepted from experience that the fouling propen
sities of lignites depend upon their content of alkaline metals
and, in this respect, the alkaline metals content of the
Onakawana lignite is so low that no significant fouling
propensities would be expected, which is a major advantage.
- 6 -
2.4 Utilization
After consideration of possible ways in which
the Onakawana lignite would be utilized, it was concluded
that the most practicable and economic method to develop
the resources would be to generate electricity. This does
not preclude the possibility of using it to process metallic
ores, but this use on its own would not offer the prospect of
using more than a small proportion of the already known
reserves. However, it is obvious that a mine already pro
ducing lignite for a power plant could produce additional
lignite for ore processing purposes at a lower cost than
producing only the lignite required for ore processing.
In 1968 Alberta Coal Ltd. supplied six tons of
Onakawana lignite to the Department of Energy, Mines and
Resources, Fuels Research centre in Ottawa. Combustion tests
and fouling characteristics were reported in a publication,
which concluded, "While Onakawana lignite is a low-grade
energy resource, it is better than many in use throughout the
world, and there appears to be no technical obstacles to its
utilization that research and sound engineering cannot over
come . "
Subsequently, about 1,000 tons of Onakawana
lignite was mined and shipped to the Thunder Bay Power Plant
of Ontario Hydro. Here, with the co-operation of Ontario
Hydro staff, the lignite was tested. These tests were
satisfactory and indicated that no particular problems need
be anticipated in using Onakawana lignite as a fuel for
suitably designed large power plant boilers.
Boilers to uurn lignite, owing to its relatively
low heat content, are larger and more expensive to construct
and operate than boilers for bituminous coals. On the other
hand, lignite normally occurs close to the surface and is
usually relatively easy to mine in large quantities. With a
power plant adjacent to the mine, the lower cost of lignite
tends to offset the high cost and lower efficiency of the
boilers and other equipment required to utilize it provided
- 7 -
2.4 Utilization (cont'd)
the power plant is operated as a base load plant, i.e. is
run at full load more or less continuously.
Lignite deposits, unfortunately, are usually
distant from places where the power produced is required, and
the Onakawana deposits are no exception to this rule. There
fore, most power plants adjacent to lignite mines must incur
a transmission penalty, i.e. the cost of provision of power
lines to the power market, and the losses in these lines, are
an added cost of the power produced by the plant. Even so,
the number of lignite mine-mouth power plants built and planned
indicate that these costs are becoming increasingly acceptable.
This is due to the rising cost of alternative fuels, such as
bituminous coals, oil and gas, and because of increasing con
cern for the environment.
- 8 -
3. THE PROBLEMS OF POLLUTION OF THE ENVIRONMENT
- 9 -
l
l Pollution (cont'd)
satisfactorily controlled, with one exception, by the pro
l
little sulphur which is a virtue from every other point of
view. In this case, it is very difficult to get the electro
l
static equipment to perform satisfactorily.
Coal fired power plants in Southern Ontario have
l
another problem. Since coal cannot be delivered in sufficient
quantities during the peak winter season, coal has to be
stockpiled. In high winds, such stockpiles in an urban
l
is to use very high and expensive smoke stacks and rely upon
dilution by discharge of the boiler gases sufficiently high
l
above ground level. This problem is, of course, more severe
in an urban environment than elsewhere. Recent investigations
have concluded that coals, such as Onakawana lignite, with a
l
l - 10 -
3.3 Water pollution
All thermal power plants discharge large
quanitities of heat to the environment in the cooling water
that is required for their operation. This can cause changes,
often undesirable, in the ecology of the rivers or bodies of
water into which the heated water is returned. Cooling towers
can be used to minimize this problem, but may have some or all
of the following disadvantages. They are always costly, are
normally considered unsightly, require a relatively large
land area, decrease efficiency of operation, may present a
noise problem, and may introduce their own particular air
pollution problems in the form of local fog or local precipi
tation.
Water pollution by heat is not normally a
problem with a thermal power plant provided that the river or
body of water utilized for cooling purposes by the plant is
sufficiently large in relation to the size of the plant.
- 11 -
l
l 3.5 Onakawana (cont'd)
l
of sulphur in the boiler gases, but is not so low as to jeop
ardize the performance of electrostatic dust collection
l
equipment. The preferred method of burning Onakawana lignite
would result in about 75?; of the ash in the fuel leaving the
boiler in liquid form. With only 25?; of the ash in the boiler
l the size of the power plant would ensure that any heating up
of the river water by operation of the power plant would have
l negligible effects.
l
l
l
l
l
l
l
l
l
l
l - 12 -
ONAKAWANA POWER PROJECT
PLANT SITE
PROPOSED BY
ALBERTA COAL LTD.
4. THE PROPOSED POWER PLANT '
- 13 -
4.2 Transmission picture (cont'd)
A second 500 kilovolt line into the area would serve not only
to carry the power from the Onakawana power plant to the
south but, in conjunction with the first line, should permit
more economic full development of the hydro power in the area
which, it is understood, is not yet fully developed.
- 14 -
4. 4 Finance
Ontario Hydro raises millions of dollars each
year to expand its electricity generation facilities to keep
pace with Ontario's growing demands for power. To do this
it pledges the credit of the Ontario government.
Provided acceptable contractual arrangements
can be made, private enterprise is prepared to provide the
l capital necessary to develop the mine, and to construct and
operate the associated power plant at Onakawana. The purchase
l
l
l
l
l
l
l
l
l
l - 15 -
l
l
l
l
l
l
l
l
l
l
l
l
l
l
l
l j Typical Coal Loading Process
l
l
l
5. THE ADVANTAGES TO ONTARIO OF THE PROJECT
- 16 -
l
l 5.3 Development (cont'd)
on, it could be expected that the mine and power plant would
l
ment is an alleviation of the problems of pollution. In
Southern Ontario it is already accepted that thermal power
plants must use only low sulphur fuels for which the compet
l ition is severe.
l
Not only would the Onakawana project alleviate
pollution problems by transferring a substantial block of
thermal generation away from an urban environment, but with
l
the Onakawana project would free an equivalent area of land
in Southern Ontario for other use.
l
There is the possibility that the Onakawana lignite
may prove to be suitable for use in the processing of metallic
ores that are produced in the Sudbury area. If so, it would
l - 17 -
l
l 5.6 "supplemental" (cont'd)
l
it prove suitable for this use, would alleviate to some
extent the air pollution problem in the Sudbury area.
l
per year. After construction of the complex there would
certainly be more utilization of the railway than if the
complex did not exist.
l
suitable and economic to use in the Sudbury area for process
ing metallic ores, this would mean substantial and permanent
increased utilization of the railway.
l 5.8 Financial
l pace with the rising demands for power. To the extent that
private enterprise is prepared to finance the Onakawana power
l
block of generation. Instead, it would be paid for out of
annual revenues.
i 6. CONCLUSION
l
It is submitted that the Onakawana power project
is a viable project, and that it is in the best interests of
the people of Ontario that it should be commenced forthwith.
l
l
l - 18 -
1 f)
1 *
1 APPENDIX I
1
LIGNITE BURNING POWER PLANTS
1
Name of Station Unit Size Year of Coal
Location MW Commission Type/% Mois./BTU/lb
1 1. U.S.A.
A. U.P.A. Stanton
1
North Dakota 175 1966 L /25-40/6800-7600
B. Leland Olds
North Dakota 216/248 1966 L /34-40/5600-7370
1 C. Center, Minnkota
Power Co-op
1970 L /35-40/6000
1
North Dakota 220/260
D. Big
Brown, Texas 2 x 543 71/72 L /25 /7590
1
E. Dave Johnson
Wyoming 360 1972 L /40 /6800
F. Leland Olds
1 North Dakota
'
420/440 1975 L /34-40/5600-7370
1
2. AUSTRALIA
A. Yallourn
Victoria 642(T.C.) 1962 BC/65-68/2600-3000
1 B. Hazlewood
Victoria 3 x 200 1966 BC/58-64/3250-3750
1
C. Hazlewood
Victoria 5 x 200 1971 —— ~~
D. Yallourn "W"
1
Victoria 2 x 350 1973 BC/65-68/2600-3000
1
3. CANADA
A. Boundary Dam 2 x 66
Saskatchewan 2 x 150 1970 L^35 /6500
1 B . Brandon
Manitoba 1 x 100 In. Op. ' L^35 /6500
1
C . Onakawana
Ontario
(proposed) 2 x 500 ? L/45-55/4800-5600
1 - 1Q .
1
1 * APPENDIX I
— 4. GREECE
1
* A. Ptolemais P. S.
Ptolemais 125 1965 L/55 /4250
1 5. FRANCE
1 A. Gardanne 250 - L/ ——
1 6. GERMANY
A. RWE
Goldenberg, Werk 100 1951 BC/ ——
1 B. RWE-KW
Frimersdorf 2 x 150 58/60 BC/50 /2700
1 C. Preag, KW
Bo r ken
D. RWE-KW
100 1961 BC/ ——
1 Frimersdorf
E. RWE
Nevrath
300
300
1963 -
1969
BC/50
BC/50
#700
/2700
1 F. BKB
™ Offleben 325 1969 BC/48 /3780
I G. RWE
Weiswetter 600 1970 BC/60 /2700
1 7. ITALY
A. Selt Valdarno
I
Sta. Barbara 2 x 125 1956 BC/ ——
8. RUMANIA
f A. Industrial
Import 330 1967 BC/43 /2880
1 - 20 -
l
l APPENDIX II
l
______And Associated Companies—.—.————.-
l
Experience; Alberta Coal Ltd. and its Subsidiaries account
for nearly 351 of Canada's present annual production of coal.
l
The Company operates six open pit mines, four
in Alberta and two in Saskatchewan. Three of the Alberta mines
and the two in Saskatchewan are located at thermal generating
l
business and all highly qualified in their particular area of
work.
Continuous exploration to ensure adequate reserves
l
l
l - 21 -
42M2NE030a 83.1-56 GARDINER
900
P. O, Box 2880
Calgary 2, Alberta
29-March-72
Mr. G. T. Stevens,
Research Officer,
Ontario Department of Mines
cc Northern Affairs,
Whitney Block, Queen's Park,
Toronto 182, Ontario*
/.
P.O. Box 2880
Calgary 2, Alberta
27-Jan-71
W.R. Kenschel
Secretary 5- General Counsel
wrh :pf
ends.
/
-3-
CANADA
PROVINCE OF ALDERTA
/
EXHIDIT "A"
During a four (4) wccfc period In November end December of the yacr
1970, ono thousand (1,000) tons of coal W2ro excavated from ft
•location as shown on the attached plan on lends covered by the
licence aforesaid.
This coal described obove was delivered, by way of ths Ontario '
Northland Railroad to Ontario Hydro st Thunder Day, Ontario for
Power Plant test burn purposes.
Equipment used In procuring the coal consisted of:
l - 5 cyd, Front-End Loader
1 - D-8 Ooscr end Ripper
2 - End Dump Trudys
V/atcr Pumps .
tto furtlTor drilling v;as conducted during calendar year 1970,
however, a wctchrncn was employed to make periodic checlcs on our
camp throughout 1970.
X
-5-
CANADA
PROVINCE OF ALBERTA
.f-
A. F. Collins
ejp: Executive Vice -Pre ?idmt
afc:jd and General Manager
end.
CANADA
2 OF ALCEPiTA
"lrsr,i';*-^i''ti f fr"**v*'
-t-t..v-^— •w--*,i...rtj,. - ^- y.. ,
•y.-..
ce 2
TI'.c power so r.snoratod v.-oald be sold to tha public fcy Ontario Hydro
Electric Power Ccwmlsston through Its transmission systems. .
A nwvibcr of discussions hova teen 'hold with Offterlo Hydro
\ . : . . -
C i\ M A D A
VIMCE OF ALDEfcTA
gyPLCTAT.!OM
This docs not Include salaries or travol oxpensea for cwr suporvlsory
arid odni in le t rat t va personnel* .
.i-.'^i'-:-^
V J .j~~ -••4? .
P.O. Box 2880
Calgary 2, Alberta
21-Jan-69
WU y em R. Blain
Secretary 5- General Counsel
Encls.
CANADA
PROVINCE OF ALBERTA
.FOR Oftf.KAWAMA
-
1-,'agcs snd so l dries -15,597.25
Equipment rental JO, 8.92.30
Repairs end supplies ^2,357.04
Fuel
Freight 2,235.72
Drilling fi. testing expense 5.138.68
Exploration permit 1.009,00
87*7*2.37
This does not includo salaries or travel expenses for our supervisory and
administrative personnel.
CANADA )
PROVINCE OF ALBERTA )
•i. .4-
•ir'-'
-n-
Cont'd/2.
March 1968: Cutting of winter roads to drill sites continued.
Tect drill holes No's 68-42 to 68*55, 2, 330 lineal
feet of hole in the aggregate, were completed to
March 15th. Drill logs are attached. Samples
retained are stored in .Alberta Coal Ltd. warehouse,
Calgary, Alberta.
Moderating temperatures after March 15th precluded
any further work in the bush and drill equipment was
shipped out. The camp was left in care of a watchman.
It is the intention of Alberta Coal Ltd. to maintain*
a fully equipped camp at the site pending further
exploration or other work. , ^
v/
. 3 -
S. P. Lfeng, P.Eng,
Chief Engineer
-20-
O.K. /Thompson
Controller
2nd.
GET:dm
CANADA
PROVINCE OF ALBERTA
(
-22-
CANADA
PROVINCE OF ALBERTA
1.. That I am Chief Engineer of Battle River Coal Company Limited and as
such have a personal knowledge of the matters hereinafter referred to
except where stated to be on information and belief. -
2. That Battle River Coal Company Limited is the licensee under
Exploratory Licence of Occupation No. 13*902, dated January 10, 196?
and granted by the Minister of Mines for the Province of Ontario.
3. That I prepared the report attached hereto as Exhibit "A" and
that the contents thereof are true to the best of my information and
belief.
U. That I make this affidavit for the purpose of inducing the Minister
of Mines for the Province of Ontario to release to the licensee, Battle
River Coal Company Limited, the' deposit of ^25,000.00 made by the licensee
pursuant to the terms of Exploratory Licence of Occupation No. 13,902.
•iff '
Cont'd/2
-15-
- 2 -
E. fir -
-15-
- 2 -
X^X';
S
S. P. Lang,
S
gf.
t^J'
Eng.
Chiei Engineer
SPL/im.
"*~"''. 'i
-Zlo-
g. Septic tank ; v ;
. .' .'":.."" ;.
h. Deep well pump for camp water '
2. DRILL EQUIPMENT .7 ; . :-
* . - "' * "
Cont'd/2
-r?-
O "2" -
AUXILIARY EQUIPMENT Cont'd ;
j. Pumps
1-1/4" Monarch, deep well, jet type, l-1/2 h.p. elec.motor
Samplers, 20#, 3'4', " " ' " - " ' -' ; -
, Cont'd/2.
^ COAL COMPANY LIMITED
' .
January 6, 1968
l Q .
W ————:————"
ONAKAWANA EXPENSES
156,551.67
- ^61,526.67
O
/
Quote rao , .
BRANCH FUEL RESEARCH LABORATORIES
Fucle and Mining
CANADA
Practice Division.
DEPARTMENT OTTAWA,
OF
-f*
MINES AND TECHNICAL SURVEYS
REPORT OF ANALYSIS
Snmplo of coni cubrr.ittocl by Alborta Coal Ltd. aa por advieo addressed to Chief, Fuols and Mining
Practice Division dated August 9, 1967. Sample designated ae Onakawana 0x6' ,
. ft'
Ligaito ft .
ft-
ft
•ft
ft
Reported by:
Solid Fuel Lsborotorw
Dictrifcution:,
Alberta Coal Ltd.,
P.O. Box 2880, n\A\{t*A
Calgary, Alborta (2) —
D *S * - MoJit/jjoiflOiryj
' v \
1*^
y\
Hoad, IPiiols Roooaroh Centre^
,/
-32"
Quote File ....
SS BRANCH FUEL RESEARCH LABORATORIES
Fuels and Mining
CANADA
Practice Division.
LSPARTMENT OTTAWA,
OF
MINES AND TECHNICAL SURVEYS
REPORT OF ANALYSIS .
o? ooal submit led by AlbefrtA Codl Ltd. 1 db pen* advlda adJPoflaed to Chief ^ Fuola and Mining
Practice Division dated August 9* 1967* Sample designated as Onakawana 8 x 12'
Remarks:
Distribution:
REPORT OF ANALYSIS
of coal submitted b/ Alberta Coal Ltd. as per advice addressed to Chief, FuolO and Mining
Practice Division dated August 9, 1967* Sample designated as Onakawana IS 1 east end of pit*
ft
ft
Ranlc (A.S.T.M.) Lignite ft
*
ft
Rcmarko:
Distribution:
Alborta Coal Ltd,
P.O. Box 2880,
Cslgary, Alborta (2) N
D.S. Montgomery,
Head, Fuels Research Centre
-34-
Formerly
CANADIAN INSPECTION A TESTING CO. LTD. E6T. I9O9
CHARLES WARNOCK COMPANY EST. 1027
Intpttlion MILTON HERSEY COMPANY CST. 1000 .
Phjtitjl, Cktmi
tlon-Dttltuilivt Tilling *— 233 Port Street, YJINNIPSG l, IU CLMSUC BTHZX
MONTACAL M. C
P 3531 4- 13*21^
P 3532 5 25*oW isrc * 'i-' j ' r-o.i
tftl./ " j!
\_r\t AT; j .-.AWN
w
P 3533 6 19*63^ "i*;T.Ti:ins""
7 6,71# i, J "K'^"V"
j-'ii- i*i.,.ii.;
P 3535 8 32*8.7*
P 3536 9 12*1
P 3537 10 16*95^ 10a20^,
? 3538 11 22,76^ 10o03^
P 3539 12 7*70^
P 13/ 11*97^
Composite of
samples l *. 9
Traoo
0*0003^
PS/HS
4^
F* Sav/chulc,
THIS RCPOr.T 1C
Manager* Contrnl DIvialor
ONUY
PCHOONAL uae OF THE CLIENT NAMTO Aoovr ANP MAY
HCi'llOOUCiO
iO DfwJtfft PEHMIflSION FHOM TKK WARNOCK HCOSf.V CO"fV^ l. ID.
/""
;
l THE-WARNOCK HERSEY COMPANY LTD.
Formerly t .
CANADIAN INSPECTION A TESTING CO. LTD. EST. 1*03
F 3528
OP QMS .(1) SAMPLE '
REPORT
MARKED, NO* l
AS 'KBG'BTfSD
Air-drying Loss, ~~ ' 37*18^
Moisture, —-———w 22*03^'
Volatile Matter, —*
Pixod Carbon, ——-i 22*0
Ash, ——~——————w
S ulphvt?, *—-—-—t-
B. T* U* per 7*729
F* Sawchuk,
FS/ES Manager, Central Division*
THIO nnpont icjron THE exCLucive AND PCROONAL use or THE CLIENT NAMED ABOVE AND MAY
AI4WV l"- Hi;. IHioWatB OY WniTTfcN PKftMIBBION FROM TMR WARNOCK NCNSCY COMPANY LTD,
-31,-
^Q l-.n^
C
f' -.^^
'M 1 11 T HE WARNOCK HERSEY COMPANY LTD.
Formerly .
CANADIAN INSPECTION A TESTING CO. LTD. EST. IOOS
CHARLES WARNOCK COMPANY CST. 1927 HiaJO/fic,
MILTON MERSEY COMPANY EST. 1060 '
m
, Chtmittl, '233 Port Street, WINNIPEG l, MONYRCAl. U. OWC.
Tilling ~
C E NT R A.L
DIVISION
October 6, 1967.
Soil Mtthsnifl
P* Sav/chuk, v
Manager, Contral 3)ivision*
THIC ncponv to rcn THE cxciiO&ive AND PERSONAL uac oc THE CUCNT NAMED ADOVK AND MAY
rr nrrnooucr.d'rtY WHITTKN rcnMissiON FHOM TMR WAINOCK Mtnsev COM rAM Y I.TD.
-37-
-vo
x
CANADIAN INSPECTION ft TESTING CCvLYD. CST. IBOS
CHARLES WARNOCK COMPANY fiST. 108.T HtOO C///IC*
MILTON KERSEY COMPANY EST. 1000
233 u. B.M.L.C
•^ Port Street,' Y/INNIPSG l, .
, lniptdion
' Pbjtitil, ChtmStal, - MONTREAU aa. eui
Ntn-Dttlruttive *OM""
AffHjiieh — R CENTRAL n|V,g|QM October 6, 1967.
Soil Misbjii
ANALYSIS OP COAL '
P (COMPOSITE OP SAMPLES 10 TO 13 DEL*)
REPORT
BATTLE RXV3S COAL OOMPANT,
P. O. BOX 2880,
CALGARY, ALBERTA.
. aa?* Sherman Lang*
ANALYSIS OP
Acid-insoluble,
Silica (Si02 ), —— -
Aluminum Oxide (A1203),
Iron Oxide (Pe? 0-)j -- 17*36^
Titanium Oxide^f^iCs),
Calcium O^de (Gao), -•— — —
Magnesium Oxide (MgO)
Sulphur Trioxido.
Alkalies (2fa2 O
by diTf cronco,
•-^\i.W
PS/ES, Contral Divioion*
THIC RSPOnT IS rOR THE CXCLU5'V'C AND PERQONAL USE OC THE CLIENT NAMED APOVC AND MAY
OMLY OC flZPnOOUCfct) DY WRITTCN PCRMI&SION FRON THE WARNOCK HtHSCY COMPANY LTD.
-38-
Temperature/
Softening
Fusion Point, 2,300^
"l
LJ__jJt±:!__l
i i...-, '....j
; i.;r. \i\A*
--r.-ft- ***~"^."^ii4^v'
-i-i.is'-
.^'4
•"-**L ^
January 6, 1967
- -o
ONAKAWANA LIGNITE
(3) (4) (5)
(1) (2) BTUs from Ash @ BTU @
Sample Air Dried 1200 B.TU Equiv. Equiv.
^Lab.No. Marked Moist. Ash DMMF MoisU(43ft) Moist. (43ft)
Comp.
F3541 ' 1-9 15.40 14.88 8160 10.8 5400 Composite 1-9
above
Comp - p
- ,t
4
: . - - ! -- .-- - . -.
' l ; .' : --:. -, :? - i . : '-i- ' ; -- - : .
,- -i -: ,. . . .
. --
. ..
'
. J. J -
' - -
.
.i., .
. .... i-.; - , .. -. . ; -' . . - .. .
.: . : - ,;.'.:-; ; . j..... , -,
; - : : -j".V * .:/ ' - : : ':.
' : "" ; ;' -' - -i- ; ' /-
. .. : . . ... -
: " ' : -. - . . -
; '
' l
. .
:~ '••'•.'' -' .V.: '"•/' : :" -*! '"'' V •'•' .. :;"!. " ---
'/s?tt/,*:
o
OH.4+ .
CH3' O
JT
l
A C-
D.IC45. 0-M.4Z O.K.W
o./M' OJ&;
c/r C.lf C.3f
O.M.4I
el/0*
CV/
OMSl
O
Fi;. 3—P}.-1.,! fho-.v!n^ pc;U:on* of drill holes and shafts, also thickness ia fc?t of overburden (O) and lignite (C) at each drill hole.
1.
ONAKAWANA - DRILL HOLE LOGS.
- - *
0 4' Muskeg .
*
2.
ONAKAWANA - DRILL HOLE LOGS
3 - li 1 Gr.ey clay
X
1 ' '"'-"-
* -'. ' 'i*
11 - 19' Sandy clay le stringers sand 4c gravel
53 75'
'."•' .'. :- ' . 8800 ' f 0,000 •'.••'':, j "i '' ^;V; ' "' f, ' . .'.."' '~
Hole No. 68-09
:o - . ',. ;' 3' ! :; Muskeg ' ' ".' '-..'- - :y.'*' - : ; :: ;: X-'- ^^••^.•.'•' :::l^':. '
' *;' ' ;V: - 'v .9'.
' '.. -' , -. ' * ,. ^ ' - - ' -* ' '•, . - -. -' - - -••-tt ' . - - -r*? - " "" " -. f '
63 75' '.-V.YY'; '.Grey clay ' :--; " , : -. '' .^'^ ; -.; i-'v •• :T:Y;-'j: -: /';' : '
0 - 3' : '.' :" '''^Muskeg •'.':'.-; ;-"1 :*v.-,;! ••'•'•'' . V Y'.' •••- 'v- -' '•^• ;..;:; ;'- Y ;- ;-
3 . 8' '- -; Grey clay " ' ' '-".Y""-' '- ; ' ' " >•;.•••••
. . Cont'd/page 4
s "' " - - ' 4
ONAKAWANA - DRILL HOLE LOGS
' *''- ',. - ' '." -. ' -' . - ' . "' " ' '
99 102' Brown clay ^ '- ; ; .; ;' - .' v
102 115' Grey clay . ' -1..V' V f -. ''? •^•'- '^-: -\.' '''
0 4' - . : Muskeg- '-, ' - \ , '" ': .?;: •/ :':'V' -.^; 7U."V :v /•.'.- ' ; '
' ' ' '•;':"V' •/•:''^;-."' ' '- -.•• : ':','- ;"- -1 '-
4 : -- ' 22' - -, T ' ''
Sandy clay St sand fe gravel" v
.-- -
;;': ,- ; ' v
'.:'- v.":.^'' '"r ^"^:'./.:"' •v^; ; ''-"v:.-;: ^
22 -.' : 52'.. ^ Grey clay ,- •;'-';::^:Kt-;H'V''''.;C^? ^' '^"v:- -' . ..-•••.'.
73'',:"-': ,-\V
52 Sandy clay SE boulders ; '' ,, :*V •^'•^^v^/vM, ; '" '
.r. ~ , f t '. ,' "' .-"^ .-^""''''*: :';-'^:'"^v'.:; ; :'-' ;'' ; - - *:'--
73, 81' 'T Brown clay ' ' '•-'-•'•'- - - -••.•^^^^'•^••VJ;-/-';?.;::;-- -.' :; v -'7
' -.•-- -"* j^ ," ' *ri V *'^- " . ".ji' ".r-' '"'' : - '"**-'"' -"' -'''; -*-'' * -; "' , " (' - '
81 95' , Grey green clay . ". : ' ^^••-•••".-^.'•4^'^- :' "v^'.-'.----- --,
. - - ' . ^ ••;-.V'^.;;V.'-:'i .'..-.--;.-. ' • ; :.... ' -,, ^
9floo ^ 8600 .\ . •'•'.-...; -.: t r , - .
Hole No. 68- 12 Location-fe^^*N^-^aa3^E , . '' ! -,^.^i:'- v ; V; ' \^ -v
'.*"'. •••;- :, ; 'f :-'^7i}.\ -}"'' * .-.-i':
, 0 3' Muskeg - ' -" "' ' - '"" •'•': ;''^;:- .'••'••.-'.'. " ' P: -.- . ;; - "
- - ' ' , '. ' -' ' ' "--i ''•:"~ .', ,' v'f " ,- ' .•••-i".- '' ' -',
39 95' •;'( :- ; .-:'^ 1".:': Sandy clay b boulders, stringers sand b gravel
... - ' '" * -v,v •' .' . .'.:' . '. ' '
Hole No.68-i5. Location 1000'N - 2000'E. -:- ••-: . '.: ' V " ;
0 •;;';V;,-vV^ , Muskeg . ." . - V;'.. '•'••i\''- ' -':''" -' '-'.'' " ' :-:
' ' ' ' . ' '•'. : .;'--.v'.v -V:---' .'•''••'•'•'•.^ '
3 ' ..'-^ \-.."io'.^-.'-'.-.'-'-V Grey clay
•' . . /' : '"'. "V '-.V. :: . :-
10
. ; - ••.• :; -'3i'' ;,,; : ;:;.': ; \- Sandy clay it' boulders : ,. :, .^ . ' ' , ; ' .
,'* ' \ -' ; :. . '.'/'' ' ; "'.'" -' '
31 ;.' '- " ; ;. -39' :; ; '^::; .'.' Sand (gravel stringers) ' -, ; : ; ; ;
•" '^ - .-'' '. " •'.;v'." :: - ^" ••; -'
- ' -' - . ' > , ' ' - -
39 '\--/ .49* ,: '.:\':; ; - : ' Sandy clay b boulders V1 J : . . - . ' ; ;:
.'.a,;. - ;- 3' - ;. \ Muskeg ' .V' " -" ' ''-' : -'-*/--:: ,V -; v-:. ; ' -. . - •••-' : --
• ; , ^v^..^^f^;ve:.--,-'-,-:
3 ' - ; -: '11' ; .'.^' Grey clay •- •.•..•"-:u^;^^-^^-',-v;. -'
". •.•'•.'•'*:3-'/ '•••'-. .-f':"' - . S' ..'- - -
11 . . - , 28' . ,:;.. ' . . Sandy clay k boulders
'28 . ;' ; - 'Vv-.'-.' - 38'/' -' --' "' ;-,v Gravel . :; ';;; ' , ;::';1
0 - 2' . Muskeg
. " 7,
0 2' . ' Muskeg . . . ." •'•f,:' ..'f:,'i^-. '.•:: - r, - : : ^. , - '. . :' :- '.'.r ' -.
2y - 8' •:
' " '
•'"'Grey clay. . - .. V- ; -: ^^^''^ ^ ^-.. -'
" ' ' '"'j1 : " '"J -.' - -' '""' ' -* '"' ' ' '
/;
* - , , , ' ' " . ; " - - -' - :- - * : ' -. .
8 - 21' 'Sand St gravel ^' *y-: ';, ' '-'J. :' '
0 - ' 3' '; _ -Muskeg ' \ . .' •.•Y^.-'.^yy y.y. :':';^-- ^ '- :.... - ;
" . 3 , i -; '.i. 22' .' ' ' Sand St gravel . ' V '.^•' ; ^;,'v!' -;: "'^ ' ; -v ' '' '-': ; V' " " : :
. r l .' -' . r 1 . - *"*'-'*"'"- .. V.'sjf'v.^ Vi---.* v:". '-''^ - - '. .*," ;* -, , ' ...- -
. 22 . - \ '•.. 41' •' y : . ;: .;. Grey clav: ; . ,.! ' ---^^:^^^ .^H^:: ;- :' '•.:
'. y -. -. 41;.. -. ." 56' ••' ;,V Sandy clay St boulders ' '•'^.1''^^'^^'^^ '''.^^'••.^•'•'
• - -: . ' .-" : . ./' - •"••"v^-..:;v,v.'.--!'-^'.v"'.-v; -.".r.''. --. .-'- v- v ' - '- v
,- •';: ;i.-"'-.'v . .V:"o: :: :'^.-'0,::-^^.'n'Jv?^'''-.^'-iv;':--.,:-:i -:'v ::, r .-., . ....
y . | ' 56 . y.y; 57' '..•/'•-.- :..-.: Brown clay^ ..' ,.; '.v : .' •^^•'^^^^•'•^^^'^•^•'^•^'':'' : "- -
" ; -'57 ' -' - 75' •' ^. Coal 18' ^•\;; 'r^^V^^i!:^;^|t^^
; - 75 - •' ;; . 77' ..' :f''-';.; :- Brown clay '" - : .'/ ' ' : '''•^'.^t'': '^^^.':'- :'i^;''- : -''.'-'
, ''j
. 77 - 95 'V 7 y'- ;V Grey clay " "'- . ^ ./..^•..^•/^^'y'";'^''" t '^ ' '' \•'
.Hole No. 68-20 _• f : ': location i2,ooo'N -ras*'E. :' ' ;- •';, ,\.;/ ';
• :':v--: . -, .- - ^.-•..v\.,^-:V:;v;-;.i, ^ :A ;: •-•..•.. ;--
B
4 '"-•••'"' .'' 11' . ; ''-/.;'. V- Sandy clay St boulders' '-''''^y^yvy '•••:\.'"-*---:. ' *. -
: ' ' ' - li'; y- "" 25' ' - '\ Sand St gravel ' ••''•^\ :-^^^^'}'-''^-''.''-----';-'^
' ; " 25 •-•'. ' 45'., . Sandy clay St gravel ; -v, N:;:^ .''^.'^ .^vV'^:.-.-.;*'^ ' '-:.'"/. -~
. ;, *. * w ". - . -l ••.••'••"'•••'" •-..'•••; i ' "••'. ' ,. -- " " '
45 "'- y 60' Grey clay St boulders' ,' " ,; . ' '-V v '. . -
60 * - - 95' Sandy clay St boulders
.w
4
,; ;.;/ •/.•.. * ,' ,',;- ^
1 '- " - '"f - ' ' r"--~ff' '-.. - - ••"•' ••-••JwSlftrV---*' -*-i-i, w* .4 p
8,
Hole No. 68 -21 t Location 5, OOO'N - 1,000 'E, Vicinity of aid shaft.
4 - 11' X
•* "* ' Grey clay - - . V
127 145*..-:.'..};..:;; Grey clay "..'-.- .':' ;'-;"..-'-'- . v ' : .;'. - ":
1 . -l .' - f - .' "" ' ' . . .. - ,'
Hole No. 68 -22 -' ' -* ' *. -*
Location 8, OOO'N - 4, OOO'E." A; .';' .
4'V-; :: V...':'. 'Muskeg
* .' ' \ . "-
41 ' - X' ' : 56V x-f-v- Sandy clay St gravel . ; ' ': ; . j,,' v
56 - V 57,:; ..:,x^, Brown clay :~ ' " . .' :il''-''. V'.v'J-.'.f .''; V.'i-.'v,':' ; -"' ^ ;- . *-.y -
61'"'.'.rf : .'.;V''
57 - . '- - ' "-' '-'.'-t v'.' '/i'-' ' •'-.•- ' ' ; :' ' ;'' .
. . ' -
' , * . '.' ' . .' . . - ."••- : : \ -.' -' .* - V, -, . '
61 - 951 y'-'..--,/" ' Sand St clay St boulders ' '. '- - - '
•0 -v
*-^j .Muskeg
' ' ' -
.. J
* " -' "
. "'
- ''-. '.v v'-.:/- ; 'V,'-''--' "-' -
' . i - "••- '.'
., , - - ' , ' '
'
'-'-
*
--
*' .
':
44
53 •* ' D3
. -' ; \ ' '
' ' ' " l-
p - LV
Grey
j
clay St boulders : ' ^ : ' ;! 0
- * * ,. T-^'i ,' ;- * '.•"* v
,--,-^.^JHS^A
-ra
0 - 4'
Muskeg . .;
4 12' Grey clay .
38'
* W ' ' '. -. . /. . ' " ,- B. . l
Hole No. 68-29 * ''. ' ' ' - Location Sutcliffe Line -*- 1 * OOOE.
S'.'.:'^;'/."''
0 '.^•Muskeg , :v';-. •"''•.-.f ;\:. '. .-.'-.' '''':- - •'-' '. '..'. - -
53 - 57'^vV .' :,..", Gravel ' ' ,. . . '.'••'••:.f ,. -V.. '.'. ' ' '.""' ' ' --' '
84'' •.-••••' '-':;.-
57. - ; . Sandy clay St boulders '
84 91' v .. ' Brown clay* ..,-.. ',
''-. : ' "..'
JL IS 1'.';/:'",
--i
91 - Grey clay St boulders "' •..'.'•'•'
Hole No. 68 -30 * . ' . ' - '. -. ; Location 13, 700N - 3, OOOE Sutcliffe Line
4' "••'s.'. ;'
0 . - Muskeg ,
4 ; - 12' v Grey clay 44
70' Sandy clay St boulders (stringers of gravel) M
~ Tl
12 VM 22
70 93' ; Sandy clay St fine gravel -
93 114' Coal 21'.————-—-——— '""—— ——— FC. 2C
- Top 5' soft, took sample of top 5' St bottom 16' A -H
117' ' 100.*
114 Brown clay
117 125' Grey clay
0 4' j Muskeg
4 - 12' - Grey clay .
12 40' :.'-' :' Sandy clay it boulders -
40 47' ,.;. Sand ir gravel
47 70' Sandy clay it stringers sand it gravel
70 - 74' : Gravel
74 - 76' /;
80'
Sandy clay it boulders -
76 Brown clay it coal traces
80 92'. ' Sandy clay it boulders
92 106' ; Coal 14' M- 44
106 108' ;- Brown Clay VM - 20
108 125' Grey clay FC - .17
A- 19 100ft -
Hole No. 68- 32 . ' .' ' ' Location Sutcliffe Line 13.700N - OOOE. '
-:, ' .. -. '^ - ' - - -
Hole No. 68 -33 * ."' "' - * ' -" Location 12.200N - OOOE. \':7';.; '^ , ;; ; -' : .' :
o .".-•..;" .-••' 4'- ;v'Vv','-" Muskeg -, ''': ^^^P'!^^^r^^•.:
4 /•-'•'•*.(-'--: 9 . ..Y. .': Grey clay "'""•'^{"^'•'•'^ ' : "--. : ' •••'••'.
9 44' " , Sandy clay it boulders . '. --r;' v \ ' '/V . .^ :; ',
44 56' ' - : :- Sand it gravel ; ' y- -'fVX.!;-'-'-.':: -,'. * :. ";- '
56 - i2i' .:: Sandy clay it boulders .^- j? tvT '..- .: .' \ ' '
121 132' . ;.:\'/'.' : Coal 11' h-.;-- ' /.^i-;p;^;.V^,-'-VV: V; .;.
132 133* ••• J ,';V Brown clay . -.^";: ^ : .- :
133 145' .•"•••'- ;.-. Grey clay - - .
.
•^"••A':*i..f. ; 't ; :- Vl''v -; . - -\ ' '-.
- ' - .- '' .t ' t ; '- . .
J:nr*Hnn j^SSlM .'&SS*"'' ' C "': '':' : '' ' " ' '
Hole No. 68-34 4 '
/
-rs-
12.
ONAKAWANA - DRILL HOLE LOGS.
0 4' 'Muskeg . -
•4 - 11' Grey clay
11 . - 65' Sandy clay St boulders .
65 85' Sandy clay 8t boulders
85 - 95' Gravel, sandy clay fc boulders
95 104' Sandy clay St boulders
104 108' Coal it traces brown clay. - 4 1 mixed
108 121' Grey shale - . - , :
121 126' Coal 5' y '••'"•; - ,: . /. ; : - -y; , - ''••' ' ''
126 128' , Brown clay .' . -' . .,
128 135' : - . Grey clay ': .' ;. " ' - . -
0 4' . -V
.Muskeg , ;'';\; '- '' ' r ,.'.'-.';,' ', "';
4 62' Grey clay St boulders ,' :. .
' 62 68' ': Sandy clay St boulders . . . -; . "
68 - 83' Gravel St sand . : , . ir
83 - us 1 : •;:-; -. Sandy clay St boulders ; V '^ '
118 123' ;. ; -..^ Brown clay St coal traces
123 140' ' .Coal 17' M-. 44 " '
' . ' 1 40 142'' - ..-: Brown clay J*,*', 16
142 155' Grey clay A ..- 30 , :'
' '
' ' 0
5' . '
-
-'•••-
.
'.
i?'5 . 'yy;y/;
v' ' .' :; ';'; 'Muskeg
. Grey clay -"
**
'
' '•''"' " -'••• :.' /: : - : -v.-v!' . ^ -' :.' •'•'•'"''- -':'i
" ' . ' '-- '' t * ' -
; .' . ••; ''':". .•.•' •/•^ "•-.- '^'
' - *-
] V' .'.'
' * - ' ' ~ -V ' *
,'
,-
45'
- .
17 -
45
- . :.,
50' 'y../.- Sandy clay St boulders
Sandy clay St gravel
; ;*.
y
;;'
-;
'*
- :
50 - 100' Sandy clay St boulders. -:y 7 ' ^,
100 125' Brown clay St traces of coal . ;
125 158' . ; J Coal 28' TjZ,' ' ' . : , , ,' .'y :. : V -' •-• : y." "
158 175* y -Greyclay' ;-' ••'••.' -r' st '-. "' : : " -- , . '.
'"' . ' '.
Hole No. 68-38 Location 7, OOON - 5, OOOE. .
- , 11 * . * - . ' --
t
o -; 5' : . :. .-; Muskeg ' ''.*".'' ' - i -1 :'-'" '•'•' ' ,: "' "' ,, ' '•'•. -
5 12' Grey clay
12 50' Sandy clay St boulders
50 . - 75' Sandy clay St gravel - .
75 104' Brown clay ,
104 - . 127' Coal 23' M " 44
127 129' Sand VM - 19
129 135' Brown clay ^*^ " ^
135 150' Sandy clay St boulders A " . JQ*,
150 165' Sandy clay St gravel . 10U7o.
165 185' Brown clay
185' 205' Grey clay
13.
ONAKAWANA - DRILL HOLE LOGS.
Hole No. 68-40 - ^.-,V' Location Sutcliffe Line 13, 700Nr8, OOOE. '
t - . " ** ' ': i' * - ' . ' * ' -. ' ' ^
0 - 7' -, . ••/W.; Muskeg -. . ^ - v.^'. '.'.- 'C'- '',. \'' ' ' '
7 12' '^.••r;;.;.-Grey \ . ^[ '--' -. -';' .' -''^ : ;-''. - -
12 - V 89' Sandy clay St boulders, stringers sand St gravel
89 - : . 112' ,- . :,7 . , Sand 'St gravel '- ^/..^v^V-v;'— - '•":'"'-1 1: "- - ' .
112 : - V\ ' 121' . .....;.; : Sandy clay St boulders\v; ; ; ::;-V-:;^v.,;\...:,. . V; ;-..;,. . " :.
127' '.;; -.'': - Sand St fine gravel -". •;.v; '".": r' ;'.: .^•K.V'%".;-.
121
129' '- : ;. - .:v' Sandy clay Sto boulders -''! 'v''.'••••,f.\'- 't' . '-' . ';.'
' .
127 . - \:^'.C-''-.v."; ; " - ,. : V.,:
129 131' ,": ;.'C;;,' Gravel ' /-.. : '^••. '^' v- ": '-- ' " : . ' •*.
131 . - 175' ,- ; Sandy clay St boulders . : . v,: ':.-'..'\ v-".'-'
175 255' v ''-.;f. Sandy clay St boulders : iv.^ :V; A; .; -' r-
182 196' : Grey clay St boulders .t/ : . ., - i V . ' '
255.'"' : ,; Grey clay ' ' •;\-'-f;';' '- -ti"- -~. ^-l- "' --' '' '.-
196 -1 . * * ' . , - * -* '. ' ' \- : * - ' ; ' i*, ~ - ' -
'" ' ' •'•"':. .'\ * _ - 's-,-v '. ".. .;* \ '-'S •/'"•'•' ' ' ' '
Hole No, 68-41 , •Location 13, 700N-20, OOOE. ' ' ' - '
0 - 71 ..•••'•;.; Muskeg -; '••- '-V : /.;- i..;V-'::' ; ';'v';" , v -'
7 - 12' ; , ; ..-,".: Brown clay . ' .' •'':.\"'''-'-- ; \'" - - -- •••'• : ••-
12 - 30 Brown clay St boulders ' ' - ;, ; '
30 49' ' : Sandy clay St gravel
\
49 79 Gravel St sand "'
79 - 98' Sandy clay St boulders .- .
98 ' - 110' Brown clay , ' Vi . .
110 - ' 125' Grey clay ' . . ' . ' .
125 - 135' Brown clay . .
135 167' Grey clay
167 185' Grey clay St boulders
-57-
14.
ONAKAWANA - DRILL HOLE LOGS.
Hole No. 68-47. ;. ' .7 ;V Location 12, OOO'N - 2, OOO^E. ?', T^ V "'V -
j 0- : '-:;^.6' -;. " ,. ,- ,- Muskeg ' ' .';- '-'.;.;''/,'' *.V' : -' ••'•'•''' .'-": . i ' - ' '"' --'
6 : ' : - ; ';-.:; -\ 12' : \';,: ' ,:" Grey clay ' - 1 - V':'^ ' ."'••.^-".-.- -* : ; V;-:,y :v. '
•l 12 . - ;- . 20' - ' ; .':,.- \: Grey clay St boulders '. ;^ ' '•': -.{'. ;l '':t \'' /•':;'H :
'20 . •'•-.- V; 35' '
. , Sandy clay St boulders ' v "' v ' - :". " '.
. '- , k '60
35 - 60' .; -.•'- Grey clay . ' . ;- '- ; ; ;., ,;.;'--'. " -' - ;'
- 80 1 : Sandy clay St boulders . - ' -, ' i' ' ' ;
80 - - . 90' - '. - . ' L/oal
^. . . , iu
i /M * " i "ii " iM ' ' "*-^^A- VM- M -44 22 - -x " '~
90 - 92' Grey clay St boulders FC - 20
'i 92 - . ' 110' ...•Coal 18' ——-^ A -^H
•j 110 135' Grey clay M -44 lOO^o
t{"i "
, . VM- 19
. FC - 19 .
ii
•m
A - 18
ID'0%
*'
i
i i ' i * . . -
l i- "- -
i - '
i
' .; * ' -: "' '* ' - ' '^ ' .' - ;- ;
v_
167
ONAKAWANA - DRILL HOLE LOGS. t.
Hole No. 68-50 * L ' ,. ' ~ ' ' ' Location 1,000 'N - 2,000'E, . ^\ : ,V
•0 ' .' 4' . ; v' ' ; -:
Muskeg .. ..''-w , ..
4 - -' - •'-. 12' Grey clay - ' , ,- ;'.''''-\' -'. ';
12 : - - so 1 : Sandy clay, gravel St boulders -
30 - . ' . 35' Sand ' ' ; : .-•'•;:.' : :'r
35 65' Grey clay it boulders .1,' ..-.\ -
65 75' Sandy clay ir boulders : V ''-:,'[ ; :
75 - . 79' Brown clay ' ', . ' !
79 - 81' ,. Coal 2' -' ; '//••^.\::". uvi ' ';' ''-.. :-
81 90' Brown clay ' ; ;v \ '•'-. :''-'' ; : 'i ^ •\,:'\ :': "*-' '.
90 135' Grey clay '
-to-
17.
ONAKAWANA - DRILL HOLE LOGS.
0 - 4' ,': ;;. ;.'. Muskeg " '^} •'::;^'^'--vv:^:' ; '!:'.- :A'
4 - : '12' ": Grey clay . ^'- ';- ::xV-'^:''"^^' :fM
12 33' Sandy clay St boulders' - ; ^ 'V^
33 47' Sand ' . \:;V ••: "::i'-^/.;:.^
47 110' Brown clay St boulders ••'''"l^v^' 1 ^'.'^
110 115' Brown clay, stringers of coal : ;5? ' ; v ^
115 127' Brown clay St boulders ; .; ^| ,.^.y
127 145' Grey clay . V; ^; : j
Hole No, 68-54. Location 12, OOO'N - uToOO'E. .' ';^ " ^
- -'. . . . '. v-/ V..r."..(.-' .'i':: -,-'
0 - .6' Muskeg . - '.;. --' ..-y1; .;^'":-;^:---'O' ,;
6 - . li'- :. Grey clay -. ' ; v vr * '-."
11 65' Sandy clay St boulders -. .'.:.'-v^;: :^
65 80' Brown clay ' .'••' ' . : .
* ', ,*'-"/ ' ' ' -,
18.
ONAKAWANA - DRILL HOLE LOGS,
resent surface-mining practices in the United States into the mountainside.) rose from 43,167,000 tons to
'are devastating large areas of land and are produc 213,373,000 tons.-'
ing great environmental damage. The growing na In coal surface mining, the overburden (the earth and
tional concern over this problem is evidenced by rocks lying above the coal seam) is first removed, and the
the number of different surface-mining regulation bills that' exposed coal is then extracted. Surfaee mining conducted
arc currently before Congress. Some of these bills would in relatively flat terrain is commonly called area stripping.
only slightly alter present strip-mining practices, while The surface of the land is first scalped of trees, and a deep
others would require a substantially greater degree of land trench is then cut through the overburden to expose a long
reclamation after completion of the mining, and at least strip of the coal bed. The earth, clay, and rock overburden
one bil! would prohibit future coal stripping altogether. is deposited adjacent to the trench to form a long "spoil"
A program ensuring the lull restoration of all lands dis bank. After the coal is removed, a second trench is cut
turbed by surface mining could bc an environmentally ac parallel to the first, liiid the overburden is dumped into the
ceptable alternative to banning the pi notice completely. first trench. The process is repeated until all of the coal has
This option has been adopted by the Federal Republic of been extracted, resulting in a series of parallel, adjacent
Germany (West Germany) and several other European spoil ridges, which give the mined land the appearance of
countries. To assess the feasibility of this approach to having been worked over by a giant plow. The 'final cut
the problem, we visited the Rhine-land brown-coal fields of produces an open trench bounded by a steep wall called a
West Germany and studied the land restoration methods highwall.
employed to reclaim the huge, open-pit lignite (brown Contour stripping in hilly regions progresses in the same
coal) mines of that region. Here, we were particularly manner except that the process is halted sooner—as the
interested in the German reclamation laws and how well thickness of the overburden becomes too great. Starting at
they are enforced. In general, we found that the German the outcrop of coal along the hillside, a slice of overburden
land restoration program is highly successful. Many fea is removed and dumped on the downslope side. The coal is
tures of the planning, technological, and regulatory proce then removed and a second cut is made through the over
dures used in West Germany to ameliorate the adverse burden to expose more coal. Finally, when the overburden
environmental'consequences of large-scale surface mining is too thick for further economical stripping operations,
are applicable to strip-mining problems in the United Slates. augers as large as seven feet in diameter may be used to
The nature and extent of environmental damage from drill horizontally some several hundred feet into the moun
surface mining in the United States have been documented tain lo bi ing out additional coal. Using this combination of
in several excellent reports.' Essentially, two basic factors stripping and angering, the mining operations proceed along
have contributed to the magnitude of the problem we face the hillside, leaving a'twisting trail of churned earth in their
today: the rapid development of strip-minim; of coal since wake. On one side the bench (or shelf) is bounded by a
the beginning of World War li and the greatly increased steep, nearly vertical highwall, and on the outside by the
consumption of coal for electric power generation. Coal mass of spoil material precariously balanced on the down
consumption for electric power generation increased from slope of the mountain.
51,474,000 tons in 1940 to 310,312.000 tons in 1969 To our knowledge-, an accurate survey of the total land
and, during the same period, the amount of coal that had area disturbed by thciSuffacc mining of coal has never been
been cither strip-mined or augered (mined by boring made. On (he basis ;of data reported by coal producers,
Paul Averill has estimated that, as of January 1. 1970, the
li. A. Ni.i'HLW is H research st;i)T mcmhei ;it the O.ik Rutac.National cumulative past production yf 4.4 billion tons of strip-
l aboratory. He is currently engaged in a National Science J'Oimda mined coal resulted in,2^450 square miles of disturbed land
lion program, "The Environment and Technology Assessment," in the U.S.' He further estimates that the mining of the re
v. liich includes ;m investigation of ihe environmental impacts of
electricity production arid use maining 128 billion tfrns of stfippablc coal in the O to 150-
foot-thick overburden category would create an area of
, VOL. 14, No. I
The West Germans appear to have
deveiojRil an exemplary process for
exploiting the mineral resources of a
region without permanently impairing
the quality of their environment.
disturbed land comprising 71,000 square miles. At present even though only a small fraction of the land is disfigured.
coal strip-mining rates, roughly 100 square miles of addi The destruction of watersheds (catchment areas from which
tional disturbed land are being created each year, We must stream waters are drawn) by sedimentation and acid water
consider that advanced earth-moving machinery and chang runoff also extends the harmful effects of strip-mining.
ing economic conditions will probably make deeper deposits (Acid water is water containing high levels of sulfuric
accessible to surface-mining methods. This would expand or other acids.) According to a recent study/ contamina
the strippable coal reserves and the total amount of future tion caused by both deep and surface mining has substan
land damage. tially altered the water quality of tfpme10,500 miles of
The damage often extends well beyond the boundaries streams in Appalachia. Acid drainage seriously pollutes
of the actual mining areas. Where mountains are scarred about 5,700 miles of streams, reducing or eliminating
by contour mining, the whole landscape is rendered ugly aquatic life. A recent study by the U,S, Department of the
of;y,
developing
be brought to
^ti^^^^
Interior on the environmental effects of strip-mining in vegetation methods effective in areas of low average rainfall
Cane Branch Basin, McCreary County, Kentucky, showed must be developed, soil conditions must be investigated, and
a marked decrease in the variety and abundance of inverte groundwater movements must be determined. (Ground-
brate bottom fauna in Cane Branch and in Hughes Fork water is the water beneath the earth's surface, between
downstream from the strip-mined areas." This was caused saturated soil and rock, that supplies wells and springs.)
by alternate deposition and erosion of sediment and the Much work remains to be done. However, it is already
killing of aquatic vegetation by acid water, effectively de clear that strip-mining, whether it is conducted in Appa
stroying ihe stream habitat. Annual erosion losses from lachia, in the arid regions of the Southwest, or in the harsh
freshly strip-mined areas in Appalachia are as high as climate of the northern coalfields, can seriously affect the
27,000 tons per square mile, or up to 1,000 times greater natural ecological balance of the region. y
than for undisturbed lands. J
Strip-mining is only now beginning on a large scale in
the western states, so the extent of damage is not yet clearly Costs of Surface Mining in the U. S.
defined for climates and terrain different from Appalachia. The true economic and social costs associated with the
In addition to increasing the susceptibility of these lands to surface mining of coal have not yet been adequately as
wind and water erosion, surface mining in the semidesert sessed. Coal can be strip-mined at an average cost of about
regions of the Southwest poses the danger of exposing 51.50 per ton less-than deep-mined coal, largely because a
highly saline material to the surface.11 This overburden ma number of important externalities,' such as the cost of
terial, enriched in salts by the process of percolation of adequate land reclamation work, are not included in the
surface water, if brought to the surface, would make it production costs. For a coal density of 1,800 tons per
difficult to establish and maintain even sparse vegetation acre-foot and a recovery factor of 80 percent, the yield
on the disturbed land. Before the environmental impact of of a typical three-foot-thick seam is about 4,300 tons per
surface mining in arid regions can be fully assessed, re- acre. This means that some 16,000 per acre could be spent
14 ENVIkONMKT, VOL. 14, NO, l
cost {Mfcwisons are difficult. State regulations iy ^2,600 per ncre. . ^
generawr require only what is called primary rec These and other studies must be used cautiously ,
lamation, in which heavy equipment is used, to bury to assess the expense of comprehensive reclama
acid-containing materials and to smooth, but not tion. The estimates are well within the range of
'grade, nine-field ridges. The major aim is to al- reclamation costs in West Germany, but the Ger-;
.leviate water pollution due to acidic mining wastes. man restoration practices are far more extensive-;
Strip-mine fields that have undergone only primary than anything that has been done on a large
reclamation still retain long furrows,-; as though in the United States; On the other hand, ttya Get
turned up by gigantic plows. Furthermore,,the fer system appears tp be profitable in aspects
tile topsoil, saved carefully in the German mining neglected in America, The German approach p,rb^Kj
technique, is forever destroyed or'.buried- in. the motes' Systematic, utilization oi .^j|)'iihjo'^r.!n.a)V^
typical American strip-mine field; The fi^W that has riai-r-coa(f ;feVtile topsoil, even ;sr~ J --^ ;——•-;i ' i
undergone primary reclamation is.a wftitftiand on v.i TheVtresfpredland "againip
j ! I'L-rkv.*.j j/:**-1'. ".'*:- \t.' l1: j.-—". -
which only the hardiest vegetatiorf^hii^yrVty^t-'ll
Reclamation '. practices arfe^ ;somew}^t'i j^^r^,;^'^^,.^:
Pennsylvania ia and Ohio, which ^^^fj^r^s^an^jl^'i .. *s Into^econpmic l la bitit
dards than . other;Appalachja'i^state?^^|^|Jl||^; v
The few U.S^tudies'or^lHe.cost ^'^an^aH^j^ii^^^^
may be of ' ii***i*j*.y'
lirrtttdd **.*^B^iijv-^*fjifcWfc ^*^ijtim/rii^frt'^'i^fV'thfl^
r Tj'7*r3?-- ,
Jv T v '""" -^
-- *- ^ f '•iv'/V' i'f* ' at jdris froov strl
country, In a l^.Piii'ir^t;^ 'tf^^^^n^j^^'''TH inrt Regional Comm
sylvania in l9^r'thVc6stemt
'' " "^ ' ' ' '
^fe-af)ifillin^M,^ - Im
'
on land restoration without destroying the competitive The consumption of coal for electric power generation
position of strip-mined coal with respect to deep-mined is expected to inc'rease greatly during the coming decades.
coal. In West Germany, the actual costs of restoring mined- Perry has estimated that the use of coal for this purpose
out lands to full agricultural productivity range from alone will reach some one billion tons by the year 2000."
S3,000 to S4,500 per acre. To the extent that strip-mining This would represent nearly a threefold increase over
is carried out without subsequent restoration of the land, present coal consumption rates for electric power genera
a portion of the true production costs of strip-mined coal tion. More and larger strip mines may bc expected. The
is being imposed on neighboring communities and on problem of meeting the ever-growing energy demands of
posterity. society without needlessly destroying land, water, and forest
It is easy to find evidence that the burden of external resources must somehow be resolved.
costs associated with strip-mined coal is not fairly borne In view of the extensive environmental damage already
by the consumer. In some regions of Appalachia, approx inflicted by coal surface mining, and the anticipated future
imately 40 per cent of the maintenance budgets for state
and county roads is used to repair damage caused by heavy
coal-truck traffic." Land made worthless by strip-mining
operations no longer serves as a tax base to provide needed The key to the West German success in
revenues for local community development. Floods and
landslides resulting directly from conditions created by coal land restoration lies in detailed advance
surface mining destroy both public and private property. planning based on the needs of the
Funds that could otherwise provide needed local services
are thereby diverted to repair the damages. Poverty, apathy, region as a whole.
and blighted social development all too often characterize
our coal-producing regions.
JANUARY /FIMUAKY 1972 IS
-^-4^%-v^g
*-^.^^Lfci^'i -**
(X^^g^^l^gj
1972
THE ONAKAWANA LIGNITE DEPOSIT
REPORT OF
Dear Sir,
The Fuel Commission of Ontario appointed by
Order-in-Council in October 1943 has reviewed the problems associated
with Government expenditure and its future policy in regard to the
lignite deposit in northern Ontarioo
In our Report, which vie nov/ forward for your
consideration, we have endeavoured to assess this project as a self-
supporting publicly owned enterprise.,
To date the mining, processing and utilization
in this area of lignite have been too limited and qualitative in
character to provide sufficient quantitative data on which to base
sound conclusions regarding costso
A shor-t-term experimental programme is outlined
with careful estimates as to its costs and the results which may be
achieved, provided the enterprise is given adequate technical and
executive supervisionc,
To assist your Government in its formulation of
policy we have endeavoured to picture the undertaking from a long-term
point of view by comparing estimated costs of processed lignite at various
points in the area with prevailing costs of other fuels*
The conclusions to be drawn from these comparative
figures are limitedo Incomplete information only is available regarding
the types and costs of competitive fuels which will be offered for sale
in this area in the post-war periodo
I remain, Sir,
Your obedient servant,
"HoB. Speakmanjt
Chairman, Fuel Commission
of Ontario
I. INTRODUCTION
lo greface
The Onakawana lignite deposit is situated on the Tendakaming and
Northern Ontario Railway on the west bank of the Abitibi River, 126 miles
north of Cochrane and 380 miles north of North Bay0 It is the only solid
fuel deposit in Ontario large enough to warrant consideration of commercial
development. The following is a brief history of this deposit*
During the years 1927-28, Dr. W. S c, Dyer and other members of the
staff of the Ontario Department of Mines conducted important investigations
into the geology of the Moose River basin. As a result of their findings
the surrounding territory was withdrawn from staking and the Department
undertook a drilling programme to determine the area and depth of the lignite
deposits situated near Blacksmith's Rapids on the Abitibi river* (See Fig* 1)
The drilling outlined what is now known as the Onakawana lignite deposit.
iixamination of preliminary samples from the deposit showed that
the lignite was unlike any hitherto discovered in Canada since it contained 50#
of water and disintegrated rapidly on exposure to the atmosphere* It was
obvious, therefore, that more than a mining problem was involved in the
development of the deposito
In 1929, the Department of Mines requested the Ontario Research
Foundation to investigate and report upon the technical and economic factors
involved in a commercial development of these deposits* The Department sank
a shaft and did a certain amount of lateral exploration to investigate the
deposit and secure large samples for processing tests on a commercial scale
in Europeo The physical and chemical survey of the lignite seams, the commercial
tests on briquetting and processing and an analysis of the market were completed
in 1932o The properties of the processed fuels were such that it was evident
that difficulties would be encountered in their use, which could be avaluated
only by combustion tests in commercial equipmento
-2-
1317,072.37
By jtha^ft JLO^ Railway
1939 - 1943
Absorbed in Lands St Forests Totals l 138,937o38
By the. Department jof Itan,dst Sp jForests
1942 - Deco 31, 1943 538,779.52
1855,851.89
Bartky
jeaja ^s j^qedi ;.
Moistureooooooooo............*oo*per cent 50 50 50
Asho.oooo..............i.*.oo;.i..per cent 4*8 5o45 7o85
Calorific value, Bo toUo •'•per Ib..... i...;* 5,435 5,295 4*880
the earthy lignite can only be used far-raising steam at the deposit, the
peaty lignite i sv intermediate in valueo
As indicated in the Table, the lignite occurs in two seams, an upper
and a lower seanu Both seams contain all three types of lignite and no practical
mining method could avoid taking a mixture of the threeo The survey work
suggested that the lower seams contained a relatively high proportion of wxxiy and
peaty lignite, 76 per cent as compared with 28 per cent woody and peaty in the
upper seam, the remainder being earthy lignite. The lower seam, therefore, has
much greater economic valueo
Extensive drilling has shown that the lignite deposit can be
divided into three clearly defined areaso Two of these known as Area A and
Area B are shown in Figo 2 and are of most interest in connection with the
-6- -. . | .;i - -
proposed development. A third area lying to the west of the Onakawana River has
a heavy overburden and would be of interest only if the development of the other
areas proved to be unuspally successful.
Area A extends from the Abitibi River to the Toft N.O* Railway egad
includes about 100 acres o An idealized section through this area is shown in
Figo 2* Area B lies between the To St 11*0. Railway and the Onakawana River to
the south and west of Area Ao It was largely outlined by drilling after the
1932 Foundation report was written. An idealized section is shown in Fig. 2.
When the Foundation report was written in 1932, it was considered
that only lower seam lignite occurred in Area A but subsequent closer drilling
and initial stripping operations have shown that upper seam lignite is present
in at least part of this area and that some of the footage previously classified
as lower seam lignite is in fact upper seam lignite. An examination of the
drill records indicates that the parting may have been missed in some cases
and the lower seam not penetrated in otherso
All mining proposals have been based on initial operations in Area A
for the following reasons:
The overburden has been partially removed by erosion and a terrace
runs parallel to the river; the Abitibi river bed is available for the
disposal of stripped overburden and the ratio of lower to upper seam lignite is
higher,,
From a study of the drill records, Gerow estimated the totals
shown in Table III for the lignite in these two areas.
ABLEJS! . aEROW ESTIMATE, ,OF jJfiHCEE RESERVES IB AREAS A AND B
Designation Area. Jterea. Qyerburden .CoiJuycla.^ Upper Seam Lower Seam
tons
Area A 100 8,530,000 237,000 2,703,000
Area B U3 12,797,000 4,352,000 3,17?*000
3o
As shown by Table II of this report, raw Onakawana lignite con
tains 50 per cent moisture* It disintegrates rapidly on exposure to the
atmosphere and can be burned only in specially designed equipment. From both
technical and economic viewpoints it can be used only to raise steam at the
deposito
FIGURE 3
350 teas
Vibrating Soreems
The large industries buying coal directly from importers or coal mines
include paper mills and metal mines which use the coal for steam-raising and the
Noranda smelter which uses the coal in smelting furnaces. In the latter case, a
high flame temperature is of utmost importance and Fleissner lignite could not
compete due to its relatively high moisture contents
In the majority of paper mills and metal mines, some form of continuous
fuel feeding device is used and the available heat values of Table IV provide a good
estimate of the relative fuel value of Fleissner lignite in so fas ae available
heat units are concerned,,
Where boiler installations have been designed to burn wood or wood-
waste no difficulty would anticipated in substituting lignite*.
Where boiler settings and furnaces have been designed to burn bituminous
coal difficulties may be anticipated in changing to Fleissner lignite or to a
Fleissner lignite- coal mixture of a 1:2 or higher ratio due to the fact that
TABLE IV
COMPARISON OF AVAILABLE HEAT OF ELEISSNER DRIED LIGNITE
AND SOME COMPETING FUELS
Air Dried Air Dried Fleissner Alberta U. S. Nova Scotia U. S. Low U.S.
Pine Slabs Maple Dried Drumheller Bituminous Bituminous Volatile Anthracite
Lignite Sub-Bituminous
( over 4 M ) Egg and lump
Bulk Density 17 32 32 47 50 48 51 52
(Ibs./cu.ft.)
Gross Calorific value 8090 6970 8890 10,140 13,500 13,980 14, 080 13,190
(B.t.u./lb.)
Available Heatl 7289 6151 8210 9,456 12,950 13,265 13,554 12,851
(B.t.u./lb. )
Amount to equal 1.61 2 1.03 2 1.58 1.37 1.00 0.98 0.96 1.01
1 ton U.S. Bitum (cords) (cords) (tons) ( tons ) (tons) (tons) (tons) (tons)
inous ,
Available Heat4- 124,000 197,000 262,720 444,000 647,500 636,720 691,000 668,000
(B.t.u./cu. ft. bulk)
Bulk Volume to equal 5.22 3.29 2.47 1.46 1.00 1.02 0.94 0.97
1 cu.ft. U.S.
Bituminous
Moisture ^ 10.1 18.0 20.0 15.8 1*5 1.2 0.8 2.9
Volatile Matter fa 73.8 66.0 35.7 31.1 40.5 34.7 19.8 5.1
Ash ^ 0.7 1.1 6.8 6*8 7-5 7-5 8.1 9-5
Sulphur f0 0.0 0.1 0.75 0.8 3.5 3.4 - 2.8 0.9
1 After allowing for evaportion of moisture and~ water produced by the burning
of the hydrogen in the fuel. Flue gas exit temperature taken as 600 6F. This
is a good measure of industrial fuel value. However, in hand-fired domestic
stoves and furnaces, the high volatile fuels lose combustible matter up the
flue after each stoking, the high ash fuels tend to lose combustible matter
through the grates, so their actual fuel value will be less than that shown
in the table.
2 Corresponding amounts for spruce and birch would be 1.1 and 1.7 cords respectively
o
P
TABLE V
ESTIMATED ANNUAL COAL CONSUMPTION
IN NET TONS (2000 Ib. )
•f**""*"'1™*'-'"'
-11-
approximately twice the volume of fuel would have to be handled by the feeding
equipment and the fuel bed more apt to be disturbed by the forced draft* The
difficulties will be most serious where it is customary to operate the equipment
close to its maximum capacity with bituminous coal for extended periods*
In Appendix fi of the Sutherland Report, Mr. Sutherland described tests
made/sgjtt January 1942 on an underfeed stoker boiler installation in the T.& N.O.
Shops in North Bay using a mixture of li tons of lignite dried at 200 Ib./sq. in.
steam pressure to l ton of bituminous coal*! Bo concluded that this mixture
could replace the coal without necessitating a change in the burning equipment but
that replacement by Flei ssner lignite alone would mean lowered combustion efficiency
and capacity.
* ~' ' **
and commercial stoker and hand-fired installations in February 1942 wej submitted
to the Commission on March 6, 1944*
Under domestic conditions where firing may occur at 12 hour intervals,
i . *
the values given in Table IV for available heat no longer apply without modifica
tion since the high volatile fuels will lose more combustible matter up the flue
immediately after firing and the high ash fuels will lose nore combustible
matter through the grates*
: "- . : ' -'" ' . i
would be 90 tons of Fleissner lignite per day or 2340 tons per month. If this ie
achieved, approximately 18,000 tons of Fleissner lignite or i.6% of the proposed
annual commercial output will be available for marketing investigation during the
winter of 1944-1945* 7
A detailed estimate of the cost of the propsed experimental develop
ment has been prepared by Mr. Do G. Sinclair of the Ontario Department of Mines
and is repreoduced as Appendix D of this report. He estimates the total
expenditure as follows:
180,000 Capital expenditure
135,000 Operating cost for equivalent of nine
10o preface
In order to assist the Government in reaching a decision as to whether
further expenditure on t his experimental programme is justifiable, your Commission
has reviewed all the reports and recommendations previously made to the Government
on the basis of a sull-soale conkercial operation* The difficulties of arriving
at any final conclusion will become more apparent in the
""-X-'
succeeding
'
sections
'
of
the report. .
Csts
i ,. .~ -
The economic success or failure of a commercial development of, the
Onakawana lignite deposit rests largely on mining costs o
It is impossible to get accurate figures on the costs of mining,
because there is no data available on lignite mining operations carried on under
comparable conditions of climate, overburden and wet lignite* The mining costs
quoted here have made some allowance for such contingencies, but in general
they are based on favourable operating conditions* There is more likelihood
that these figures will be found to be low, than that tfcey idll be high, if a
commercial production is undertaken. -
Mining cost figures prepared by Dr* T. Ho Hogg, toronto} T.G.J&erow,
Vice-President of the Truax-Traer Coal Company, Chicago} and P, G. Sinclair,
Department of Mines, Toronto are shown below. These are based on mining 300,000
tons of lignite per annumo
-16-
NOVEMBER
Co,s t -
This is an estimate of the total cost of excavating and
delivering lignite to the drying planto It includes ttfxttav fuel,
maintenance and overheado
Stripping and mining to be by Dieselrpotfered walking
draglines and shovel 0 Haulage from pit to drying plant by truck*
The Hogg report is 12 years old and much of the data is no longer
applicable. Gerow8 s report is based on labour rates and equipment costs not
applicable .at Onakawana o The Sinclair report is the closest approximation we
have at presento *
12e Erocfsaiflg jlaats.
The only recent estimate of processing costs is that included in
the Sinclair report (Appendix E). ^ ;
-l1?.
13o ffpmmercjLaJ.
Sinclair (Appendix E) gives detailed coste for mining and
processing 300,000 tons of raw lignite per annum to produce 100*000 tons
of Fleissner lignite o Provision is made for the purchase of heavier mining,
loading and transporting equipment and for expanding the power and processing
plantSo
The memorandum may be summarized as follows:
iggsndj^^e, (in addition to that contemplated in
preliminary development)
Outside equipment #486,800
Power plant 119^400
Processing plant 142,000 -
1748,200
Tables VI and VII show the freight rates for lignite from Onakawana
to consuming centers of interest) the selling prices of 1.6 tons of Fleissner
lignite and the corresponding cost of competing fuels as determined by a recent
survey made by the Commission, and the prices quoted in the 1932 Foundation
report. Table VI refers to industrial fuel and Table VII to domestic fuelo
In both cases the factors given in Table IV were used in calculating equivalent
quantities of fuel.
The prices given in the 4th column of Table VI are very close to
those paid by the gold mines in 1943* The fifth column gives the corresponding
figures for the paper companies who buy in much larger quantities. It is
obvious from the last column that coal has increased materially in price since
1932o Since Sutherland reported only a small increase to 1939, most of the
above increase has occurred since the waro
There is no specific rate available for the movement of Lignite on
the CoK.Ro Therefore we have used the prevailing rates for bituminous coal to
Smooth Rock Falls and Kapuskasing* The TO& N.0 0 Railway has quoted the special
rates used in this reporto
In Table VII, dealer* s margins have been added as shown. The figures
...,. , 'i '' '' .** ' " V .; . .. . , l ,. .ft";.- ' ' ' . -''- ' - .
for population show that it will be necessary to ship as far as Kirkland Lake
and Timmins in order to contact any considerable proportion of the demesne market.
In both Tables, the selling prices of Fleissner lignite are shdwn both
on a #4oOO and a I5o30 production coste, ,
No allowance is made for the inconvenience to the consumer in
lo 6 times the weight and 2o5 times the voltaite of fuel) etc. but the dealer is
compensated for the extra weight by adding his~margin before multiplying by ^Io6o
A study of Tables V, VI and VII shows that if a production cost of
#4*00 is realizable there would be a favourable price differential in some
principal consuming centreso As the production cost increases above this
estimate the potential market decreases* The above tables show that when the
revised estimate of I5o30 per ton is reached, processed lignite in the same;
consuming centers has lost its price advantage and becomes more expensive than
'
it -
#
- " '
the competing coal at present available* - i
lo Haw lignite can only be used at the deposit and it is not a commercial fuelo
Processed lignite alone or in admixture with bituminous coal can be used for
domestic and certain industrial purposes in spite of technical difficulties
provided the economic factors involved are sufficiently favourable. For
reasons stated processed lignite should not be regarded as a potential fuel
for use on locomotives now operating on the T.-& N.O o Railway*
o Up to thd end of 1943 a total of fc855,851o89 had been spent by the, Ontario
Government on drilling, research, experimental development and planto
Expenditures for January l, 194A— March 31, 1944 will be approximately
^56,000*
. An estimate has been made of the cost of completion of the experimental plant
and a nine months programme of mining, processing and marke^4nves^igation,
namely, |215,0000
. With adequate technical and^jwnagerial sv^ervision thits programme should
produce reliable data in regard to, (a) the ohtraot*ristit)9 of tiw deposit,
-20- - . . , : ; - ':-."
(b) mining problems and coste, (o) processing methods?-- (d) consumer
reaction in the industrial and domestic fields provided the fuel IB sold at
a cost which is based on estimates' for a commercial operation.
5. Insufficient data is available upon which to base anything but an estimate
as to what processed lignite will cost on a commercial scale. Estimates
of both capital expenditure and processing costs -are submitted.,
fi,- .-'- - _ '-" . '
Delivered4 Delivered4
ft
Delivered5
1
1
1 , (15,382) (1941) 14.53; 16.61 13*96 14i50 . . -.. . .
l Cobalt 276 2.08
1
l
v (2*376) (1941)
North Bay 378 2.48 15.17 17.25 12.90 13.63
1 " (15,599) (1941) •' "-' ,. '.' -
A. Tnel udes dealer rnargj
1. -,-,-~ .
Includes Tisdale Township 5* . " ' .50 per ton
2. Via
Teck C.N.R. Rate forvbitumnouss UWCIJL,
Township 6. Egg-stove price 60 cents/ton higher or 58
3. Yia C.N.R. Rate for-bituminous coal,
no special
- - rate
*- on
— lignite available.
on a production costcents
•^4^*,^^- 0 ATTftilAble
(a) -Based for .96 tons.
of 44.00/ton
(b)-" " " " * " 15.30/ton.
to
APPENDIX - A .
briquettingo
Properties of briquettes determined.
Designation -Bc of M0 #lV e
3.
(9) Onakawana Lignite Development,
Gerow T.G* January 1942 e ' , '
Contents - Plan for mining and costs worked out for exploratory
stage and commercial stage.
Designation - Gerow Report,
(10) Burning of mixtures of Steam-Dried Onakawana Lignite and Bituminous
Coals in Locomotives and in a Stationary Boiler of the T. ft NoO* fcy*
in 1941-42 o
R.L. Sutherland, 1942.
Contents - As indicated by. title.
Designation - Second sutherland Report.
(11) Burning Characteristics of Semi-Commeroialiy Dried Ontario Lignite.
Swartzman E 0 Feb 0 1942* Bureau of Mines, Ottawa.
Contents - Two domestic sizes of steam-dried lignite burned in
station-type stove*
Designation - B e of M* #7,
(12) Summarized statement of Work Done in Connection with Development Of
the Onakawana Lignite Field since September 1939 e
Nixon WoG. August l, 1942.
Contents - As indicated by title.
Designation - Nixon Statement l,
(13) Memorandum on Lignite Development,
Sinclair D.G* Jan 0 21, 1944, Ontario Department of Mines.
Contents - l - Financial statement of expenditures to date.
11 - Estimate of cost to March 31, 1944.
ill - Estimate of cost of experimental production
March Jl, 1944 to March 31, 1945. (Revised, see
Appendix D).
IV - Estimate or cost of commercial production March
31,1945 to March 31,1955 and of equivalent selling
.4.
price at various points in Northern Ontario,, (Revised,
Appendix E) . "
Designation - Sinclair memorandum.
(14) Memorandum to Fuel Committee 0
Cavanagh A,H 0 Chairman.ft Gen 0 Manager T. db H.'.O* Ry- February 1,1944.
Contents - i - Memorandum on use of raw and steam-dried lignite
on the T, ft* N.O. Ry e
11 - Supplementary statement by Mr 0 7. Ge Foster,
Supt e Motive Power ft Car Equipment ToA N.
Designation - Cavanagh Mrmorandum 0
APPENDIX B
AUDITED STATEMENT 07 gOVgRNMEBT
EXPENDITURES RE ONAKAWANA LIGNITE
TOTAL 141,
By Lands 6 Forests;
1942-43 299,993.55
1943.44 238,785.97
(to DeOo31)
TOTAL 1538,779.52 1538, 779.52
854,256.05
FORECAST Jan.-Mar. /44 J55.829.35 55,829.35
GRAND TOTAL 4910,085.*0
COPY
OFFICE OF PROVINCIAL AUDITOR
Toronto , February 14,1944.
Dr. H, B. Speakman,
Chairman,
Fuel Commission of Ontario,
Ontario Research Foundation,
43 Queents Park,
Toronto ,
Dear Sir:-
The figures re Expenditures on Lignite Development supplied
to you by Mr. Sinclair of the Department of Mines and subsequently
forwarded to us have been examined. They are returned herewith and
commented upon as follows:
Development Expenditures
The -amounts shown in this column totalling |269*416.89 are
in agreement with the public Accounts for the years indicated. In
addition thereto the Public Accounts show the following expenditures
set out by years:
477.50
1936-37 496.96
1937-3& 218.25
1938-39 196.87
1939-40 183.00
1940-41 23.46
l
These figures have apparently not been reported to you since they
consist almost exclusively of Watchman and Maintenance Expenditures,
Research;
The Items in this column have been agreed with the expenditure
as shown in the Department or Mines records.
T. ft N.O. Railway Expenditures -
The breakdown of T. * N.O. Railway Expenditures for the raa?8
1939 to 1943, totalling Jl41,528.61 was obtained by Mr. SinoA^W
from figures submitted by Mr* H, C. Nixon as indicated on the sheet
appended hereto. Audit Office records indicate the T. d; N.O*
Railway Expenditures by fiscal years to have been:
4u 117,501,76
1940-41 25,674.51
1941-42 37*740.56
1942-45 60,220.75
1158.957.58
A reconciliation between these figures has not yet been arrived at
as it is felt that Mr. Nixon*s figures were derived from records
which were subsequently altered on audit and consequently paid at
a different figure than indicated by MT. Nixon,• o
Expenditures by Lands and Forests;
The figures of t299,995o55 for 1942-45 is in agreement
with the Public Accounts for that year and the amount of |258 yf85*97
for expenditure to December 51, 1945, is in agreement with the
Audit Office records c
Expenditures re Salaries to January 18, 1944 0
Mr 0 Sinclair's report indicates this amount to be
f47,455.67 o This figure is substantially correotthere having been
two minor changes resulting from audit of these accounts which would
reduce this total by #505.70. You will appreciate, of course, that
these payments were not all through the Audit Office records by
the 18th of January 1944, but were paid subsequent to this date in
certain instances.
Expenditure re Maintenance to January 15, 1944 0
The total of {196,200.89 for Maintenance and operation
expenses to December 51, 1945, Is in accordance with the Audit office
records. Accounts passed for payment totalling |2j769*?2 have also
been paid through our records during .the month of January 1944*
The figure for credits on hand of |725.5Q was supplied by Mr o
McMillan of the Department of Lands and Forests and we are informed
that this is represented by credit advices from suppliers which
had not yet passed through our hands.
No attempt has been made to verify the accuracy of
any estimated figures supplied to you by Mr. Sinclair.
Trusting that this information will serve your purpose
as outlined in your letter to the Honourable J&v Frost dated
February 9th, 1944* I remain,
Yours very truly,
Sgd: H. A. Cotnam
HAC/FD. PROVINCIAL AUDITOR.
LIGNITE DEVELOPMENT
i
(a) on the basis of the calendar year as from the commencement of the
work In July 1939to the end of August 1942. January to Deoemben
July 1939 - December 31, 1939 l 12,253.95
Jan. 1/40 - December 31, 1940 23,418.58
Jan* 1/41 -December 31, 19*1 41,917.56
Jan. 1/42 - August 31, 1942 63*938.52
(b) on the basis of the Government fiscal year as from April 1st.
to March 31st:
July 1939 -March 31,1940 | 17,614.60
f
Mr e A 0 Ho Cav.anagh,
"•IS,
-3-
has, it would appear that it was not economically sound to proceed with
the developments of this lignite for use as a locomotive fuel, Had the
possibilities from an economical view point been established, no doubt
the number of new engines, they have since built, consideration would
have been given to designing locomotives that would have successfully
burned this low grade fuel D
In October 1940, during my trip through North Dakota with
Mr. Sutherland, to investigate the burning of Lignite fuel, i had the
privilege of meeting Mr. Manor, Engineer of Tests of tfcbe Northern
Pacific Railway 0 This Railway is burning a sub-bituminous coal known
as Rosebud, with an average of 8750 B.T.U* value and 251t moisture,,
During our conversation it developed that when tests were first started
they were made with a Mikado Engine without a combustion chamber e
I judged from Mr. Manor's conversation that they were far from being
successfulo Further, it appeared to be the policy of the Railraad
that this fuel must be used and the Engineering Department were then
instructed to develop a locomotive with a sufficient grate area and
heating surface that would successfully burn this serai-bituminous
Rosebud fue! 0
In 1926 they received the first of their new locomotives,
and since that time all locomotives built by them have followed in
principle the same design as far as fire box proportions are concerned,
and apparently they are successfully burning this semi-bituminous fuel,,
So far, I have never seen any figures that wo, uld indicate that the
changes made on the Northern Pacific Locomotives have effected any
economies, as far as fuel conservation is concerned,, From my
interview with Mr. Manor, there was no doubt that the management of
the Railway was determined that this class of fuel was going to be
used 0
I also had an interview with Mr 0 Wolden, Fuel Supervisor of the
Soo Line, who had conducted tests on two 2-8-2 Mikado Locomotives
using a Lignite Bituminous Mixture, and while he seemed satisfied with
the tests, nevertheless the data he submitted to the Management did
not appear to have sufficient encouragement for them to proceed any
further, notwithstanding that this is the Railway that handles a
large amount of the coal from the North Dakota deposits,, I believe
the reasons were similar to our own, that it would take such a vast
capital expenditure to change their locomotive turntables, coaling
plants and engine houses, in order to have the proper facilities
that the savings in the burning of this mixture did not warrant the
capital expenditure necessary to make the changes,
I also noticed, while at the Main Shops of the Soo Line
at St. Paul, they had just remodelled tiieir stationary boiler plant 0
I was somewhat surprised to observe that as they had every opportunity
of investigating the economical use of lignite or lignite mixtures,
no provision was made in this plant to burn this class of fuel;
-4-
Sgd: F o Go Poster
SUPERINTENDENT OF MOTIVE POWER AND CAR EQUIPMENT
APPENDIX D
COST OF EXPERIMENTAL DEVELOPMENT
D. G, Sinclair, Ontario Dept. of Mines*
BOILERS PLANT
1 Chief Engineer
2 Shift Engineers 432.00
3 Firemen
3 Trimmers 39boOU
PROCESS PLANT
l Foreman J300.00
3 Operators(3rd class) 504.00
3 Helpers 405 c 60
2 Pickers 228 . 80
l Grizzlyman 114.40
l Utility man 114.40
{1,667.40
C, of L.Bo 5* 83.40
STAFF
Superintendent | 400 0 00
Accountant 175.00
Time-keeper-Storesman 125.00
Salesman 300.00
Salesclerk,Steno 0 ' 75oOO
fl,075oOO
C, of L.B. 51^ 53.75
-2- - ". .
PROCESS PLANT
6 - Autoclaves |54,000
3 ~ Vacuum Vessels 12,000
l -Vacuum 2,000
2^ -Autoclave cars 12,000
Secondary Crusher ft Auxiliary
equipment 10,000
Increased Plant Storage 10,000
Increased Storage(Boiler Fuel) 10,000
Enlargement of Process Bldg, 5,000
Enlargement of Washing Equipment 5*000
|120,000
Plus 10")!, Contingiencies 12,000
|132,000
GENERAL
Fire, Water 4 Sewer Expansion f 10,000
RECAPITULATION OF CAPITAL EXPENDITURES,
Pit and Outside Equipment {486,800
Power Plant 9,400 plus f110,000
Process Plant 132,000
General 10 ,OQ .————
#638,200 1110,000
DEHRBCIATION
Depreciation Initial Small Scale Plant |432,100 e IXty |4J,200
Depreciation Large plant less Add* l
Boilers f6J8,200 © 10* 63,800
TOTAL f 107, 000
O F E R A T I N G COSTS.
MINING
Stripping - 8 month operation, two shifts per day,
(a) Labour Daily Monthly per Year
2 - 9W operators 10 hrs 0© f l .10 22,00
2 - 9W oilers " " 8 65 UoOO
2 - Groundmen tt " 0 55 11 0 00
Dozing and supervisions
charged to loading on
12 mo o basis but covers
this phase also ____ ______ ____b—
00
Cost of Living Bonus 5ft - 478.40
TOTAL - |39il66.40
Cost per ton of raw lignite 9 300,000 tons per .year | 0..122
ESTIMATED PRODUCTION COSTS OF LIGNITE OPERATION Cont'd, ;J
-6-
(2) Loading and Hauling - 11 months production plus l month general
X overhauls ;
(A) Labour ' - )
Daily c Monthly per Year'
l - 54B operator 8 hrs. C |1.10 8.80 ;
i - 54B oiler " o .6^ 5.20
1 - Tractor man " © .75 6.00 '
2 - Truck Drivers " ^ .70 11.20
l - Mechanic " 9 .90 7.20
l - Ass't Mechanic " O ,bG 6,40 ;
l - Utility Man " O .60 4.80
3 - Ground Men " @ .55 l?.20
l - Foreman -___- 300*00 ..."L--
J62.80 J1932.00 423,193.60
Cost of Living Bonus ft 51!. of J23,193.60
Overtime for repairs and maintenance ' r
including 9W Dragline 4400.00 4,800.00
' 429,153.50
(B) Maintenance A Supplies, ;
54B Fuel 6 Lubrication 10.00
Maintenance db repairs 25.00
35.00 4910.00 410,920.60
Tractors 15.00 390.00 4,680.09
Diesel Trucks (2) 70,00 1820.00 21,840.0.0
Macnine Shop 10.00 300.00 3,600.QO
Eit Pumps, etc. 7.00 210.00 2,520.00
Explosives 10,00 260.00 3,120.00
146,680.00
Grand Total(A) © (B) ~" "
Cost per raw ton -4 0,253
ESTIMATED PRODUCTION COSTS OF LIGNITE OPERATION Cont'd.
-7-
ADMINISTRATION A OVERHEAD
(1) Staff per year
Genpeal Superintendent
Accountant
Timekeeper-Storeskeeper
2 - Clerks ** |10U per month
Sales Engineer
Sales Clerk-Stenographer
11,275.00
Cost of Living Bonus * 5% of f15,300.00 765.00
-9.
Cookery Extras 5,000.00
Unemployment Insurance 600.00
Miscellaneous 3,115 e00
. 20,715.00
Grand Total t36 f780.00
Cost per dried ton fO.368
INSURANCE
Fire Insurance on |750,OOG O |2.00 per f100.00 f15,000.00
Cost per Dtied Ton |0 6 150
DEPRECIATION per year f107,000.00
Cost per dried ton |1 0 070
Processing 0.954
Administration A Overhead 0,368
Insurance 0.150
Depreciation 1.070
TOTAL COST 3,697
Interest 0.303
FoO.B. Selling price |4.00
A M li S
Moosonee
ONAKAWANA Ql,
X //i LIGNITf .1
\(\ FIELD i.
PORCUPINE
Timmins ©
RoLiyn
S/vast i ka ^
MATACHEWAN M
t Ik Lake
GOWGANDA "" a^^
•x COBALT
SUDBURY
Georgian
TOROM O
42ii2NEe3es 83.t-se GARDINER
070
DRILL RECORDS
DRILLED AT ONAKAWANA
l.'1
;a;A"--:5fcjsst
,^^^-,^^^,m^- i!-^^^J^ifi^fa^Xjfafis^S.
.- •••-' •-?C;^'•^c::.v^^-*;;:;^.to-'J.s^lfli:-ii,:;JHtie:i5i^J|?f?"tTH|
-L.:.- -^..^- -:- ,. :: .-.-.~-~i-.-'- -••-'•^^ '--r:-' JES^^'-^-Pr'^f-n
,i ,,v:J..:^i-rt~a;~-^:i:zr:: ;lww:^: i tsKS*i*i|3-!!i*A: i':ajffs,^J
-,-^ ':-:r^'s^, JiCi-f-yas r'; ?atri. 'Sf~ff^Wi
- -" "*^
El. 153.86 u . . * -" " - - "—~^ . , ..—.-.-.j™™., -: ' - . i*- ? ,.: .. -rn iniiifil i ' - ^ -^aSi*ifcjkj-^:-E
. , : .;- ^'^ss^sais^saiitiiii
Tuesday, January 12, 1932 (startdf^i^^^gii
Muskeg 1 ! , blacB ^/aTOt^s*™^ ' i.'f
Drillers fobtage 79
J
DRILL HOLE C-3 (No. 29) January 18, 1932
i) fi
i~ ^
t
DRILL HOLE C-4 (No. 37) January 20,-1932
0-1 Muskeg
1-4 Silty clay with pebbles
4 - 4'6" Sand
4'6"- 9 Gray plastic boulder clay
9-28 Grey sandy boulder clay drive casing to 28'
28 - 34 Grey sandy boulder clay sheet and drive casing
to 34'
34 - 44 Very sandy boulder clay from 40-44* Shoot and
drive casing to 44'
44 - 45 Grey plastic clay (Cret, or Inter.?)
45 - 47 Black boulder clay (reworked Cret.)
O 3 Muskeg
3 7 Silty clay with pebbles
7 18 Grey sandy boulder clay - drive casing to 18'
18 21 Grey boulder with a high ^ of 4 go of pebbles
21 32^ Grey plastic stoneless clay start to core at 21*6"
34- Greyish brown boulder clay Drive casing to 28'
34- 35 Black fire clay-cored
35 37i White silica sand-cored
39 Black fire clay-cored
39 - 39 '9" White silica sand-cored
39 '9"- 4-0 Black fire clay cored
4.0 - 51 Black fire clay cored
51 - 52 Lignite and black fire clay mixed cored
52 - 72 Lignite-chopped
El. 150*6
January 25, 1932
l
-7-
Muskeg
Silty clay
Blue grey plastic clay with pebbles
Grey sandy boulder clay
Gravel and clay mixed shoot and drive casing to 10'
Dark grey sandy boulder clay
Soft grey sandy boulder clay
Gravel sand and fragments of lignite
Shoot or drive casing to 39'
El. H7.4
142.12
January 29, 1932
0-2 Muskeg
2-12 Grey Sandy Boulder clay
12-23 Grey stoneless plastic clay
23-28 Dark grey sandy boulder clay. Shoot and drive casing
to 28'
28-32 Hard grey boulder clay-no caving
32-58 Lignite, hard woody
Note: 36-37^ Soft peaty lignite (no clay)
58-61 Black grey fire clay-cored 2' recovered
61-63 Black grey fire clay-cored l 1 recovered
Due to caving of peaty lignite at 36-37-^ the casing has to be
driven to 39' in order to close it off. Shot put down to
break-up boulder clay 28-32.
63-67^ Black fire clay-cored complete recovery
0-1 Muskeg
1-4 Sandy brown clay (loam)
4-17-1 Grey sandy boulder clay
17^-21 Gravel and sand-lignite fragments
21-28 Sandy boulder clay, shoot and drive casing to 20'
28-31 Boulder clay with some reworked black fire clay, shoot
and drive casing to 29 f
31-36 Grey plastic. No samples taken on account of gravel
contamination from above
36-37 Lignite shoot and drive casing to 37'
37-56 Lignite
56-59 Black fire clay with band of cream fire clay
February 2, 1932
February 3, 1932
February 4, 1932
31-41 Grey plastic clay shoot and drive casing to 39*
41-43 Hard sandy boulder clay-no large pebbles or boulders
43-46 Black grey fire clay-cored
46-47 Lignite-cored
47-56 Lignite-chopped-shout and drive casing to 49'
56-68 Lignite-chopped
68-75 Lignite-chopped
68-71-i peaty and earthy lignite
70-72i cored drive casing to 54'
75-77 Lignite-chopped
77-81 Black grey fire clay 77^-81 cored complete recovery
81-84 Black grey fire clay-cored complete recovery
84-86 t! tt tt tt "
tt "
It "
86-88 Green-grey cret, clay with bands of black brown
fire clay-cored
February 5, 1932
0-2 Muskeg
2-7 Yellow sandy clay or silt
7-13 Hard sandy boulder clay
13-16 Soft plastic boulder clay
16-20 Grey plastic clay, shoot and drive to 19 f
Take core 20-24 (sampled)
20-24 Grey plastic clay
24-36 n " " , shoot tend drive casing to 29 !
36-42 Boulder clay, shoot and drive casing to 39'
February 6, 1932
DRILL ''
i HOLE C-13 (H6.75) '
February'9, "1932
CW2 ,
'2*3'" Muskeg
Grey sand ,.v- ;: ''v
' :' -
3-10 Grey boulder clay
10-12 . -' Gravel '- Y V'
12-14 Sandy bo'ulder clay
1A-18 Sand and gravel,'^
18- 29 :. Gravel and sand lldtlt'a lew bands of
ing to
... .,.
Tvl"
&A^i'^-v-' '^'•'-j^':''~')^
^-' '•'- " hs : : l" J, ,- , '.' 'A' ' ' ' ' J '*" 'i'-' :'"'' '' ' *- - '' '''* ' -"-1" 1-"/1 "' ': ', : ;i' '. V- ^' .1- -^ •J'- r ' i- ' - *
''^
.. ,
-w-
PORTAGE MOVE f
Note, From points "A", "d", "e", chainage taken from lower
portion of blocks of ice on shore line.
-18-
PORTAGE- Outcrop A
(100' North of outcrop A)
Drill Hole P.I.
0-1 Muskeg
1-12 Yellow sandy clay
12-16 Gravel and sand
16-20 Hard sandy boulder clay shoot and drive
. casing to 19'
20-28 Hard sandy boulder clay. Just enough clay
to hold body together shoot and drive casing
to 28'
28-32 Sand- a few fragments of lignite. Drive casing
to 33'
32-52 Black to dark grey boulder clay. The powder
to break up boulders at 52
52-62 Very sandy black grey boulder clay.
Note: The sand in clay from 52-62 was hlgLf limestone and
half quartj,. Also a few fragments of dirt rock. The sand
grains nearly all angular or subangular.
PORTAGE - P2
March l, 1932
45-49 Sand and gravel- use powder to break up large
boulders
49-59 Grey sandy boulder clay
50-58 Hard, dark gray boulder clay. Shoot and drive
casing to 58
58-73 Dark grey boulder clay
73-74 i" " " n -cored
74-81 " " t! " -chopped
March 2, 1932
81-102 Sandy dark grey boulder clay, lignite fragments
102-104 Sand (silica and limestone) and lignite about
104-105 Sand-cored-See sample
105-112 Boulder, sand and lignite fragments
112-115 Grey Cret, clay-cored
115-117 Grey Cret, clay-cored
117-120 n tt n -cored
120-123 tt tt tt
123-1231 Very hard (sandstone, iron stone
123|r-124i r Sand-cored
124|-125i
1251-126
126-128 Sand and Kaolin-cored
128-129 Greenish grey cret, clay-cored
Drillers footage 130'
-zo-
PORTAGE - P3 (Outcrop-B)
March 3, 1932
0-6 Boulder clay and boulders
6-10 Fine grey sand ;
March 4, 1932 V ,
10-12 Grey sand fine ;
12-14 Black-grey fire clay-chopped Casing driven to
14-18 Black-grey fire clay-cored. 9" of core. Ream out
18-23 hole to obtain sample* IV of core i,
23-26 Black-grey fire clay-cored. Complete recovery* :--r:
26-31 Black-grey fire clay-cored complete recovery. ;
(possibly at31-32i Black grey fire clay-no core in barrel-Shell Of
pyrite concretion core barrel badly bent and smashed-Woodylignite
or) at 32^ -. -. . ;-. . - - ' , - : . : . - -' /••'. "-"4: ,-':..
32^-34 Lignite-woody and peaty-chopped . -,
34-40,r Peaty lignite-cored . 3 ,*
40f-43ir Black-grey fire clay-cored 2' bf core recovered
43i-46:r Black-grey fire clay-cored l* recovered ;fe ;
46f-50ir Black grey fire clay-cored (last 6* earthy lignite) fe ;
complete .- ' ' -'.' . ' : '.',- ;v ' ' '^'"^' '•'•^•.v;'V.-
50|-53i Earthy lignite-cored 2' of core (50^-51 clay and lignite)
53i-55 Woody lignite-no core in barrel* Very -hard at 55-bi1eak w;
end of core barrel. :
55-57 Hard woody lignite-chopped
57-59 Light grey to grey Cret, clay-chopped ; ,'*
Toronto, March 10, 1932
Fusion tests on clays taken from P3 ;
14'-23' cone 24
23'-38' cone 24
28'-32' cone 27
40'-46' cone 26
46'-50' cone 26
59'-62' cone 19
March 4, 1932 , ,,
59-62^ Light grey to grey cret, clay-cored complete tecogery
Light grey to grey cret, clay complete recovery
641-65 chopped
65-67 " " " " " " : cored complete recovery
Drillers footage68'
Black grey fire clay 12-32 -20'
Lignite 32^40i - 8'
Black grey fire clay 40^-57- 9i
Lignite 50-57 - 7
Light grey cret, clay 57-67- 10'
From drill hole surface to top of banto - 10'
PORTAGE - P4 (Outcrop C)
March 5, 1932
0-8 Yellow sandy clay
8-13 Hard yellow boulder clay Shoot-drife casing to 13 f
13-20 Gravel
March 7, 1932 ?
20-29 Hard sandy boulder clay with seams of sand and
gravel. Casing to 23* when piece breaks out. Pull
and put down new casing
29-40 Boulder clay (dark grey) with seams of sand and
gravel. Casing at 34 f * Fragments of lignite :
40-45 Dark grey boulder clay (reworked cret.)
45-47 " " " " -cored
47-51 n n n " -chopped
51-52-White silica sand (cret.)
52-56 Black silty clay no pebbles? possibly'reworked cret.
56-69 " " " - cored
69-70 Light grey silty cret, clay-cored
Drillers footage 71'
Outcrop C to drill hole P4 218'
Drill hole to slope of bank 110'
PORTAGE -P5 (200'Wof P3)
March 9, 1932
0-4 Yellow silty clay
4-10 Grey sand
10-18 Gravel and sand casing at 18 f
18-24 Black grey boulder clay shoot and drive to 24
24-35 Dark grey sandy boulder clay and lignite fragments
35-51 Very sandy grey boulder clay
51-52 Dark grey boulder clay-cored (reworked cret?)
52-55 Grey silty to sandy cret, clay no pebbles (reworked
cret.)
55-57 Grey silty clay-cored
Drillers' footage 30 r
Drill hole located on shore line at clay qutcrop 200' south of No. l
I5 f -20' towards bank from clay pit.
Floor of drill shack to water level - 4'l *5-t
" " " " " top of bank -25 f (Approximately)
Water level to top of clay pit 3f
Note Luke Potvin, Smith and Travers 1 foreman agreed to stop hole
at 30' and to accept 30' as footage for hole.
-25-.
0-4 Muskeg
4-4^ Silty clay , - :
44-12 Grey boulder clay : ;
12-18 Soft, grey boulder clay
18-20 Grey plastic clay , 'V
20-27 Grey boulder clay - ,:
27-28 Black fire clay and lignite. Shoot and drive casing
to 29' ' . ;.- ;-; : ; ; ' ' ; '. ' ' ". ' : ' : - ';
28-58 Lignite, woody and peaty drive casing to 33'
58-63 Grey to dark grey Cret, clay
Note 28-33 peaty and earthy lignite
60-63 Fusion cone V
0-3 Muskeg
3-4 Silty clay
4-10 Boulder clay
10-15 gravel ,
15-17 Boulder clay ,
17-26 Grey plastic clay
26-29 Grey boulder clay-casing to 28 r
29-38 " " w
39-41 Brownish black boulder clay. Shoot and drive casing
to 40'
41-44 Bark grey boulder clay
44-45 Black fire clay and lignite
45-48 Grey cret, clay-cored
Drive 2#' f lush- joint inside 3i to stop caving from
above — 47* of casing. Only one foot of clean cor a.
48-52 Grey cret, clay with bands of light grey clay-cored
52-56 Light grey and whitish grey cret, clay
Drillers footage 57 !
•27-
0-2 Muskeg
2-6 Silty clay
6-9 Grey boulder clay
9-12 Gravel with a little clay
12-25 Grey sandy boulder clay
25-4,7 Grey plastic clay (interglacial) casing drive to 49
47-55 Grey boulder clay
55-56 Boown boulder clay and lignite fragments
56-58 Black cret, clay and lignite
58-61 Black grey cret, clay
61-63 Lignite, woody and peaty-cored
63-69 " " " -chopped
69-74 " " " -cored
Coring tube-,broke off and was left in hole was fish it out
tomorrow. v; -
fei
'- , ' "- - 'V :" i,-;'. ' ' •''"' "~-:- :.?'"'.'~-~: tf-.'~f:'-?i''f-',' '"''l
Drillers footage 77
Footage
Drill hole C-12 60-631 Cone '* 18
C-14 41-45^ 1! 17
C-14 46-49 n 16
C-14 49-54 n 15
C-17 60-63 n 14
C-17 63-66 n 14
C-18 45-48 tt 17
•JO-
Overburden - 61 feet
Lignite - 14 feet
October 4, 1939
0-1 ~ Muskeg
1-7 Brown swamp clay
7-21 Sandy boulder clay
21-25 Grey plastic clay
October 5, 1939
25-39 Grey plastic clay
39-40 Lignite and dark grey cret, clay
40-63 Lignite
40-45 compressed peaty '
45-49 woody -
49-50 earthy and woody
50-63 hard woody
October 6, 1939
63-72 Brown cret, clay with rounded pebbles
72-75 Greenish grey cret, clay, some limestone pebbles
Overburden - 40 feet
Lignite - 23 feet
BORE HOLE No. 4 Elev. 154.99
October 6, 1939
0-3 Muskeg ,
3-7 Brey swamp clay ".
7-15 Bark grey boulder clay, very plastic-no large
boulders
October 7, 1939
15-32 Dark grey boulder clay, very plastic no large boulders
32-34 3Dark grey stoneless plastib Clay
3-4-40 Dark grey boulder clay, very plastic and similar to
reworked stoneless plastic clay.
40-45 Lignite
40-41 Earthy lignite ; . ,
October 9, 1939
45-72 Lignite
40-45^ Peaty, earthy and woody
50-52 woody
52-60 Peaty, earth and woody
60-66 Woody, hard.
66-67 Earthy, sdmie brown clay
67-72 Hard woody
72-73 Black cret, clay and lignite
73-75 Black grey cret, clay
75-81 Grey cret, clay
81-82 Greenish-grey cret, clay
Overburden - 40 1
Lignite - 32'
BORE HOLE NO 5. Elv. 154.03
Overburden 36'
Lignite 36-43 - 7'
46-60 -14'
Lignite 21'
-it-
Overburden 54'
Lignite 7*
-37-
0-3 Muskeg
3-5 Swamp clay . ' ;, " "
5-11 Sandy boulder clay '
11-25 Grey plastic stoneless clay
25-3-4 Grey sandy boulder clay : ; "
34-36 Limestone boulder :
36-37 Brown boulder clay \,
37-47 Brown, reworked cret, clay and lignite and boulder
clay, see sample B.No.8 ^ , ' '
Overburden
Lignite 17 '
-H-
Overburden 53'
Lignite 53-60 -7'
Lignite 62-72 -10' 17'
V, -yo-
Overburden 32'
Lignite 32-50 - 18'
•'.T-
BORE HOLE No., 12
Overburden 21
Lignite 21-28 - l
30-39 -9
Lignite 16'
BORE HOLE No. 13 ^ -
- ' , .r "V '*
Elev i,'140*57
October 27, 1939 - '' : ' ; ' 'v'/V'"" ;: **''":'^.. i:^/ - : ' "' -'
' "' ' ' .'. ' *., " ' ' -'' .': ; :if'
28- 38Reworked cr et. clay, boulder s \'-. some lignite
possibly a 2 1 seam of,lignite ;at 36 1
38-44 Grey xiret. clay ;.; - - ;
44-45 Light grey cret, clay ^ ; ;? '
No lignite ; - \' ,^. ,,^' ., ;: ;.v- ; ;:'v:;".^.-" [.^-' : . \'
BORE HOLJ! No.1-4
Overburden 16 T
Lignite 16-31 - 15
Lignite 39-55 - 16
Lignite 31'
BORE HOLE UO ; 15,
, .••'•••j-^..--.^.;- - .••-'f /-'- .-- - - ••
'Started October 28
'
October 28, 1939
0-2 Muskeg ' -
2-6 Brovm swamp clay
6-23 Boulderclay
October 30, 1939 -.
, " . -.. . . -"-
23-26 Plastic bedded stoneless ; grey ;|?lay r ; '
26-38 Hard sandy boulder Clay. . '•' : '---".^J^.';v,;'v:
28-56 Lignite - .- . -;-. V'V-c- ^^Q^ii^t '.-fi*' t ,
J -|-,Er"
at 38' earthy lignite on -' bit col^l?:? of
brown to black, bailor s ample -lignite; :Mf?.
'iA- -
A"*! -nV'.'
November l, 1939 A *V :;
61-79 Lignite 61' earthy on, bif
61-66-soft driliing-fartny snfl- peaty V
67-76-hard solid drilling-wbody
77-79-softer drilling-ea3?1;hy p^aty afid
at 79 f dirty sample (cave)~
79-80 Dark grey plastic clay
N.B. Measuring stick being ;, 'sKoi't •2*)i;6jf-'^e':^
Overburden 61 f
Lignite 18
BORE HOLE No. 17 Elevi 146.95
,- -, -
Started-Novejnbfcr 1-2 p'nj
Finished-November 3-11 ja
November l, 1939
0-1 Muskeg
1-6 Swamp clay
6-28 Sandy boulder clay
November 2, 1939
28-40 Stoneless plastic clay 28* softer^drilling t
28-32 Stoneless plastic 'i- ; j : ;-
32-35 water-grey with streaks of i darker .grey ' J
bit-stoneless-llght and dark beds ; ;
sludge-stoneless plastic and some boulder clay
soft drilling . . .'.,; ;"'- (' ' .••V^: t : : -X- . ' :: '-. :,u,...V
35-37.5 water-streaked - s .
sludge-bedded Stoneless ; , . ^ " ;
harder drilling at 37* i ;: *
40 ! -a plug-cave ,- - . :. ;' - s ' : 1S -;,/'
bit sample-bedded Stoneless i
sludge-bedded s toneless ^ ^ ; x' j '
water-streaked \. 5- .T '
feel-softer drilling ; -;, ^
drove pipe at 35 and 40' -
40-52 Sandy boulder clay .; - -- " .
42' hard drilling hf , '
water-grey bit-boulder clay f } , ,- /r
feel (cable) -hard drilling) sludge-boulder clay and
plastic Stoneless 48* arid 52 ha:fdr sandy boul^e* c!6y
52-78' Plastic boulder clay ,' , f
58' ha^rd drilling ' i , :;
water-darker grey than sandy boulder clay 7 - v -.
sludge-plastic thick boulde? Cla^j spa^l sharp
bit-clean feel-hard sharp'
78-84 Lignite-78' black plastic clay^
82' hard woody at end of run '
water- black j bailor-hard woody 3 tbit-^clean '
84-86 Cretaceous clay ^^ ,-
overburden -75
Lignite 6 .'. ' ;\- ,
N.B. checked depth of hole-found assumed hole
2.5 ! deeper than clieck measurement J -
Log of hole adjusted to correct measurement
BORE HOLE . No . 18
Started Novejsper
November 1939
26-28 Plastic stoneless clay ^-x". ; .
20*- a little plastic stdnel©ss*sOBi^
29-
caj/e a atlittle
27' plastic stoneless-sdma
, ':'--*-\\''''-\~--\. clay'
32.5 bedded stoneless clay -
35.5 bedded stoneless clay JSOBIIBi '.e'a^
water streaked grey j bit sandy btfuldec1- 'Sbfii '*trill-*
ing ' -/ : . ; :,-;^;;.- ;,,;.^
3B-51 Boulder clay . ; -,-.-.';. :r x; .- .••v\.'-'--- i^^-.;i : :,^: ,, :;
4-0 ! sand on bottom of'bit | sides-pfasiic arid
clay hard drilling-hole inaf||i|'wate^
4-5' Sandy boulder clay-hard
50' dark plastic clay BM
water-dark brown; bit-clean
51-72 Lignite 53 ! lignite and 'dark
water-brown; bit clean; sludge^lgif|;|^fia^d -driiilng
55 f -softer drilling 60 ' earthy in
plastic clay. ' ' . - , '-'-. ,. .",--.
62' sample largely earthy;
65' first good clean sample 70*
n,* ^ rt 72 ' softer drilling; tested
72-78 Dark grey plastic clay " :
at 78 green cret. ' ;, : * ; .-';"
Overburden 51 ' - •••' !
Lignite 21- .- ".'.
-Ut-
November 6. 1939
0-2 Muskeg
2-7 Brown silty clay
7-12 Grey clay (Marine?)
12-14- Very sandy boulder clay
18-32 Grey boulder clay, sand and gravel. Much caving.
Drive pipe to 39'
32-45 Free running sand (find) Drive pipe to 44*
November 7, 1939
45-48 Fine sand. Drive pipe to 50'
48-67 Grey plastic stoneless clay
67-71 Grey sandy boulder clay
71-84 Lignite, woody and compressed peaty
84-92 Dark grey cret. clay, some lignite and limestone
fragments
92-95 Grey cret, clay, with last foot showing streaks of
light grey cret, clay
overburden 71 !
Lignite 13'
BORE HOLE No. 20 Elev. 166.41
November 8, 1939
0-7 Brown sandy clay-no large boulders
7-15 Soft grey boulder clay
15-28 Sandy boulder clay
28-43 Grey plastic stoneless clay
43-49 Hard grey boulder clay
49-60 Lignite, woody and peaty
November 9, 1939
' 60-62 Lignite, peaty and earthy
62-64 Grey cret, clay and lignite
64-83 Lignite
64-70 Peaty and earthy
70-83 Woody and peaty
83-84 Black cret, clay and lignite
84-88 Dark cret, clay
88-90 Grey cret, clay
Overburden 49'
Lignite 49-62 - 13
64-83 - 19'
Lignite 32'
-50-
overburden 78'
Lignite 78-84 - 6'
- s2 "
Elev. 168.35
Overburden 63 T
Lignite 63-71 - 8'
BORE HOLE No. 24
Elev. 168.63
Overburden 56'
Lignite 56-74 - 18
75-90 - li
Lignite 33*
Lignite seam did not cave and samples were clean
-Sfe-
December l, 1939
94-97 Lignite, woody and peaty
97-98 Black-grey cret, clay, some lignite
98~ib05 Grey to light grey cret, clay
Overburden 81'
Lignite 81-97 - 16'
-w-
December l, 1939
0-1 Muskeg
1-6 Brown silty clay
6-12 Grey marine clay
12-20 Grey sandy boulder clay, very easy drilling
December 2, 1939
20-35 Grey sandy boulder clay ^ '
35-^3 Grey plastic clay (interglacial)
53-60 Grey sandy boulder clay
60-65 Lignite, woody and peaty ,-
65-67 Lignite, eathy with a little grey silty clay
67-79 Lignite, woody
79-80 Lignite, peaty, some earthy
80-84 Lignite, woody and peaty
84-85 Lignite, peaty and earthy
December 4, 1939
85-86 Lignite, peaty and earthy
86-90 Chocolate - grey cret, clay
90-95 Grey to light grey cret, clay
Overburden - 60'
Lignite 60-86 - 26*
BORE HOLE No. 30
Elev. 156.49
December 4, 1939
0-6 Brown silty clay
6-19 Grey sandy boulder clay
19-25 Sand, some clay
December 5, 1939
25-61 Grey sandy boulder clay
61-62 Nest of boulders
62-66 Grey sandy boulder clay
66-75 Lignite, woody and peaty
December 6, 1939
75-32 Lignite, woody and peaty
82-83 Black clay and lignite
83-88 Dark grey cret, clay
88-90 Grey to light grey clay
Overburden - 66 !
Lignite 66-82 - 16
BORE HOLE No. 31
Elev. 153.70
December 6, 1939
0-2 Muskeg
2-8 Silty clay
8-20 Sandy boulder clay
December 7, 1939
20-46 Sandy boulder clay. Pipe at 43 ! -bed of boulders
at 42* and 46'. Through boulders at 46'
46-57 Lignite
46-48 earthy and peaty
48-57 woody and some peaty
57-64 Black to dark grey cret, clay
64-65 Greenish-grey cret, clay
Overburden 46'
Lignite 46-57 - 11*
BORE HOLE No. 32
Elev. 153.49
December 7, 1939
0-3 Muskeg
3-10 Swamp clay
December 8, 1939
10-30 Boulder clay
Nest of boulders at 12 - 15'
Grey plastic stoneless clay on bailer at 30 !
30-33 Plastic boulder clay, much of it stoneless,. no
evidence of bedding ,
38-69 Boulder clay, some gravel at 49 f
69-81 Lignite
69-72 earthy and peaty
72-79 woody
79-81 woody, some earthy bit sticky
December 9, 1939
81-82 Dark grey cret, clay, some lignite
82-85 Dark grey cret, clay
85-89 Light grey clay at 89. Dark grey cret.- clay
Overburden 69'
Lignite 69'-81' - 12'
BORE HOLE NO 33 Elev. 151.84
December 9, 1939
0-3 Muskeg
3-8 Swamp clay
8-44 Boulder clay, some s,and at 15'
Overburden 56'
Lignite 56-70 - 14'
-M-
Overburden - 48 T
Lignite 48-70 - 22'
BORE HOLE # 35
Overburden 62'
Lignite 62-77 r 15 f
-US-
BORE HOEE # 36
Overburden 67*
Lignite 67-83 ~ l6 f
Footage September 26, 1939-December 19, 1939 2902*
No. of working shifts 73
Averyage per shift 39.7'
BORE HOLE #37 ' .
Start 11t00 a.mt
January 11, 1940
0-1 Black muck
1-8 Grey-brown swamp clay
8-17 Grey boulder clay
17-30 Soft grey sandy boulder clay
30-35 Hard sandy boulder clay Pipe at 31'
January 12, 1940
35-38 Hard sandy boulder clay
38-51 Very sandy boulder clay
51-58 Hard sandy boulder clay
58-60 aravel
Pipe at 60'
January 13, 1940
60-63 Gravel and sand
63-75 Lignite
63-65 peaty and earthy
65-73 woody
73-75 peaty and earthy i
75-76 Black cret, clay and lignite
76-80 Dark grey cret, clay becoming lighter from 78'-80*
Pipe at 66'
Overburden 63*
Lignite 63'-75' - 12'
BORE HOLE #38
Pipe at 66*
Overburden 65*
Cret, clay at 65
Lignite-none
BORE HOLE # 39
0-3 Muskeg
3-10 Swamp clay
10-19 Grey boulder clay
19-20 Boulders
^6-2^20=20 Plastic clay
28-35 Grey sandy boulder clay Piperat 19'
January 18, 1940
35-52 Grey sandy boulder clay
52-54 Gravel, some clay
54-55 Grey plastic clay and earthy lignite
55-78 Lignite, woody and peaty
78-83 Dark grey cret, clay
83-85 Grey cret, clay
19* of pipe in hole and recovered
Overburden 55*
Lignite 55-78 s 23'
BORE HOLE # 40
BORE HOLE # 41
Overburden 64'
Lignite 64-89 - 25*
-•71-
Bore Hole # 42
BORE HOLE # 43
92-96 Lignite
94-96 Peaty and earthy
96-97 Black grey cret, clay
97-100 Grey cret, clay 77' of pipe
Overburden 81'
Lignite 81-96 - 15'
-71-
BORE HOLE,#44
N.B. 68-76 hole caving badly lignite sample salted .and unsatisfactory*
Pipe drive to 76' . . ; cr' r . ;^, : -'./V ;'^.'••;..\."; :;-,;\ : v:v :-';V.
' ' ' \,-- "" :' . •..'•5 ;'*";? '.v*; s.'' ' ( :. •*':''.-. ;-': "j.^-/ '
' '-"' :" . "' -J.;" :*M..' -. ' "' "i ! ,;
' ' ' ' . -' ' ,' . . '- - -'-, ."'''-'^("v -'" "' "- ' *s*'"
' '. -. ,tV . - ' -' - ' ' '-si f -- - '
" ' ' ": - - ^ A '.'' :' - "- -' '''.i ' '' ^ -, !"'- ' ' , :'
'•- -'': ''""' ' !~'V'^'"--:/^ ;^.'- : .:'' V - ,-,; '"-/ '.-;" ^^:J"
MMllyfiff -t
BORE HOLE •s;: -m
' ''"-
*?eT)ruary 5, 4*00' ?p.a.
February 3, 1940
Overburden 82
Lignite 21
V.***',.
BOREHOLE 46
Started p.m.
inished
Pipe 6?
**iX •'•-Y-: *;
,".?*'--. . ,,;.Y '..fi . '
j,f-' -'^-""V ice
.. ;. .. . . ".-,^}. J * "
70-79 Boulder clay and some reworked ejfeipeous just aboTe ^eaifc (ligait^
79-98 Lignite 79-83 Earthy peaty and itep^ - - v, ^ : ^...V.-^'^Y
83-93 Woody and peaty - -j: v-* ^:,.^--'.-...----'.. r,v-.v^-*.. .-' ' ' -
93-95 Woody-earthy-peaty v^: : ; ':
95-98 Woody and earthy :, \ -- :ii ;
98-104 Cretaceous clay -: ^^ ; f. ; -,, : V;",
Overburden 79
Lignite 19
BORE HOLE .47
Overburden 70
Lignite 70-84
85-97 26
BORE HOLE 48
Overburden 73
Lignite 73-84
84-97 23'
-78-
BORE HOLE 49
Started February 14
Finished February 15
Pipe 67
0-3 Muskeg
3-12 Marine clay
12-30 Boulder clay with sand and gravel beds
Overburden 94
Lignite 9
Overburden 74
Lignite 19
l
-80-
BORE HOLE 51
Started February 20
Finished February 22
Pipe 48*
Overburdne 70
Lignite 13
J
-81-
BORE HOLE' 52
Started February 23
Finished February 26
Pipe
Overburden 70
Lignite 13
-82-
BORE HOLE 53
Started February 29
Finished March 4
Pipe ?8
March 2, 1940
55-59 Dark gray clay and lignite
59-71 Reworked zone-gravel and lignite
71-89 Lignite
71-75 earthy, peaty, woody
^5-83 woody and peaty
83-89 woody and peaty
89-94 Cretaceous clay
Overburden 71
Lignite 18
'-IH-
BORE HOLE 55
Started March 5,
Finished March 7,
Pipe 83'.
March 5, 1940
0-3 Muskeg
3-9 Marine clay
9-11 Gravel
11-19 Boulder clay
March 6, 1940
19-35 Boulder clay
35-40 Very sandy (boulder clay?) sharp with lignite fragments
March 7, 1940
52-65 Grey sand and gravel
65-71 Sandy boulder clay
71-83 Grey sand (free running)
83 * Lignite
-45-
BORE HOLE 56
March 8, 1940
0-3 Muskeg
3-9 Marine clay
9-20 Sand and gravel
20-42 Sandy boulder clay
42-48 Plastic stoneless clay
48-58 Plastic boulder clay
Kerch 9, 1940
58-68 Clay-gravel-lignite {lignite water worn)
68-79 Lignite-water black yet samples still salted?
carrying gravel and clay
79-85 Grey clay
Overburden 68
Lignite 68-79 - 11
BORE HOLE 57
Overburden 72
Lignite 72-83 - 11
-B7-
BORE HOLE 58
No lignite seam
-88-
BORE HOLE 59
No lignite seam
-85-
BORE HOLE 60
0-3 Muskeg
3-9 Marine clay
9-12 Sand and boulder clay
12-21 Boulder clay
March 2© , 1940
21-40 Boulder clay (repatts March 20-1:30 p.m.)
{ March 21-2:00 p.m.)
March 21, 1940
Overburden 58
Lignite 58-73 ~ 15
BORE HOLE 6l
NO LIGNITE
-41-
BORE HOLE 62
Overburden 59
Lignite 15
BORE HOLE 63
April 2, 1940
Overburden 64
Lignite 17
BORE HOEE 64
April 5, 1940
0-3 Muskeg
3-9 Swamp Clay
9-10 Boulders and clay (some boulders in pipe) '
10-1? Marine clay
17-26 Boulder clay
26-27 Boulders
27-38 Plastic bedded boulder clay {limestone pebbles?)
38-44 Sandy boulder clay and gravel?
April 6, 1940 . .
44-58 Sandy boulder clay and gravel
48-59 Coarse gravel and some boulder clay
59-83 Lignite
59-64 earthy and peaty (soft drilling)
64-70 earthy,?oody and peaty
70-75 woody-peaty earthy harder drilling-a little dark grey clay
in sample (parting?) l 1
75-83 woody and peaty hard drilling
83-87 Dark grey cretaceous clay
Overburden 59
Lignite 59-74 - 15
75-83 - J.
BORE HOLE 65
April 8, 1940
0-3 Muskeg
3-10 Swamp clay
10-1? Marine
17-20 Boulder
20-25 Sand
25-32 Plastic boulder clay
April 9, 1940
32-36 Sand and gravel
36-53 Very sandy boulder clay 45-53 appears to be fine sand
53-62 Ve y sandy boulder clay
62-76 Plastic boulder clay
76-82 Gravel and sandy boulder clay?
82-86 Dark carbonaceous clay and gravel
86-90 Grey clay cret.
90-92 Green cretaceous clay
No lignite
BORE HOLE 66
Overburden 87
Lignite 87-96-9
97-109-12 21
-Ifc-
BORE HOLE 6?
April 15
0-3 Muskeg
3-9 Marine Clay (in swamp clay)
9-15 Probably marine clay and some carbonaceous bed
and gravej. boulders at 9*
15-20 Sand and gravel
20-30 Very sandy boulder clay and sand
30-43 Plastic bedded boulder clay
43-44 Sandy clay-no boulders-some bedding
April 16
46-51 Sand and gravel-may be very sandy boulder clay
51-71 Sand and gravel
71-78 Sandy boulder clay
April 17
78-97 Sandy boulder clay
BORE HOLE 68
BORE HOLE 69
April 22
0-3 Muskeg
3-9 Swamp clay (sandy clay)
9-14 Marine clay
14-29 Plastic boulder clay
29-41 Boulder clay-largely boulders with some sand and clay
41-46 Gravel (may be coarse boulder clay)
46-65 Boulder clay-very coarse appears to be almost a gravel?
May 9
65-70 Boulder clay (much sand and pebbles)
70-73 Sand and gravel with earthy lignite
May 10
73-87 Lignite
73-78 earthy and peaty
78-85 woody peaty .and some earthy
at 85' water color dark grey probably due to parting
May 11
85-87 woody with gravel at bottom of hole may be cave. Water
worn carries jaspers, g.si, limestones and quartz
87-90 Grey clay
Overburden 73
Lignite 14
BORE HOLE ?0
May 11
0-3 Muskeg
3-8 Marine clay
8-18 Plastic boulder clay
May 13
18-30 Plastic boulder clay .
30-48 Sandy boulder clay
May 14 .
61-48 Sandy boulder clay
May 15
61-67 Sand and boulder clay
May 16
Drilled -| day
67-73 Sand and boulder clay
May 17
Overburden 76
Lignite 14
-100-
BORE HOLE 71
May 18
0-3 Muskeg '
3-8 Swamp clay
8-12 Marine clay
12-20 Boulder clay-some sand
May 19
20-31 Boulder clay
May 20
31-A5 Boulder clay
45-55 Plastic bedded clay
55-58 Sandy boulder clay at 58 some sand
May 21
58-75 Sand} boulder clay
75-91 Lignite-with doubtful parting
75-79 Earthy and peaty some woody
79-83 Earthy peaty woody
82-83 Clay a little dark grey clay at 83
83-91 Woody and peaty
91-97 Dark grey cretaceous
Overburden 75
Lignite 7^-82 7
83-91 8 15
-101-
BORE HOLE 72
May 22
0-2 Muskeg
2-# Swamp clay
6-12 Boulder clay
12-14 Sand and lignite
14-16 Lignite
16-18 Sand and lignite (sand cave?)
May 23
18-31 Lignite
31-40 Fine clay (parting)
40-45 Lignite
45-47 Dark grey clay
Overburden 14?
Lignite 14-31 17
40-45 JL 22?
Driller reports sand seams in lignite
-102-
BORE HOLE 73
May 2k
0-2 Muskeg
2-4 Swamp clay marine?
4-26 Boulder clay
26-54 Lignite
May 2?
54-65 Grey clay
May 28 Polling pipe
Overburden 26
Lignite 28
BORE HOLE 74
May 28
0-2 Muskeg
2-17 Boulder clay
17-18 Lignite
May 29
18-36 Dark grey cretaceous clay
36-52 Lignite
52-70 Dark grey cretaceous clay
Overburden 36
Lignite 16
-IOH-
BORE HCLE 75
May 29
0-2 Mufckeg
2-30 Boulder Clay
Kay 30
Overburden 35
Lignite l?
BORE HOLE ?6 f
- l
May 31
Overburden 35
Lignite
BORE HOLE 7?
'June 3
0-1 Muskeg
1-4 Swamp clay
4-26 Boulder clay
26-27 Lignite
27-33 Grey cretaceous clay
33-51 Lignite
51-53 l Grey cretaceous clay
June 4
Morningapulling pipe
Overburden 33
Lignite 18
-107-
BORE HOLE ?8
June 8
0-2 Muskeg . -•/•-•--; ' ^;: 'v:^U,- ,,\; V'- ;
2-10 Swamp clay " ) ; ; ",;T* f ' - /*
10-18 Light grey boulder clay-sotae doubtful bedded, plastic
* ' J ' . ' - ' ' " ' l ' ' ' "' -
June 10 j' 'V*...
. .. . - |- . . i . -. - -r-.-hf , ^ . - -\
Overburden 33
Lignite 33-39 6
40-52 12 18
BORE HOLE 79
June 11
0-2 Muskeg ; , , - ;!,
2-6 Silty clay : - : . \':
6-16 Hard boulder clay ' r
16-20 Sandy boulder clay, sand gravel; end bouldefrs
20-22 Lignite, some sand " ' -^
June 12 •••- ' ' ? , '
22-59 Lignite-woody ? ,, v[
22-33 woody " vt ' i;--: " A'
33-35 earthy \
35-42 woody
42-43 earthy - ; ;i
43-46 hard woody .f
June 13 46-47 hard woody "^ '
47-49 earthy with small pebbles "l
49-58 woody ' ' .Y-" 1
58-59 earthy
59-60 Black cretaceous clay
60-62 Dark grey cretaceous clay
Overburden 22 V A
Lignite 37 :, ;, ;, :
-Idfl-
BORE HOLE 80
June 14
0-4 Muskeg
4-8 Swamp clay and sand
8-12 Boulder clay ""
12-30 Plastic clay and some boulders
30-35 Hard boulder clay and sand
June 15
35-45 Hard boulder clay
45-57 Dark grey cretaceou s clay
57-70 Green cretaceous
No Lignite
-iio-
BORE HOLE 81
June 17
0-2 Muskeg
2-10 Swamp clay
10-12 Boulder clay
f-...
i June 18
12-28 Boulder clay
28-35 Boulder clay end sand,
35-5® Plastic boulder olay mfta-sa*
June 19
fc.f-.' ^, - ;- :
f."-'--. 50-56 Plastic boulder eJ^y va.nd j^iiaadH^v'
f 56-72 Lignite and clay :
56-60 lignite *and clay
69-64 woody and peaty
65-72 woody, compressed peaty
72-73 Black grey cret, clay
73-75 Grey cret, clay
75-77 Grey cret, clay
Overburden 56
Lignite 16
-III-
BORE HOLE 82
June 21
0-2 Muskeg
2fi6 Swamp clay
6-12 Swamp clay and sand
June 22
14-26 Hard boulder clay
26-32 Sandy boulder clay
32-40 Hard boulder dlay
June 24
BORE HOLE
Overburden - 63
Lignite 63-67 - 4
Pipe 57'
0 N A K A TUT A N A J, I G ,N I T E
74' of casing
Overburden 40*
Lignite {40-66 - 26 391
(75-88 :
- US-
BORE HOLE 86
August l
6-2 Muskeg
2-8 Marine Clay
8-2? Boulder Clay
27-30 Hard Boulder clay SOBS fine sand.
30-33 Dark Grey Clay suggestion of bedding -:;
33-35 Sand and clay with fragments of lignite
- V . ' : -" ' - . ; ' Vt'r '"
Overburden - 48* ;
Overburden -55
Lignite 55-72 s 17
77-95 s. 18
. ..;:-:. J^
-m-
BORE HOLE 88
Started August 15
Finished August 19
0-3 Muskeg
3-12 Marine Clay
12-30 Sandy Boulder Clay
30-35 Sand and Gravel
/J^-w**
35-38 Silica, enad1 with some dark carbonaceous material
38-42 Dark Grey Clay (fire clay)
42-47 Lignite
47-60 Dark Grey Clay (fire clay) some earthy lignite 58-60
69-73 Lignite-woody
Overburden - 60
Lignite 60-73 ~ 13
78-95 s 12.
-llft-
Hole 89
0-2 Muskeg
2-8 Marine Clay
8-19 Boulder Clay
19-21 Boulder Clay bed of boulders.
21-33 Boulder Clay at 33 some carbonaceous material *
33-40 Dark Grey boulder clay considerable carbonaceous material
probably reworked fire clay
40-57 Dark Grey clay with th*n beds of green cretaceous
60-70 Dark Grey Clay - fragments of lignite
70-87 Lignite
87-92 Dark grey clay at 92 green cretaceous
Overburden 70
Lignite 17
-m-
BORE HOLE 90 September 23
0-2 Muskeg
2-8 Marine Clay
8-20 Plastic Boulder Clay
20-30 " n
30-35 Sand
35-42 Bedded Plastic Clay
42-47 Dark Grey Boulder do.
47-52 Sand and Gravel
52-55 Plastic Clay
55-61 Dark grey to Black Boulder Clay
61-67 Sand and Gravel
67-73 Dark grey clay with sand and gravel (reworked)
73-75 with lignite fragments
75-77 Coarser gravel some clay
77-82 Sand
No lignite
- 12.0-
BORE HOLE 91
October 4
0-3 Muskefe
3-10 Marine Clay
10-14 Boulder Clay
14-1? Sandy Boulder Clay
17-23 Dark grey carbonaceous clay (boulder clay)
23-26 Grey boulder clay
26-32 Dark grey carbonaceous clay and sand
32-36 Grey sandy boulder clay
36-39 Dark grey sandy clay some carbonaceous material
and lignite
39-43 Sand and gravel (some silt) dark grey sandy clay at 43
43-54 " " "
October 5
54-57 Dark grey clay and lignite
57-58 Earthy lignite and some clay
58-61 Lignite - earthy
61-65 M - woody and peaty
65-73 " - woody
73-76 Earthy - woody - peaty mixed with parting clay - parting clay
at ?6 f
76-79 Lignite - earthy - some clay
79-90 Lignite - woody and peaty :
October 7
90-100 Dark grey clay (Cretaceous)
Overburden 58
Lignite 58-73 s 15
76-90 s 14,
I
-111-
Bore Hole 92
October 7, 1940
0-4 Muskeg
4-9 Marine clay
H-16 Hart boulder clay
October 8
16-35 Soft boulder clay
35-37 Coarse boulder clay
37-40 Fine sand-some gravel
40-49 Fine sand-fast drilling
49-55 Blue plastic clay
55-63 Hard boulder clay
63-66| Black clay some boulder and lignite
October 9
66|-68 Lignite and black clay
68-77 Earthy lignite
77-80 Black clay
80-83 Black clay-some boulders
October 10
83-85 Black clay-some gravel
85-87 Fine sand-some clay
Overburden 68' L:0:: 1:7*5
Lignite 9'
Bore Hole 93
October 11
0-3 Muskeg
3-12 Marine Clay
12-25 Boulder Clay
25-35 Fine Sand
35-41 Coarser gravel and sand
41-53 Gravel (probably boulder clay)
53-57 Hard Boulder Clay
57-60 Lignite - earthy
60-63 Lignite - earthy, woody and peaty
63-67 Lignite - earthy, woody and peaty
67-78 Lignite - earthy, woody and peaty
78-79 Parting clay - no lignite
79-82 Parting clay {some gravel-cave?)
82-8? Parting clay and lignite
87-95 Lignite - hard woody
95-97 Black clay and lignite
97-103 Black clay
103-105 Dark grey clay
105-110 Grey Clay
Overburden 57
Lignite 57-78 s 21 ^
87-95 c J* 29
October 18
0-3 Muskeg
3-8 Marine Clay
8-20 Fine sand
20-25 Fine Sand some gravel
25-30 Grey boulder clay
36-35 Grey boulder clay hard drilling
35-48 Sand
48-50 Grey boulder clay - hard drilling
50-57 w n w nw
57-60 Lignite earthy - some woody
60-66 Lignite hard woody
66-70 Lignite earthy and woody soft drill
•^60-81 Lignite woody and peaty - earthy
81-87 Earthy Lignite some clay soft drilling
87-90 Lignite - earthy and woody
90-92 Lignite - some clay at 92 f
92-98 Black-grey clay (Cretaceous)
98-102 Grey clay - Cretaceous
Overburden 57
Lignite 35
Doubtful parting at 01'
Tractor driver spilled core-box while bring it to camp.
BORE HOLE 95
Started October 22 It00 p.m.
Finished October 24 12:00 noon
Overburden 45
Lignite 45-70 s 25
79-89 s 10
-125-
BORE HOLE 96
Muskeg
3^-8 Murine clay
8-20 Gray Boulder clay
20-34 Gray boulder clay (soft drilling)
34-37 Dark brown clay and fine sand
37-43 Silica sand
43-47 Coarse gravel and sand
47-57 Boulder clay (hard drilling)
57-60 Earthy and woody lignite
60-69 Hard woody lignite
69-74 Hard woody lignite - some earthy
74-78 Black fire clay and earthy lignite
78-81 Peaty and woody lignite some clay
81-88 Hardy woody - some earthy
88-90 Earthy lignite
90-95 Black clay (fire)
95-101 Black gray clay (fire) cretaceous clay
Overburden 57'
Lignite 2?'
Clay 4f Lignite 39'
Lignite ;. 12 f
BORE HOLE 97
BORE HOLE 98
November l, 1940
0-3 Muskeg
3-8 Murine clay
8-1? Gray boulder clay
17-18 Coarse gravel and sand
18-20 Coarse gravel and some clay
20-23 Coarse gravel
23-26 Gravel and fine sand - some clay
26-31 Coarse gravel and sand
November 2, 1940
31-49 Plastic bldr. clay (hard drilling)
49-61 Plastic bldr. clay (fair drilling)
61-64 Plastic bldr. clay - fine sand (fair drilling)
64-67 Dark sand and clay (soft drilling)
67-68 Bark sand and clay - some lignite
68-70 Lignite - hard, woody - some earthy
November 4, 1940
70-73 Lignite - hard, woody
73-85 Lignite - earthy and woody
85-88 Black fire clay - some lignite.
88-90 Black fire clay
90-103 Light gray clay
Overburden 68
Lignite l? L:0: 1:4
-JZ8-
BORE HOLE 99
November 6, 1940
0-3 Muskeg
November 7, 1940
3-10 Marine clay
10-14 Gray boulder clay and gravel
14-16 Coarse gravel
16-19 Boulder clay and gravel
19-29 Fine sand and gravel black clay
29-31 Dark brown sand some clay
31-37 Sandy boulder clay
37-42 Sandy boulder clay
42-45 Lignite - earthy
45-52 Lignite earthy and woody
November 8, 1940
52-66 Lignite earthy and woody (clay in last 6?)
66-67 Earthy lignite and clay
67-69 Black fire clay
69-71 Lignite - earthy and woody
71-74 Lignite earthy, woody and peaty .
74-84 Lignite earthy and woody (clay atrke in H 30)
84-90 Black fire clay cretaceous
90-95 Light gray clay
Lignite 15
-121-
BORE HOLE 100
Started November 9, 10:05 a.m.
Finished November 14
November 9, 1940
0-3.5 Muskeg
3.5-7.5 Silty murine clay
7.5-10 GraveJ (bed at bottom of murine clay
Boulder clay-gray
10-11 Boulders
11-17 Plastic boulder clay
17-25 Very plastic boulder clay gray
25-30 Plastic clay - sand and gravel gray
30-32 Silica sand p gray
32-34 Very fine silty boulder clay gray
34-37 Sticky-sandy gray boulder clay
37-40 Hard dark gray boulder clay
November 11, 1940
40-47 Gravel and very fine silt
47-53 Dark gray boulder clay
53-55 Dark gray quick sand - water
November 12, 1940
55-66 Gray boulder clay - coarse gravel water
66-70 Boulder clay - slightly carbonaceous
76-71 Clay and lignite
71-74 Lignite - earthy and woody
74-77 Lignite - mostly woody
77-80 Lignite - peaty and woody
80-83 Lignite - earthy and woody
83-89 Lignite - woody
November 13, 1940
89-91 Gray fire clay
November 14, 1940
91-100 Lignite - woody
100-101 Earthy lignite and clay
101-104 Dark gray plastic fire clay cretaceous
104-107 Light gray plastic clay
Overburden 71* Lignite 27'
Lignite 18'
Clay 2' L:0::l:2.7
Lignite 9'
-rjo-
BORE HOLE 102
December 5, 1940
0-4 Muskeg
4-10 Marine Clay - Brown
10-1? Very fine Black Clay
17-23 Sandy Black Clay
23-25 Sandy gravel and black clay
25-29 Gray black clay
29-32 Darker black clay
32-34 Fine black clay and gravel
December 6, 1940
34-36 Fine black clay and gravel
36*38 Very plastic gray clay - No boulders
38-41 Fine plastic gray clay - No boulders
41-43 Fine plastic gray clay - No boulders
43-50 Fine plastic gray clay - No boulders
50-53 Plastic gray clay - fine gravel
53-54 Dark semi-plastic clay fine gravel
54-56 See 50-53
56-63 Light gray boulder clay 50J6 gravel ;
63-64 Very fine clay and gravel
64-72 Gray fine silty clay and gravel
72-76 Semi-plastic black clay - fine gravel
76-80 Very dark semi-plastic clay and gravel
80-81 Dark gray clay and gravel and earthy lignite
82-85 Very dark fire clay - gravel
85-87 Dark gray plastic fire clay - gravel
87-92 Lighter gray plastic fire clay
Overburden 81*
Lignite
-135-
BORE HOLE 10?
December 9, 1940
0-3 Muskeg
3-9 Marine clay-gray
9-17 Gray boulder clay
17-20 Gray sandy boulder clay
20-24 Dark gray black clay-sand and gravel
24-33 Light gray black clay-plastic-gravel
33-35 Plastic light gray black clay
35-38 Earthy lignite and clay
December 10, 1940
38-43 Lignite-woody-some earthy and peaty
43-46 Lignite-woody-some earthy
Lignite-wwody-aome earthy (pebble)
57-60 Lignite-woody some peaty and earthy (water)
60-65i Lignite-woody, some earthy
65^-72 Very plastic black gray fire clay
72-78 Lignite-woody some earthy
78-81 Lignite-woody
81-84 Plastic black gray fire clay
84-8? Lighter gray fire clay
Overburden 38*
Lignite 27i Lignite
Clay of-
Lignite 9 L:0:: 1:1
BORE HOLE 108
January 2, 1941
0-4 Muskeg
4-10 Brown Marine clay (silt)
10-26 Boulder clay-sand and gravel
26-32 Black clay mostly gravel and sand
January 3, 1941
32-34 Gravel-water
quick sand
44-50 gravel-water
5P?53 quick-sand
53-57 gravel-some clay
57-61 gravel
January 4, 1941
61-63 Lignite-earthy-peaty-woody
63-65 Lignite-earthy-peaty
65-73 Lignite-earthy and woody
73-74 Plastic black gray-cret. fire clay
74-79 Lignite-woody
79-83 Lignite-peat and earthy-some woody
83-85 Lignite-woody
85-90 Black gray cret, fire clay
90-92 Lighter gray cret, fire clay
January 4, 1941
0-3 Muskeg
3-7 Marine clay (silt) brown
January 6, 1941
7-17 Quick running sand-some small boulder-1/8" to 1/2"
17-20 Gray plastic boulder clay-l/S"-!"
20-28 Sandy non-plastic black clay
28-40 Sandy clay (silty) boulder
40-41 Gravel
41-45 Lignite-earthy and peaty some woody
45-51 Lignite-mostly woody
51-54 Lignite-woody, earthy
54-57 Lignite-mostly earthy some woody
57-60 Lignite mostly woody some earthy
January 7, 1941
60-61^ Lignite-woody
61^-65 Lignite earthy and peaty-some woody
65-68 Fire clay black gray
68-78 Lignite-woody-some earthy
78-88 Black gray to lighter fire clay
Overburden 41* Lignite 34
Lignite 24
Clay 3 LsO:: 1:1.2
BORE HOLE 112
January 7, 1941
0-3 Muskeg
3-8 Mariaa clay-brown-silty
January 8, 1941
8-14 Gray sandy black clay
14-20 Very sandy silty-(running)-(quick sand)
20-23 Grey black clay-less sandy l/8*-1/2*
23-26 Very plastic black clay i"-f"
26-28 Mostly gravel-fine silty clay
28-43 Gravel
January 9, 1941
43-52 Gravel course-bits of lignite
52-56 Gray black clay-very fine clay
53-76 Black gray fire clay gravel V8"-V2" in it
76-78 Lignite-earthy-peaty-and woody
78-90 Lignite-woody-some earthy
90-102 Black gray fire clay-no gravel
No Lignite
BORE HOLE 115
Overburden 6l'
Lignite 31'
L:0:: 1:2
BOKE HOLE 11?
No lignite
-Stop hole-on and of pipe-running gravel-stopping drill.
BORE HOLE 119
February l, 1941
0-3 Mus ke g, sphagnum
3-14 Marine clay greyish brown
14-20 Grey semi-plastic black clay
20-25 Silty black clay 1/8"-!"
February 3, 1941
25-30 Sand, some clay and gravel 1/8**^" quick running
30-34 Creamy clay, sand and gravel
34-38 Light gray clay and gravel
38-41 Dark grey black clay and gravel l/S"-!/^"
41-44 Dark gray plastic black clay
44-69 Dark grey clay and gravel
69-75 Mostly gravel
75-77 Lignite, earthy and peaty
77-79 Lignite, earthy and peaty and some woody
79-88 Lignite, woody some earthy
88-105 Black grey fire clay
Overburden 75* Lignite 13
L:0::l*6
-M-
BORE HOLE 121a
February 4, 1941
0-3 Muskeg, sphagnum
3-10 Marine clay, brown grey
10-20 Gravel and clay
20-28 Gravel, little clay
28-33 Grey black clay plastic,
33-37 Dark grey plastic black clay 1/8"
February 5, 1941
37-45 Very plastic grey black clay
45- Large boulder, forced to move- 7t
BORE HOLE 121B
St art-February 5, 2i3b p.m.
Finish-February 7, 10i15 a.m.
February 5, 1941
0-3 Muskeg-sphagnum
3-10 Marine clay brown
10-17 Grey black clay and
17-25 Grey plastic black clay
25-28 Grey black clay
February 6, 1941
Grey plastic black clay wad gravel
Dark grey-plastic black clay y8"-y2"
Non plastic da*k grey black clay V8
Dark grey plastic black clay mostly gravel
Black clay and gravel hard drilling lignite fragments
Fine gravel Lignite eait&y
dispersed Lignite, earthy some peaty and woody
Lignite earthy woody, earthy and peaty
Lignite woody, .some peaty
Lignite woody some peaty and earthy
Lignite, woody some peaty and earthy
February 7, 1941
80-83 Lignite, woody some earthy and peaty
83-88 Black gray cretaceous fire clay
88-06 Lignite woodjr some earthy
98-105 Black grey testaceousfire city
February 7, 1941
0-3 Mu skeg, sphagnum
3-11 Marine clay brown gray
11-14 Grey black clay, gravel and sand
February 8, 1941
14-17 Gravel some clay and saad
17-22 Sand and gravel, lignite, hard
22-27 Gravel, lignite
27-32 Dark grey black Hay ln
32-39 Black clay, gravel
39-43 Black grey fire clay-lignite
43-48 Black grey fire clay more lignite earthy
48-50 Lignite earthy, peaty, woody
50-52 Lignite, earthy woody
52-55 Lignite woody
February 10, 1941
55-70 Lignite woody earthy
76-72 Lignite earthy some woody
72-74 Lignite earthy peaty woody
74-78 Black grey fire clay, some gravel
78-84 Lignite, woody
84-91 Lignite woody earthy peaty
91-101 Black grey fire clay
New cable
Overburden 48 Lignite 39
Lignite 26
Clay 4' L:0:: 1:1.23
Lignite 13
-152-
BORE HOLE 123
Overburden 73 Lignite 25
Lignite 12
Clay 5 L:0:j 1:3
Lignite 13
BORE HOLE 124
Overburden 28 Lignite 44
Lignite 30
Clay 12 L:0: 1:0.64
Lignite 14
BORE HOLE 125
NO LIGNITE
-isv-
BORE HOLE 12?
NO LIGNITE
BORE HOLE 129
Overburden 52 Lignite 14
Lignite 2
Clay 4 LiO:: Ii3.7
Lignite 12
Overburden" 72
Lignite 7 Lignite 19
Clay l
Lignite 12 L:0::l:3.8
-1U6-
March 4, 1941
0-3 Sphagnum Muskeg
3-9 Brown gray marine clay
9-15 Light gray sandy brown clay l78"-fw
15-24 Light gray velvety, black clay l/S^-f*
24-32 Creamy coloured clay and fine gravel
40-45 Very fine gravel
32-40 Dark grey quick sand
45-48 Gravel and clay
48-50 Gravel and clay (some fire clay-eroded)
50-54 Dark grey clay some gravel
54-55 Black grey cret, fire clay some lignite
55-57 Lignite, woody, earthy and peaty
March 5, 1941
57-59 Lignite, woody, some earthy
59-65 Black gray plastic fire clay
65-87 Lignite, woody, some earthy
87-100 Black gray fire clay-lighter below 91
Overburden 55 Lignite 26
Lignite 4
Clay 6 L:0:: 1:2.1
Lignite 22
-Ifrl-
BORE HOLE 132
March 6, 1941
0-6 Brown sandy loam—marine
6-14 Grey black clay ^"-f"
14-20 Grey sandy black clay -^"-2"
20-22 Light grey sandy semi-plastic black clay
22-25 Light gray sand, gravel and clay
25-30 Very fine gravel, and clay
30-32 Fine gravel, some large
32-35 Fine gravel and clay
35-38 Clay and gravel
38-40 Light gray clay and bouidere
March 7, 1941
40-42 Light grey clay and gravil
42-45 Mostly gravel, and clay light gray
45-49 Semi plastic black clay grey l78w-fn
49-53 Light gray clay and gravel
53-63 Fine gravel
63-6? Fine gravel and clay
67-69 Clay and gravel grey
69-71 Gravel and clay, lignite fragments
March 8, 1941
71-77 Black grey cret, fire clay
77-79 Lignite, earthy, peaty and woody
83-85 Lignite woody, some earthy
85-96 Cret, fire clay
96-102 China clay
Overburden 77
L:0:: 1:9.6
Lignite 8
-IU2-
BOEE HOU; 133
Start: March 10, 11:00 a.m.
Finish: March 12, 10:15 a.m.
Overburden 68 Lignite 21
Lignite 8
Clay 7 L:0:: 1:3.2
Lignite 13
-IW-
BORE HOLE 134
Overburden 65
Lignite J&
L:0:: 1:11
BORE HOLE 135
Overburden 73 Lignite 30
Lignite 18
Clay 3 L:0:: 1:2.4
Lignite 12
BORE HOLE 136
April 7, 1941
86-90 Silty clay, gravel and sand
90-100 Gravel and clay
NO LIGNITE
BORE HOLE 140
April 9, 1941
42-45 Gravel and clay
45-46 Quicksand and gravel
48-56 Fast running sand
56-58 Gravel coarser—up to
April 10, 1941
58-62 Very fine gravel 1/8"
62-65 Gravel up to l"
65.-71 Gravel up to -|w (fine clay)
72-75 Gravel up to fw and clay
75-78 Fine gravel 1/8
78-84 Very fine clay and sand
Sfl-85 Clay and sand and lignite (woody)
85-90 Quick sand
NO LIGNITE
-no-
BORE HOLE
B141a
April 11, 1941
0-3 Muskeg
3-10 Brown grjty marine clay
1^-14 Dark grey brown clay up to
B141B
April 12, 1941
0-3 Kuskeg
3-10 Brown gray Marine clay
10-16 Gray pi. clay up to ^w
16-21 Gravel and clay
21-25 Gravel coarse up to 2" little clay
25-28 Gravel -|w -
28-32 Gravel l"
32-36 Gravel 4r"
36-43 Gravel l"
43-50 Gravel j?"
April 14, 1941
62-92 Lignite, woody some earthy, peaty
92-104 Black gray plastic fir© clay
Overburden 50 Lignite 42
BORE HOLE 142
Overburden 39 )
Lignite l 646 .Lignite 42
Sand 3J
Lignite 22 L:0:: 1:1.1
Clay 4
Lignite 20
BORE HOLE 145
BORE HOLE
May l, 1941
0-7 Brown marine clay ' ' -•..••! ;J ;, ' -i.
7-12 Dark gray black clay f* ." :' ; '
12-22 Grey black clay f-2" hard : ; .''' ; ,
22-25 Gravel and clay hard ' .:
25-27 Fine gravel and sand V .' : .' - v , ^ ;-
27-35 Sand-water running 50 ft,
1 - i ' . ,' ' ' ' ,' . . . r 'M - , ' ' ;v
May 2, 1941 - " '-, '" .':. : ^'l/ : '' ''.- '' *"'f"
Overburden 73 Lignite 31
Lignite 13
Clay l L:P:t It2.4
Lignite 18
-I7U-
BORE HOLE
May 6, 1941
0-3 Muskeg, sphagnum
3-10 Brown marine clay
10-30 Grey boulder clay hard
30-33 Clay gravel and lignite
33-35 Grey silt -"..
May 7, 1941
35-37 Dark grey silt, and gravel
37-48 Dark grey (cret.) clay and gravel
48-56 Dark grey cret, clay gravel and lignite
56-58 Dark grey cret, clay gravel and check fragments
58-60 Dark grey cret, clay some earthy lignite
60-65 Dark grey cret, clay ches* fragments gravel
65-72 Dark grey clay, gravel lignite (earthy)
72-97 Dark grey cret, clay (in place) chest fragments
NO LIGNITE
-P7-
Overburden 29 Lignite 57
Lignite 3 fi
Clay 6 L:0:: 1:0.J
Lignite 19
-ne-
BORE HOLE 149
NO LIGNITE
-ICO-
June 2, 1941
38-45 Plastic gray clay interglacial
45-80 Lignite woody earthy
80-84 Lignite woody earthy
84-90 Black cret, fire clay
90-106 Lignite woody earthy
106-115 Black to light cret, clay
Overburden 45 Lignite 55
Lignite 39
Clay 6 L:0:: 1:0.8
Lignite 16
Hole- BI54 Start: June 4/41, 10 a.m.
Finish: " 9/41, 3.30 p.m.
June 4. 1941
0-2, Muskeg
2-7, Brown marine clay
7-25, Grey boulder clay
25-31 Grey boulder clay, much gragel and some sand
June 5
31-37, Fine running sand
37-53, Plastic interglacial clay
53-72, Dark grey feoulder clay
June 6
72-86, Dark grey boulder clay
j86-93,LIGNITE, woody, some earthy
June 9
j93-104, LIGNITE, woody, some earthy
I04-IIO, Dark Cretaceous fire clay
IIO-II5, Light Cretaceous clay.
Overburden: 86 feet.
Lignite: 18 feet.
B 155 Starts June 10/41, 10 a.m.
Finish: " 13/41, 4.30 p.m.
Overburden 92 feet
Lignite 14 feet
Startj June 1^/41, JO p.m.
Finish! " 18/41, 4tI5 P.m.
Overburden 56 feet
Lignite 41 feet
Overburden 79 feet
Lignite 15 feet
July 4, 1941.
O - 2, Muskeg
2-10, Greyish brown marine clay
10 - 31, Grey boulder clay
31 - 32, Grey sandy boulder clay
32 - 35, Fine running sand
35 - 39, Grey gravelly boulder clay
July 5
39 - 44, Grey fine gravelly and sandy boulder clay
44 - 70, Dark grey boulder clay
70 - 77, Dark grey boulder clay, some float lignite
i 77-78, LIGNITE, earthy and woody
: 78-86, LIGNITE, woody and earthy
July 7,
86 - 94, LIGNITE, woody and earthy
94 -100, Dark grey cretaceous fire clay
100 -107, Lighter crey Cretaceous clay
107 -110, Light grey China clay
Overburden 77
Lignite I? feet
July 8, 1941.
0-3, Muskeg
3-8, Grey Marine clay
8 -37, Grey boulder clay
37 -40, Dark brown fine gravel
40 -50, LIGNITE,woody and earthy
50 -54, Dark grey Cretaceous fire clay
July 9.
54 -74, Dark grey Cretaceous fire clay
74 -80, Very light grey Cretaceous flhina clay
Overburden 40 feet
Lignite 10 feet
Overburden 23 feet
Lignite 27 feet
Clay 4 feet
Lignite 8 feet
Total lignite 35 feet
Location B 163, from B 145, 200 feet.
B 164 Start s July 12, li15 p.a.
Finish: July 17, IIi30 a.m.
July 12, 1941.
Muskeg
- 8 , Lt. grey Marine clay
July 14
l 8-30 Grey boulder clay
X 30-32 Grey boulder clay and some earthy lignite
July 15 32 - 33 Float lignite, woody
33 - 35 Silica sand
35 - 37 Dark grey boulder clay and lignite fragments
37 - 41 Float lignite, woody, some clay
41 - 49 Dark grey boulder clay
49 - 51 Dark grey boulder clay and some lignite
51 - 58 LIGNITE, woody and earthy
58 - 61 Mixed, Lignite and fire clay
6l - 70 Dark grey fire clay
70 - 73 LIGNITE, woody, earthy
July 16
73 - 85 LIGNITE, woody, earthy
85-89 Dark grey Cretaceous fire clay
July I?
89 - 93 Dark grey Cretaceous fire clay
93 -100 Grey Cretaceous clay
Overburden 51 feet
Lignite 9 feet
Clay 12 feet
Lignite 15 feet
Total lignite
float 5 feet
in place 24 feet
29 feet
July 21
: 70 -90 LIGNITE, woody, earthy
90 - 95 Dark grey Cretaceous fire clay
95 - 98 Grey Cretaceous clay
98 -101 Light grey Cretaceous clay
101 -103 Bluish china clay
Overburden 57 feet
Lignite 7 feet
Clay 4 feet
Lignite 22 feet
Total Lignite 29 feet
Location B 165 from B 88, 200 feet north, 200 feet east,
B 166 Start : July 22, Is 30 p.m.
Finish : July 25, 3*30 p.m.
O -2, Muskeg
2 - 8, Brownish-grey marine clay
8 - 15 Grey boulder clay
15 -2? Grey sandy boulder clay
July 23.
27 - 33 Sandy and gravelly boulder clay, grey
33 - 36 Fine light grey sand
36 - 38 Grey sandy boulder clay
38 - 40 Impure silica sand and gravel, also boulders
40 - 42 Dark grey Cretaceous fire clay, some lignite
42 - 46 Grey sandy boulder clay
46 - 52 Grey boulder clay
52 - 53 LIGNITE, earthy, woody
July 24.
::53 - 57 LIGNITE, earthy, woody
t 57 - 65 n woody, earthy
65 - 81 Dark grey Cretaceous fire clay
July 25.
81 - 86 Dark grey Cretaceous fire clay
: 86 - 89 LIGNITE, earthy, woody
: 89 -100 " woody, earthy
100 -106 Dark grey Cretaceous fire clay
Overburden 52 feet
Lignite 13 feet
Clay 21 feet
Lignite 14 feet
Total Lignite 27 feet
Location B 166, from B 88, 200 feet north, 200 feet wfcst,
B I6? Start : July 26, 9.15 a.m.
Finish: July 29, 5 p.m.
July 28
40 - 45 Grey boulder clay
45 - 55 Dark grey boulder clay
55 - 58 Fine silty boulder clay, brownish
58 - 63 Fine silty clay, some sand, brownish
63 - 68 Coarse sandy and gravelly boulder clay
68 - 75 Dark grey boulder clay
July 29
75 - 78 Black Cretaceous fire clay
: 78 - 82 LIGNITE^ woody, earthy
82-84 Black Cretaceous fire clay
i 84-98 LIGNITE, woody, earthy
98 -103 Dark grey Cretaceous fire clay
103 -112 Grey Cretaceous clay
112 -115 Light grey China clay.
Overburden 78 feet
Lignite 4 feet
Clay 2 feet
Lignite 14 feet
Total Lignite 18 feet
August I, 1941
O* - i5 Black loam
.5 -9 Brown Marine clay
9-20 Grey boulder clay
20 - 25 Coarse sand and gravel, some clay
25 - 30 Coar se sand
August 2
30 - 40 Fine sand
40 - 45 Grey boulder clay
45 - 50 Grey gravelly boulder clay
50 - 60 Grey boulder clay
60 - 65 Dark grey boulder clay
August 4*
65 - 70 Dark grey sandy boulder clay
August 5*
Pipe trouble
August 6.
70 - 75 Black grey boulder clay
75 - 79 Black grey Cretaceous fire clay
: 79 - 82 LIGNITE, earthy woody
: 82-93 LIGNITE? woody, earthy
93 - 96 Black Cretaceous fire clay
96 -100 Dark grey fire clay
100 -103 Grey Cretaceous clay
103 -110 Light grey China clay
Overburden 79
Lignite 14 feet
Location B 168 from B 87, 200 feet north, 220 feet west.
- lift-
August 8.
31 -35 Grey boulder clay
35-42 Dark grey boulder clay, float lignite
42-48 Grey boulder clay
48 - 54 Black Cretaceous fire clay
:54 - 56 LIGNITE, earthy, woody
:56 - 78 LIGNITE, woody, earthy
78 - 81 Black Cretaceous fire clay
:8I - 96 LIGNITE, woody, earthy
96 -zoo Dark grey cretaceous fire clay
August 9-
100 -110 Grey Cretaceous clay
110 - Cretaceous China clay
Overburden 54 feet
Lignite 24 feet
Clay 3 feet
Lignite 15 feet
Total Lignite 39 feet
August 9, 1941
0-3 Muskeg
3-8 Greenish grey Marine clay
8-1? Grey Boulder clay
17 - 18 Black fire clay
j 18-20 LIGNITE, earthy, woody
20 - 34 Black Cretaceous fire clay
August 12.
Overburden 59 feet
Lignite 19 "
Clay 2 "
Lignite 16 "
Overburden 55 feet
Lignite 19 "
Clay 6 "
Lignite 14 "
Total Lignite 33 feet
Location B172 from B85 200 feet north 2QO feet west
-202-
August 22
12-25 Light grey boulder clay
August 26
25-29 Dark sandy boulder clay ^
29-40 Dark grey Cretaceous fine clay
: 40-58 LIGNITE woody, earthy
: 58-64 " earthy, woody
64-66 Black Cretaceous fire clay
: 66-84 LIGNITE, woody earthy
84-86 Black Cretaceous fire clay
August 27
86-95 Dark grey Cretaceous fire clay
95-106 Light grey Cretaceous clay
106-108 Light China clay
Overburden 40'
Lignite 24*
Clay 2'
Lignite 18'
September 2. 1941
0-3 Muskefe
3-12 Grey Marine clay
12-20 Grey boulder clay ^w
20-24 Gravel jtn
24-30 Sand and gravel j?"
30-35 Dark clay, some float lignite
35-41 Gravel, some float lignite
41-49 Dark boulder clay, some lignite
September 8
49-50 Reworked black Cretaceous fire clay, some lignite
: 50-55 LIGNITE, earthy, woody
j 55-71 " woody, earthy
71-74 Black Cretaceous fire clay
74-90 LIGNITE, woody, earthy
99-99 Dark grey Cretaceous fire clay
September 9
99-104 Dark grey Cretaceous fire clay
104-110 Grey Cretaceous clay
110- China clay
Location B174 from B85; 200 feet north, 200 feet east
B 175 a Start: Sept. 10;08:00 a.m.
Finish: Sept. 11
September 10 fc 11
Drill 43 feet, boulder
Overburden 47 feet
Lignite 21 '
Clay 8'
Lignite 13 '
Total Lignite 34 feet
Sept 18 fc 19
53 feet, boulder move
Overburden 58 feet
Lignite 6 '
Parting 6 '
Lignite 10 '
Total Lignite 16 feet
Overburden 58 feet
Lignite 10 '
Parting 8 '
Lignite 14 '
Totiil Lignite 24 feet
October 4. 1941
0-3 Muskeg
3-8 Grey Marine clay
8-16 Grey boulder clay
October 6.
16-26 Grey boulder clay
26-46 Grey, fine running sand
46-70 Grey boulder clay
October 9
70-77 Grey boulder clay, some float lignite
77-79 LIGNITE, earthy, woody
79-81 Black Cretaceous fire clay
81-95 LIGNITE, woody, earthy
95-103 Dark grey Cretaceous fire clay
103-106 Light Cretaceous clay
* Overburden
Lignite
Parting
Lignite
77 feet
2 '
2 '
14 '
Total Lignite 16 feet.
Location B178, 200 feet south, 400 feet west from D.H. 26
B 179 Start: November 22, 1100 p.m.
Finish: November 29, 11:00 a.m.
Finish pipe, November 29, 3:00 p.m.
Overburden 52 feet
Lignite 4 feet
Parting 4 feet
Lignite 28 feet
Total Lignite 32 feet
Location B179, from D.H. 26, south 200 feet, west 600 feet,
-204-
December 9, 1941
0-3 Muskeg
3-9 Grey Silty Marine clay
9-15 Grey silty gravelly boulder clay
15-23 Grey plastic boulder clay, some gravel
23-30 Grey gravelly boulder clay
December 10
30-38 Grey fine running sand
38-40 Grey sandy gravel
40-42 Grey sandy boulder clay
December 11
42-44 Grey sandy boulder clay
44-52 Dark grey boulder clay, some gravel
52-54 Coarse sandy gravel, some float lignite
: 54-76 LIGNITE, woody, earthy
December 12
76-80 Black Cretaceous fire clay
: 80-95 LIGNITE, woody, earthy
95-100 Black Cretaceous fire clay
100-112 Light Cretaceous clay
Overburden 54 feet
Lignite 22 feet
Parting 4 feet
Lignite 15 feet
Total Lignite 37 feet
Location B181, from D.H. 26, 200 feet west, 400 feftt north,
-a H-
-
126-127 Light smooth Cretaceous clay
Overburden 64 feet
Lignite 17 "
Parting 5 "
Lignite 16 "
Total Lignite 33 feet
Location B182 from D.H. 26, 200 feet west, 600 feet north
NOTE. DIVERS NORTH OF
IAOOON ARE. ONLY
APPROXIMATE..
LEGEND
6ft- 12 -ALBERTA COAL LTD DRILL HOLE * No
DH-37-ONTARIO DEPT OF MlNtS DRILL HQLEL^No
C-21 -ONTARIO DfcPTOF MINES DRILL HOLE 4 No ————— LIMIT OF COAL
B 45 ONTARIO NORTHLAND RAILROAD DRILL HOLL'No
783 ELEVATION
o *,'J
y eir?-
K. - -;
LEGEND
66-12 ALBERTA COAL LTD DRILL HOLL t No
DH-37- ONTARIO DEPT OF MINLS DRILL HOLL*NJo
C-21 -ONTARIO DEPT OF MINES DRILL HOLE* No 1——"——
B'45 ONTARIO NORTHLAND RAILROAD DRILL HOLEJNu
DRILLED B/'No
1783 -ELEVATION
O8'" 1 o fl'"*"
DRILL HOLE
LOCATION
ONAKAWANA LIGNITE
EASTERN SECTION
Ratio
Scale; ZOO Feet = l Inch
400 ,
D.HJ2
S 74-06 O
0-82
L-3
ONAKAWANA LIGNITE DEVELOPMENT
DISTRICT OF COCHRANE, ONTARIO
Lignite Area A
\
\ Y li
\\\ \ \ x
Section C~D
r ile of Fei:t
X. \ ' \
v- -. \ N
1 Boiler Pant.
2 Processing Plant,
^ Garage and Machine Shop.
A Pump House.
Lignite Area B r, Office.
e Canip Buildings.
\\\
\ \
\ \
VA\ \ \ \ \\ \ \ \ ' '
v -V— \ V -V- Surface
v \ r\
v\ \ \ \\^\ v "-y''
Section A"B
63.l-56 GARDINER
-...' ,:. ' , , - . X- ' ' N.
. .. :-.;.v.-.;-A.^-.
V::;.-.v. ,-.. -.-.v
'-- V-
'•- - *ijy:x?.^:
' ' '
:-^r*?"' ;-"I.' :; ';
li-'." . -
Utfld
i.saiA uj.aos auu