You are on page 1of 1

Statement showing the DCC Material payments pending position

for the years 2021-22 and 2022-23 as on 17.06.2022 (Amount in Crores)


Grand Total
DCC 2021-22 DCC 2022-23
Pending
Sno Name of the district
No. of FTOs Amount No. of FTOs Amount No. of FTOs Amount

1 2 7 8 9 10 11 12

1 Adilabad 88 30.05 68 6.30 156 36.35


2 Bhadradri Kothagudem 344 16.13 43 11.68 387 27.81
3 Hanumakonda 73 11.56 160 8.33 233 19.89
4 Jagtial 239 13.91 15 0.97 254 14.87
5 Jangaon 341 42.09 81 10.65 422 52.74
6 Jayashanker Bhopalapally 215 11.12 17 1.14 232 12.26
7 Jogulamba Gadwal 41 12.90 200 8.17 241 21.07
8 Kamareddy 303 26.88 35 8.25 338 35.14
9 Karimnagar 286 16.10 253 12.40 539 28.49
10 Khammam 164 27.73 5 1.23 169 28.97
11 Kumarambheem Asifabad 228 18.82 4 0.18 232 19.01
12 Mahabubabad 629 28.62 363 14.24 992 42.86
13 Mahabubnagar 420 10.58 38 7.81 458 18.39
14 Mancherial 81 17.98 4 2.55 85 20.53
15 Medak 347 23.20 101 5.96 448 29.16
16 Medchal - Malkajgiri 143 3.19 0 0.00 143 3.19
17 Mulugu 255 19.54 22 1.05 277 20.59
18 Nagarkurnool 197 14.83 22 4.75 219 19.57
19 Nalgonda 256 26.18 280 18.75 536 44.93
20 Narayanpet 140 10.11 10 0.08 150 10.19
21 Nirmal 309 37.82 53 2.67 362 40.49
22 Nizamabad 146 35.89 45 7.93 191 43.82
23 Peddapalli 97 11.90 68 1.83 165 13.73
24 Rajanna Sirsilla 126 8.43 0 0.00 126 8.43
25 Rangareddy 148 25.96 47 7.12 195 33.08
26 Sangareddy 23 14.17 2 0.83 25 15.00
27 Siddipet 330 22.07 15 1.06 345 23.13
28 Suryapet 402 22.02 151 7.07 553 29.10
29 Vikarabad 666 25.67 95 3.14 761 28.81
30 Wanaparthy 414 18.24 7 0.21 421 18.46
31 Warangal 287 58.67 215 11.42 502 70.09
32 Yadadri Bhuvanagiri 112 12.25 46 2.04 158 14.30
Total 7850 674.63 2465 169.80 10315 844.43