Professional Documents
Culture Documents
Vs
With
Contempt Case (AT) (MRTP) No. 05/2017
In Transfer Original Petition (AT) (MRTP) No. 04/2017
(Old Contempt Application No. 02 /2016
in Old RTPE No. 176/1999)
Vs
Present:
JUDGMENT
ASHOK BHUSHAN, J.
The Transfer Original Petition and Contempt Case have been heard
1
2. We may first notice the facts and sequence of events of the Transfer
Original Petition.
construction.
as well as on the ground floor. The rates and area of the shops
2
(iii) The Delhi Development Authority (“DDA”) had cancelled the
depositing ground rent and stamp duty etc., which was replied
(iv) The Complainants filed complaint under Section 10(a) (i), (iv),
2(o) (ii), 36B (a)/(d) read with section 36A (i), (ii), (iv), (vi) and
(ix) of the MRTP Act, 1969. The Complainants alleged that acts
Complainants:
3
Sq. fts., B2 measuring 332 Sq. fts., G9 measuring
92 Sq. fts. & G10 measuring 138 Sq. fts. as
required by the complainants in serviceable
conditions;
(e) To grant an ad-interim exparte injunction as prayed
for in the application under Section 12A MRTP Act
(f) Any other or further orders as may be necessary.
(f) Relief.
(g) Costs.”
would amount to unfair trade practice on the part of the Respondents. The
Commission were restrained from creating any interest of any third party
in the subject matter of the proceeding till further order. The interim
notices issued to the Respondent though were served, but Respondents did
thereafter and filed reply on 16.04.2001. In the reply one of the pleas of
the Respondent was that Respondents are ready and willing to give
evidence and further direction was to fix the case for ex-parte final
4
appeared and sought adjournment on the ground that there is possibility
dated 23.09.1999.
for recording of the evidence before the Registrar. In the year 2014 on the
request of the parties matter was also referred to Delhi High Court
Supreme Court. The Complainants were given liberty to revive the RTPE
in case they fail to get relief from the Hon’ble Supreme Court.
before the Delhi High Court, on 16.09.2002, the Company Judge admitted
02.09.2004, the Company Petition was finally allowed by the High Court.
The High Court vide order dated 02.09.2004 directed the Provisional
5
Liquidator to act as the Liquidator. By order dated 17.08.2006 passed by
Hon’ble Supreme Court in T.P. (C) No.113 of 2006, Company Petition No.96
of 1997 along with all other Company Applications pending before the High
Court were transferred to Supreme Court. The Hon’ble Supreme Court vide
to the Petitioner in full and final settlement of all the claims, consequently
Court. The Transfer Petition(s) Civil No.1862 of 2014 was dismissed by the
vide its order dated 08.08.2016 revived the RTPE No.176 of 1999 and
of the case, the evidence of the parties were recorded including the cross-
by Act 7 of 2017 (The Finance Act, 2017) with effect from 26th May, 2017,
under Section 410 of the Companies Act, 2013 from the date of
commencement of Part XIV of Chapter VI of the Finance Act, 2017 for the
purposes of Competition Act, 2002 and the old complaint RTPE 176 of 1999
6
7. The Original Transfer Petition has been heard before this Appellate
Tribunal. On request for the parties, Transfer Original Petition was also
could not arrive at a consensus, hence, the matter was listed for hearing.
No.2 and Shri Prabhjeet Singh, son of Shri Tejwant Singh as Respondent
No.3 for willful and deliberately flouting the order of the Tribunal. In the
Respondent Nos. 2 and 3 have deliberately and willfully flouted the order
Contempt Application No. 2 of 2016, in fact order was reserved on 18th May,
dated 26th May, 2017, by which Notification, Section 53A was substituted
by Act 7 of 2017 of Finance Act and with effect from 26th May, 2017,
the purposes of the Competition Act, 2002. After coming into force the
substituted Section 53A, the Contempt Application No.2 of 2016 was re-
7
registered before this Appellate Tribunal as Contempt Case (AT) (MRTP) No.
05/2017. The Contempt Case (AT) (MRTP) No. 05/2017 and Transfer
Original Petition (AT) (MRTP) No.04 of 2017 were heard together and as
Respondents.
10. The learned Counsel for the Complainant submits that the
the basement and flats bearing Nos.G-9 and G-10 on the ground floor of
Community Centre, Ajit House, 12, Yusuf Sarai, New Delhi being
year, applied for the above mentioned four premises and made payments
towards all the above premises from 1982 to 1985 and also paid plot
and even after lapse of 17 years, did not offer the possession to the
twice and it was restored on account of efforts made by Flat Owners and
8
undue charges issued in the year 1990, 1992, 1998 and 1999 were duly
coupled with undertaking to pay all legitimate dues, but Respondent No.1
unduly cancelled the allotment of all the four flats vide letter dated
deducted 35% of the total flat cost from the amount paid by the
adopted various dilatory tactics to delay the decision on the complaint. The
Respondent before the Commission, COMPAT and also before this Tribunal
made repeated requests that they want to settle with the Complainants out
were restrained from creating any third party right in the subject matter of
the complaint, in defiance of which they created third party right by selling
the shops to third party, by denying the right of the Complainants, the
Respondents are entitled for refund of the entire amount paid by the
The Respondents are also liable to be punished under Section 52-B of the
MRTP Act, 1969. The Complainants, who were languishing for more than
9
18 years and are victim of mala-fide intention and unfair trade practice
11. Shri Ashish Makhija, learned Counsel appearing for the Respondents
that the complaint filed by the Complainants was on behalf of Bansi Lal
Arora Trust. The Trust cannot file any complaint under the MRTP Act,
1969 as Trust can never be a ‘consumer’, hence the complaint itself was
not maintainable. Respondent No.1 Company has been struck-off from the
Haryana under sub-section (5) of Section 248 of the Companies Act, 2013
and the Company stands dissolved with effect from 21.08.2017, hence, the
Directors of the Respondent No.1 and hence, is not personally liable to the
failed to deposit the balance payment, hence, the Company had no option
except to cancel the allotment of flat by letter dated 08.04.1999. Along with
booking amount were sent, which the complainant did not encash. Out of
the four flats in question, two flats which were on ground floor have already
been mortgaged to Ajit Singh House Flat Buyers Association through its
Flat in the basement has been sold to M/s Buildmore India Ltd. through
reasonable charges and the Respondent has shown their willingness to give
10
possession of the alternative Flats on payment of Rs.15,51,413.70. The
Respondent has offered the refund amount deposited by the flat buyers
vide letter dated 09.12.1988, but the Complainant after receiving the said
letter did not take refund of the deposit made by them. The letter head of
avails of any service for a consideration, but does not include a person who
obtain such goods for resale or for any commercial purpose. The prayer
granted in view of the law laid down by the Hon’ble Supreme Court in
2008 SC 2569]. Learned Counsel for the Respondents disputed the claim
Respondent submits that the said amount is not paid to the Respondent.
12. The learned Counsel for the Complainants in her rejoinder to the
submission of the learned Counsel for the Respondents contends that the
Respondents in their reply to the complaint has never taken any plea that
11
Such submission at the time of hearing raised by the learned Counsel for
the Respondents need not be entertained and be rejected at the outset. The
COMPAT that their Company is in liquidation and the said fact was
concealed before this Appellate Tribunal also to delay and defeat the
13. The learned Counsel Prema Priyadarshini further submits that the
year 1999 itself, from which liability, the Respondents cannot escape on
the ground that their Company has been struck-off. It is submitted that
as per Section 248, sub-section (7), the liability of every Director, that is,
14. Learned Counsel for the parties have also placed reliance on
submissions in detail.
15. From the submissions of the learned Counsel for the parties and
materials on record, the following are the questions, which arise for
12
(1) Whether the Complainants have pleaded and proved in the
(3) Whether the complaint filed by a Trust, that is, Bansi Lal
Question No.(1)
parties and perused the record including the documentary and oral
evidence, which was led before the Commission and the COMPAT. The
“restrictive trade practice” and “service” has been defined in Section 2(o)
13
“2(o) “restrictive trade practice” means a trade
practice which has, or may have, the effect of preventing,
distorting or restricting competition in any manner and in
particular,--
(i) which tends to obstruct the flow of capital or
resources into the stream of production, or
(ii) which tends to bring about manipulation of
prices, or conditions of delivery or to affect the flow of
supplies in the market relating to goods or services in
such manner as to impose on the consumers unjustified
costs or restrictions.
2(r) “service” means service which is made
available to potential users and includes the provision of
facilities in connection with banking, financing,
insurance, chit fund, real estate, transport, processing,
supply of electrical or other energy, board or lodging or
both, entertainment, amusement or the purveying of
news or other information, but does not include the
rendering of any service free of charge or under a
contract of personal service.
Explanation.—For the removal of doubts, it is
hereby declared that any dealing in real estate shall be
included and shall be deemed always to have been
included within the definition of “service”.
right to complaint under MRTP Act, 1969. The complaint was filed under
Section 10(a) (i), (iv), 2(o) (ii), 36B (a)/(d) read with section 36A (i), (ii), (iv),
(vi) and (ix) of the MRTP Act, 1969. After having gone through the complaint
14
to unfair trade practice under Section 36-A and 36-B of the MRTP Act,
1969.
18. By Act 30 of 1984, ‘PART B’ was inserted in the MRTP Act, 1969 with
effect from 01.08.1984 with the heading “Unfair trade practice”. Section 36-
A (1) (i), (ii), (iv), (vi) and (ix), which are relevant in the present case are as
follows:
15
be deemed to refer to the price at which the product or
goods or services has or have been sold by sellers or
provided by suppliers generally in the relevant market
unless it is clearly specified to be the price at which the
product has been sold or services have been provided by
the person by whom or on whose behalf the
representation is made;”
19. Section 36-B, empowers the MRTP Commission to inquire into any
unfair trade practice. Section 36-B of the MRTP Act, 1969 is as follows:
20. We need to look into the complaint and evidence brought on record
as defined in Section 36-A is made out in the facts of the present case or
not. We need to recapitulate the facts and sequence of the events and
16
21. Respondent No.1 is engaged in the business of real estate,
constructing and selling flats and building for inter-alia office/ commercial
use. One of such building for commercial use offered to be used and
constructed was for 12, Community Centre Complex, Yusuf Sarai, New
Delhi. The Complainant No.1, which is Bansi Lal Arora Trust entered into
premises No. 12, Community Centre Complex, Yusuf Sarai, New Delhi for
year 1982 to 1985 against the two premises in basement, that is, B-1, 350
sq. ft. at the cost of Rs.1,05,700; B-2, 332 sq. ft. at the cost of Rs.1,00,264/-
and the two premises at ground floor, that is, G-9, 92 sq. ft at the cost of
Complainants were informed that layout plan for the building has been
Rs.40,105/- for B-2; Rs.33,120 for G-9and Rs.49,680 for G-10. The
construction of the building did not begin and Respondent started issuing
notice to the Complainant to make payments. The plot which was allotted
by DDA got cancelled due to non-payment of lease and ground rent charges
17
four premises for the amount as claimed by Complainants has not been
18
22. A reply was filed to the complaint by Respondent. Paragraph 14 and
following effect.
23. The pleadings made in the complaint were duly supported by the
19
10.12.1988 to the Complainant to take refund of the amount deposited by
them. The Complainant did not opt for receiving any refund or for taking
premises for which allotment was made. The Respondent vide letter dated
letters were issued with regard to all the four premises, with regard to
premises B-1, arrears upto 95% amount, i.e., Rs.43,790/- was demanded
along with Rs.25,950/- towards charges for Marble finishing etc. Separate
letters were issued with regard to all the premises demanding different
amount as per the letter. The Complainant sent a separate reply dated
15.02.1990 with regard to all the four premises. It was mentioned that
Complainants are ready to make balance payment of 95% cost of the flat
within seven days from the receipt of your confirmation. With regard to
To,
M/s Skipper Towers Pvt. Ltd.
Skipper Bhawan,
22, Bahakhamba Road,
New Delhi.
20
Sub: Basement No.B-1, on Basement Floor in Plot No.12,
Yusuf Sarai Community Centre, New Delhi.
Dear Sir,
21
24. By letter dated 09.05.1990, the Complainant was communicated the
statement of account towards all the above four premises separately, where
the amount deposited by Complainant and area, rate and total cost was
confirm the actual area to be given and to give them the actual date of
ready to make payment of actual arrears due, after receiving the reply on
the points indicated in the letter. There was correspondence between the
letter was however withdrawn on the next date, that is, 09.06.1990. The
Complainant that they have received letter dated 02.04.1998 from the Dy.
Director (D.D.A.) by which their plots have been restored. It was further
indicated that Respondent has already deposited from their own sources a
sum of Rs.45,000/- before DDA towards restoration fee of the plot, hence,
the payment of restoration fee and stamp duty was demanded by the said
letter separately with regard to all four premises. The Complainant wrote
on account of stamp duty. It was mentioned that the charges for stamp
22
duty have already been paid, hence, the said demand is illegal and
following effect:
Dear Sir,
23
due to the efforts association we leave the matter to the
association to decide on if applicable.
Thanking you,
Yours faithfully,
For B.L. Arora Trust
Sd/-
(Manish Kumar Arora)
Trustee.
25. Similar letters were issued with regard to letter dated 07.05.1998 for
Flats G-9, G-10 giving the details of amount paid to the DDA towards the
stamp duty. After the above, letter dated 12.02.1999 was issued by
24
Sub: PROJECT 12, YUSUF SARAI, NEW DELHI.
Dear Sir/Madam,
Thanking you,
Yours Faithfully,
for & onbehalf of
M/S. SKIPPER TOWERS (P) LTD.
Sd/-
(Authorised Representative)”
25
Ref: Flat No.B-1, 12, Community Center, Yusaf Sarai,
New Delhi.
Dear Sir,
26
equipments installed and genset if actually installed.
However, the question of fire fighting charges of
Rs.28,000/- escalation charges of Rs.28,000/- and security
deposit interest does not arise.
As you are well aware, work on the building has begun only
recently after restoration, at which point of time no work
had been done when the building was taken over. Inspite
of that we had deposited money with you on the faith and
trust that we shall get possession as promised. However,
after a period of 15 years we have still not received
possession from you and instead of you are making
demands without any basis this demand is not only
arbitrary it fails even to set out as to how the cost of the flat
has been more than doubled when not even the basic work
is complete in the building and you are in no possession to
handover the building even now.
Thanking you
Yours faithfully,
For B.L. Arora Trust
Sd/-
Trustee”
27. The letter dated 19.02.1999 written by the Complainant was not
separately for all the four premises regarding cancelling the allotment. It
is useful to extract letter dated 08.04.1999 for Flat No.B-1, which is to the
following effect:
27
E-30, Greater Kailash Part-I,
New Delhi.
M/s Skipper Towers Pvt. Ltd.,
Top Floor, Skipper Corner,
88, Nehru Place,
New Delhi.
28
28. Along with letter dated 08.04.1999, a cheque of Rs.5285 was also
enclosed. The letter dated 08.04.1999 mentions that 35% of the total flat
cost has been forfeited from the amount paid by the Complainants. With
regard to B-1, admittedly the payment which was received from the
08.04.1999, the Complainant chose to file complaint under the MRTP Act,
unfair trade practice has been alleged. In paragraph 29, 30 and 31,
29
quality and grades whereas they have been found to be
defective incomplete and not capable of occupation. By
falsely representing under Section 36(A) (i) (iv) that their
services have performance etc. which such services do
not have. By enhancing prices arbitrially. The
respondent has also failed to fulfill and perform the
representations made by it under Section 36A (i) (vi) by
making a false and misleading representation regarding
the usefulness of its services and goods, under Section
36-A (i) (ix) by materially misleading the consumer
regarding the prices at which its goods and services have
been provided.
31. The respondent has committed also inter-alia
several restrictive trade practices as defined under
Section 2(o) (ii) of the MRTP Act, by indulging in trade
practices which have brought about the manipulation of
prices and conditions of delivery and imposed unjustified
costs and restrictions on the complainant by enhancing
the prices initially stated by it, charging interest both
simple and penal changing the areas of the flat,
unilaterally asking for a higher price for the same, not
offering vacant possession of the premises even after a
period of 17 years sitting on the deposit of the
complainant without any recompense blocking the
money paid. The complainants also apprehend that the
respondent will change the location of the flats allotted to
them and/or will give less area as agreed to. The
complainants are also entitled to interest on the
payments made by them and on other counts as well.”
29. In the affidavit of evidence, which has been filed by Complainant No.2
30
the reply submitted has been proved. The premises which was allotted to
the Complainants in the year 1982-1983 for which part payment was
received by the Respondent, till the year 1999 the possession was never
that they are ready to pay within seven days, the actual balance amount
payable by them as per the agreed costs. The letter written by Respondent
for the premises B-1. Similarly, different amounts were demanded with
regard to other three premises. The total cost of the flat which was agreed
the agreed amount for the cost of the flats and the unwarranted charges
of the Complainant, the Respondents claimed in the reply that they have
allotted the plots to other persons, which has been mentioned in paragraph
31
Mr. M.P. Singh on 30.08.1999 and one flat with
buy has been sold to M/s Buildmore India Ltd
through its MD. Manmohan Kaur on 20.05.1999 to
the knowledge of the complainant. It is further
submitted that the complainant is paragraph 27 of
its complaint has since stated that they are ready
to take possession subject to payment of charges,
then, the respondents one ready and whiling to
give possession of the alternative flats on payment
of Rs.15,51,413.78. The two flats on ground floor
may be given on receipt of the amount from the
complainants and getting the mortgage clean from
the Association. But the respondent will be given
alternative area in the basement as the flat is
basement has already been sold on 20.05.1999.”
30. The Respondent also stated that they are willing to give possession
above context, we may notice one earlier letter written by the Respondent
make the payment, they will have no option except to reduce the area of
dated 26.03.1990 has been filed and has been admitted by the Respondent.
Separate letters dated 26.03.1990 were issued for all the premises, in
32
reduce the area of your flat proportionate to amount
outstanding on your account.”
31. The ingredients of unfair trade practice have been clearly laid down
(India) Ltd. vs. MRTP Commission and Others. In paragraph 16, the
32. From the pleadings of the Complainants and the evidence on record,
following are the incidence of unfair trade practice which are found to have
33
total cost of the flats with area and rate offered in paragraph
Respondents;
the agreed cost of the Flat from time to time. In the last
following chart:
34
1985 is another incidence of unfair trade practice. The
cancelled and 35% of total Flat cost has been forfeited. The
35
Even the notice which preceded the cancellation of allotment
Respondent.
(iii) The advertisement which were issued in the year 1982 inviting
(iv) After the cancellation of the Flats, when complaints were filed
with the specific plea that the Respondents are ready and
36
objected to various illegal demanded amount, which was never
that “for the purpose of promoting the sale, or for the provision of any
unfair trade practice within the meaning of Section 36-A of the MRTP Act,
1969. The above noted incidence of unfair trade practice, clearly fall within
34. The ingredients as laid down by the Hon’ble Supreme Court in the
above case are clearly fulfilled in the complaint filed by the Complainants
and proved by the evidence, which was led in support of the complaint as
noticed above. We, thus, are satisfied that the Complainants have
practice within the meaning of Section 36-A of the MRTP Act, 1969.
35. The learned Counsel for the Complainants has placed reliance on
(MRTP) No.5 of 2017 – Dr. (Mrs.) Manjeet Kaur Monga vs. Mr. K.L.
Suneja & Anr. In the above case, one Smt. Gursharan Kaur, a home buyer
deposited three instalments, after which she died and her daughter Dr.
(Mrs.) Manjeet Kaur deposited the 4th instalment and was issued allotment
37
letter dated 21.05.1992 of Flat No.D-301. The allottee resisted payments
payment was made. A complaint was filed under Section 36 of the MRTP
the Complainant about the time within which the project was to be
completed, but the Respondent did not complete the project for more than
one decade. The Respondent was held guilty of practice under Section 36-
A (1) (i), (ii) & (ix). It was held that the Complainant was justified in not
paying further installments. The COMPAT while declining the issue for
annum. The order of COMPAT was assailed by both the parties. The
direction:
38
respondent in the complaint before the Competition
Appellate Tribunal, New Delhi.
(ii) The builder shall pay the compensation worked
@15% compound interest up to 30.04.2005.
(iii) Whether there should be any compensation and if
so, what should be the amount payable after
30.4.2005 and whether the Citibank is liable to
pay any interest to the account holder by the
Tribunal.
39
was to be completed i.e. three years but did not complete
the construction for more than one decade. COMPAT,
accordingly, held the Respondents guilty of unfair trade
practice as defined under Section 36A(i), (ii) & (ix) of the
MRTP Act. COMPAT further held that the Complainant Dr.
Manjeet Kaur Monga, having deposited three
installments besides three installments initially
deposited by Smt. Gursharan Kaur (total Rs.4,53,750)
did not deposit further installments because the
Respondents did not complete the construction within the
stipulated time. COMPAT was of the view that the
Complainant was justified in not paying further
installments of price and the Respondents committed
grave illegality by cancelling the allotment. In regard to
prayer for direction to respondents to deliver possession
of Flat No. B-301 in Siddharth Shila Apartments, Vaishali
Township Ghaziabad, COMPAT, following the law laid
down by Hon’ble Apex Court in ‘Ved Prakash
Aggarwal’s’ case held that the Tribunal was not
competent to issue direction to the Respondents to deliver
physical possession of the flat but there was ample
justification for awarding compensation by invoking
Section 12B of the Act and even otherwise because the
Complainant and her legal representatives have been
subjected to harassment for the period of more than 25
years. It observed that between August, 1989 and
October, 1993 Smt. Gursharan Kaur and the
Complainant deposited a total sum of Rs.4,53,750/- in
the form of installments and the Respondents not only
failed to complete the project but also failed to return the
installments deposited by them. The amount was
returned only alongwith the cancellation letter and the
Complainant had returned the Pay Order with the legal
40
notice sent on 7th September, 2005. With regard to
quantification of compensation COMPAT observed that
though Section 12B empowered the Tribunal to award
compensation but no criteria had been laid down for
exercise of that power. Having regard for the fact that the
construction of the flat was delayed by more than a
decade and the amount of installments deposited by
Smt. Gursharan Kaur and the Complainant totaling
Rs.4,53,750/- was retained by the Respondents for a
period between 12 to 15 years, COMPAT directed the
Respondents to pay compound interest @ 15% per annum
to the legal representatives of the Complainant. The
interest was directed to be calculated on each installment
from the date of deposit till 30th April, 2005 i.e. the date
on which the allotment was cancelled. This was besides
the deposited amount of Rs.4,53,750/- that was directed
to be paid alongwith the compound interest as aforesaid
to the legal representatives of the Complainant within
three months from the date of the order. While disposing
of the appeals filed by both sides, the Hon’ble Apex Court
dealt with the issue of compensation determinable under
Section 12B of the Act, as follows:-
“5. We do not think that there needs to be any
elaborate consideration of the meaning of the word
“compensation” in terms of the amount referred to
under the Section. The amount referred to under
the Section is the amount @ 15% compound
interest on the amount already deposited, as
ordered by the Tribunal. Merely, because a
liquidated amount is not stipulated or determined
by the Tribunal, it cannot be said that it is not the
compensation. Once the interest, as ordered by the
41
Tribunal, is calculated that will be the amount of
compensation referred to under Section 12B of the
Act.”
directed:
42
“16. …….It is manifestly clear that the legal
representatives of the Complainant did not get the refund
of Rs.4,53,750/- in terms of order dated 3rd August,
2015 passed by COMPAT as the funds were credited
back to the account of Respondent No. 2 Company on 16th
June, 2016 and a fresh Pay Order bearing No.262910
dated 16th June, 2016 favouring ‘Suneja Towers Pvt.
Ltd.’ was issued by Respondent No. 3 on the request of
Respondents No. 1 & 2. From affidavit sworn by
Respondent No.1 on 18th October, 2017, it emerges that
the Respondents No. 1 and 2 refunded the amount of
Rs.4,53,750/- in favour of the legal representative of the
deceased Complainant by enclosing Managers Cheque
No. 021566 for the same amount with their letter dated
7th May, 2016 in lieu of cancellation of the Managers
Cheque given to Complainant in the year 2005. This is
stated to have been done in compliance to the orders of
Hon’ble Apex Court dated 8th April, 2016 and 29th April,
2016. The letter alongwith the Managers Cheque in
question forms Annexure ‘C’ to the affidavit. It is
abundantly clear that the legal representatives of the
deceased Complainant did not get the refund of
Rs.4,53,750/- in terms of order of COMPAT till 7th May,
2016. This factual position is not refuted by the legal
representatives of the deceased Complainant who did
not respond to assertion of facts by Respondents No. 1
and 2 in their affidavit which is supported by
documentary evidence. It is accordingly found that the
direction of COMPAT in terms of order dated 3rd August,
2015 in regard to payment of Principal amount of
Rs.4,53,750/- stood not complied with till 7th May, 2016.
In view of the same, the legal representatives of the
Complainant would be entitled to further compensation
43
in the form of compound interest @ 15% per annum on the
principal amount of Rs.4,53,750/- w.e.f. 1st May, 2005
till 7th May, 2016 further entitled to pendentelite and
future interest till realization of the accumulated arrears
from Respondents No. 1 and 2…….”
36. Learned Counsel for the Complainants submits that what was held
by this Appellate Tribunal in the above case is fully attracted in the present
case. The Complainants are clearly entitled for refund of the amount
2008 SC 2569] in which case, the Hon’ble Supreme Court laid down that
under the MRTP Act, 1969, the Commission could not direct for giving the
in the said judgment, the Hon’ble Supreme Court simultaneously laid that
trade practices. The Hon’ble Supreme Court has laid down following in
44
MRTP Commission was clearly in error in directing GDA
to hand over possession to the respondent.
14. Under the Act, there are provisions for inquiries
that can be instituted by the MRTP Commission while
Section 36-D read with Sections 12-A and 12-B lay down
the powers of the MRTP Commission in dealing with
instances of unfair trade practices. None of the provisions
seem to indicate that the MRTP Commission has the
authority to do what it did in this case. The MRTP
Commission has the power to impose damages or give
compensation to the respondent as a mode of redressal
for harm caused by the unfair trade practices, but it
certainly cannot assume the powers of the civil court
because the action of the MRTP Commission in this case
virtually amounts to grant of specific performance.”
37. In view of the above discussion, we hold that the Complainants have
pleaded and proved that Respondents have adopted unfair trade practice
within the meaning of Section 36-A of the MRTP Act, 1969. The question
Question No.(2)
45
trader or class of traders or any consumer, such
Government or, as the case may be, trader or class of
traders or consumer may, without prejudice to the right
of such Government, trader or class of traders or
consumer to institute a suit for the recovery of any
compensation for the loss or damage so caused, make an
application to the Commission for an order for the
recovery from that undertaking or owner thereof or, as
the case may be, from such person, of such amount as
the Commission may determine, as compensation for the
loss or damage so caused.
(2) Where any loss or damage referred to in sub-
section (1) is caused to numerous persons having the
same interest, one or more of such persons may, with the
permission of the Commission, make an application,
under that sub-section, for and on behalf of, or for the
benefit of, the persons so interested, and thereupon the
provisions of rule 8 of Order 1 of the First Schedule to the
Code of Civil Procedure, 1908 5 of 1908 shall apply
subject to the modification that every reference therein to
a suit or decree shall be construed as a reference to the.
application before the Commission and the order of the
Commission thereon.
(3) The Commission may, after an inquiry made
into the allegations made in the application filed under
sub-section (1), make an order directing the owner of the
undertaking or other person to make payment, to the
applicant, of the amount determined by it as realisable
from the undertaking or, the owner thereof, or, as the
case may be, from the other person, as compensation for
the loss or damage caused to the applicant by reason of
any monopolistic or restrictive, or unfair, trade practice
carried on by such undertaking or other person.
46
(4) Where a decree, for the recovery of any amount
as compensation for any loss or damage referred to in
sub-section (1) has been passed by any court in favour of
any person or persons referred to in sub-section (1) or, as
the case may be, sub-section(2), the amount, if any, paid
or recovered in pursuance of the order made by the
Commission under sub-section (3) shall be set off against
the amount payable under such decree and the decree
shall, not- withstanding, anything contained in the Code
of Civil Procedure, 1908, 5 of 1908 or any other law for
the time being in force be executable for the balance, if
any, left after such set off.”
39. We have noted above the contents of the complaint filed by the
the payments made by the Complainant with regard to B-1, B-2, G-9 and
G-10, but learned Counsel for the Respondents submits that the
charges and proportionate ground rent charges for arriving the total
Respondents that the said amount was not paid to the Respondents. Be
efforts of the Association as well as Respondent No.1. The Delhi High Court
has permitted the Association to directly pay the ground rent, consequent
to which, ground rent was paid by Flat Buyers and Shop Owners
47
of ground rent as well as restoration charges were made by the Association
after collecting it from all Flat Buyers. The payments made by the
Association were towards the liability, which Respondent No.1 owed to the
Respondent to pay ground rent, the plot was cancelled, hence, the
that total payments made by them towards all the Flats as well as
40. The question is as to whether in the facts of the present case, the
12-B. The learned Counsel for the Respondents has made strenuous
Complainants under Section 12-B, they are not entitled for payment of
filed in the year 1999, by which time the judgment of Hon’ble Supreme
The Complainants had prayed for handing over vacant possession of Flats.
Apart from above prayer in prayer clause (f) there was a general prayer “any
other or further order as may be necessary”. In prayer clause (g) and (h),
the Complainants have also prayed for relief and cost. Prayer clauses (e),
(f), (g) and (h) have been added in handwriting, which is part of the original
48
Complainant. In the facts of present case, we are of the view that claim of
only on the ground that no separate application has been filed. The
them for 17 years, were suddenly met by an order cancelling the allotment.
We, thus, are of the view that Complainants are entitled for award of
Question No.3
41. The learned Counsel for the Respondents has submitted that the
hence, the complaint is not maintainable. The learned Counsel for the
Complainants has refuted the said submission on the ground that such
plea was never raised before the Commission, in the reply or by any other
allowed to raise this plea. The reply to the complaint was filed by the
42. There is one more reason for not accepting the submission of learned
perusal of the complaint indicates that complaint had been filed by five
person and Complainant No.1 is Bansi Lal Arora Trust, Complainant No.2
49
is Manish Arora, Complainant No.3 is Ritu Arora, Complainant No.4 is
Deepti Arora and Complainant No.5 is Vani Arora. The paragraph 1 of the
complaint states:
43. The Trust was setup by the father of Complainant Nos.2 to 5 for their
the submission of learned Counsel for the Respondents that the complaint
Trust, but there are four other individuals, who are beneficiaries of the
Trust. The learned Counsel for the Respondents has placed reliance on
Pratisthan and Ors. vs. Manager, Canara Bank and Ors. The above
case arose out of the Consumer Protection Act, 1986 and Hon’ble Supreme
50
availed of by a complainant and so on. A “complainant”
is defined in Section 2(1)(b) of the Act in the following
words:
“2.(1)(b) “complainant” means—
(i) a consumer; or
(ii) any voluntary consumer association registered
under the Companies Act, 1956 (1 of 1956) or
under any other law for the time being in force; or
(iii) the Central Government or any State
Government; who or which makes a complaint; or
(iv) one or more consumers, where there are
numerous consumers having the same interest;
(v) in case of death of a consumer, his legal heir or
representative;”
3. It is quite clear from the above definition of a
complainant that it does not include a trust. But does a
trust come within the definition of a consumer?
A “consumer” has been defined in Section 2(1)(d) of the
Act as follows:
“2.(1)(d) “consumer” means any person who—
(i) buys any goods for a consideration which has
been paid or promised or partly paid and partly
promised, or under any system of deferred
payment and includes any user of such goods
other than the person who buys such goods for
consideration paid or promised or partly paid or
partly promised, or under any system of deferred
payment, when such use is made with the
approval of such person, but does not include a
person who obtains such goods for resale or for
any commercial purpose; or
(ii) hires or avails of any services for a
consideration which has been paid or promised or
51
partly paid and partly promised, or under any
system of deferred payment and includes any
beneficiary of such services other than the person
who hires or avails of the services for consideration
paid or promised, or partly paid and partly
promised, or under any system of deferred
payment, when such services are availed of with
the approval of the first mentioned person; but
does not include a person who avails of such
services for any commercial purpose;
Explanation.—For the purposes of this clause,
“commercial purpose” does not include use by a
person of goods bought and used by him and
services availed by him exclusively for the
purposes of earning his livelihood by means of self-
employment;”
44. In the case before the Hon’ble Supreme Court, the complaint was
filed by a Trust, whereas in the present case, the complaint is also by four
Question No.4
52
Act, 2013, striking-off the name of 2495 companies. In that list, the name
Counsel for the Respondent is that in view of the said Notice, the Company
alone. Section 248 of the Companies Act, 2013 enumerates the power of
The Section 248, sub-section (5), (6) and (7), which are relevant to the case
are as follows:
53
(7) The liability, if any, of every director, manager
or other officer who was exercising any power of
management, and of every member of the company
dissolved under sub-section (5), shall continue and may
be enforced as if the company had not been dissolved.”
46. There is no dispute that the name of Respondent No.1 Company has
been struck-off by Notice dated 01.09.2017. The Respondent No.2 was the
under the Act at the relevant time. Unfair trade practice committed by
Respondents at the relevant time, that is, upto 08.04.1999 were to be dealt
by under the Act. The complaint was filed by the Complainant immediately
54
applicant/ complainants have been able to establish
their prima facie case for the purposes of this interim
relief application.
The balance of convenience is also in favour of the
applicants/ complainants for the simple reason that they
have already paid 35% of the price of the property to the
respondents and, if no interim relief is granted at this
stage, the success, if any, of the applicants/
complainants on logical conclusion of the proceedings
would become infructuous and illusory. As against this,
grant of ad interim relief would not cause any harm or
hardship to the respondents inasmuch as they have
already with them 35% of the price of the property as
aforesaid. It is therefore necessary to prevent the
respondents from creating any interest of any third party
with respect to the subject matter of this proceeding.
In the result, an ex parte ad interim injunction is
ordered to be issued to the respondents restraining them
from creating any interest of any third party in the
subject-matter of this proceeding till further orders.”
Respondents. We have gone through the order of the Commission and the
COMPAT, which indicate that the Respondents did not cooperate with the
55
“Today the case is fixed for final arguments.
Learned advocate who is representing the respondent, in
this case, has entered appearance today and he prays
for an adjournment, as according to him, there is
possibility of an out of court settlement and he wants to
bring about an amicable settlement of the dispute. As
prayed, the case is adjourned to 15th April 2004 for
consideration and/or for directions.”
since a submission was made before the Delhi High Court Medication and
enter settlement. Even before this Tribunal time was taken by the parties
Tribunal have been noticed above. The mere fact that complaint could not
56
be decided before the date when Company was stuck-off from the Register
other officer, which may be enforced, as if the Company had not been
and they cannot go away scot-fee merely on the ground that Company has
been struck-off with effect from 21.08.2017. We, thus, reject the
50. The Commission vide its order dated 23.09.1999 had restrained the
Respondent from creating any third party interest in the subject property,
Section 12-A (2) of the MRTP Act, 1969 was filed on 12.03.2011 by the
No.3. The COMPAT had directed Shri H.P. Sharma, who was functioning
An affidavit was filed by Shri H.P. Sharma dated 06.02.2010 stating that
57
there was no violation of the orders and no third party appears to have
been created. On the basis of the said report of Court Commissioner, the
Respondents have created third party rights, violating the injunction order.
applicants Nos.2 and 3. The notice could not be easily served and could
heard by this Tribunal. The learned Counsel for the Complainants relying
record including the record from office of DDA and other material to
indicate that third party rights were created, which was successfully
and 3 have been denied by the learned Counsel for the Respondents
submitting that Contempt Applications have already been rejected twice for
parties and have perused the record. We have already noticed the
58
Authority vs. Ved Praksh Aggarwal (supra) that in proceedings under
1969 Act, no direction can be issued for handing over possession of the
and in the reply, which has been filed by the Respondents to the Contempt
Application, they have clearly stated that out of the four Flats in question,
two flats which were on ground floor have already been mortgaged to Ajit
Singh House Flat Buyers Association through its President Meera Prasad
has been sold to M/s Buildmore India Ltd. through its MD on 20.05.1999.
proceed any further with the Contempt Contempt Case (AT) (MRTP) No.
Question No.(5)
noted and dealt above, we are of the opinion that Complainants are entitled
ORDER
59
the aforesaid payment within a period of four weeks from
today.
(ii) Apart from refund as we have directed at point (i) above, the
as directed above.
53. In the result Transfer Original Petition (AT) (MRTP) No.04 of 2017 is
allowed to the extent as directed above. The Contempt Case (AT) (MRTP)
No. 05/2017 is closed. The parties shall bear their own costs.
NEW DELHI
Ash/NN
60