ASSIGNMENT No.02b.
.
LECTURER: Dr. J. KAFUKU
GROUP 2 MEMBERS:
NAME: REGISTRATION NUMBER:
IBRAHIM NYIRENDA 2021-06-00892
DANIEL NKRUMAH 2020-06-01434
GEORGE KIGORA 2021-06-00877
1
INTRODUCTION. .............................................................................................................. 3
1.1 PROJECT OVERVIEW. .................................................................................................. 3
1.2 OBJECTIVE OF RISK MANAGEMENT PLAN. .......................................................... 3
TOP THREE RISKS. ........................................................................................................... 3
2.1 COVID-19 PANDEMIC. ................................................................................................. 3
2.2 SAFETY HAZARDS DUE TO LOCAL COMMON PRACTICE. ................................. 6
2.3 QUALIFIED LABOR SHORTAGE AND PRODUCTIVITY ISSUES. ......................... 6
RISK MANAGEMENT APPROACH. ............................................................................... 7
RISK IDENTIFICATION. .................................................................................................. 7
4.1 EXPERT INTERVIEW. ................................................................................................... 7
4.2 RISK ASSESSMENT MEETING. .................................................................................. 7
4.3 HISTORICAL REVIEW OF SIMILAR PROJECT. ....................................................... 8
RISK QUALIFICATION AND PRIOTIZATION. ............................................................. 8
RISK MONITORING. ......................................................................................................... 8
RISK MITIGATION AND AVOIDANCE. ........................................................................ 9
RISK REGISTER. ............................................................................................................... 9
2
INTRODUCTION.
1.1 PROJECT OVERVIEW.
Hypothetically, the Tanzania Building Agency (TBA) is proposing to build 3500
residential houses in the Nzuguni Region of Dodoma on behalf of the Tanzanian
Government. The project's first phase will entail the construction of 150 residential units.
These homes will be utilized to house public servants and Government personnel who are
currently unable to find housing in Dodoma. We have been assigned as a team to produce
a Project Risk Management Plan for this initial part of the project before it is
implemented. (Assuming that, we are in for the post contract stage).
1.2 OBJECTIVE OF RISK MANAGEMENT PLAN.
The proposed project allows project team to operate in an area of uncertainty that comes
along with developing new and unique products (150 residential units). By doing so, the
project team take chances which results in risk playing a significant part in the project.
The purpose of the risk management plan is to establish the framework in which the
project team will identify risks and develop strategies to mitigate or avoid those risks.
3
Our recommendations are as follows:
1. Site supervisor (or occupational health and safety officer or any other senior
personnel) should be responsible for screening employees based on questionnaire
to check for symptoms or signs of Covid infection. Temperature screening using
infrared thermometers before and after shifts can be considered. The same should
be applied to inspectors, regulators (Government or from collaborating
companies). Visitors should have approval to be on site at least one day prior to
being physically present.
2. Staggered work is preferred. Personnel should work as far apart as possible. The
work should be planned so that only the necessary personnel are present.
Furthermore, maximum 50% of the workforce should be present at any time to
complete a task. When working within 2 m of each other, PPE must be worn, and
hygiene precautions strictly observed. In between shifts, any items such as tools,
frequently touched surfaces should be cleaned or disinfected.
3. Consider work teams. As an example, the workers working in one shift should
always be paired together and should not be teamed with others coming in
different shifts, if shifts are changed then the whole team should change shift
together. There should be minimal, if possible, zero, interaction between workers
from one team with the other and between workers and the general population
(only their families and their work teams).
4. Everyone entering the work premises should wash hands when entering and
leaving their work sites. They shall change into their work clothes and should not
work with clothes used to come to work with. Items such as keys, purse, wallets
and cellphones should be cleaned before entering the work site. In addition,
facemasks and hand sanitizers should ideally be provided for workers and they
should be aware of how to properly use these and their limitations.
5. There should be easy access to hand washing facilities, tissues and bins with
closed lids and workers should be encouraged to perform effective hand washing
regularly and observe coughing and sneezing etiquettes. Posters in English and
Swahili will be posted in various areas by the HSE contractor to sensitize on
matters such as:
a. Corona virus infographics;
b. Effective hand washing;
c. Enhanced hand rubbing (with alcohol concentration of at least 60%);
d. Coughing and sneezing etiquettes;
e. Maintaining a physical distance of at least 2 m between individuals. This includes
2 m between individuals in restrooms, break areas and walkways. Reflective or
high visibility jackets can be used to monitor physical distancing;
4
f. Line of communication for someone who needs to self-report symptoms or wants
to notify of a sick colleague;
g. To stay home if feeling sick or unwell;
6. Each worker should have access to their own gloves and face masks in the
scenarios where work will be executed, and distance of 2 m will not be able to be
maintained for that task e.g. working on ladders which needs minimum of two
people. There should be no sharing of personal items at all.
7. The environment for reporting symptoms should be friendly to encourage
notification. Pay cuts for days off should not be used to penalize workers that fall
sick by Covid-19 like symptoms.
8. If there is a sick person who is either a suspected or confirmed case for Corona
Virus, the protocols must be adhered to which also specify conditions for return to
work after illness. In addition, the flow chart should be followed as well.
5
11. Food vendors serving the workers should be encouraged to have pre-packaged
meals which can be distributed (ideally in disposable utensils) to avoid communal
settings and self-serving options.
12. Lunch times and breaks can be scheduled to avoid gathering of too many people
in an area at once. Also the site manager to audit daily site keeping and cleaning
effectiveness to ensure quality.
2.2 SAFETY HAZARDS DUE TO LOCAL COMMON PRACTICE.
Due to local common practice, there is a high risk of HSE incidents or near misses during
construction. As project managers, we will ensure that the following list is followed
throughout the duration of the project. This will include, but not be limited to, the items
listed below.
a. Emergency drills are properly organized, performed and records are kept properly;
b. First aid record forms are adhered to;
c. First aid treatment forms are adhered to;
d. HSE accidents record forms are adhered to;
e. Safety (SJA) checklist forms are adhered to;
f. Safety induction programmes are executed appropriately;
g. Body temperature records are adhered to;
h. Toolbox meeting to be conducted regularly;
i. Site inspection forms are adhered to.
2.3 QUALIFIED LABOR SHORTAGE AND PRODUCTIVITY ISSUES.
Not having enough workers available to complete a project or hit productivity goals is a
huge risk when taking on new projects. Without the manpower to perform the work, the
project can suffer from longer construction schedules and potential delays in delivering
the project on time to the owner.
The construction industry lost over a good number of jobs from the very first wave of the
Covid-19 pandemic but has since gained back all that was lost and the number of jobs is
now higher than it was prior to the start of the pandemic. To fill vacancies, many
construction firms have been taking on employees with little or no previous construction
experience. This is not necessarily a bad thing, but there are additional risks that come
with having a less experienced crew. These workers will not have the same skill sets as
experienced workers, meaning they will be less productive and will probably need closer
supervision when they are first starting out.
Added to the above, safety is also a construction project risk factor to consider when
working with new employees. They lack the training and experience to know all the rules
or be able to identify hazardous situations on the jobsite. Safety training is just as, if not
more, important as skills training and should be a top priority with new hires.
6
We recommend the following approach to combat labor shortages, offer competitive
wages and benefits, and develop a strong company culture that values employees and
rewards hard work and dedication. This requires time and money to invest in the training
and development of your workforce.
Finally, to retain workers, provide opportunities for training, mentoring, and continuing
education courses available to both your new and existing employees. Establish
advancement opportunities and career paths for workers to move up within the
organization.
RISK IDENTIFICATION.
We assume that, risk identification was conducted in the initial project risk assessment
meeting. The method used by the project team to identify risks was the Crawford Slip
method. We, the project managers chaired the risk assessment meeting and distributed
notepads to each member of the team and allowed 10 minutes for all team members to
record as many risks as possible.
4.1 EXPERT INTERVIEW.
We assume that, two Expert Interviews were held for this project. The interviews
revealed several risks which were then mitigated by making changes to the project plan.
The remaining risks are to be included in the Risk Register.
4.2 RISK ASSESSMENT MEETING.
We assume that, a risk assessment meeting was held with key team members and
stakeholders. The risks identified during this meeting were added to the project plan and
Risk Register.
7
4.3 HISTORICAL REVIEW OF SIMILAR PROJECT.
We assume that, the project team reviewed the history of similar projects in order to
determine the most common risks and the strategies used to mitigate those risks.
RISK MONITORING.
The most likely and greatest impact risks shall be added to the project plan to ensure that
they are monitored during the time the project is exposed to each risk. During the bi-
weekly project team meeting will discuss the status of that risk; however, only risks
which fall in the current time period will be discussed. Risk monitoring will be a
continuous process throughout the life of the project. As risks approach on the project
schedule we (the project manager) will provide the necessary status updates which
8
include the risk status, identification of trigger conditions, and the documentation of the
results of the risk response.
RISK REGISTER.
The Risk Register for the proposed project is a log of all identified risks, their probability
and impact to the project, the category they belong to, mitigation strategy, and when the
risk will occur. The register was created through the initial project risk management
meeting led by the project managers. During this meeting, the project team identified and
categorized each risk. Additionally, the team assigned each risk a score based on the
probability of it occurring and the impact it could potentially have. The Risk Register
also contains the mitigation strategy for each risk as well as when the risk is likely to
occur.
Based on the identified risks and timeframes in the risk register, each risk has been added
to the project plan. At the appropriate time in the plan—prior to when the risk is most
likely to occur—we, the project managers will ensure adherence to the agreed upon
mitigation strategy. Also, we will provide the status of the risk at the bi-weekly project
team meeting for risk’s planned timeframe.
9
Table 2: Example of a risk register.
10