MANILA WATER CALAWIS WATER TREATMENT PLANT

Civil Works Early Handover Ready for MEICA Erection


(as per Acceleration Programme Rev. 0)

PROCESSING UNIT TARGET DATE

UCD SYSTEM - WATER [122] / COAG. TANK [121] Stream 1 & 2 29-Dec-21

UCD SYSTEM - WATER [122] / COAG. TANK [121] Stream 3 & 4 6-Jan-22

GENSET-II [939a] 1-Feb-22

RAW WATER BLENDING TANK [115] 7-Feb-22

OIL TANK-I [933b] 8-Feb-22

GENSET-I [933a] 27-Feb-22

CHEMICAL BLDG [800] 28-Feb-22

POWER STATION & MV - MCC200 [930] 1-Mar-22

SLUDGE STORAGE SILO [348] 2-Mar-22

POWER STATION - MCC400 [932] 9-Mar-22

UCD - MCC300 10-Mar-22

TREATED WATER PUMPING STATION [290c] 16-Mar-22

ADMIN. BLDG [911] - SCADA CONTROL, SERVER, UPS & LABORATORY ROOMS 16-Mar-22

CHLORINATOR & NEUTALIZATION BLDG [853] 18-Mar-22

SLUDGE THICKENING TANK [321] 22-Mar-22

OIL TANK-II [939b] 23-Mar-22

BACKWASH WASTEWATER TANK [311] 27-Mar-22

UCD SYSTEM - SLUDGE [312] 27-Mar-22

SLUDGE BUFFER TANK [319] 28-Mar-22

SLUDGE DEWATERING ROOM [342] 10-Apr-22

MCC BLDG - MCC700 17-Apr-22

DECANTATION LAGOON [353] 9-May-22

DISINFECTION CONTACT TANK [290a] / TREATED WATER STORAGE TANK [290b] 20-May-22