Professional Documents
Culture Documents
Steel of Spillway
Steel of Spillway
2 Nov 64
jump. Thorough investigations of foundation conditions and liberal allowances for uncertainties
are necessary as a basis for such design.
/. Floor Slab Anchorage. Anchorage is usually provided for spillway chute and stilling basin
floor slabs on rock foundations by dowels grouted in holes drilled into the rock to a depth sufficient
to engage a mass of rock the submerged weight of which will withstand the net upward forces,
assuming the mass of rock bounded by a 90° apex angle at the bottom with allowance for overlap.
This criterion applies to other anchorages also. Anchorage for a spillway chute floor slab without a
drainage blanket should be provided for at least 5 feet of excess hydrostatic uplift at the invert (as
outlined in par. 2-08c) when conditions are favorable. A larger uplift pressure should be used
for anchorage design when investigations indicate higher values under natural or reservoir con
ditions. The uplift forces acting on a stilling basin floor slab are generally greater than the uplift
on a chute floor and should be based on paragraph 2-08(2.
g. Floor Slab Reinforcing. In thick slabs on rock foundations normally covered with tail-
water, horizontal reinforcement is not necessary except possibly in the baffles. Uplift on a slab
should be taken care of by adequate anchors as discussed above.
Two general plans of reinforcement for crack control in spillway chute and stilling basin floor
slabs are in common use. In one plan the slab is divided into independent approximately square
blocks by contraction joints, parallel and perpendicualr to the channel or basin center line and
close enough to avoid serious shrinkage and temperature cracking with the use of nominal reinforce
ment, which does not extend across the joints. In the other plan the reinforcement steel is con
tinuous through all joints (which thus become construction joints) and a somewhat larger percentage
of steel is used. Details of these two plans are discussed below.
Independent Block Plan. This plan provides satisfactory crack control with a rninimum amount
of reinforcement steel for a slab on unyielding rock. However, on relatively yielding rock or earth
foundations the independent floor blocks are subject to possible differential movement of adjacent
blocks. With this system of reinforcement, a key at each transverse contraction joint (extending
into the foundation under the joint, attached to the slab downstream and supporting the slab
upstream from the joint) is required on earth foundations and on some yielding rock to prevent the
downstream side of a joint from being raised above the upstream side, as water at high velocity
striking such a projection would increase the hydrostatic pressure in the joint and hence the uplift
under the slab. The higher the velocity the more serious will be the condition resulting from such
relative movement.
Generated on 2015-08-26 06:27 GMT / http://hdl.handle.net/2027/coo.31924077820375