PREVIOUS EXPERIMENT: 3 CASHIER AND 4 BARISTA (200 Customers)

payment_wait_time payment_time order_wait_time order_time


0 0.60 18.90 3.10 53.10
1 1.10 19.60 7.40 59.90
2 1.20 20.90 2.40 53.90
3 1.30 20.40 7.20 59.30
4 0.80 20.10 6.30 59.20
5 0.40 19.10 3.20 54.50
6 0.90 20.00 3.50 54.60
7 0.90 20.20 4.50 58.20
8 0.80 20.20 4.80 58.00
9 0.70 19.70 3.30 55.30
AVERAGE AVERAGE AVERAGE AVERAGE
0.87 seconds 19.91 seconds 4.57 seconds 56.60 seconds

EXPERIMENT 2: 4 CASHIER AND 4 BARISTA (1000 Customers)

payment_wait_time payment_time order_wait_time order_time


0 0.10 19.10 3.90 54.90
1 0.10 19.00 3.30 53.50
2 0.10 18.80 2.70 52.90
3 0.10 19.20 3.40 54.70
4 0.10 18.70 3.30 53.20
5 0.10 19.00 3.30 54.00
6 0.10 18.80 3.50 53.50
7 0.10 18.90 5.80 56.80
8 0.10 19.20 5.40 57.10
9 0.10 19.30 4.90 55.50
AVERAGE AVERAGE AVERAGE AVERAGE
0.10 seconds 19.00 seconds 3.95 seconds 54.61 seconds
EXPERIMENT 1: 3 CASHIER AND 4 BARISTA (1000 Customers)

payment_wait_time payment_time order_wait_time order_time


0 0.70 19.40 3.40 53.80
1 0.70 19.40 4.20 54.80
2 0.60 19.50 4.20 55.30
3 0.70 19.30 6.90 59.20
4 0.70 19.40 2.90 53.90
5 0.80 19.40 5.00 56.60
6 0.80 19.50 3.50 54.30
7 0.60 19.50 4.30 55.20
8 0.80 19.70 3.70 53.70
9 0.70 19.30 4.10 56.10
AVERAGE AVERAGE AVERAGE AVERAGE
0.71 seconds 19.44 seconds 4.22 seconds 55.29 seconds

Despite having a large number of customers, changes in


store working hours, and adding one payment method and
one item on the menu, Mr. Darkness still can accommodate
all the customers in less than 1-2 minutes with the same
three cashiers and four baristas.

However, hiring one more cashier will make the serving time
much lesser. Thus, Mr. Darkness might need more income if he
wanted to add more cashiers to satisfy his customers.