You are on page 1of 17

DRAFT SECURITY OF PAYMENT ACT

(As of 03 March 2022)


ED Santiago Ducay’s comments in Green
Atty. Anne Roa’s comments in Red

SECTION SUBJECT PROVISION COMMENT / QUERY PROPOSED REVISION / PROVISION


1 Short Title SECTION 1. Short Title – This Act shall be known * Proposed amendment for consistency SEC. 1. Short Title – This Act shall be known as
as the “Construction Industry Security of Payment In the use of “SEC.” rather than the “Construction Industry Security of Payment
Act”. “SECTION”, as adopted throughout the draft bill. and Adjudication Act” or the “SOP Law”.
* Propose to reinstate “Adjudication”
in consonance with the intent to
provide an efficient adjudication
mechanism for security of payment
to be governed by the CIAC Rules.
* For this purpose, CIAC will implement
rules of general application to allow
for ad hoc Adjudication based on
complementary contractual terms,
while retaining primary and exclusive
jurisdiction to enforce Adjudication
Determinations, whether ad hoc or
institutional, to ensure security of
payment within the purview of this
law.

2 Statement of Policy The Civil Code of the Philippines provides Proposed revision for brevity and intent. This Act promotes the basic principles of justice
and Objectives of that every person, in the exercise of his and equity in contractual relations, pursuant to
this Act rights and in the performance of his duties, Article 19 of the Civil Code of the Philippines.
must act with justice, give everyone his due,
and observe honesty and good faith. It is on The objective of this Act is to facilitate and ensure
such principle that the basic principles of a timely compensation of Payment Claims under a
contract are based, as well as this Act. Contract by providing a Qualified Person the
statutory right to:
This Act provides a statutory right to a person (a) an entitlement to a Progress Payment;
or party to a construction contract who has
carried out works or services or has supplied (b) a procedure for making a Payment Claim;
goods for a construction work, to receive (c) an efficient mechanism for the Adjudication
progress payment in a timely manner. of an unsettled Payment Dispute; and
The means by which this Act facilitates progress (d) remedies to secure the timely settlement of a
payment is by establishing a procedure that Payment Claim and the prompt payment of a
involves– due Adjudication Determination, through:
(a) the making of a payment claim by the person (i) the right to suspend Work or the supply of
claiming payment, and Goods or Services; and
(b) the provision of a payment schedule by the (ii) the right to access retention money by
person by whom the payment is payable, and providing an equivalent performance
(c) the referral of any disputed claim to the bond.
default nominating authority, and
(d) the payment of the progress payment so
determined.

3 Scope and (1) This Act shall apply to all construction Proposed revision for clarity and intent (1) This Act shall apply to all construction
Application contracts executed and carried out in the to limit the benefit of the law to PCAB- Contracts executed and carried out wholly or
Philippines on or after [date of effectivity of accredited Contractors and suppliers of partly in the Philippines, entered into by a
the Act]. Goods and Services for Work executed Qualified Person in any territorial jurisdiction
only by PCAB-accredited Contractors. on or after the effectivity of this Act.
(2) This Act shall not apply to any contract for
the carrying out of construction work at or (2) This Act shall not apply to any Contract
on, or the supply of goods or services in involving Work executed by a Contractor who
relation to, any personal or residential is not accredited by the PCAB on the effective
property. date of such Contract.

4 Interpretation and As used in this Act: Propose to add a provision for Interpretation and Definition of Terms
Definition of Terms “Interpretation” under this heading and
to capitalize all defined terms for ease (1) Interpretation
of reference. (a) Defined terms shall have the meaning
stated herein, unless the context requires
All other proposed amendments are otherwise.
intended for brevity, precision of
language, and consistency. (b) Words indicating the singular also include
the plural, and words indicating the plural
also include the singular.
(2) Definition of Terms

(a) Adjudication NEW Proposed addition for clarity of intent. means the alternative dispute resolution
mechanism provided under this Act to ensure
security of payment through the expeditious
settlement of Payment Disputes arising from
unresolved Payment Claims under the Contract;

(b) Adjudication NEW Proposed addition for clarity of intent. means the Construction Industry Arbitration
Authority Commission (CIAC), which shall govern all matters
pertaining to Adjudication under this Act in
accordance with its applicable rules (CIAC Rules);

(ac) Adjudication means the payment claim under adjudication Proposed revision for precision of means the Payment Dispute under submitted for
Claim including any interest payable under this Act; language. Adjudication including any interest payable under
this Act;

(bd) Adjudication means the determination of the adjudicators Proposed revision for precision of means the determination of the Adjudicators
Determination on a payment claim dispute; language. on an payment claim dispute Adjudication Claim;

(ce) Adjudication means the process of adjudication under this Proposed revision for clarity of intent. means the process of Adjudication under this
Proceedings Act; Act, which may either be ad hoc in accordance
with the terms of the Contract, or institutional
to be conducted by the CIAC, both of which must
conform with the CIAC Rules;

(df) Adjudicator refers to an individual who passed the The CIAC Rules shall contain the Refers to an a individual natural person who is
qualification standard and is trained and minimum qualification requirements for Passed the qualification standard and is trained
accredited by the default nominating authority, Adjudicators to accommodate selection and accredited by the default nominating
to adjudicate on payment dispute that has been in accordance with contractual terms authority, to adjudicate on payment dispute that
referred to adjudication; for ad hoc Adjudication. has been referred to adjudication qualified to
determine an Adjudication Claim based on the
CIAC Rules;

(eg) Claimant refers to the person or party who initiated the It must be stressed that only qualified refers to the Qualified Person or party who
adjudication proceedings; persons can benefit from security of initiated the Adjudication Proceedings;
payment under this Act.

(fh) Construction means an agreement under which a person or Proposed revision for precision of means an a written agreement under which a
Contract party undertakes to carry out works or services language. Qualified Person or party undertakes to carry out
or supply goods for another person or party for the Works or the supply of Goods or Services or
a construction project; supply goods for another person or party for a
construction project;

(i) Contractor NEW Proposed definition based on: means a natural or juridical person duly licensed
(1) PCAB Rules and Regulations by the PCAB as a “Constructor”, being a
promulgated under Republic Act contractor or builder, subcontractor or specialty
No. 4566, where “Constructor” shall contractor, who has undertaken to execute the
have the same meaning as Work under the Contract;
“contractor” in Sec. 9(b) of Republic
Act No. 4566; and
(2) Art. 1.13 of CIAP Document 102.

(gj) Court refers to the appellate court;

(hk) Day means a calendar day; Proposed revision for clarity. means a calendar business day when banks are
open;

(i) default means the body authorized under section 8; Propose to delete, with “CIAC” as the means the body authorized under section 8;
nominating Adjudication Authority to ensure
authority security of payment under this Act.

(jl) Due Date means, in relation to progress payment, the date Proposed revision for brevity. means, in relation to progress payment, the date
on which the progress payment becomes due on which the a Progress Payment becomes due
and payable; and payable;

(km) Goods means materials or components that are to form Proposed revision for precision of means materials or components that are to form
part of a building or structure or civil work which language. part of a building or structure or civil the Work
requires construction or on-site installation; or which requires require construction or on-site
plant or materials for use in connection with the installation by the Contractor; or plant or
carrying out of construction work; materials for use in connection with the carrying
out of construction the Work;

(ln) Notice of means the written notice that the payment claim Proposed revision for conciseness. means the written notice that the a Payment
Adjudication will be referred to adjudication for determination; claim Dispute will be referred to Adjudication for
determination, which must contain:
(a) the nature and description of the Payment
Dispute including the Contract provisions to
which it relates;
(b) the remedy sought; and
(c) the pertinent supporting documents available
to the Claimant;

(o) Party NEW Proposed revision for clarity. refers to a contracting party to a Contract,
whether as project owner, Contractor, or
supplier of Goods or Services;

(mp) Payment means a claim for progress payment by a person Proposed revision for conciseness. The obligations of the contractors before
Claim or party against another person or party who is they are paid should also be included.
liable to make the progress payment under a
construction contract; means a written claim for Progress Payment by a
Qualified Person or party against another person
or party who is liable to make the progress
payment under a construction contract the
Principal, which must state:
(a) the amount claimed calculated in accordance
with the Contract, or by reference to the
Contract if not provided for therein,
(excluding the cost of any expense, loss, or
damage arising from a breach of contract,
unless the Contract provides otherwise);
(b) the Due Date;
(c) a description of the Work, Goods or Services
to which the Payment Claim relates; and
(d) the Contract provision under which the
Payment Claim is made or, in the absence of
any such provision, a statement that the
Payment Claim is made under this Act.

(nq) Payment means disagreement arising from a payment Proposed revision for conciseness. means a disagreement arising from a Payment
Dispute claim; Claim or any portion thereof, or the non-payment
of an approved, undisputed or settled amount of
the Payment Claim within the period prescribed
under this Act;

(r) Payment NEW Proposed revision for conciseness. means the written response of the Principal to a
Response Payment Claim, which must include:
(a) the certified amount to be paid under the
relevant Payment Claim; or
(b) if the full amount of the Payment Claim is
disapproved, or if the certified amount is less
than what is claimed, then it shall state the
reasons therefor;

(s) PCAB NEW Proposed revision for brevity. refers to the Philippine Contractors Accreditation
Board;

(ot) Principal refers to a person or party in a construction Proposed revision for conciseness. refers to the a person or Party in a construction
contract for whom the construction work or contract who is principally liable to make a
services is to be carried out, or to whom goods Progress Payment under the Contract, for whom
are to be supplied; the construction Work or services is to be carried
out, or to whom the Goods or Services are to be
supplied;

(pu) Progress refers to – Proposed revision for conciseness. refers to –


Payment (1) a milestone payment under a construction (a) a milestone payment under a construction
contract, being a payment that is based on the Contract, being a payment that is based
an event or date; on an event or date;
(2) a single or one-off payment for construction (b) the final payment for construction work
work carried out, or services rendered, or Carried out, or services rendered, or goods
goods supplied, under a construction Supplied under a construction based on the
contract; and Contract, including payment of inclusive of
(3) final payment for construction work carried the final progress billing and all approved
out, or services rendered, or goods supplied claims including, but not limited to,
under a construction contract, including variations in the Work;, contract price
payment of the final progress billing and all adjustments;, escalation;, and acceleration of
approved claims including, but not limited to, Work; and
variations in the work; contract price (c) a single or one-off or lump sum payment for
adjustments; escalation; and acceleration of the construction Work carried out, or for the
work; supply of Goods or Services rendered, or
goods supplied, under a construction the
Contract upon completion.; and

(v) Qualified NEW Proposed revision for clarity of intent. refers to a PCAB-accredited Contractor, or to a
Person supplier of Goods or Services under a Contract
involving Work executed by a PCAB-accredited
Contractor, to whom the benefits of security of
payment under this Act applies;

(qw) Respondent refers to the person or party on whom the notice Proposed revision for conciseness. refers to the person or party Principal on whom
of adjudication is served; the Notice of Adjudication is served;

(r) request for means a written request for payment of progress Propose to delete. A “Payment Claim”, means a written request for payment of progress
payment payment as defined, is sufficient for the purpose payment
of requesting payment.

(sx) Services means – Proposed revision for brevity. means, in relation to the Work –
(1) the conduct of feasibility studies, planning (a) the conduct of feasibility studies, planning
service, the submission of applications or service, the submission of applications or
other documents to any relevant authority, other documents to any relevant authority,
site supervision services, professional site supervision services, professional
engineering services, or architectural, design, engineering services, or architectural, design,
surveying or quantity surveying services, in surveying or quantity surveyings ervices, in
relation to construction work; relation to Construction Work;
(2) project management services in relation to (b) project management services in relation to
construction work; Construction work;
(3) building, engineering, exterior or interior (c) building, engineering, exterior or interior
decoration or landscape advisory services decoration, fit-out, or landscape advisory
in relation to construction work; or services in relation to construction work; or
(4) the provision of labor to carry out (d) the provision of labor to carry out
construction work; Construction work;

(ty) Work refers to all labor, materials, equipment, and Proposed revision for conciseness. refers to all labor, materials, equipment, and
facilities provided and supplied that are necessary facilities provided and supplied that are necessary
to commence, complete and fulfil all obligations to commence, complete and fulfil all obligations
called for in the Contract. called for in the Contract.
means the permanent works to be executed
under the Contract, including all labor,
materials, equipment, and facilities and
temporary works of every kind provided and
supplied by the Contractor or supplier of Goods
or Services that are necessary to commence,
complete and fulfill all of the Contractor’s
obligations called for in under the Contract.

195 Prohibition of on Any conditional payment provision in a Proposed revision for clarity of intent. Any conditional payment provision in a
Conditional construction contract in relation to payment Construction Contract in relation to payment
Payment under the construction contract is void. Under the construction contract is void.
For the purposes of this section, it is a conditional For the purposes of this section, it is a conditional
payment provision when: payment provision exists when, in relation to a
a) The obligation of one party to make payment Progress Payment, the obligation of the Principal
is conditional upon that party having received to make payment to a Contractor or supplier of
payment from a third party; or Goods or Services under the Contract is
conditioned upon:
b) The obligation of one party to make payment
is conditional upon the availability of funds (a) the Principal having received payment from a
or draw down of financing facilities of that third party; or
party.
(b) the obligation of one party to make payment
is conditional upon the availability of funds
or draw down of the Principal’s financing
facilities of that party.; or
(c) any other prerequisite that imposes payment
on a “pay when paid” basis.

56 Right to Progress A person or party to a construction contract who Proposed revision for brevity and A person or Party to a construction Contract who
Payments has undertaken to carry out work or services or conciseness, with sub-section (b) has undertaken to carry carried out Work or
supply goods is entitled to receive in a timely incorporated in the definition of supplied Goods or Services or supply goods is
manner progress payment for work done or “Payment Claim”. entitled to promptly receive in a timely manner
services rendered or goods supplied. the corresponding Progress Payment for work
(a) A request for payment shall be submitted done or services rendered or goods supplied
periodically or in a manner as specified in the in accordance with the following procedure.:
construction contract or as agreed upon by (a) A Payment Claim shall be submitted –
the parties. (i) not later than the relevant date or expiry
(b) A progress payment to which a person or of the period stated in the Contract; or
party is entitled under this Act does not (ii) if not specified in the Contract, not later
include payment for any expense, loss or than the relevant date or expiry of the
damage incurred because of a breach of a period agreed in writing by the Parties;
construction contract. or, in the absence of any such agreement,
(c) Unless otherwise stipulated in the periodically but not more than once a
construction contract or subsequent month within thirty (30) days from a
agreement of the parties, the progress milestone date or event for milestone
payment shall be made within thirty (30) days payments, and within thirty (30) days
after receipt of the request for payment, from completion of the Work or supply of
inclusive of the period for evaluation and Goods or Services for the final payment
issuance of certification for payment, as may or for a single one-off or lump sum
be required. payment.
(d) In case of disagreement, such shall be If a previously approved Payment Claim or
communicated in writing within seven (7) any undisputed or settled portion thereof
days from receipt of the request for payment remains unpaid as of the Due Date, such may
or as stipulated in the contract or within the be included in a subsequent Payment Claim.
period subsequently agreed upon by the (b) A progress payment to which a person or
parties. party is entitled under this Act does not
(e) The parties shall attempt for an amicable include payment for any expense, loss or
settlement within a period of fifteen (15) days damage incurred because of a breach of a
and shall effect payment on agreed amount construction contract.
within the 30-day period prescribed above, (b) A Payment Response shall be made –
otherwise, such disagreement or failure to
pay shall be deemed a dispute which shall be (i) within the period stated in the Contract;
referred to adjudication as provided in this or
Act. (ii) if not specified in the Contract, within
ten (10) Days from receipt of the
Payment Claim by the Principal.
(f) Payment claim not paid on due date shall (c) Payment shall be made –
earn interest computed from due date in
accordance with the 30-day regular loan rate (i) not later than the Due Date stated in the
prevailing at the time payment is due. Contract; or
(ii) if not specified in the Contract, or if the
Due Date stated in the Contract is subject
to a conditional payment provision,
within thirty (30) Days after from receipt
of the requestfor Payment Claim by the
Principal, inclusive of the period for
evaluation, and issuance of payment
certification for payment, as maybe
required, and amicable settlement of any
Payment Dispute which, if not settled in
full, shall give rise to the obligation to pay
any undisputed amount within such thirty
(30)-Day period.
(d) In case of disagreement arising from a
Payment Claim, the Principal shall serve a
Notice of Payment Dispute upon the other
Party –
(i) within the period stated in the Contract;
or
(ii) if not specified in the Contract, within
ten (10) Days from receipt of the Payment
Claim by the Principal.
(e) The Parties shall attempt for an endeavor to
arrive at an amicable settlement of the
Payment Dispute –
(i) within the period stated in the Contract;
or
(ii) within a period of fifteen (15) Days from
service of the Notice of Payment Dispute
by the Principal and shall effect payment
on agreed amount within the 30-day
period prescribed above, otherwise, such
disagreement or failure to pay shall be
deemed a dispute which shall be referred
to adjudication as provided in this Act.;
failing which, the unsettled Payment Dispute
relating to the Payment Claim or any portion
thereof, may be referred to Adjudication
by the aggrieved Party after the Due Date.

(f) An approved Payment Claim or any


undisputed or settled portion thereof, which
is not paid on Due Date, shall earn interest
computed from such due date until full
payment, in accordance with –
(i) the terms of the Contract; or
(ii) the thirty (30)-day regular loan rate of the
Land Bank of the Philippines prevailing at
The time payment is on such Due Date.

67 Right to Suspend Any person or party to a construction contract Proposed revision for conciseness. In the event of any outstanding Payment Dispute
Work or Supply of has the right to suspend the works or the supply after the Due Date, the aggrieved Any person or
Goods or Services of goods or services if no payment on its request Party to a construction contract has shall have
for payment is received on due date or if the the right to suspend the Works or the supply of
parties failed to arrive at an amicable settlement. Goods or Services if no payment on its request for
payment is received on due date or if the parties
A written notice of suspension shall be served on failed to arrive at an amicable settlement. A
the other party, its principal, and the owner, and written thereafter by serving a Notice of
such shall take effect two (2) days after it is Suspension shall be served up on the other party,
served. Its Principal, and the project owner (if the
Such party who exercises such right to suspend Principal is a Contractor), and the funders (when
is not in breach of contract and is entitled to the required under the Contract) such, which shall
following: take effect two (2) Days after it is served.
(a) a fair and reasonable extension of time to SuchThe suspension contemplated herein shall
complete its obligations under the contract; not be deemed a breach of the Contract, and the
(b) to recover any loss and expenses incurred Party who exercises such right to suspend is not
as a result of the suspension; and in breach of contract and is shall be entitled to
the following:
(c) shall resume work or supply of goods or
services immediately upon receipt of (a) a fair and reasonable extension of time to
payment. complete its obligations under the Contract;
(b) to recover any loss and expenses incurred
as a result of the suspension; and
(c) shall resume carrying out the Work or
Supplying of the Goods or Services
immediately within two (2) Days from upon
receipt of full payment.

78 Payment Disputes Any disagreement or dispute arising from a Proposed revision for conciseness. Any disagreement or Payment Dispute arising
Submitted for payment claim shall be referred to adjudication from a payment claim shall be referred to that
Adjudication under the jurisdiction of the default nominating remains outstanding after the Due Date shall
Right to authority as conferred by this Act. entitle the aggrieved Party to refer the same to
Adjudication Adjudication under the jurisdiction of the default
Nominating authority as conferred by this Act.

89 Default This Act assigns to the Construction Industry Proposed revision for clarity of intent. This Act assigns to the Construction Industry
Nominating Arbitration Commission (CIAC) the functions, Arbitration Commission (CIAC) the functions,
Authority duties, and responsibilities of the default duties, and responsibilities of the default
SOP Law nominating authority which shall have nominating authority which shall have
Adjudication jurisdiction over disputes arising from payment jurisdiction over disputes arising from payment
Authority claims under a construction contract executed claims under a construction contract executed
and carried out in the Philippines. and carried out in the Philippines.
The CIAC shall have sole and exclusive jurisdiction
over all matters pertaining to Adjudication under
this Act, and shall implement the applicable
CIAC Rules for this purpose, including but not
limited to:
(1) setting qualification requirements for the
accreditation and appointment of
Adjudicators;
(2) maintaining a roster of accredited
Adjudicators;
(3) providing training programs for Adjudicators;
(4) exercising the authority to appoint and
replace Adjudicators in institutional
Adjudication Proceedings, and as the default
nominating authority for ad hoc Adjudication
Proceedings;
(5) providing administrative support in the
conduct of Adjudication Proceedings;
(6) imposing an effective mechanism for the
enforcement of payment obligations arising
from ad hoc or institutional Adjudication
Determinations, including requiring deposits
and holding the same in escrow to secure the
prompt payment of any such monetary
obligations;
(7) determining and collecting Adjudication costs,
fees and charges for the performance of its
duties under this Act; and
(8) performing such other functions as may be
necessary for the proper discharge of its
powers and authority under this Act.

9 Powers and The CIAC, as the default nominating authority, Propose to delete and incorporate The CIAC, as the default nominating authority,
Functions of shall perform, among others as may be conferred CIAC’s powers and functions in the shall perform, among others as may be conferred
the Default by law, the following: provision declaring CIAC as the by law, the following:
Nominating Adjudication Authority for unresolved (a) Formulate and prescribe rules and regulations
Authority (a) Formulate and prescribe rules and regulations Payment Disputes that have ripened
for the adjudication of payment claims and for the adjudication of payment claims and
into Adjudication Claims under this Act. disputes arising from a construction contract
disputes arising from a construction contract and for enforcement of the determination
and for enforcement of the determination by the adjudicators;
by the adjudicators; (b) Set qualification and competency standard
(b) Set qualification and competency standard and criteria for selection and accreditation
and criteria for selection and accreditation of adjudicators;
of adjudicators; (c) Establish and maintain a register of accredited
(c) Establish and maintain a register of accredited adjudicators and provide training programs
adjudicators and provide training programs for them;
for them; (d) Exercise such authority to appoint and
(d) Exercise such authority to appoint and replace adjudicators;
replace adjudicators; (e) Provide administrative support for the
(e) Provide administrative support for the conduct of adjudication proceedings;
conduct of adjudication proceedings; (f) Exercise such authority to determine and
(f) Exercise such authority to determine and collect fees, costs of adjudication, and other
collect fees, costs of adjudication, and other charges as may be necessary in the
charges as may be necessary in the performance of its functions and
performance of its functions and responsibilities under this Act;
responsibilities under this Act; (g) Receive and hold any fees and expenses
(g) Receive and hold any fees and expenses deposited by the parties on behalf of an
deposited by the parties on behalf of an adjudicator including the fees for an expert,
adjudicator including the fees for an expert, as well as the deposit representing the
as well as the deposit representing the amount due and payable under the
amount due and payable under the Adjudication Determination in the event the
Adjudication Determination in the event the dispute is referred to arbitration or to the
dispute is referred to arbitration or to the Court for final determination/resolution;
Court for final determination/resolution; (h) Any function necessary for the efficient
(h) Any function necessary for the efficient conduct of the adjudication proceedings.
conduct of the adjudication proceedings.

1410 Adjudication The adjudication proceedings shall commence Proposed revision for clarity of intent. The adjudication proceedings shall commence
Proceedings after the acceptance of appointment by the after the acceptance of appointment by the
adjudicator/s and shall be conducted in a manner QUERY: When does an Adjudication adjudicator/s and shall be conducted in a manner
as may be prescribed by the CIAC. Proceeding commence? Is it upon as may be prescribed by the CIAC.
initiation by service of the Notice of A Claimant shall initiate ad hoc or institutional
Adjudication; or only upon acceptance Adjudication Proceedings by serving a Notice of
of appointment by the Adjudicator(s)?
Aren’t Adjudicators appointed only Adjudication as a condition precedent.
upon acceptance?
Ad hoc Adjudication Proceedings shall be
conducted in accordance with the applicable
provisions of the Contract that conform with
the CIAC Rules; otherwise, institutional
Adjudication by the CIAC shall apply.

The Adjudication Proceedings shall be conducted


in the manner prescribed in this Act and in
accordance with the CIAC Rules.

1011 Notice of Any person or party to a construction contract Proposed revision for brevity and Any person or party to a construction contract
Adjudication may, after the expiry of the period the payment clarity of intent. may, after the expiry of the period the payment
claim is supposed to be due and payable or claim is supposed to be due and payable or
after the expiry of the 15-day period within which after the expiry of the 15-day period within which
the parties shall settle the dispute amicably as the parties shall settle the dispute amicably as
contemplated under Sec. 5(e), initiate the contemplated under Sec. 5(e), initiate the
submission of a payment dispute to adjudication submission of a payment dispute to adjudication
under the jurisdiction of the CIAC by serving on under the jurisdiction of the CIAC by serving on
the person or party concerned a written notice of the person or party concerned a written notice of
adjudication and submitting to the CIAC its adjudication and submitting to the CIAC its
request for adjudication in the form and manner request for adjudication in the form and manner
as may be prescribed. as may be prescribed.
The Claimant shall serve a Notice of Adjudication
upon the Respondent, the project owner (if the
Respondent is a Contractor), and the funders
(when required under the Contract):
(a) within the period stated in the Contract; or
(b) if not specified in the Contract, within fifteen
(15) Days from the Due Date of the Progress
Payment or portion thereof which is the
subject of the Adjudication Claim.

1112 Costs of All expenses of the adjudication, including the Proposed revision for brevity. All costs, charges, and incidental expenses of the
Adjudication fees of the adjudicators, all incidental expenses Adjudication, including the Adjudicator’s fees,
and other related charges which may be imposed shall be computed and paid in accordance with
by the CIAC, shall be computed and paid in the schedule of fees as maybe prescribed or
accordance with the schedule of fees as may be assessed by the CIAC.
prescribed.

1213 Adjudicators One or more adjudicators may settle a payment Proposed revision for brevity and One or more adjudicators may settle a payment
dispute who shall be appointed in accordance clarity of intent. dispute who shall be appointed in accordance
with the rules as may be prescribed by the CIAC. with the rules as may be prescribed by the CIAC.
Adjudicators shall be men of distinction in whom Adjudicators shall be men of distinction in whom
the stakeholders of the construction industry and the stakeholders of the construction industry and
the government can have confidence and are the government can have confidence and are
available to render services when called to available to render services when called to
adjudicate. They shall possess the competence, adjudicate. They shall possess the competence,
integrity, and leadership qualities to resolve integrity, and leadership qualities to resolve
payment disputes expeditiously and equitably. payment disputes expeditiously and equitably.
They shall be given fees for each payment They shall be given fees for each payment
dispute they settled. dispute they settled.

The adjudicators shall come from different The adjudicators shall come from different
professions. They may include engineers, professions. They may include engineers,
architects, construction managers, engineering architects, construction managers, engineering
consultants, and businessmen familiar with the consultants, and businessmen familiar with the
construction industry and lawyers who are construction industry and lawyers who are
experienced in construction disputes. experienced in construction disputes.
An Adjudication Claim shall be determined by
one (1) or three (3) Adjudicators to be selected
based on the qualification requirements and
appointed in the manner prescribed under
the CIAC Rules.
The CIAC is appointed as the default nominating
authority for Adjudicators in any ad hoc
Adjudication where the selection process based
on the Contract is deficient or inadequate.
Adjudicators shall not be held civilly liable for
lawful acts done in the performance of their
duties, except in a clear showing of bad faith,
bribery, fraud, or gross negligence.

13 Adjudicators The adjudicators shall not be civilly liable for acts QUERY: Is an Adjudicator deemed a The adjudicators shall not be civilly liable for acts
Exempt from done in the performance of their official duties public officer within the purview of the done in the performance of their official duties
Civil Liability for except in a clear showing of bad faith, malice, or Administrative Code of the Philippines? except in a clear showing of bad faith, malice, or
Official Acts gross negligence as provided in Sec. 38 (1), Is there employment by the State upon gross negligence as provided in Sec. 38 (1),
Chapter 9, Book 1 of the Administrative Code of inclusion in the roster of pre-qualified Chapter 9, Book 1 of the Administrative Code of
1987 (Executive Order No. 292, signed on July 25, Adjudicators by the CIAC? What about 1987 (Executive Order No. 292, signed on July 25,
1987). Adjudicators appointed through the ad 1987).
hoc selection process who are not in
the roster of pre-qualified CIAC
Adjudicators?
Propose to incorporate the intent of
exemption from civil liability in the
discharge of duties as Adjudicators
under the preceding section on
“Adjudicators”.
1514 Confidentiality Any person or party to an adjudication Proposed revision for brevity. Any person or party to an adjudication
of Adjudication proceedings including an adjudicators, shall not proceedings including an adjudicators, shall not
Proceedings disclose to any person, except for the principal or disclose to any person, except for the principal or
the owner, any information; statement; and the owner, any information; statement; and
document created or made for the purpose of the document created or made for the purpose of the
adjudication, except with the consent of the adjudication, except with the consent of the
parties; or when the disclosure is necessary for parties; or when the disclosure is necessary for
the enforcement of the Adjudication the enforcement of the Adjudication
Determination or any proceedings before a Court Determination or any proceedings before a Court
or any other dispute resolution proceedings; or if or any other dispute resolution proceedings; or if
the information is already in the public domain. the information is already in the public domain.
Any person who violates shall be subject to the Any person who violates shall be subject to the
sanctions as may be prescribed or initiated by the sanctions as may be prescribed or initiated by the
CIAC, which shall include administrative/ CIAC, which shall include administrative/
disciplinary and/or suspension or disbarment disciplinary and/or suspension or disbarment
action if the violator is a lawyer. action if the violator is a lawyer.
The confidentiality of Adjudication Proceedings
and all matters taken up therein shall be
maintained at all times by the parties thereto,
including the Adjudicator, with the exception of
permitted disclosures in accordance with the
CIAC Rules.
Any person who violates this confidentiality
requirement shall be meted the corresponding
sanctions prescribed by the CIAC Rules.

1615 Adjudication The determination of the adjudicators on the Proposed revision for clarity and The Adjudication Determination of the
Determination payment claim shall be rendered promptly conciseness. adjudicators on the payment claim shall be
within fifteen (15) days from commencement of rendered promptly within fifteen (15) Days
the adjudication proceedings or within such from commencement of the Adjudication
period as may be prescribed by the CIAC, which Proceedings and appointment of the
shall be made in writing in the prescribed format Adjudicator(s), or within such longer period as
containing, among others, the following: may be prescribed by allowed under the CIAC
(1) reasons for such determination; Rules, which and shall be made in writing
In the prescribed format containing, among
(2) the time and manner the sum due is payable; Others at least, the following:
(3) the cost of adjudication, which should include (a) the reasons for such determination;
the fees and expenses to the adjudicator/s
and the fees paid to the CIAC; and the (b) the time and manner the any sum due is
determination on which of the parties should payable; and
bear the costs and in what proportion should (c) the final cost of Adjudication, which should
it be shared by the parties. include the fees and expenses to the
adjudicator/s and the fees paid to the CIAC;
The adjudicator shall, motu propio or upon and the determination on which of the
request of a person or party to adjudication, parties who should bear the such costs and,
correct the Adjudication Determination on any of or in what proportion it should it be shared
the following grounds:
(a) an evident miscalculation of the figures, a by the parties Claimant and the Respondent.
typographical or arithmetical error; or The Adjudicator(s) shall, motu propio or upon
(b) an evident mistake in the description of any request of a person or party to Adjudication,
person, party, date, or amount. correct the Adjudication Determination on any of
the following grounds:
(a) an evident miscalculation of the figures, a
typographical or arithmetical error; or
(b) an evident mistake in the description of any
person, party, date, or amount.

1716 Finality of The determination of the adjudicators is binding Proposed revision for conciseness. The Adjudication Determination of the
Adjudication upon the parties, unless – Adjudicators is shall be binding upon the
Determination Parties Claimant and Respondent, unless –
(a) it is set aside by the Court on any of the
following grounds: (a) it is set aside by the Court on any of the
following grounds:
(1) the adjudicator committed fraud or
bribery; (1) the an Adjudicator committed bad faith,
Fraud,or bribery, or gross negligence;
(2) there has been a denial of due process;
(2) there has been a denial of due process;
(3) the adjudicator has not acted
independently or impartially; or (3) the an Adjudicator has not acted
independently or impartially; or
(4) the adjudicator has acted in excess of
his/her jurisdiction; (4) the an Adjudicator has acted in excess of
his/her jurisdiction;
(b) the subject matter of the determination is
settled by a written agreement between the (b) the subject matter of the determination
parties; or Adjudication Claim is was settled by a written
agreement between of the parties Claimant
(c) the dispute is finally decided by arbitration or and Respondent prior to finality of the
the Court. Adjudication Determination; or
Any person or party to adjudication may (c) the dispute Adjudication Claim subject of the
commence proceedings to set aside the Adjudication Determination is finally
Adjudication Determination or refer the dispute subsequently decided by arbitration or the
to arbitration for final determination. Court.
In that case, the person or party who was The Any person or party to against whom the
held liable to pay under the Adjudication Adjudication Determination was made may
Determination shall deposit to the CIAC the full commence proceedings in Court to set aside the
amount due and payable in such manner as may Adjudication Determination, or refer the dispute
be prescribed by the CIAC, pending final to arbitration for final determination.
resolution of the dispute. In that any such case, the person or party who
was held liable to pay under the Adjudication
Determination shall deposit to the CIAC the full
amount due and payable in such the manner as
may be prescribed by, and for proper disposition
in accordance with, the CIAC Rules, pending final
resolution of the dispute by the Court or arbitral
body.
1817 Execution and The Adjudication Determination is executory Proposed revision for conciseness and The Adjudication Determination is shall be
Enforcement of immediately upon receipt thereof by the parties clarity of intent. immediately executory immediately upon receipt
Adjudication which shall be enforced on motion of any of the thereof by the parties Claimant and Respondent,
Determination parties in accordance with the rules as may be which and shall be enforced on motion of any
prescribed by the CIAC. either of the parties them in accordance with the
rules as may be prescribed by the CIAC Rules.
Where a party fails to pay the whole or any part Where a party fails to pay the whole or any part
of the adjudicated amount, the aggrieved party of the adjudicated amount, the aggrieved party
is entitled to any of the following: is shall be entitled to any of the following:
(a) apply for an enforcement of the Adjudication (a) apply for an enforcement of the Adjudication
Determination as if it were a judgment debt; Determination with the CIAC as if it were a
or judgment debt; and
(b) exercise lien on goods supplied under the (b) avail of payment from the retention money
construction contract that are unfixed and upon submission of a performance bond in
which have not been paid for; or accordance with the CIAC Rules; or
(c) request payment directly from respondent’s (c) exercise a lien on the Goods or Services
principal. supplied under the construction Contract
that are unfixed and which have not been
Any such amount paid by the principal under this paid for; or
section shall be treated as payment for any
amount due or may be due to the respondent (d) request payment directly from respondent’s
under the construction contract. Principal the project owner or funders, as
applicable.
The remedies provided in this Act are without
prejudice to other rights and remedies available Any such amount paid out of the retention
in the construction contract or those provided money, or by the principal project owner or any
by law. of the funders under this section, shall be treated
as payment for any amount due or may be due to
the Respondent under the construction Contract.
The remedies provided in this Act are without
prejudice to other rights and remedies available
in the construction Contract or those provided
by under the law.

2018 Separability Clause The provisions of this Act are declared to be Proposed revision for brevity. The provisions of this Act are declared to be
separable, and if any provision on the application separable, and if any provision on the application
hereof is held invalid or unconstitutional, the hereof is held invalid or unconstitutional, the
validity of the remaining provision not otherwise validity of the remaining provision not otherwise
affected shall remain in full force and effect. affected shall remain in full force and effect.
If any provision of this Act is held unconstitutional,
the other provisions shall not be affected thereby.

2119 Repealing Clause All provisions of existing laws contrary to or Proposed revision for clarity of intent. All provisions of existing laws contrary to or
inconsistent herewith are hereby repealed or inconsistent herewith are hereby repealed or
modified accordingly. modified accordingly.
All contrary provisions of existing Contracts
eligible for security of payment under this Act
are deemed superseded by this Act.

2220 Effectivity Clause This Act shall take effect fifteen (15) days after
its publication in the Official Gazette or in a
newspaper of general circulation.

You might also like