Professional Documents
Culture Documents
CHAPTER – 8
ECONOMIC ANALYSIS
The underlying objective of Economic Analysis is to maximize the returns on the investment. The
concept behind the economic appraisal of the Project is that if it is implemented, the resulting
benefits will be the decreased costs road users when compared to the costs of the ‘base’ situation.
This objective is accomplished by determining the appropriate improvement alternative that leads
to the minimum total transport costs.
The total transport costs comprise two basic components (Table 8.1), viz. road supplier costs and
road user costs.
The economic appraisal is carried out by using the HDM-IV model. The model is used to
generate cash flow streams of VOC and travel time to compute the net economic benefits, as
JMSPL, DHARWAD: BANGALORE | 1
[VIJAYAPURA TO SANKESHWAR ROAD] FEASIBILITY REPORT
inputs for the estimation of the Economic Internal Rate of Return (EIRR) and Economic Net
Present Value (ENPV).for Project evaluation.
Total road length of 168.875 km is divided into four packages. Each package length includes
average of 40.00 km. For the present study of economic analysis package – I is selected which
starts from Vijayapur (Afzalapur Takke) to near Savalagi cross i.e, 0.00 to 40.00km.
In brief, the following two Strategies have been considered and evaluated in this study:
This strategy has been termed “Do Minimum Scenario” where the existing road network is
maintained at current levels and no improvements are envisaged. In this situation, the projected
future traffic is assumed to use the existing road in a congested traffic flow condition.
Agency costs (maintenance cost), distance and time related vehicle operation costs together with
travel time costs and accident costs pertaining to this alternative will form the base on which net
project cost and benefit streams during the analysis period are calculated for each ‘with project’
alternative.
construction is complete, the agency will perform routine maintenance and other maintenance
works every year. Also the road will receive a 20mm functional overlay whenever IRI reaches 6,
which would reduce surface roughness to 2.5m/km.
This strategy forms a ‘With Project’ alternative and is compared to ‘Without Project’ alternative.
Length (Km)
Carriageway
MT NMT
Width (m)
Width (m)
Shoulder
Speed Flow Surface
ID Name Road Class Climate Zone
Type Class AADT AADT
Remarks
2019 yr 2019 yr
Vijaypur - Two Lane Primary or Subtropical -
A-01 Bituminous 40 7.00 1.50 7,363 118
Sankeshwar Wide Trunk Hot / Semi-arid
Table 8.5 HDM Input: Road Sections- Geometry of the Project Road
Speed
Rise + Fall Curvature Horizontal
ID Name Speed Flow Type Limit
(m/km) Deg/km Superelevation (%)
(km/h)
Table 8.6 HDM Input: Road Sections – Pavement Condition of the Project Road
Current Previous
Last Last Base
Surface Surface
ID Name Material Type Construction Rehabilitation Thickness
Thickness Thickness
Year Year (mm)
(mm) (mm)
A-01 Vijaypur - Bypass Asphalt Concrete (AC) 60 50 1998 2003 320
8.1.7 Traffic
JMSPL, DHARWAD: BANGALORE | 5
[VIJAYAPURA TO SANKESHWAR ROAD] FEASIBILITY REPORT
The Assignable traffic likely to use the Proposed Project Road has already been discussed in the Traffic Study Report. For the economic Analysis, fast
moving motorised traffic including two wheelers and non-motorised vehicles have been considered. The motorised and non-motorised with vehicle
composition are shown in (Table 8.7).
Table 8.7 MT and NMT with Vehicle Composition
Tikota
Vehicle
ADT,No' Composition
Type of Vehicles s
Car 2270 31.00
Mini -Bus 90 1.00
Pvt bus 12 0.00
Govt Bus 396 5.00
LCV 579 8.00
Truck-2axle 340 5.00
Truck-3axle 308 4.00
Truck-4 to 6 axle 340 5.00
2 wheelers 2846 39.00
3 wheelers 182 2.00
Cycle 84 1.00
Animal Drawn 34 1.00
Total (No) 7481 100
The capital costs (financial) of the project road have been converted into economic costs by using
a standard conversion factor of 0.9, to construction costs (road works and structures). The
economic cost of acquisition, Quality and Project Development cost has been taken as the same
as financial cost, without resorting to shadow pricing or assessing opportunity cost in any other
alternative. The project costs, over the construction period, are shown in Table 8.9 below:
Table 8.9 The breakup of Total Project taken in the Analysis is as follows
Sl.No
Item Amount, Rs Amount, Cr
.
I ROAD WORKS
1 Site Clearance 2,70,605.00 0.03
2 Earthwork 19,05,76,973.00
II Structure Works
2,54,26,17,965.0
Total Project cost including centages = D 254.26
0
Total Length of project (km) 39.845 39.845
Other maintenance: additional operational expenses associated with project such as traffic
signposts, lighting etc., are considered as annual charges and included in routine maintenance
costs. For annual supervision & administration charges, it has been assumed that the arrangement
under ‘without project’ will continue for the ‘with project’ situation.
Details of the maintenance programme followed for the project road sections under different
situations along with their unit rates, followed in the analysis, are summed up below in Table
8.11 to Table 8.13
Table 8.12 Annual/Periodical Maintenance Programme for the Existing Road Sections
Sl. Starting Interval
Maintenance Type Overlay Thickness (mm)
No. year /Intervention
1 Crack Sealing 2020 Annual 100% repair of cracks
2 Patching & Pothole filling 2020 Annual 100% repair of damaged area
3 Thin Overlay 2020 Every 5 Years 20 PMC
Values of the selected construction items such as LA cost, structures, sub-base, social
displacement cost etc. are included in the economic analysis as residual values at the end of the
analysis periods. These residual values are considered, as benefits to the project in the analysis.
In order to maintain uniformity among studies, (MoSRTH and Government of India) has
suggested that 20% of the project cost shall be considered as salvage value at the end of the
analysis period for economic evaluation studies for BOT highway projects in India. The same has
been adopted for present study.
A pilot survey has been conducted to estimate the wages of drivers and their assistants. The crew
cost is estimated with 2400 hours of work time per annum. With respect to maintenance and
labour costs, local workshops have been contacted to assess the annual wage bill and assuming
2400 hrs of work per annum, the labour costs have been calculated per hour.
The value of passenger time has been calculated based on the average annual income of
passenger collected with the assumption of 2400 hours of work time per annum. About 30
percent of the trips are assumed to be made during non-work hours. Finally, a weighted average
of time value per hour has been calculated. Time saving values applicable to the year 1990
(IRC:SP-30) have been adopted and projected to year 2015.
Based on the above considerations, the economic costs estimated for different VOC components
are presented in Table 8.14 below:
2-Wheelers
MA-Truck
Car (OT)
Car (NT)
Mini Bus
2-Truck
3-Truck
Basic
Bus LCV
Characteristics
A. Vehicle Characteristics
Gross Vehicle
1.4 2 0.2 2.5 10 3.5 15.7 25 40
Weight (t)
ESAI Factor Per
0 0 0 0.1 0.7 0.3 4.5 4.5 4.5
Vehicle
Number of Axles 2 2 2 2 2 2 2 3 5
Number of Tyres 4 4 2 4 6 4 6 10 18
Number of
4 5 2 20 55 2.3 2.4 2.5 3
Passengers
B. Vehicle Utilization Data
Service Life (Yr.) 10 10 10 10 10 12 10 10 12
Hours Driven per
1950 1950 700 1500 2000 1600 2100 2200 2400
Yr.
Km Drive per Yr. 32000 32000 21000 60000 70000 60000 85000 86000 120000
Annual Interest
12 12 12 12 12 12 12 12 12
Rate (%)
C. Economic Unit Costs
New Vehicle Price
303400 266028 35000 444500 897139 383145 842200 869472 1661131
(Rs.)
New Tire Price
660 1291 350 3592 6255 3593 7613 7613 7613
(Rs.)
Maintenance
120 120 110 120 120 110 110 110 120
Labour (Rs./hr.)
Crew Cost
105 105 90 105 105 105 105 105 105
(Rs./crew-hr.)
Passenger Time
30 30 40 20 20 10 10 10 10
(Rs./pa-hr.)
Cargo Time
0 0 0 0 0 50 60 85 100
(Rs./veh-hr.)
Gas/Petrol Price
51
(Rs./ kg.)
Diesel Price
39
(Rs./lt.)
Lubricants Price
140
(Rs./kg.)
The effect of traffic congestion is considered separately in HDM Manager for distance related
components (fuel, lubricants, tyres, spare parts & maintenance labour) and time related
components (depreciation, fixed costs, wages, value of passenger time and value of commodity in
transit.
The detailed analysis of HDM-4 report has been furnished in Anexure-8.1 to 8.4.