Professional Documents
Culture Documents
fenix
‘… a step towards the future of
electricity networks’
Prague, 8-11 June 2009
Objective
Enabling Distributed Energy Resources (DER) to make
the EU electricity supply system cost efficient, secure
and sustainable through aggregation into Large Scale
Virtual Power Plant (LSVPP)
Prague, 8-11 June 2009
Project Coordinates
United Kingdom
Romania
France
Slovenia
4
Prague, 8-11 June 2009
VPP concept
400 kV 400 kV
400kV =
G G
132kV
VPP
(G&L)
P, Q
P, Q
Characteristics of
aggregated active
generation and
33kV 11kV
G L
load:
G L
11 kV/0.4 kV (1) Output
(2) Reserve
LV area 1 LV area 2
TVPP area 1 TVPP area 2
(3) Dynamic response
(4) Cost characteristics
Prague, 8-11 June 2009
Progress We
are
here
Specification
Building the
and
demonstrations
development
Market
Market
Sale of
electricity / Use of
flexible TSO transmission
demand Ancillary system
services Services
Distributed
Distributed
Distributed
Distributed
Distributed TSO TAO
TAO
Energy
Energy
Energy TSO
Energy
Energy
Energy CVPP
CVPP
Resource
Resource
Resource
Resource
Resource
Connection
Local & use of
Network distribution
Services system
TVPP
TVPP DAO
DAO
6
Electricity
Revenue
Prague, 8-11 June 2009
2. Identify network needs and the way to satisfy them using DER
4. Investigate aggregation (VPP) so the limited size of DER and their non-deterministic
behaviour limitations can be overcome
Demonstration
Bilbao
Alava Network
Valladolid
• Area around 3.000 km2
• 169.001 Low Voltage Customers
Madrid – 70% Urban
– 12% Suburban
Toledo Valencia – 17% Rural
Alicante • 1.234 MVA = Total Capacity
– 687 MVA Installed capacity (1775 T.C.)
– 547 MVA Contracted capacity (799 T.C.)
• 1.907 Km of lines
Región Este
– 80% aerial
Región Madrid
– 20% underground
Región Centro
Región Norte
Región Oeste
Control Centre
Prague, 8-11 June 2009
G SALINERA G G
7,5 MW 13,2 kV
BADAIA
G 50 MW
PUENTELARRA ALSASUA
What is demonstrated?
What is new?
1. Aggregating DER of different technologies
2. In Spain Generation schedules are validated only by TSO,
considering the Transmission Network
3. Currently no SO is using DER capacities to give system
support, eg. tertiary reserve
4. VVC optimizing Distribution networks that consider DER
outputs as a control variables is non exiting (requires State
Estimation in Distribution).
5. Back-up generators are not allowed to export energy into
the network
Prague, 8-11 June 2009
FB - Communications
Environmental benefits FENIX future
CVPP - DEMS (Higher DER
TVPP - DSO/TSO developments and Energy –price reduction penetration)
If Current Status Quo operational costs
Tertiary reserve price reduction
Distribution
Networks
DER
Transmission
Networks Distribution
and
Transmission
Networks
Central control
Fenix control
Central
Generation Central
Generation
Regulatory recommendations
- Allow DNOs to benefit from active networks investments if
Distribution
Distribution defer capital expenditure
network
network revenue
revenue
regulation - Unbundling of network businesses should not block
regulation
cooperation among DER and network operators
Subsidies
Subsidies for
for
renewable
renewable energy
energy - Support mechanisms for DER must allow to benefit from
generation participating in ancillary service provision (ex. through Virtual
generation and
and
CHP Power Plants)
CHP
Impact
• Potential impact is large, and grows with
penetration (…as DG becomes comparable in
size to centralised generation, and hence
implements more flexibility)
• However DG was not designed technically to
give support to the system. And still many
barriers still exist (too many “new” things),
and differ among countries
• At the end of the project an impact for the
2020 EU scenario will be released
José M. Corera – Spain Round Table RT4
Prague, 8-11 June 2009
We see FENIX as a
forerunner to the future
Smartgrids. But a lot has
to be done yet.
Thank you!
José M. Corera – Spain Round Table RT4