Drilling Junk Sub

Operation & Maintenance


Manual

Tianhe Oil Group Huifeng Petroleum Equipment Co., Ltd.


Tianhe Oil Group Huifeng Petroleum Equipment Co., Ltd.
LB type Drilling Junk Sub
Operation & Maintenance Manual

Contents

1. APPLICATION .......................................................................... - 1 -

2. CONSTRUCTION AND WORKING PRINCIPLE ..................... - 1 -

3. OPERATION METHOD ............................................................ - 3 -

4. MAINTENANCE ....................................................................... - 3 -

5. TECHNICAL PARAMETERS ................................................... - 6 -

6. HOW TO ORDER ..................................................................... - 6 -

PDF 文件使用 "pdfFactory" 试用版本创建 www.fineprint.cn


Tianhe Oil Group Huifeng Petroleum Equipment Co., Ltd.
LB type Drilling Junk Sub
Operation & Maintenance Manual

1. Application

During drilling process, LB type drilling junk sub is applied mainly for

fishing of shivers and fallen objects such as carbide tooth, drill bit and

bearing which can't be carried out of hole by conventional fluid

circulation etc. It possesses important functions to keep hole cleaning,

increase bit service life, reduce and prevent drill bit from unexpected

damage.

2. Construction and Working Principle

2.1 Construction

LB type drilling Junk sub has two kinds of structures, integral

mandrel and two-body mandrel, see fig. 1 and 2.

1. Mandrel 2.Outer barrel

Fig. 1 Structure diagram for Junk Sub with integral mandrel

- 1 -

PDF 文件使用 "pdfFactory" 试用版本创建 www.fineprint.cn


Tianhe Oil Group Huifeng Petroleum Equipment Co., Ltd.
LB type Drilling Junk Sub
Operation & Maintenance Manual

1. Mandrel 2.Outer barrel 3.Lower sub 4.O-ring

Fig. 2 Structure diagram for Junk Sub with two-body mandrel

2.2 Working Principle

Due to the fact that the body O.D. of junk sub is bigger and a

smaller annular space is available between body of junk sub and

well hole;the mandrel diameter at cup mouth is smaller so that it

has a bigger annular space,therefore,the fluid at the cup mouth

form a swirls and suddenly falls down so as to reduce the

carrying capacity. By this way,some heavy objects will drop in

cup and be fished out so that the purpose of cleaning hole.

- 2 -

PDF 文件使用 "pdfFactory" 试用版本创建 www.fineprint.cn


Tianhe Oil Group Huifeng Petroleum Equipment Co., Ltd.
LB type Drilling Junk Sub
Operation & Maintenance Manual

3. Operation Method

3.1 The junk sub should be assembled on the top of the drill bit, flat

bottom milling shoe, scraper or junk basket.

3.2 Generally no more special operation, the junk sub can fishing

during the drilling. If specialized in fishing then wait the sand

flush out at well bottom, rotary it at well bottom, change the

displacement and flush few minutes, then pull out of the well.

3.3 Pay attention to the mouth of the junk sub to scrape casing shoe

during trip-out process.

4. Maintenance

4.1 Disassembly

After used, the junk sub should be cleaned with water, and then

disassembled by following steps.

4.1.1 For the integral mandrel: clamp the mandrel with the chain

tongs, and clamp the outer barrel with the other chain

tongs, and then rotate with right hand to remove the barrel.

- 3 -
Tianhe Oil Group Huifeng Petroleum Equipment Co., Ltd.
LB type Drilling Junk Sub
Operation & Maintenance Manual

Integral mandrel

4.1.2 For the two-body mandrel:

a) Clamp the mandrel with the chain tongs, and clamp the

outer barrel with the other chain tongs, and then rotate

with right hand to remove the barrel.

b) Heat the connection of mandrel and lower sub to about

220℃. Clamp the mandrel with the chain tongs, and

clamp the lower sub with the other chain tongs, and

then rotate with left hand to remove the sub.

c) Take out the seal ring on the mandrel.

- 4 -
Tianhe Oil Group Huifeng Petroleum Equipment Co., Ltd.
LB type Drilling Junk Sub
Operation & Maintenance Manual

Two-body mandrel

4.2 Assembly

4.2.1 Clean all the disassembled parts.

4.2.2 Check all parts carefully, if found the damage, repair it then

repeat use it if the parts can be repaired, and otherwise

replace it with new one if over-repaired. The connect

thread and surface should be flaw detected, if found the

crack, replace the part.

4.2.3 After passing the inspection, reassemble the tool according

to the reverse order of the disassembly progress. All of the

seal rings should be replaced with new one.

4.3 Maintenance

After assembly, the tool should be equipped with thread

protectors, and properly stored in dry place to avoid dust and rust for

the next used.


- 5 -
Tianhe Oil Group Huifeng Petroleum Equipment Co., Ltd.
LB type Drilling Junk Sub
Operation & Maintenance Manual

5. Technical Parameters

Lower end
Lower Length Overall
O.D. * upper I.D. Hole size
Model connection * of barrel length
end O.D. mm mm
upper connection mm mm
mm
LB79 79*79 2 3/8REG B*P 19 250 845 88.9~98.4
LB89 89*78 2 3/8REG B*P 19 250 845 108~117.5
LB94 94*79 2 3/8REG B*P 19 250 850 108~117.5
LB102 102*93 2 7/8REG B*P 31.8 250 850 117.5~124
LB114 115*105 3 1/2REG B*P 38.1 250 915 130~149
LB118 118*105 3 1/2REG B*P 38.1 250 875 139.7~149
LB127 127*108 3 1/2REG B*B 38.1 250 850 152.4~162

LB127 127*108 3 1/2REG B*P 38.1 250 915 152.4~162

LB140 140*108 3 1/2REG B*P 38.1 250 875 165~190.5


LB146 146*108 3 1/2REG B*P 38.1 250 875 168~190.5
LB168 168*140 4 1/2REG B*P 57.2 250 915 190.5~216
LB178 178*146 4 1/2REG B*P 57.2 250 915 219~244.5
LB219 219*197 6 5/8REG B*P 76.2 250 915 244~289
LB245 245*203 6 5/8REG B*P 76.2 250 960 292~330
LB327 327*241 7 5/8REG B*P 76.2 250 1050 375~444.5

6. How to order

6.1 If some of the required technical parameters are contained in

tables, please specify the model in the contract.

6.2 If the required technical parameters are special, please specify

the details.

- 6 -