Professional Documents
Culture Documents
ASSIGNMENT (1)
1. If the cost of manufacturing (direct material and direct labour) is 70% of sales and
profit is 13% of sales, what would be the improvement in profit if, through better
planning and control, the cost of manufacturing was reduced from 70% of sales to 60%
of sales?
Profit = 13%
Profit = 13%
After improvement -
overhead = 17 %
Before improvement profit was 13 % and after improvement it reaches at 23%. So,
2. In problem 1, how much would sales have to increase to provide the same increase in
profits?
0.23+0.87 = Sales
Sales = 1.10
3. On the average, a company has a work-in-process lead time of 12 weeks and an annual
cost of goods sold of $25 million. Assuming that the company works 50 weeks a year:
B) If the lead time could be reduced to 9 weeks and the annual cost of carrying
inventory was 18% of the work-in-process inventory value, what would be the annual
savings?
4
=$1,500,000
4. If the opening inventory is 700 units, demand is 1250 units, and production is 900
5. A company wants to produce 35,000 units in a 4-month period. The months have 22, 21,
20, and 21 working days, respectively. What should the average daily production be?
1 22
2 21
3 20
4 21
5
Total 84
= 35000 / 84
7. Demand for bicycle helmets is expected to be 12,000, 15,000, 14,000, 8,000, and 5,000
for the next 5 months. Create a table showing a 5-month production plan for using a
chase strategy.
Answer -
1 12000 10800
2 15000 10800
3 14000 10800
4 8000 10800
5 5000 10800
= 54000 / 5
= 10800
So, company will produce 10800 bicycle helmets in each month for completing
expected demand.
8. A production line is to run at 1300 units per month. Sales are forecast as shown in the
following. Calculate the expected period-end inventory. The opening inventory is 700
Period 1 2 3 4 5 6
Planned 700
Inventory
9. A company wants to develop a level production plan for a family of products. The
opening inventory is 100 units. The demand for each of the periods is given in what
Period 1 2 3 4 5 6 Total
Demand
Planned
Production
Planned
Inventory
1 875 1010
2 1100 1010
3 1220 1010
4 835 1010
8
5 1050 1010
6 980 1010
Answer – Yes, there is one problem in the 3 rd period. There forecast demand is 1220 and
Planned production is 1010 units so if we join the planned inventory and planned
D) If it cost of carrying inventory is $2.50 per unit per period based on ending inventory,
Answer -
5 70 2.50$ 70 X2.50=175
10. Because of its labour contract, a company must hire enough labour for 100 units of
production per week on one shift or 200 units per week on two shifts. It cannot hire, lay
off, or assign overtime. During the fourth week, workers will be available from another
department to work all or part of an extra shift (up to 100 units). There is a planned
shutdown for maintenance in the second week, which will cut production to half.
Develop a production plan. The opening inventory is 200 units, and the desired ending
inventory is 300units.
Week 1 2 3 4 5 6 Tota
Planned Production
10
Planned
Inventory
inventory
while, in second week the production will cut for half so total week is 6 and
Each week production is 200 units so 200 X 5.5 = 1100 units will produce in
5.5 weeks.
In forth week, shift worker from other department for extra shift
1180 – 1100 = 80 units (this is the extra units produce in fourth week)
Plan production –
Week 2 – 100 units (because half shift shut down for maintenance)
Week 4 – 200+80 = 280 units (80 units extra produce with extra labour)
demand
Reference
https://www.chegg.com/homework-help/questions-and-answers/level-strategy-formulas-
production-required-total-demand-beginning-inventory-minimum-produ-q27084916
https://www.chegg.com/homework-help/questions-and-answers/level-strategy-formulas-
production-required-total-demand-beginning-inventory-minimum-produ-q27084916.(n.d.).