SCOPE OF WORK INSTALLATION OF CHEMICAL TRANSFER PUMP

AREA/LOCATION
ACTIVITY NO.
ITEM ACTIVITIES
[A] PREPARATORY WORKS
Conduct safety toolbox meeting with the team prior to installation of Chemical Transfer Pump including checking of proper
1
and complete Personal Protective Equipment (PPE).
Explain the methodology of installation of Chemical Transfer Pump including the Job Hazard Analysis (JHA) by aligning to
2
the approved Hazard Identification and Risk Assessment Criteria (HIRAC).
3 Isolate the work area from unauthorized personnel by installing Safety Signage’s, Protection and Barricades.
4 Secure permit to work and once approved post a copy of it in specific workplace location.
5 Mobilization/Hauling of equipment and materials.
[B] WORK PROCEDURE
INSTALLATION
1 PREPARE THE MATERIALS AND TOOLS PRIOR FOR THE INSTALLATION OF PUMP
2 COORDINATE WITH GEN-CON PERSONEL.
3 PREPARE TEMPORARY PLATFORM/SCAFFOLDING TO SUPPORT ON INSTALLATION OF PUMP
4 LAY-OUT THE PUMP LOCATION AS PER ASSEMBLY LAY-OUT/DRAWING
5 INSTALL THE Chemical Transfer Pump
6 LEVEL THE PUMP THROUGH PUMP FLANGE AND TIGHTEN THE NUTS AND BOLTS
7 APPLY GROUTING PROCEDURE
8 RECHECKING OF PUMP ALIGNMENT AND CHECK THE FOUNDATION BOLTS IF TIGHTENING IS NECESSARY
[C] HOUSEKEEPING WORKS
1 Removal/Clearing of work area.
2 Removal of caution tapes and other safety signage installed as needed.
3 Return of all tools/equipment used to warehouse/designated approved equipment yard.
[D] MANPOWER
1 Project Manager
2 Mechanical Supervisor
3 Safety Officer
4 Foreman
5 Boom Truck Operator
6 Fitter
7 Scaffold Installation Worker
8 Rigger
9 Labor/Helper
[E] TOOLS & EQUIPMENT
1 Socket Wrench
2 Safety signage
4 Combination Wrench
6 Scaffolding
7 Platforms
8 Chain block
9