You are on page 1of 83

EXECUTIVE SUMMARY....................................................................................................

4
I. INTRODUCTION.................................................................................................... 10
II. NEED AND JUSTIFICATION OF THE PROJECT................................................ 12
III. SITE SELECTION AND EVALUATION OF SITE.................................................. 17
IV. SITE FEATURES AND FUEL LINKAGE...............................................................22
V. SELECTION OF TECHNOLOGY AND PLANT CONFIGURATION..................... 25
VI. FEATURES OF PROPOSED PLANT....................................................................34
VII. ENVIRONMENTAL ASPECTS...............................................................................56
VIII. PROJECT EXECUTION.........................................................................................63
IX. PROJECT COST ESTIMATION AND TARIFF CALCULATION........................... 68

List of Tables:

Table II-1:Installed Capacity Sector wise as on Sep’2020


...........................................................................................................................................................
13
Table II-2: Month wise Power Supply Position
...........................................................................................................................................................
13
Table III-1: Evaluation of Proposed Site
...........................................................................................................................................................
21
Table IV-1: Site Details
...........................................................................................................................................................
24
Table V-1: Comparison of Single Shaft Vs Multi Shaft
...........................................................................................................................................................
27
Table V-2: Brief Technical Parameters and Performance of possible CCPP ( Option –
1: 1 Block of 700 - 800 MW with H class Gas Turbine)
............................................................................................................................................
30
Table V-3: Brief Technical Parameters and Performance of possible CCPP ( Option –
2: 1 Block of 700 - 800 MW with advanced class (F Class) Gas Turbine)
............................................................................................................................................
31
Table V-4: Land requirement for Gas Turbines
...........................................................................................................................................................
32
Table VI-1: Auxiliaries and supply voltage
...........................................................................................................................................................
43
Table VII-1: Emission guidelines as per World Bank
...........................................................................................................................................................
56
Table VII-2: List of Permits, Clearances and Licenses & the responsibility matrix
...........................................................................................................................................................
58
Table IX-1: Assumptions for Cost Estimation
...........................................................................................................................................................
69
Table IX-2: Capex Breakdown
...........................................................................................................................................................
70
Table IX-3:Phasing of Expenditure
...........................................................................................................................................................
72

List of Figures:

Figure II-1: Installed Capacity as on Sep 2020 12


Figure II-2: Fuel Mix of thermal power generation as on Sep 2020 12
Figure II-3: Demand Vs Availability (Peak) 14
Figure II-4: Demand Vs Availability (Energy) 14
Figure II-5: Energy Requirement Forecast (Ex Bus) - MU 14
Figure II-6: Yearly average Load Profile 15
Figure II-7: Yearly average Wind Generation 15
Figure II-8: Yearly average Solar Generation 15
Figure IV-1 :Project Location 22
Figure V-1 :Capacity/Efficiency of MHPS Machines (ISO Condition) 26
Figure V-2 :Capacity/Efficiency of GE Machines (ISO Condition) 26
Figure V-3 :Capacity/Efficiency of Siemens Machines (ISO Condition) 26
Figure IX-1: Variation in Capital Cost Vs Cost of Generation 74
Figure IX-2: Variation in Gas Price Vs Cost of Generation 74
Figure IX-3: Variation in PLF Vs Cost of Generation 75
Figure IX-4: H Class Vs F Class 75

List of Appendix:

Appendix.1: Fuel gas Analysis & Cost


Appendix.2: Sea Water Analysis
Appendix.3: Financial Analysis

List of Exhibits:

Exhibit – 1: (a) Plot Plan (Option 1); (b) Plot Plan (Option 2)
Exhibit – 2: Heat and Mass Balance Diagram
Exhibit – 3: Water Balance Diagram
Exhibit – 4: Single Line Diagram Exhibit
– 5: Project Milestone Chart
EXECUTIVE SUMMARY

Introduction

1. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) was


constituted after unbundling of Tamil Nadu Electricity Board (TNEB). With the rise in
economic growth of the state, the electrical power demand continues to rise. Further IOCL
is in the process of building a Liquified Natural Gas (LNG) Terminal at Ennore, Chennai.
TANGEDCO desires to utilize the above sources of RLNG for augmentation of power
generation in the State. TANGEDCO has planned to set up a high capacity (about 700 to
800 MW) gas based combined cycle power project (GT CCPPs) in and around Chennai.
TANGEDCO has appointed Tata Consulting Engineers Limited (TCE) for preparation a
Feasibility report (FR) for the proposed Power Plant.

Purpose

2. The purpose of this report is to study the feasibility of setting up a high capacity 700 – 800
MW gas based combined cycle power plant in and around Chennai.

3. This report also highlights the details of the selected site, gas linkage to plant site, water
requirements, technical features of the main plant equipment, cooling water system,
electrical systems, evacuation of power, environmental aspects, schedule and type of
project implementation and estimates of project cost and cost of generation for the
proposed combined cycle power project.

Scope

4. The scope of this feasibility report covers the following:

a) Site selection study for the installation of the power project considering the
topography, soil conditions, accessibility, fuel linkage, availability of water, power
evacuation arrangements and availability of land.
b) Power project capacity selection based on the availability of land and the high
efficiency Gas Turbines.
c) Gas Turbine configuration study with advanced class and latest technology
machines.
d) Preparing salient technical details, the details of the major equipment/systems
proposed.
e) Studying the environmental aspects.
f) Preparation of preliminary plant layout, heat and mass balance diagrams, water
balance diagram and electrical single line diagram.
g) Preparation of preliminary project implementation schedule.
h) Study of installation & operation methodology of the proposed plants through
various models (EPC + LTSA, EPC + PPP, IPP, EPC).
i) Preparation of first order cost estimates for the project based on data available
in- house cost data bank and data obtained from standard published information.
j) Computation of cost of power generation and levelized tariff as per CERC
guideline.

Need for the Project

5. As per National Electricity Policy (24x7 Power for All), all households, industrial,
commercial and all other electricity consuming entities shall be electrified, and Tamil Nadu
has achieved a 100% Household electrification. However, with continuous economic
growth rate and rising industrial development, it is evident that there must be capacity
addition in terms of power station to improve power supply position during peak & off-peak
hours and minimize the demand-availability gap in Tamil Nadu.

6. About 43% of power for Tamil Nadu is sourced from Renewables. The Renewables
generally possess a varying output due to the change in the climatic condition. To cater
the varying nature of the power, and to satisfy the power required during the peak time, a
fast ramping power plant is required. Due to the economic growth of the Tamil Nadu, it is
evident that the state requires additional power generation (with faster ramp rate to cater
the variation in renewables).

7. The Gas based power plant are design for faster ramping rate and typically the gas
turbine takes <30 mins to startup (Hot Startup). The combined cycle power plant takes
<50 mins,
<100 & <300 mins for starting during Hot, warm and cold condition respectively. The Hot,
warm and cold startup depends on the HRSG drum metal temperature. Further the ramp
rate of the gas turbine is about 80 to 88 MW/min. This provides a faster response to the
grid requirement during the RE variations. Installation of 700 – 800 MW gas based
combined cycle power plant will satisfy the requirement.

Land

8. The proposed power plant would be located at the identified site 10 km from Chennai
city, Tamil Nadu and the site area is about 39 acres. The identified land would be
adequate for the proposed installation of the CCPP.
Site characteristics

9. The area proposed for the power plant is with vegetation and seems to be fairly even and
requires minimum grading. The final grade level in power plant area would be established
after a detail topography survey is carried out.

Access to Site

10. Proposed site is accessible by road, rail and by air. The site is located 10 km from the
Chennai city and is 3 km away from State Highway–56 (SH-56) connecting Thiruvathiyur
and Panchetty. The nearest railway station is Kathivakkam (sub urban) about 2 km from
the site, nearest airport is Chennai International Airport, Chennai about 34 km from project
site and nearest port is Ennore port about 11 km from the project site.

Source of Raw Water and its Requirement

11. The source of water is from the Bay of Bengal. The sea water will be tapped off from the
water intake facility of upcoming 660 MW Coal based power plant. The water requirement
for the plant would be about 69.6 MLD.

Source of Fuel Supply and Cost

12. Regasified Liquified Natural Gas (RLNG) will be the primary fuel for the proposed project.
The RLNG will be sourced from IOCL. The transportation of the fuel gas will be through
IOCL pipeline which runs in proximity of the proposed site. The operating pressure would
be between 40 bar and the temperature would be about 40°C (max). The Fuel gas
analysis and the landed cost is as shown in Appendix – 1. The RLNG delivered at site by
IOCL will be under fixed price Gas Supply Agreement / Contract. The estimated natural
gas requirements for the proposed power plant would be about 894 MMSCM/annum,
considering the load profile of gas turbine.
Technology Selection

13. TCE has performed the analysis considering various Gas Turbine options to produce the
power of 700 to 800 MW. The Study was performed with Thermoflow software &
combination of market analysis and in-house cost data bank is considered for the
analysis. The Various options considered for the study are as follows;

- Option – 1: 1 block of 700 - 800 MW in single shaft / multi-shaft configuration


with advanced class machines (H Class). Single shaft configuration will have 1
gas turbine, 1 HRSG and 1 steam turbine in a single shaft mode with a common
electric generator and one generator transformer. While in multi shaft
configuration will have 1 gas turbine, 1 HRSG and 1 steam turbine and 2
generators (1 for gas turbine and another for steam turbine).
- Option – 2: 1 block of 700 - 800 MW in multi-shaft configuration with F class
machines, where in the block will have 2 gas turbine, 2 HRSG and 1 steam
turbine with 3 electric generators (2 for gas turbine and another for steam
turbine).

14. The Land required for the above options are illustrated in table below;
Buildings Option-1 Option-2
Power block, acres 5.2 6.5

Electrical Area, acres 0.8 1.6

Cooling System, acres 1.2 1.3

Fuel gas system, acres 0.6 0.8

Land for other miscellaneous requirements (BOP, PECC, road, 7.2 8.8
etc.), acres
Total, acres 15.0 19.0

15. Considering the load profile and renewable generation (solar & wind) profile of Tamil
Nadu, the plant may operate in two modes either in base load operation or cyclic
operation. For the purpose of the report it is assumed that the plant will be operate in
cyclic mode of operation with 12 hrs at base load and 12 hrs as min emission load. The
following table illustrates the comparison of gas turbine performance at site condition:
Performance at Site Conditions
No of Gross Gross Weighted
Sl. CCPP Output of Output of average Weighted
Manufacturer GTs +
No Model the Plant the Plant Heat average
STs
@ 100% @ MEL, Rate, Efficiency,
MCR, MW KJ/kWh %
1 X 109
1 GE 1+1 737.358 283.805 6221.50 58.22
HA.02

2 MHPS 1 x 701J 1+1 789.281 392.00 6458.00 56.91

1 x SCC
3 Siemens 5 – 9000 1+1 794.570 407.357 6067.00 59.3
HL
2 x GT
4 Ansaldo 2+1 832.248 287.064 6884.5 52.94
26

1 X 209
5 GE 2+1 839.275 296.878 6853.0 53.10
F
2 x SCC
6 Siemens 5– 2+1 891.981 453.792 7042.0 52.30
4000F
Note:
a) The gross power output, heat rate and efficiency of the CCPP at site conditions are based on Thermo flow
software and may differ a little with actual output and efficiency offered by the manufacturer
b) The CCPP models are based on “Gas Turbine World – 2019 Performance Spec Handbook” and published literature
c) The output and heat rate are based on following;
- RLNG analysis: as per Appendix-I.
- Ambient temperature:33 °C
- Relative Humidity: 70%
- Altitude: 6 m above MSL
- Temperature rise across condenser: 10°C
d) The auxiliary power consumption is as per the HBDs generated by GTPRO software and the heat rate is calculated
on the LHV basis
e) The Weightage average heat rate is calculated based on the plant operating 12 hrs @ 100% MCR and 12 hrs @
MEL (Minimum Emission Limit)
f) Ansaldo GT 36 was not considered in the comparison as the output of the machine is less than 700 MW at the site
condition and MHPS 701 G was not considered in the comparison as the output of the machine is greater than 900
MW at the site condition.

Main Plant Equipment

16. The proposed gas turbine combined cycle power plant would consist of One (1) number of
Gas turbine with one (1) unfired Heat recovery steam generator to produce steam which
would be used in steam turbine generator to produce overall power capacity of 700 to 800
MW. The plant will be in single shaft configuration. The generator would be designed for
0.8 to 0.9 power factor at the generator terminals. The gas turbine and the steam turbine
would be designed as indoor equipment, while the HRSG will be designed as outdoor
type. For the purpose of the report, Siemens 1 x SCC5-9000 HL is considered.

17. All the necessary Balance of Plant such as fuel gas conditioning skid, water treatment
plant, cooling system, compressed air system, etc., will be installed.

Power Evacuation

18. The CCPP generator will be connected to the 400kV Air Insulated Substation (AIS)
through a generator transformer. The generated power from the proposed power plant will
be evacuated at 400 kV level by two (2) single circuit lines. 400kV AIS will be connected to
400kV S/S of the new 660 MW plant (around 1km from site) can be considered as an
option for interconnection. The bus rating of the Switchyard to be considered as same of
the interconnecting substation.

Environmental Aspects

19. The site proposed for the power plant is situated away from the nearby towns / cities. All
necessary pollution control measures are proposed for the plant, no adverse impact is
expected to the environment.

Project Schedule

20. It is envisaged that the project would be executed through EPC basis. Based on expected
deliveries of main plant equipment, project implementation period is considered as 34
months from zero date/Notice to proceed to commercial operation of the plant.

Project Cost and Tariff

21. The preliminary project cost works out to Rs.4279.51 Crore including interest during
construction, financing charges and considering taxes and duties with an error rate of +/-
20% (as per American Association for Cost Estimation – Maturity level of Class 4).
Accordingly, the Levelised cost of generation works out to be Rs. 5.54/ kWh with a fixed
cost of about Rs. 2.29/ kWh & variable cost of about Rs. 3.25/ kWh. The Weighted
average plant load factor for the proposed combined cycle power plant works out to be
73.8% based on the prevailing load profile.
CHAPTER – I

I. INTRODUCTION

1. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) was


constituted after unbundling of Tamil Nadu Electricity Board (TNEB) in 1 st Nov 2010 as per
the provisions under the section 131 of the Electricity Act,2003. The certificate of
commencement of business was obtained w.e.f. 16th March 2010. The Company is mainly
responsible for maximum energy Generation to meet up the energy demand in the state of
Tamil Nadu.

2. As present, the Tamil Nadu Generation and Distribution Corporation Limited


(TANGEDCO) and Tamil Nadu Transmission Corporation Ltd (TANTRANSCO) are
functioning as the State-owned generation and transmission & distribution utilities,
respectively.

3. With the rapid industrialization, successful rural electrification and large-scale use of
electricity for the irrigation purpose, the demand for electricity has registered a significant
growth. As per the National Electricity Policy, steps have been undertaken to electrify
every household of Tamil Nadu. Owing to the increased development and better economic
activities during the last few years, the average peak electricity demand has increased in
Tamil Nadu. It is a fact that there has been a steep increase of demand for power during
the last 3-4 years in the state.

4. Tamil Nadu has a total installed power generation capacity of about 32.8 GW, which
includes TANGEDCO owned state projects, share from the Central Generating Stations
(CGS) and Private Power Projects. About 43% of the share is from the renewable energy
source. The present demand for electrical power continues to rise with the economic
growth of the state.

5. To meet the growing demand for liquefied natural gas, Indian Oil Corporation through its
Joint Venture Company, Indian Oil LNG Private Limited is in the process of building a
liquefied natural gas import terminal of 5 MMTPA capacity at Kamarajar Port in Thiruvallur
district at the outskirts of Chennai. Ennore LNG Terminal will be the first LNG terminal on
eastern coast of India. This LNG import terminal is expected to spur industrial growth in
the area. The re-gasified LNG will be distributed to power generation plants, fertilizer
plants and other industrial units.

6. TANGEDCO desires to utilize the above sources of RLNG for augmentation of power
generation in the State. TANGEDCO has planned to set up a high capacity (about 700 to
800 MW) gas based combined cycle power project (GT CCPPs) in and around Chennai.
TANGEDCO has appointed Tata Consulting Engineers Limited (TCE) for preparation a
Feasibility report (FR) for the proposed Power Plant.

7. The scope of this feasibility study report shall cover the following:
No Scope of work Covered in Report
1 Site selection study for the installation of the
Completed.
power project considering the topography, soil
(Site visit was
conditions, accessibility, fuel linkage, availability of
completed on 15th
water, power evacuation arrangements and
and 16th Sep 2020)
availability of land.
2 Power project capacity selection based on the
availability of land and the high efficiency Gas Completed
Turbines
3 Gas Turbine configuration study with advanced
Completed
class and latest technology machines
4 Preparing salient technical details, the details of
Completed
the major equipment/systems proposed
5 Studying the environmental aspects Completed
6 Preparation of preliminary plant layout, heat and
mass balance diagrams, water balance diagram Completed
and electrical single line diagram
7 Preparation of preliminary project implementation
Completed
schedule
8 Study of installation & operation methodology of
the proposed plants through various models (EPC Completed
+ LTSA, EPC + PPP, IPP, EPC)
9 Preparation of first order cost estimates for the
project based on data available in-house cost data
Completed
bank and data obtained from standard published
information
10 Computation of cost of power generation and
Completed
levelized tariff as per CERC guideline
CHAPTER – II

II. NEED AND JUSTIFICATION OF THE PROJECT

1. Tamil Nadu is one of the Six (6) states in the Southern Region (SR) of India, bordered on
the north by the states of Andhra Pradesh and Karnataka and on the west by the state
of Kerala. The state’s power sector went through major reforms in 2008 under the
provision of Electricity Act’2003 and the sector was restructured into various functions of
generation, transmission and distribution of electricity. Tamil Nadu Generation and
Distribution Corporation Limited (TANGEDCO) is one of the companies which is mainly
responsible for maximum energy generation to meet up the energy demand in the state.

2. At present the installed generation capacity of Tangedco is about 32.8 GW out of which
14.5 GW are available from Thermal sector with an equal portion of 14.7 GW from
renewables and the remaining from Nuclear and hydro-power plants. Figure II-1 & II-2
illustrates the share of the fuel mix in the Installed capacity.

Figure II-1: Installed Capacity as on Sep 2020

(Source: CEA website)

Figure II-2: Fuel Mix of thermal power generation as on Sep 2020

(Source: CEA website)


3. Tamil Nadu has a total installed power generation capacity of about 32 GW, including
allocated share in joint and central sector utilities. The breakup of installed capacity from
each sector is furnished in below Table: II-1

Table II-1:Installed Capacity Sector wise as on Sep’2020


Installed Capacities (MW)
Sector
Thermal Nuclear Hydro RES (MNRE)
State 4844.08 0.00 2178.20 122.70
Private 5452.47 0.00 0.00 14390.50
Central 4216.07 1148.00 0.00 231.90
Sub Total 14512.62 1148.00 2178.20 14745.10
(Source: CEA website)

4. The anticipated month-wise power supply position of entire Tamil Nadu state for the year
2019-20 was anticipated by CEA as shown below

Table II-2: Month wise Power Supply Position


Month Peak E
n
er
g
y
Demand Availability Surplus (+)/ Demand Availability Surplus
Deficit (-)
(+)/
Deficit (-)
MW MW MW % MU MU MU
Apr-19 14981.3 14981.3 0 0 9874 9862 -12
May-19 14730.9 14702.3 -28.5 -0.2 9676 9658 -18
Jun-19 14870.3 14850.7 -19.6 -0.1 9477 9469 -8
July-19 15028.7 14928.7 -99.9 -0.7 9714 9706 -8
Aug-19 14734.1 14700.6 -33.5 -0.2 9418 9411 -7
Sep-19 14556.5 14553.1 -3.3 0 8971 8959 -12
Oct-19 14367.5 14332.8 -34.7 -0.2 8645 8634 -10
Nov-19 13893.3 13287.3 -65.9 -0.5 7790 7780 -10
Dec-19 14037.6 13985.8 -51.8 -0.4 8580 8570 -10
Jan-20 13997.5 13952.1 -45.4 -0.3 8499 8495 -4
Feb-20 15041 15023.5 -17.5 -0.1 8542 8542 0
Mar-20 15483.1 15448.1 -34.9 -0.2 10297 10295 -1
Figure II-3: Demand Vs Availability (Peak)

Figure II-4: Demand Vs Availability (Energy)

5. As per National Electricity Policy (24x7 Power for All), all households, industrial,
commercial and all other electricity consuming entities shall be electrified, and Tamil Nadu
has achieved a 100% Household electrification. However, with continuous economic
growth rate and rising industrial development, it is evident that there must be capacity
addition in terms of power station to improve power supply position during peak & off-peak
hours and minimize the demand-availability gap in Tamil Nadu. The forecasting of CEA at
their 19th Electric Power Survey of India report has been shown as below;

Figure II-5: Energy Requirement Forecast (Ex Bus) – MU


The following Figure illustrates the load profile (Yearly Average) of Tamil Nadu along with the renewable
generations.

Figure II-6: Yearly average Load Profile

Figure II-7: Yearly average Wind Generation

Figure II-8: Yearly average Solar Generation


6. About 43% of power for Tamil Nadu is sourced from Renewables. The Renewables
generally possess a varying output due to the change in the climatic condition. To cater
the varying nature of the power, and to satisfy the power required during the peak time, a
fast ramping power plant is required.

7. The Gas based power plant are design for faster ramping rate and typically the gas
turbine takes <30 mins to startup (Hot Startup). The combined cycle power plant takes
<50 mins,
<100 & <300 mins for starting during Hot, warm and cold condition respectively. The Hot,
warm and cold startup depends on the HRSG drum metal temperature. Further the ramp
rate of the gas turbine is about 80 to 88 MW/min. This provides a faster response to the
grid requirement during the RE variations.

8. Due to the economic growth of the Tamil Nadu, it is evident that the state requires
additional power generation (with faster ramp rate to cater the variation in renewables)
even though, currently about 5700 MW of coal-based power plant are in various stages of
the installation, these generation.

9. The gas-based combined cycle power plant would possess;


 It has higher net plant efficiency and better heat rate
Carbon (CO ) emission would be lower compared to solid fuel based plant.
 2
 It is more flexible with higher rate of ramp up.
 It would provide clean energy with lower emission level.
 Less capital investment and installation time.

In view of the above, it is justified to install the gas based combined cycle power plant in
Tamil Nadu in order to meet the increasing demand and drive the state’s growth.

CHAPTER – III

III. SITE SELECTION AND EVALUATION OF SITE

1. The basic criteria for selection of a site for installation of 700 - 800 MW gas based
combined cycle power plant would be as follows;

 Availability of free hold land for main power plant.


 Meteorological conditions influencing plant power output at site
 Adequate water availability for condenser cooling system and other process
requirements. In case water is not allocated to this power project, then either air
cooled condenser or dry cooling system would have to be considered. When such
a situation arises then the land requirement would be increased. Such a study
would be made only on the final selected site. It is assumed for the purpose of the
report that adequate water is available nearby for all the sites under consideration.
 Proximity to gas source and uninterrupted gas supply to plant site. It is assumed
that the natural gas would be available at the plant boundary at all the sites under
consideration.
 Power demand and power evacuation facilities in the region
 Availability of construction material, construction power and water.
 Good accessibility and approach to power plant site for movement of men, material
and equipment
 Suitability of site from important civil engineering considerations such as
adequate soil bearing capacity, nonexistence of seismic fault, extent of
undulations etc.
 Less environmental & social impact, ensuring environmental considerations.

2. Relative ranking system is adopted for all the sites, based on their overall suitability for
installation of CCPP. At first, each of the factors identified above is given maximum credit
depending on their importance in the selection process. Secondly, for a particular site
each of these factors is give credits depending on their contribution. Finally, the site
having obtained maximum credit is given first ranking.

Identified Sites
3. The following sites have been identified for examining suitability for installation of 700 -
800 MW gas based combined cycle power plant;
 Land Near Basin Bridge, vacated by M/s. GMR
 Land Near Ennore Thermal Power Station
Discussion on Proposed Site

Land Near Basin Bridge

Land, Topography, Resettlement and Rehabilitation

4. The site is within the Chennai city limit. The identified site for proposed plant was earlier
utilized for Diesel based power plant by GMR and is at present being vacant. The diesel-
based power plant is demolished, and all the civil foundations are removed, and the
surface is levelled. The site does not have major undulations and is a plain land without
appreciable level difference. However, the site needs a nominal grading of 0.5 m. The
proposed site is free of resettlement and rehabilitation issues. The site is well connected
by road and rail. The approach road has bottlenecks at few locations that would affect the
transportation of material and heavy equipment’s to site. Further there are two (2) drain
canals pass inside the proposed site.

5. The area available at the proposed site is about 29 acres

6. The site conditions are as follows;


 Altitude : 16 m above sea level
 Mean extreme annual maximum temp. : 41.4 °C
 Mean extreme annual minimum temp. : 18.1 °C
 Average design temp : 33 °C
 Average relative humidity : 70%
 Normal Annual rain fall : 1400 mm/year
 Wind speed : Design wind speed 50 m/s as per IS code

Soil Condition

7. Based on the Geotechnical investigation report furnished by TANGEDCO for the nearby
plant and also as the demolished GMR plant is in Pile foundation, the proposed power
plant would be in Pile foundation. However, the final decision on this would be done after
the site selection and subsequent soil investigation.

Water Availability

8. Source of water for the proposed power plant would be Chennai municipality water or
Sewage water. Based on the availability of the water, proposed power plant needs to be
design with wet cooling system with cooling towers or dry cooling system with Air cooled
condenser. The water required for the proposed CCPP would be approximately about
1500 m³/hr, in case of wet cooling tower and about 700 m3/hr for plant with air cooled
condenser.
Natural Gas

9. The natural gas would be available at this proposed site and would be available at the
plant boundary. The IOCL terminal is about 22 km from the site. The estimated natural gas
requirements for the proposed power plant would be around 894 MMSCM/annum.

Power Evacuation

10. The power from the proposed power station shall be evacuated at 400 kV or 230 kV level.
Use of the transmission system available at a distance of 0.5 km from the site shall be
explored further for power evacuation (upcoming 400 KV SS, Pullianthope, Chennai).

Environmental Aspects

11. The proposed site is within the Chennai city limit and is near to the residential area. All
necessary pollution control measures to maintain the emission levels of Sulphur dioxide
and nitrogen oxides, and noise level within the permissible limits would be taken and
necessary treatment of liquid effluents would be affected as per the statutory
requirements. The excess rainwater, after considering the rainwater harvesting provisions
shall be discharged to the canal which is at the proximity of site. Thus, there would be no
adverse impact on either air or water quality in and around the power station site on
account of installation of the proposed plant.

Land Near Ennore Thermal Power Station

Land, Topography, Resettlement and Rehabilitation

12. The site is about 10 km from the Chennai city limit. The identified site for proposed plant
was earlier utilized for Ennore thermal power station as stores. The proposed site is with
vegetation and also some unutilized sheds, which needs to be demolished. Once the
vegetation is removed, the site requires levelling. The proposed site is near to the under
construction 660 MW coal-based power plant, which is on pile foundation. The proposed
site is free of resettlement and rehabilitation issues. The site is well connected by road
and rail. Further there are few 230 kV and 110 kV transmission towers located inside the
site area, which needs shifting.

13. The area available at the proposed site is about 39 acres


14. The site conditions are as follows;
 Altitude : 16 m above sea level
 Mean extreme annual maximum temp. : 41.4 °C
 Mean extreme annual minimum temp. : 18.1 °C
 Average design temp : 33 °C
 Average relative humidity : 70%
 Normal Annual rain fall : 1400 mm/year
 Wind speed : Design wind speed 50 m/s as per IS code

Soil Condition

15. In the absence of soil investigation data and based on the information collected pertaining
to nearby structures, during the visit Pile foundation would be suitable for the proposed
site. However, the final decision on this would be done after the site selection and
subsequent soil investigation

Water Availability

16. As the site is in proximity to the sea, source of water for the proposed power plant would
be Sea water. Based on the availability of the water, proposed power plant needs to be
design with sea water based wet cooling system with cooling towers. The water required
for the proposed CCPP would be approximately about 2900 m³/hr.

Natural Gas

17. The natural gas would be available at this proposed site and would be available at the
plant boundary. The IOCL terminal is about 11 km from the site. The estimated natural gas
requirements for the proposed power plant would be around 894 MMSCM/annum.

Power Evacuation

18. The power from the proposed power station shall be evacuated at 400 kV level. 400kV
AIS will be connected to 400kV S/S of the new 660 MW plant (around 1km from site) can
be considered as an option for interconnection.

Environmental Aspects

19. The proposed site is within the 10 km from Chennai city limit and is near to the coastal
region and 2 km from the seashore. All necessary pollution control measures to maintain
the emission levels of Sulphur dioxide and nitrogen oxides, and noise level within the
permissible limits would be taken and necessary treatment of liquid effluents would be
affected as per the statutory requirements. The excess rainwater, after considering the
rainwater harvesting provisions shall be discharged to the canal which is at the proximity
of site. Thus, there would be no adverse impact on either air or water quality in and around
the power station site on account of installation of the proposed plant.
Evaluation of the proposed site

20. Based on discussion of the proposed sites, it is observed that various attributes have their
impact on selection of project site. In view of this, the proposed sites have been evaluated
with suitable weightage factors for the major attributes and the results have been
furnished in Table III-1.

Table III-1: Evaluation of Proposed Site


Sl.No. Attributes Weightage Weightage Points
Basin Bridge
1 Land Availability 20 15
2 Water Availability 20 10
3 Gas Availability 20 20
4 Power Evacuation 20 20
5 Site topography (Incl. other civil 15 10
engg. aspects, accessibility, storm
water
discharge)
6 Future Infrastructure 5 0
development
Total 100 75
Assumptions:
a) Land is available without any Resettlement and Rehabilitation issues (20 points), proximity to residential buildings (15).
b) Water is available for at least 30 days in a month (20 points).
c) Gas is considered to be available at the plant boundary. It is assumed that GAIL will supply the gas up to the
plant boundary from IOCL terminal
d) Distance of Water line and Power evacuation lines from various sites is based on the data furnished by TANGEDCO.
e) Weightages are given for various factors based on past project experience.

Conclusion

21. Based on Table III-1, the land near Ennore thermal power station is most favourable for
the proposed combined cycle power project.
CHAPTER – IV

IV. SITE FEATURES AND FUEL LINKAGE

1. The site proposed for the power plant is located 10 km from the Chennai city. The site is
located 3 km from State Highway–56 (SH-56) connecting Thiruvathiyur and Panchetty.
The nearest railway station is Kathivakkam (sub urban) about 2 km from the site. The
nearest airport is Chennai International Airport, Chennai about 34 km from project site.
The nearest port is Ennore port about 11 km from the project site

2. The latitude, longitude and altitude of the project site are as follows:
Latitude : 13°12'21.74" North
Longitude: 80°18'46.09" East
Altitude : 6 meters above Mean Sea Level

Figure IV-1 :Project Location

Discussion of Site Features

3. The suitability of the site for the installation of the power plant is determined by the
following major considerations:

a) Availability of adequate land free from extensive cultivation, habitation and forest
b) Availability of space for locating the main plant, transformer yard, switchyard and
all the balance of plant facilities required along with construction activities
c) Availability of proper road or rail access to the plant, site for movement of
equipment, construction materials, pipes, chemicals, etc
d) Suitability of land from topography and geological aspects
e) Availability of adequate supply of water for condenser cooling and other plant
requirements
f) Fuel supply
g) Power evacuation

Availability of Land

4. The total area required for the proposed power plant would be about 15 acres for the
proposed 700 – 800 MW nominal capacity and the same is already in possession of
TANGEDCO. The enclosed Plot Plan (Exhibit – 1) provides certain key details of the
layout.
Accessibility to Site

5. Proposed site is accessible by road, rail and by air as mentioned in item 1 above. The
site is located in close to SH-56.

Availability of Water

6. The source of raw water required for the proposed power plant would be obtained Bay of
Bengal. The sea water will be tapped off from the upcoming 660 MW thermal power
station near to the project site.

Topographical Aspects and Site Grading

7. The area proposed for the power plant is with vegetation and also some unutilized
sheds, which needs to be demolished. After removal of vegetation, the area may require
minimum grading.

Fuel Source & Cost

8. Fuel gas (RLNG) for the proposed plant would be sourced from IOCL. The transportation
of the fuel gas will be through IOCL cross country pipeline. It has been assumed that the
gas line up to the plant boundary is in IOCL’s scope.

9. The annual fuel gas consumption for the proposed power plant is estimated as 894
MMSCM per annum considering average LHV value of 11131 kcal/kg, annual plant load
factor (PLF) of 73.8% and weighted average heat rate of about 1692 kCal/kWh
(54.43%).
Power Evacuation

10. Each generator will be connected to the 400kV Air Insulated Substation (AIS) through a
generator transformer. The generated power from the proposed power plant will be
evacuated at 400 kV level by two (2) single circuit lines. 400kV AIS will be connected to
400kV S/S of the new 660 MW plant (around 1km from site) can be considered as an
option for interconnection. The bus rating of the Switchyard to be considered as same of
the interconnecting substation.

Environmental Aspects

11. The site proposed for the power plant is situated away from the nearby towns / cities. All
necessary pollution control measures are proposed for the plant, no adverse impact is
expected to the environment.
12. The following table illustrates the site details of the proposed power plant.

Table IV-1: Site Details


Sl. No Particulars Site Details
1 Population Not Applicable
2 Area of land, acres 39 (Approx.)
3 Owner of land TANGEDCO
4 Proximity to various Facilities /
infrastructures
4.1 City/ Town Chennai – 10 km
4.2 Water source Sea Water
4.4 Highway State Highway (SH 56) – 3 km
4.5 Railway station Kathivakkam – 2 km
4.6 Sea port Ennore Port – 11 km
4.7 Nearest airport Chennai International Airport, Chennai
about 34 km from project site
4.8 Nearest substation Upcoming 765 KV Pooling Station
4.9 Access roads Available
5 Terrain Appears to be flat with certain
undulations
6 Land availability Available for the project and owned by
Private/ Government TANGEDCO
Willingness to sell
CHAPTER – V

V. SELECTION OF TECHNOLOGY AND PLANT CONFIGURATION

Selection of Technology

1. Gas turbine power plants using RLNG as fuel have been in operation for a long time.
There has been considerable improvement in the design of gas turbine generators
resulting in significant enhancement in their reliability, capacity and thermal efficiency. Gas
turbine designs with higher rated outputs are under way. Combined cycle power plants
making use of the heat content of the exhaust gas from the gas turbine to raise steam in a
heat recovery steam generator and subsequent use of steam in a steam turbine generator
have a significantly higher overall combined cycle efficiency of about 55-62% on net
calorific value basis. The thermal efficiency attainable in combined cycle power plants is
far higher than the efficiency of the best available fossil fuel fired thermal power plants.

Fuel

2. For this report, Re-Liquified Natural Gas (RLNG) is considered as the fuel for the
proposed power plant. This would be sourced from the IOCL, through a dedicated pipeline
from the main gas pipeline.

Selection of plant size, configuration, equipment and source

Development trend of capacity and manufacturing technology of GTs in the world

3. For CCPPs, the entire capacity is determined by the selection of GT power and
configuration, the steam cycle capacity will depend on the selected steam turbine power
and configuration. Generally, GTs tend to be developed with increasing capacity and
efficiency. Currently, GTs have been developed to the G, H, and J class with efficiency
over 60% and the F-class GTs have also been significantly improved in terms of efficiency.

Plant Configurations Available in the market for the plant capacity under consideration

4. Combined cycle power plant with nominal capacity of 700 - 800 MW has been considered
for the purpose of this report

5. The standard CCPP configurations available currently from the various manufacturers and
their ISO output are published in the ‘GTW Handbook 2019’. This book has been referred
to choose the plant configuration for the proposed CCPP. In addition, ‘GTPRO’ program
from Thermoflow Inc, USA, is used in the selection of the gas turbine power generating
units as well as in determining the performance of the plant specific to site. The models
available
from leading gas turbine manufacturers namely Ansaldo, General Electric (GE), Siemens and
Mitsubishi have been considered.

6. The Figure below illustrates the GT class development charts of different GT manufacturers
7. Based on the GT World Handbook 2019, a list of possible configurations has been
identified for the CCPP. The site output of such configurations was determined using the
GTPRO program. The possible plant configurations, the site output, heat rate, etc. for the
power output of 700 - 8000 MW is presented in the Tables V-2 & V-3

8. The following two (2) alternatives for Combined Cycle Power Plant have been considered
for further study and plant configuration selection

9. Option – 1: 1 block of 700 - 800 MW in single shaft / multi-shaft configuration with


advanced class machines (H Class). Single shaft configuration will have 1 gas turbine, 1
HRSG and 1 steam turbine in a single shaft mode with a common electric generator and
one generator transformer. While in multi shaft configuration will have 1 gas turbine, 1
HRSG and 1 steam turbine and 2 generators (1 for gas turbine and another for steam
turbine)

10. Option – 2: 1 block of 700 - 800 MW in multi-shaft configuration with F class machines,
where in the block will have 2 gas turbine, 2 HRSG and 1 steam turbine with 3 electric
generators (2 for gas turbine and another for steam turbine)

Comparison of single v/s multi shaft configurations

11. General comparison of single shaft v/s multi shaft configurations in terms of arrangement,
are furnished below here in Table V-1

Table V-1: Comparison of Single Shaft Vs Multi Shaft


Sl. Description Single Shaft CCPP Multi Shaft CCPP
No. Configuration Configuration
1.0 Configuration Single shaft combined cycle Multi shaft combined cycle
system consists of one gas turbine, system have one or more gas
one steam turbine, one electric turbine generators and HRSGs
generator and one heat recovery that supply steam through a
steam generator (HRSG). The gas common header to a separate
turbine and steam turbine coupled single steam turbine generator
to a single generator in a tandem unit.
arrangement.
2.0 Main feature Common electric generator and Separate electric generators for
consequently common electrical each of the gas turbines and
system downstream of generator steam turbine and consequently
for both gas turbine and steam separate electrical system
turbine. downstream of generators.
3.0 Typical Single shaft combined cycle Multi shaft combined cycle
application system is installed in single phase system configuration is possible
so that the gas turbine and steam to install in multi-phases such
Sl. Description Single Shaft CCPP Multi Shaft CCPP
No. Configuration Configuration
turbine installation and commercial that gas turbines are installed
operation are concurrent. and operated prior to steam
cycle installation. However,
flexibility to operate gas turbine
in open cycle mode would
require provision of flue gas
bypass system.
However, in advanced F class
gas turbine installations, flue gas
bypass system is not installed
mostly due to gas leaks issue
and application of large size
diverter dampers. In certain
installations, blanking plates are
applied to isolate HRSG and
operate GT in simple cycle. But
blanking plate is to be installed
only after plant shutdown.
4.0 Arrangement Two different single shaft Multi shaft plants are installed in
arrangements are possible single block or multi block
GE adopt configuration where the arrangements. Each block
generator is positioned at the end consisting of either
of the shaft line.
While Siemens and Ansaldo apply a) 1GTG + 1HRSG +
generator in the middle of power
train with one end connected to 1STG or
gas turbine with rigid coupling and
the other end connected to steam b) 2GTGs + 2HRSGs + 1STG
turbine with synchronous self-
shifting clutch.
When the gas turbine is started,
the clutch will be in disengaged
position and steam turbine will be
standstill. The gas turbine will be
loaded up and when the steam
parameters from HRSG reach
required condition for steam
turbine start-up, the steam is
admitted to the steam turbine and
the steam turbine picks up speed.
Sl. Description Single Shaft CCPP Multi Shaft CCPP
No. Configuration Configuration
At precisely the point when the
clutch teeth are correctly aligned
after steam turbine (clutch input)
has reached the same speed as
the generator (clutch output), the
clutch is automatically engaged
without external control. Similarly,
disengagement of the clutch
occurs automatically whenever the
steam turbine slows down relative
to generator.
MHI supplies both the arrangement
based on customer needs.
5.0 Operating The single shaft machine is The multi shaft configuration is
Experience adopted in Torrent Sugen-CCPP- adopted in Dabhol, Pipavav,
1100MW. However, there are Hazira (GSEG) and Vemagiri in
several CCPPs of single shaft India. Also, several CCPP’s in
configuration operating abroad. MS configuration are operating
globally.
6.0 Heat Rate Marginally lower (better) Base
7.0 Generator Generator rotor removal for single Generator is always at one end
removal shaft arrangement adopted by and as such rotor removal is a
European manufacturers is more less complicated affair
complicated as the generator is in
between gas turbine and steam
turbine
8.0 O&M Generator has to be turned for No such restriction.
requirements rotor removal, as the generator is
located between the gas turbine
and the steam turbine. If generator
is placed at one end of turbine,
then rotor removal method would
be conventional type.
9.0 Space Compact and occupies less space Occupies larger space than
Requirements single shaft configuration.
10.0 Power Island Common building for GT & ST Separate building for GT & ST
structure Common crane for GT & ST Separate crane for GT & ST.
11.0 Generator Higher generator efficiency (single Higher generator efficiency
Efficiency H cooled generator) (single H cooled generator).
2 2
12. The performance comparison between advanced class (H) machines and F class machines is listed out in Tables V-2 & V-3
below

Table V-2: Brief Technical Parameters and Performance of possible CCPP ( Option – 1: 1 Block of 700 - 800 MW with H
class Gas Turbine)

orma
No of GTs +
Sl. No Manufacturer CCPP STs
Model

Gross Gross Output of Weighted


Weighted
Output of the Plant @ MEL, average Heat
average
the Plant MW Rate, KJ/kWh
Efficiency,
@ 100%
%
MCR, MW
1X
1 GE 1+1 737.358 283.805 6221.50 58.22
109
HA.0
2

2 MHPS 1 x 701J 1+1 789.281 392.00 6458.00 56.91

1 x SCC 5 –
3 Siemens 1+1 794.570 407.357 6067.00 59.3
9000 HL
Note:
a) The gross power output, heat rate and efficiency of the CCPP at site conditions are based on Thermo flow software and may differ a little with actual output and
efficiency offered by the manufacturer
b) The CCPP models are based on “Gas Turbine World – 2019 Performance Spec Handbook” and published literature
c) The output and heat rate are based on following;
- RLNG analysis: as per Appendix-I.
- Ambient temperature:33 °C
- Relative Humidity: 70%
- Altitude: 6 m above MSL
- Temperature rise across condenser: 10°C
d) The auxiliary power consumption is as per the HBDs generated by GTPRO software and the heat rate is calculated on the LHV basis
e) The Weightage average heat rate is calculated based on the plant operating 12 hrs @ 100% MCR and 12 hrs @ MEL (Minimum Emission Limit)
f) Ansaldo GT 36 was not considered in the comparison as the output of the machine is less than 700 MW at the site condition.
Table V-3: Brief Technical Parameters and Performance of possible CCPP ( Option – 2: 1 Block of 700 - 800 MW with
advanced class (F Class) Gas Turbine)

orma
No of GTs +
Sl. No Manufacturer CCPP STs
Model

Gross Gross Output of Weighted


Weighted
Output of the Plant @ MEL, average Heat
average
the Plant MW Rate, KJ/kWh
Efficiency,
@ 100% %
MCR, MW

1 Ansaldo 2 x GT 26 2+1 832.248 287.064 6884.5 52.94

2 GE 1 X 209 F 2+1 839.275 296.878 6853.0 53.10

2 x SCC 5 –
3 Siemens 2+1 891.981 453.792 7042.0 52.30
4000F
Note:
g) The gross power output, heat rate and efficiency of the CCPP at site conditions are based on Thermo flow software and may differ a little with actual output and
efficiency offered by the manufacturer
h) The CCPP models are based on “Gas Turbine World – 2019 Performance Spec Handbook” and published literature
i) The output and heat rate are based on following;
- RLNG analysis: as per Appendix-I.
- Ambient temperature:33 °C
- Relative Humidity: 70%
- Altitude: 6 m above MSL
- Temperature rise across condenser: 10°C
j) The auxiliary power consumption is as per the HBDs generated by GTPRO software and the heat rate is calculated on the LHV basis
k) The Weightage average heat rate is calculated based on the plant operating 12 hrs @ 100% MCR and 12 hrs @ MEL (Minimum Emission Limit)
l) MHPS 701 G was not considered in the comparison as the output of the machine is greater than 900 MW at the site condition.

Discussion of Various configuration

Option 1 : 700 - 800 MW Block with 1 GT + 1 HRSG and 1 ST in Single Shaft / Multi Shaft Configuration

13. The Table V-2 lists out the 1 GT + 1 HRSG + 1 ST configuration from leading manufacturers viz. GE, MHI and Siemens.
Ansaldo GT 36 was not considered in the comparison as the power output at site condition is lesser than 700 MW. The
site gross output of the plant at 100% MCR condition varies from 730 MW to 800 MW and the overall weighted average
gross efficiency varies about 56% to 59%. The auxiliary power consumption varies from about 15.7 MW to about 16.9 MW.
The weighted average gross efficiency was calculated considering that the CCPP will operate under cyclic load condition
(12 hrs at 100% MCR & remaining 12 hrs at minimum emission load).

14. The number of generators for the block of 700 – 800 MW power island in multi shaft configuration would be two (one for
GT and one for ST).

Option – 2: 700 - 800 MW Block with 2 GT + 2 HRSG and 1 ST in Multi Shaft Configuration

15. Table V-3 lists out the 2 GTG + 2 HRSG + 1 STG in multi shaft configuration from leading manufacturers viz. Ansaldo, GE
and Siemens. The site gross output varies from about 832 MW to about 891 MW and the overall weighted average
efficiency varies from 52.3% to 53.1%. The weighted average gross efficiency was calculated considering that the CCPP
will operate under cyclic load condition (12 hrs at 100% MCR & remaining 12 hrs at minimum emission load).

16. The number of generator for this power island in multi shaft configuration would be three (2 for GT and 1 for ST) and three
(3) numbers of associated generator transformers

Recommendation of CCPP configuration for the power plant

17. The Land required for the above options are illustrated in table below;
Table V-4: Land requirement for Gas Turbines
Buildings Option-1 Option-2
Power block, acres 5.2 6.5

Electrical Area, acres 0.8 1.6

Buildings Option-1 Option-2


Cooling System, acres 1.2 1.3

Fuel gas system, acres 0.6 0.8

Land for other miscellaneous requirements (BOP, PECC, road, 7.2 8.8
etc.), acres
Total, acres 15.0 19.0

Note: The above area doesn’t include Green Belt

18. For a combined cycle power plant in the range of 800 MW output firing RLNG with price ranging between $7 MMBTU, a
difference of one or two percentage points in plant efficiency is most important. Depending on utilization and average fuel
price, even a single percentage point improvement in efficiency could reduce the operating cost considerably. Hence, it is
proposed to install advanced class machines (H Class) with water cooled condenser for the proposed power project. In the
Option 1, the plant in single shaft configuration as well as multi shaft configurations having 1GT+1HRSG+1STG
combinations for advanced class (H class) gas turbines are proven in service and are technically acceptable.

19. Hence for the purpose of this study, Siemens 1 x SCC 5 – 9000 HL in single shaft configuration with water cooled
condenser (sea water based) is selected and discussed further.
CHAPTER – VI
VI. FEATURES OF PROPOSED PLANT

General

1. The proposed combined cycle power plant would of one on configuration comprising one
(1) Gas turbine with equal number of unfired HRSG to supply steam to steam turbine

2. Brief description of major equipment / systems for mechanical, electrical, instrumentation & control and civil works are
given below.

Mechanical Gas Turbine

3. The gas turbine would consist of a multistage compressor and a turbine. The heat content of the exhaust gas from the gas
turbine would be used to produce the steam in HRSG. The steam produced will be supplied to steam turbine for producing
the additional power.

4. The gas turbine generator will be provided with its air compressor, Combustor and turbine along with corresponding
auxiliary systems and equipment such as inlet air filtration system, inlet silencer, exhaust diffuser, fuel gas system, GT
cooling system, lubricating oil system, control oil system, starting system, control & instrumentation system, etc.

5. Gas Turbine units would be designed for single firing using RLNG as fuel. The starting system is based on a static
converter which runs the generator as a motor at the time of start-up before the ignition of the gas turbine.

6. A fire detection and carbon dioxide-based fire protection system would be provided to protect the gas turbine and its
auxiliaries against fire hazard

Heat Recovery Steam Generator

7. The HRSG proposed is of triple pressure, unfired, horizontal gas flow type with a self- supporting stack. A condensate
preheater to recover the thermal energy of the hot gas to the maximum extent would be provided apart from the
superheater, evaporator and economiser sections. HRSG would be provided with internal thermal insulation, platforms and
ladders as required. Feed water and steam sampling arrangements as required would be provided. Alternatively, a forced
circulation vertical type HRSG can also be considered. This would be decided during detailed engineering phase of the
project.
8. Steam from the HRSG’s would be supplied to a condensing type reheat steam turbine through main steam piping. High
pressure (HP) and low pressure (LP) bypass systems of 100% HRSG capacity for dumping the HP and LP steam to the
condenser during start up and turbine trip conditions would be provided

9. The exhaust system would exhaust the gas into the atmosphere through the HRSG. HRSG stack would be 70m above the
ground level

10. The generator is rated for 11kV terminal voltage, 3 Ph and designed to operate at 0.8 to 0.9 power factor, 50 Hz, 3000
r/min generator. Gas Turbine Generators are provided with Static Excitation system. The generator cooling is through
closed cooling water system

Steam Turbine and Auxiliaries

11. Triple pressure, reheat, condensing type steam turbine would be applied based on the selected gas turbine model. The
steam entry to the turbine would be through a set of emergency stop and control valves, which would govern the speed/
load of the machine. The steam turbine would be complete with lube oil and control oil system, jacking oil system,
governing system, protection system and gland sealing steam system.

Condensing Equipment and Auxiliaries

12. The steam turbine would be provided with a surface type condenser fixed to the turbine exhaust for condensing the
exhaust steam from the steam turbine. 2 x 100 %, (one working and one standby) mechanical vacuum pumps would be
provided for evacuation of the steam air mixture from the condenser. 3 x 50 %, (two working and one standby) condensate
extraction pumps (CEP) would be provided to pump the condensate from the condenser hot well into the deaerator
through the condensate preheater of the HRSG

Feed Water System

13. Deaerating condenser or Integral deaerator to LP steam drum for the purpose of feed water heating and deaeration of
HRSG feed water could be considered
14. The deaerator would be equipped with a feed water storage tank having a minimum storage capacity of about six (6)
minutes under 100% maximum continuous operation of the HRSG. The deaerator would be located at a suitable elevation
to provide the required net positive suction head for the feed water pumps

15. The deaerated feed water contained in the feed water storage tank would be supplied to the HRSG by means of HP
HRSG feed water pumps. The IP feed water would be from the interstage tap off of the HP feedwater pump. The feed
water flow to the HRSG would be regulated through feed water control valves. Separate LP feedwater pumps for LP circuit
would be provided.

Steam Cycle

16. Steam is generated at three pressure levels, namely high pressure (HP), intermediate pressure (IP) and low pressure (LP)
in the HRSG. HP steam is admitted to the HP steam turbine through the HP stop and governor control valves, the IP /
reheat steam would be admitted to IP turbine through the interceptor stop and control valve. The LP steam would be
injected to the interstage of IP turbine through the LP interceptor stop and control valve. The steam turbine would be a
mixed pressure, reheat condensing type. A typical heat balance scheme is shown in Exhibit-2

Cycle Chemical Dosing System

17. Phosphate and hydrazide/morpholine dosing systems would be provided to ensure chemical conditioning of the feed
water so as to prevent scale formation and to remove the dissolved oxygen and carbon dioxide present. Phosphate
solution would be added into the HRSG drum directly, while hydrazide / morpholine would be injected into the feed water
at the feed water pumps suction. Provision for dosing of hydrazide / morpholine at the discharge of condensate extraction
pumps would also be provided. Each system would be complete with solution preparation-cum-feed tanks, agitators /
mixers, metering pumps, piping, valves and fittings

Fuel Gas System

18. The RLNG will be sourced from IOCL. The transportation of the fuel gas will be through IOCL cross country pipeline to the
proposed site. The operating pressure would be about 40 kg/cm2(g) and the temperature would be about 40°C (max). The
gas conditioning system would be provided to remove of liquid and particulate matter.
19. The fuel gas conditioning skid will be designed to maintain specified gas pressure at the outlet of the skid and to remove
solid & liquid particles from the fuel gas to meet the GT requirements.

20. The Fuel gas conditioning skid comprises emergency shutdown valve (ESD), scrubber/knockout drum, pressure reducing
cum control station, filter separator, fuel gas condensate drain tank, cold vent stack, flow meter, gas chromatograph,
instrumentation, associated piping, valves and fittings. The analysis of fuel gas to be conditioned at the gas- conditioning
skid is indicated in Appendix 1. All equipment’s would be skid mounted and would be located at the plant boundary.
Compressed Air System

21. Centralised compressed air system would be provided for meeting the plant instrument and service air requirements of the
plant auxiliary systems. This system consists of 3 x 50% (2 working + 1 stand by) capacity double staged, non-lubricated,
water cooled, reciprocating double acting compressors with all accessories like inter coolers, after coolers, delivery bottles,
moisture separators intake filters, suction silencers, etc. Two (2) air receivers of suitable capacity (one for service air and
one for instrument air) with all accessories would also be provided

Air Conditioning System

22. It is proposed to air-condition the plant main control room, electronic cubicle room, shift in- charge engineer’s room,
maintenance engineer’s room, printer room, UPS room, SWAS room, excitation cubicle room, relay room, I&C lab in
service building, WT plant control room and chemical lab. Inside design conditions of 24.5  1.5C dry bulb temperature
and relative humidity not exceeding 60% would be maintained in all air-conditioned areas.

Ventilation System

23. For ventilation of the station building, and also other buildings supply air fans or louvers, exhaust air fans or roof extractors
complete with air distribution system, consisting of ducting and grilles would be provided

Cranes and Hoists

24. Cranes and hoists with all accessories, supporting structure, power supply, safety devices and controls of required sizes
and adequate capacities would be provided to facilitate the lifting and transporting of various parts of equipment during
maintenance or replacement of the various plant components. Other miscellaneous monorails, trolleys and hoists required
would also be provided. Turbine hall will be provided with adequate capacity crane to handle GT/ST generator
components.

Water Systems

25. Water system facilities required for the complete power plant are covered under the following categories.

 Sea water intake and storage system


 Circulating water (CW) system
 Auxiliary cooling water (ACW) system
 Water treatment (WT) system
 Service and potable water system
 Effluent treatment & reuse system

Sea water intake and Storage System

26. The source of water for the proposed CCPP would be drawn from the Sea from sea water intake directly for CW makeup
and shall be stored in the plant water storage tank for plant use in other systems. The total requirement of sea water
make-up is around 2900 m3/hr for the proposed CCPP. CW system requirement is about 2200 m 3/hr and rest of the plant
services around 700 m3/hr. An enclosed RCC raw water storage tank to hold One (1) days water requirement of the plant
is provided within the plant boundary. The water storage capacity of this tank is 17000 m3 capacity. Chlorine dosing system
for controlling algae/weed shall be done at the sea water intake.

Circulating water (CW) System

27. Recirculation type cooling system with cooling tower is proposed for CW system using Induced Draft Cooling Tower
(IDCT)

28. 3x50% (2W+1S) CW pumps with one standby are proposed for 800 MW CCPP. These pumps would be installed in
individual chambers connected to the CW fore bay. Each pump chamber would have provision for installing coarse screens
and stop logs. The pumps would be located indoors in a pump house. Handling of pumps would be through an EOT crane
of suitable capacity. Handling facilities would also be made available for screens and stop logs.

29. It is proposed to install Induced draft-cooling tower (IDCT). The cooling water would be collected in a basin. The cooling
tower would be designed for a cooling range of 10°C and an approach of 5°C. The design wet bulb temperature would be
about 28°C. The design hot and cold-water temperatures of the cooling towers would be 43°C and 33°C respectively. CW
flow from the cooling tower basin is proposed to be conveyed by gravity to the common CW fore bay of RCC rectangular
open channels and then to fore-bay and pump house. From the CW pump house, the CW discharge is proposed to be
conveyed to the respective condensers located in the station building, through CW inlet conduits. The hot water from the
condensers will be conveyed back to the cooling towers through CW outlet conduits

30. Condenser on load tube cleaning system (COLTCS) would be provided across the condenser in order to keep the
condenser tubes clean. Two COLTCS units per unit have been envisaged for the proposed system

31. Make-up water requirement of CW system is obtained as the sum of drift and evaporation losses from the cooling tower
and blow down from the CW system. The blow down would be discharged back into the sea. Based on the water
analysis a cycle of concentration
(COC) of 1.5 has been adopted for CW system. The CW blow down will be done from the cooling tower basin (cold side)

32. Sea water from the sea water intake will be pumped to the CW make-up chamber. In order to prevent / minimise the
growth of algae in the cooling water system, biocide dosing/chlorine dosing is proposed. Selection of the specific biocide
would be done during detailed engineering. Provision will be made for shock dosing and continuous dosing. However, the
continuous dosing rate would be adjusted during operation phase to meet the chlorine demand. To prevent
scaling/corrosion arising due to the operation of CW system at a higher COC, acid and chemical dosing system is
envisaged

Auxiliary Cooling Water (ACW) System

33. The ACW system meets the cooling water requirements of all the auxiliary equipment of the GT, STG, HRSG and BoP,
such as turbine lube oil coolers, generator air cooler, exciter air coolers, BFP auxiliaries such as lube oil coolers, working
oil coolers, drive motors, etc., condensate pump bearings, sample coolers and air compressors using passivated DM
water
34. Passivated DM water is pumped through these coolers using three (3) (2 working + 1 standby) nos. DMCW pumps. Hot
water from the auxiliary coolers will be cooled in the 3x50% ACW plate heat exchangers. On the secondary side of the
heat exchangers, the cooling water will be provided by tapping off from the associated main CW system header using
three (3) (2 working + 1 standby) nos. ACW pumps. The hot water from these heat exchangers will be connected to hot
water conduit of the associated main CW system leading back to the cooling tower

35. DMCW overhead tank of 2 m3 for each Unit is proposed to ensure positive suction to the DMCW pumps and also serve as
the source of make-up to the DMCW system. Normal make-up to the DMCW overhead tank is provided from the
condensate extraction pump discharge. Initial fill for the tank will be provided from the hot well make up pumps

Water Treatment Plant

36. As sea water is the source of water for the plant, it is proposed to desalinate the water to be made suitable for the plant
services including STG feed cycle make up. Reverse Osmosis (RO) based desalination is proposed for production of fresh
water from sea water. Followed by mixed bed polishers to generate DM water

37. The water treatment plant consists of clarifier followed by UF+CF+SWRO+BWRO+MB. Water will be supplied to the water
treatment plant by means of Three (3) X 50% (2 working
+ 1 standby) WTP supply pumps. The WTP supply pumps will take suction from the plant water storage tank

38. The water treatment plant provides water of specified quality and quantity to meet feed cycle makeup and DMCW cycle
makeup requirement

39. The WTP supply pumps provide water to the clarifier to remove the suspended solids and turbidity. This water is passed
UF+CF+SWRO membrane to desalinate the water. The desalinated water shall be used for Fire protection and other
service water consumables such as filter backwash water requirements, HVAC make-up requirements and other plant
requirements are met. Further the desalinated water is passed through BWRO membrane to obtain water suitable to fed to
DM plant. A part of this water is stored in a potable water storage tank from where potable water requirements are met.
The balance filtered water is led into the DM plant
40. The DM Plant consists of Mixed Bed units. The DM Plant is located indoor. However, all acid and alkali equipment,
regeneration equipment, degasser system are located outdoor. The regeneration chemicals are Hydrochloric Acid (HCl)
and Sodium Hydroxide (NaOH). The chemical regeneration wastes from WT plant area (DM plant) will be collected in a
Neutralising pit and neutralised. Further this neutralised effluent will be pumped to Effluent Treatment Plant (ETP). The
operation of the DM Plant shall be PLC based semi-automatic.

41. DM water from the outlet of mixed bed is fed taken to DM storage tank from where the DM water pumps (2x100%) shall
provide the feed water make up. DM regeneration is done by DM regen. Pumps (2x100%) which shall take suction from
the DM storage tank

Service and Potable Water System

42. The service water system supplies water required for the miscellaneous water requirements such as service water
requirements of the GT, STG and HRSG area, Air compressor area, fin fan cooler area (if installed), toilets, etc.

43. Two (2) x 100% horizontal, centrifugal type, service water pumps will pump water from the desalinated water storage tank
and further distributed to the different consumer points. Potable water shall be distributed from potable water storage tank
with 2 x 100% pumps

Effluent Treatment System

44. The source of plant effluents would be from WTP, HRSG blow down, workshop, TG building, oil water separator, and plant
washing/cleaning drains. The effluent system would be designed for maximum reuse of all the plant effluent. All the
effluents will be collected in ETP. Facilities in the form of chemical dosing system, effluent recirculation system, pH
correction, etc. shall be provided to treat the effluent for further reuse. Oily waste from transformer area, boiler area, TG
building wash and oil water mixture emerging from service water system would be treated using oil-water separators for
removal of oil from water.
Clear water would be discharged to ETP and separated oil would be collected in barrels to be manually disposed. The
treated effluent from the ETP will be utilized for meeting the requirement horticulture. If there is balance water, it shall be
led back through clarifier-filters- RO plant using 1x100% effluent transfer pumps in order to reuse the treated water to the
maximum possible extent
Fire Protection system

45. The plant would be provided with fire hydrant and protection system. The system would consist of fire water storage tank
of adequate capacity, fire water pumps, fire water network and hydrant system along with necessary control and
instrumentation as per the local codes.

ELECTRICAL

46. The generation voltage for the CCPP shall be as per Manufacturer’s standard voltage. Generator will be connected to the
400kV Air Insulated Substation (AIS) through the Generator Transformer (GT). Power will be evacuated through 2 no. of
400kV single circuit lines. All electrical equipment supplied will conform to the requirements of IEC standards.

47. The Generator will be rated to deliver guaranteed output, 0.85pf lag, 3000rpm, 50Hz. The generator would deliver rated
MVA output under ±5% variation in voltage and +3% to -5% variations in frequency. The generator winding (Stator &
Rotor) would be provided with Class-F insulation or better. However, temperature rise would be limited to that of Class –
B. The star point of the generator would be connected to earth through an earthing resistor. The generators shall be air
cooled type

48. The generator excitation system would be of brushless type and would have an automatic voltage regulator to maintain
steady generator terminal voltage within permissible limits under different load conditions. The voltage regulator would
also be capable of maintaining stability under transient conditions

Generator Circuit Breaker

49. The GCB will be provided in the run of the generator main connection to the generator transformer to connect or
disconnect the generator during the start up or shut down period of the plant or on generator fault conditions.

50. The GCB complete with SF6 circuit breaker, motor operated series disconnector on generator transformer side, motor
operated earth switch on either side of circuit breaker, short circuiting connection and protective capacitors along with local
control panel assembled to form a three-phase unit will be provided.
51. The GCB will be installed indoor and connected to IPB on both sides. The GCB enclosure will be of non-magnetic
aluminum alloy and isolated phase type.
52. The electrical characteristics and performance of the GCBs will conform to IEEE Std. C37.013

Isolated Phase Bus Duct (IPBD)

53. The terminals of the generator will be connected to the generator transformer through IPB of adequate short circuit
withstand capability. In case of generator, suitably rated tap-off will be provided to the unit auxiliary transformer. Necessary
generator line side and neutral side current transformers and line side voltage transformers required for protection and
metering will be provided on the busduct for Generator. Also, surge protection equipment consisting of LAs with suitable
discharge characteristics to suit generator basic insulation level will be provided in the busduct for Generator. The
busducts will be natural air cooled and will run partly indoor and partly outdoor

Non-segregated Phase Busduct (NSPB)

54. 1.1kV class Non-segregated phase busduct (NSPB) and accessories will be provided for connection between all auxiliary
transformers and their respective 415V switchgear. The continuous rating & short time and momentary current ratings of
the NSPB will be same as that of associated 415V switchgear. The NSPB will be natural air cooled.

Generator Transformer

55. Generator will be connected to 400kV Air Insulated Switchyard through generator transformers. The GT with 3x300MVA,
20/420kV, 1 phase, ONAN/ONAF/OFAF cooled with
±10% OLTC in steps of 1.25% on HV side for Generator Transformer will be provided. GTs will be connected in vector
group of YNd1 with HV winding as star connected and LV winding as delta connected. The HV side neutral will be solidly
earthed. The applied standard is IEC 60076

Evacuation of Power

56. The generator will be connected to the 400kV Air Insulated Substation (AIS) through a generator transformer. The
generated power from the proposed power plant will be evacuated at 400kV level by two (2) single circuit lines

57. 400kV AIS will be connected to 400kV S/S of the new 660MW plant (around 1km from site) can be considered as an
option for interconnection. The bus rating of the Switchyard to be considered as same of the interconnecting substation
Auxiliary Power Supply System

58. Various auxiliaries will be supplied at the following nominal voltages depending upon their ratings and functions

Table VI-1: Auxiliaries and supply voltage


Sl. No Auxiliaries Voltage
a) For AC motors 415V±10%, 50Hz±5%, 3phase,
3wire, effectively earthed
c) For AC control and protective devices 110V±10%, 50Hz±5%,
1 phase, AC supply with one
lead earthed
d) For lighting and space heaters 230V±10%, 50Hz±5%,
1 phase, AC supply with
neutral lead earthed
e) For DC motors, control and protective 220V, 2 wire unearthed DC
devices of Electrical system (GRP, GCP supply
and SRP/SCP)
f) For services requiring uninterrupted 230V, 1 phase, 50Hz, AC
power supply (UPS) unearthed supply

59. 2x100% Unit Auxiliary Transformers (UAT) will be provided and connected to Gas turbine/steam turbine generator through
SPB / Cables. UATs will feed its respective gas turbine generator and steam turbine generator auxiliaries. Common station
service load auxiliaries are distributed among the auxiliary switchgears. While starting the unit, the GCBs will be kept open
& the grid supply will be given to unit/station auxiliaries through generator transformer and unit auxiliary transformers.
Once the unit is started, the GCBs will be closed and UATs will continue to feed the auxiliaries. In the event of outage of
one of the UAT, the other unit auxiliary transformer can cater to complete unit loads of that GTG / STG and station loads
connected to that particular auxiliary switchgear

Auxiliary Transformer

60. The auxiliary transformer will supply power to the 415V auxiliary switchgear as shown in Exhibit - 4. As far as possible, the
unit and station loads will be distributed equally on each 415V auxiliary switchgears so that AT will be loaded equally.
Auxiliary Transformers of rating 2.5/2/1.6MVA, 6.6kV/433V, 3-ph, 2 winding, ONAN cooled, Dyn11 transformer with
±5% off-circuit taps in steps of 2.5% will be provided. The neutral of these transformers will be solidly earthed. The HV
terminals of the transformers will be connected through SPB / Cable and LV side by NSPB / Cable

415V switchgear

61. The 415V, 3 phase, 3 wire power for the 415V auxiliaries will be obtained from 6.6/0.433kV auxiliary transformers. The
system will be a solidly earthed system. The 415V switchgear will be of metal enclosed design with a symmetrical short
circuit rating of 50kA for 1 sec

62. Each of the switchgear shall be provided with two bus sections, two incomer and a bus coupler rated for 100% of the
loads connected to the switchgear

63. All 415V switchgears will be provided with air circuit breakers (ACB) for all incomers / bus coupler / bus tie / motor feeders
if the rating is more than 110kW and moulded case circuit breakers (MCCB) for all other outgoing feeders

DC & UPS system

64. 2x100% batteries with 2x100% float cum boost chargers will be provided for the emergency loads of unit and station.
400kV switchyard DC loads will be fed from dedicated 2x100% batteries with 2x100% float cum boost chargers

65. A 230V single phase parallel redundant UPS with static bypass having two (2) sets of rectifiers and two (2) sets of
inverters connected to the emergency bus are proposed to be provided. Also, a standby regulated AC supply will be
provided as a backup to the inverters which will be switched on through static switch in case of inverter failure. For DCS,
panel mounted instruments, CRTs, printers, analysers, recorder, etc., 230V single phase A.C un- interruptible power
supply will be provided

Black Start / Emergency power supply

66. To enable safe unit shutdown / black start during complete A.C supply failure in the station, certain important plant
auxiliaries will be provided with a reliable A.C power supply through a separate source. For this purpose, two (2) 6.6 kV,
quick starting diesel generator set with automatic mains failure (AMF) feature will be provided

67. The diesel generators will feed the 6.6 kV switchgear. Suitable tie feeders will be provided to 6.6 kV switchgears.
68. When there is no voltage in the grid, it will be possible to start the unit by means of the black start diesel generators. The
SFC of the GTG will receive power from the corresponding
6.6 kV switchgear charged by BSDG for starting. After successful black start, GCB can be closed and the Generator can be
used to charge the 400kV bus through the Generator transformer. Once the unit has started generating power, 6.6 kV
breaker in Unit Switchgear is closed after synchronising BSDG with the main Generator and BSDG can be manually
stopped by the operator.

69. When the station AC supply is healthy, the emergency loads such as lube oil and seal oil pumps, turning gear motor,
battery chargers, emergency lights and essential instrument power supply feeders will be fed from corresponding service
switchgears. When the station
A.C supply fails, the BSDG sets will start automatically and will feed the emergency loads. When the normal A.C supply is
restored, these essential loads will be manually changed over to the normal power supply.

Cabling system

70. The following types of cables will be used:

For low voltage system: Power cables of 1100V grade, stranded aluminum conductor, XLPE insulated, extruded black PVC
inner sheathed, unarmored and overall FRLS extruded black PVC sheathed cables conforming IEC 60502

For control applications: 1100V grade annealed high conductivity stranded copper conductor, PVC insulated, extruded
PVC inner sheathed, unarmored and FRLS extruded black PVC outer sheathed cables conforming to IEC 60502. Conductor
cross section will generally be 1.5mm2. CT, PT and GIS control circuits will use 2.5 or 4mm2 copper conductor cables

For instrumentation applications: 300/500 V grade stranded high conductivity annealed tinned copper conductor, multicore,
PVC insulated, flexible, twisted pair / triplets, individually and overall shielded (for low level analog signals) and only
overall shielded for digital signals, PVC inner sheathed, unarmored and overall FRLS PVC sheathed cables. Conductor
cross section will be 0.5mm2
Safety earthing and lightning protection

71. A safety earthing system comprising buried steel conductor earthing grid would be provided for the Switchyard and other
outlying areas. This would be connected to the earth grids in various buildings. The buried earth grids would be further
connected to earthing electrodes. The selection of earth conductor sizes would be based on the applicable fault levels

72. Lightning protection system comprising roof conductors, vertical air termination and down- comers would be provided for
all structures whose calculated risk index requires protection as per applicable standards
Communication system

73. For effective communication in the plant, public address system, private automatic branch exchange system (EPABX),
radio paging system, walkie-talkie and P&T telephone system with the features described below will be provided:

 Public Address System: This system will have paging and party channels comprising handset stations with
amplifiers, transmitters, receivers, and loudspeakers. This system will facilitate paging, communication and also
private conversation as in conventional telephone.

 EPABX System: This system will have adequate number of push button type handset stations, central automatic
telephone exchange, etc. The handsets in the control room would be provided with priority service facility to enable
them to have immediate access to any handset even if it is already engaged.

 Landline Telephones, Broadband connectivity: Necessary number of ISDN / PSTN landlines would be provided
at strategic locations within the plant boundary. Broadband connectivity would be provided at strategic locations for
online access of data from remote station

Fire detection and alarm and fireproof sealing systems

74. A fire alarm system would be provided to facilitate visual and audible fire detection at the incipient stage of fire in the
power station. This system will comprise manual call points located at strategic locations in areas which are normally
manned and automatic fire detectors such as optical type smoke detectors / rate of rise of temperature detectors located
in plant areas such as control room, switchgear room, cable vaults, battery rooms, etc., to detect fire at an early stage.
Multi sensor detectors wherever suitable will be used. Linear heat detectors will be provided for the cable gallery. All fire
detection systems will be of analogue addressable type. A central fire alarm panel with zone indication facility will be
provided and will be located in the Main control room and repeater panels in fire station.

75. Fireproof sealing will be provided for all cable penetrations through walls and floors to prevent spreading of fire from one
area / floor to another

CONTROL AND INSTRUMENTATION SYSTEMS

76. The proposed C&I system would be used for the operation of the power plant equipment from a centralised control room.
Plant Operation & Utility package requirement Gas Turbine

77. A dedicated OEM proprietary control system would perform the normal, start-up/shutdown and emergency operations of
the GTG and its auxiliaries. It would be designed to perform turbine governing, speed, temperature and load regulation,
protection interlocks, turbine supervisory functions, monitoring and annunciation of malfunctions. The interlock and
protection system for the HRSG would operate in coordination with the operational and protective requirements of GTG,
STG and their auxiliaries.

Heat Recovery Steam Generators and Water / Steam Cycle

78. Centralized common , Power Block Distributed Control System (DCS) would perform the following
 Normal start-up, shutdown and emergency operations of the HRSG and its associated auxiliaries, feedwater and
condensate systems.
 Open and closed loop control functions including HP / IP / LP, steam temperature controls, deaerator level control, hot
well level control and operation of the major pumps such as feedwater pumps, condensate pumps would be
performed.
 Open and closed loop control functions, monitoring and protection interlocks of condenser cooling water system,
auxiliary cooling water system and any other balance of plant (BOP) equipment / system.
 Non-synchronizing breakers of the electrical system.

Steam Turbine
79. A dedicated OEM proprietary control system would perform the normal start-up/shutdown and emergency operations of
STG and its auxiliaries. It would be designed to perform turbine governing, speed, load and frequency control, automatic
start-up/ shutdown, protection interlocks, turbine supervisory functions, automatic turbine run-up system (ATRS) automatic
turbine testing (ATT), monitoring and annunciation of malfunctions.

80. The control systems of the GTG and the STG would be interfaced to the plant DCS through communication links to enable
monitoring of the GTG and STG from the plant DCS

81. Alternately if the Power Block OEM can supply unified Control Architecture which can perform GT integral controls, STG
integral controls, HRSG controls including Water / steam cycle, BOP controls and electrical system controls, the same will
be preferred.
Utility Package System

82. Systems like, DM water plant and the clarifier system, HVAC, Compressed air package, Effluent Treatment Plant will be
controlled by PLC/Microprocessor/Microcontroller based control systems located in respective plants with due integration
with Power Block DCS for monitoring.

Fuel gas System

83. The operation and control of the Fuel gas system along with the Custody transfer metering station would be performed
from the PLC based local panels with a communication link to DCS for monitoring.

Power Block Control System / DCS features

84. State of the art DCS with integral Sequence of Recording (SER) System and integral Annunciation system will be
envisaged. For the GTGs and STGs, the SER will be integral with the respective control system. All the control systems
will be interfaced to a common Master Clock.

Control System Availability


85. The system design will have enough redundancy levels to ensure safety and maximum availability of the plant. The DCS
will have redundancy in Processor, critical Input / Output modules, Communication and Power supply levels. In the event
of any control system failure, the system design will provide for safe shutdown of the plant ensuring personnel safety and
protection of the asset. Backup panel operation will be limited to safe shutdown of the plant. Redundant field sensors will
be provided for all critical control applications. Certified safety control system will be used for GTG and STG protection.
Plant Performance Analysis system duly integrated with DCS will be envisaged for improving power generation efficiency

86. Local start and stop push button operation will be provided for all motorised drives except for solenoid valves. For
motorised valves open/close functions will be available in the integral starters of the actuators

87. The unit control desk would house the following items:
- The unit, functional group / drive level control and operation of all main plant equipment would be from a set of Human
Machine Interface (HMI) stations mounted on a control desk. The unit control desk (UCD) would house the Operator
stations (HMI) with keyboards to enable the operator to perform plant control, monitoring and alarm management
functions
- The operator stations would be with twenty-seven inch (27") flat TFT - LCD based colour monitors, which would be
fully assignable and functionally interchangeable. The operator stations would be supported by laser printers. The
operator stations of the GTG control system would be fully assignable and functionally interchangeable for GTG
related functions. This also applies to the operator stations of the STG control system and plant DCS for their
respective control domains.

88. The operator would perform the following operations from the HMI stations through the keyboards:
- Operation of pumps associated with the GTG, HRSG, and water-steam cycle, balance of plant, STG and auxiliaries.
- Operation of all control valves of the GTG, HRSG, STG and auxiliaries, water steam cycle and balance of plant.
- Plant overview, group display, individual loop display, etc. and carry out associated control operations.

89. A separate HMI station with a keyboard and a laser printer would be provided for the Shift Charge Engineer. However, the
plant operations from this station would be inhibited. To enable configuring and programming, the Instrument Maintenance
Engineer would be provided with a separate station with a keyboard and a laser printer. However, the plant operations
from this HMI would be inhibited
90. A Central Control room housing the HMI equipment would be provided for the operation and monitoring of the power plant.
It would house the following equipment in an air-conditioned environment:
- Unit control Desk: The unit control desk will house the operator stations of the GTG, STG, and BOP DCS and Electrical
systems. One section of this unit control desk will house the emergency push buttons for the STG, GTG and safe
shutdown push buttons for major auxiliaries and the Electronic water level indicator of boiler drums. The printers will be
located in a suitable location of the operating room or a separate printer room.
- Shift Charge Engineer’s station and printer in the Shift-Charge Engineer's room.
- Maintenance Engineer’s station and printer in the Maintenance Engineer's room.
- Uninterruptible power supplies system (UPS) in the UPS room.

91. Electronic cubicle rooms: The DCS cabinets will be mounted in electronic cubicle rooms. Also, remote I/Os will be located
near the various switchgear rooms / cubicles to acquire signals related to the switchgear. These cabinets will be powered
from the centralised UPS located in the central control room. The GTG control system cabinets will be mounted in
respective cubicles located near the equipment and STG control system cabinets will be mounted in the electronic cubical
rooms along with the DCS cabinets
92. The SER will be integral to DCS with adequate capacity of points for recording the cause of plant trip with a resolution of
one millisecond. The system would be provided with a dedicated printer located in the control room. For the GTG and
STG, the SER will be integral with the respective control system

93. Adequate number of analytical instruments would be provided for continuous monitoring of quality of demineralised
water, condensate, feed water and steam. Also, gas analysers for measurement of SO2, NOx, and opacity in the flue gas
as required to meet the Pollution Control Board's requirements would be provided. The opacity shall be measured by in-
site analysers and the other parameters shall be measured using a continuous emission monitoring system. The analysers
of the water and steam system and gas analysers would be located in respective air-conditioned rooms. These rooms will
also house the relevant sample handling and conditioning equipment.

94. A vibration monitoring system complete with transducers and remote monitors is envisaged for monitoring the bearing
vibrations of GTG, STG, HT drives like high pressure boiler feed pumps, condensate extraction pumps and condenser
cooling water pumps. The bearing vibrations would be measured and monitored in both X and Y directions for each
bearing

95. All final control elements of regulating type (control valves) will have actuators of pneumatic / hydraulic type. The control
valve design shall be suitable for the required fail- safe conditions of process / equipment. Pneumatic actuators would be
provided with air failure lock and remote release, limit switches, adjustable minimum and maximum stops, local position
indicators, positioner, electronic position transmitters and solenoid valves in accordance with the system requirement.
Control valves will be provided with smart positioner

96. Field transmitters, switches and temperature elements with adequate redundancy will be provided to meet the
interlock/control requirements of the power plant. Minimum number of local instruments/indicators would be provided to
enable local operators to supervise and monitor equipment / process operation. All transmitters for measurement and
control would be of electronic SMART type two-wire system with 4-20 mA DC output. All the thermocouples and RTDs
would be duplex type.

97. For Control systems, LED monitors, printers, analyzers etc., 230 V single phase AC uninterruptible power supply will be
made available for the power plant. Any other voltages required including control system supply of +/-24 VDC would be
derived from the 230 V AC UPS.

Cables

98. Instrumentation Cables: Individual / pair shielded, and overall shielded twisted pair copper cables would be used for
analog signals and overall shielded cables would be used for digital signals. All these cables shall be of 300 V AC / 500 V
grade and are unarmored. All
the insulation including overall sheath would be PVC FRLS quality. The size of the conductor would be 0.5 Sq.mm.

99. The interconnecting cables between any two cabinets and between cabinets and panels would be of prefabricated type.

100. The Special C and I cables are as follows:


- The interconnecting bus of the PLC based system would be as per manufacturer's standard.
- The communication bus of the PLC based system would be as per manufacturer's standard.
- Any other special cables would be included in the respective vendor's scope.

Instrumentation Pipes / Tubes and Fittings

101. Proposed C and I pipes, and tubes and fittings are as follows:
- For remotely located instruments like transmitters, tubes and fittings of appropriate material and rating would be used.
Junction boxes would be provided for termination of all field switches like pressure, temperature and for the
transmitters.
- All instruments fittings shall be double ferrule type and three-piece design with material of construction SS 316 or
better.

General Tools and Tackles, Special Calibration Instruments

102. All type of general tools & tackles and special calibration instruments required during start- up, trial run, operation and
maintenance of the plant shall be provided.

Earthing

103. Separate electronic earthing system with dedicated earthing pits for control systems would be envisaged.

CIVIL

Sub surface conditions and Geo-Technical Investigation

104. Based on the visual inspection and the data gathered during the site visit it is considered that all structures could be
supported on piling foundations. However, the type of foundation and founding levels would be decided after taking into
consideration the data that would be available from geotechnical investigations to be carried out at site during detailed
engineering stage
Topographical and site grading

105. The terrain of the proposed plant site is generally flat and requires minimum grading. However, the final grading level of
the plant site would be established after detailed surveying of the area is carried out

Gas Turbine and Steam Turbine Building

106. The main powerhouse building houses Gas turbine and steam turbine. The building will be of structural steel framing with
steel truss. The building will have intermediate floors and operating floor. The operating floor will be of RC floor over steel
framing constructed over pre coated galvanised MS troughed metal sheet. The floor at any other intermediate level will be
of hot dipped galvanised gratings supported on structural steel framework. Roofing shall be of in-situ RC slab constructed
over pre coated galvanised MS troughed metal deck sheets supported on steel purlins and trusses. Roof will be provided
with water proofing. Building will have a crane girder at suitable elevation to support the cranes. Side cladding will be of
brick wall/ concrete block wall up to a height of 3.0m above finished ground floor level. Cladding above 3.0m level will be
of pre coated sandwiched insulated metal sheet. The ground floor will have granolithic floor finish with non-metallic floor
hardener suitable for heavy duty loading. Operating floor will be provided with epoxy coating

107. The foundation for Gas Turbine, Steam Turbine Generator and other equipment’s will be of conventional framed type or
block type concrete foundation. The equipment foundations are isolated from the building foundations

Heat recovery steam generator area

108. Entire HRSG area from the Gas Turbine building up to the end of stack will be provided with concrete paving with
necessary drains. The drains will be of RC construction and covered with concrete cover or MS galvanised grills. The
storm water and the process leakage water in the entire area will be lead to the plant drainage system through a network
of drains. Pipes and cables in this area will be routed on overhead pipe and cable racks.

Control room

109. The electrical and control room building is an RC building consisting of brick wall for side cladding. The building houses
cable duct, cable distribution, battery room, switch gears, office space for staffs, main control room, computer room and
electronic cubicle room etc.,

Raw water system

110. The water required for the proposed power plant is drawn from common sea water intake system of the proposed 660 MW
coal-based power plant.

CW Make-up Water System


111. The plant is provided with a circulating cooling water system with Induced Draft Cooling Tower. The source for CW make-
up is from common sea water intake system of the proposed 660 MW coal-based power plant. The required make-up
water for condenser cooling will be conveyed to the forebay of CW Pump House.

Stack

112. The outlet Stack from the HRSG will be of steel stack

Roads Drains and Sewage Disposal

113. The main roads within the power plant area will be 7.0m wide. All other minor roads will be 4.0m wide. All major roads will
have 1.5m wide shoulder on either side of the road. Initially water bound macadam road will be constructed and the
surface will be provided with bituminous carpet after all the major construction activities are completed

114. The plant will be provided with network of concrete lined surface drains and catch pits. This water will be ultimately led to
the nearest water body. Water containing oil would be passed through oil separator unit before leading into surface drains

115. Sewage from various area will be collected in intermediate collection pits and will be transferred to the packaged sewage
treatment plant either through mechanical pumping or through gravity flow. The treated water shall be collected in the
storm water reservoir for use in gardening. Rejects from sewage treatment plant (semi-solid and solid wastes) will be
disposed suitably

Fencing

116. The fencing will be provided around fuel gas conditioning skid and the proposed plant. The height of fencing will be 3.0m
above the toe wall

Landscaping

117. The various services and utility areas within the plant will be suitably graded to different elevations. Natural features of the
plant site will be retained as far as possible to integrate with the buildings to form a harmonious and pleasant environment.
The entrance of Power Plant will be landscaped with ground cover, plants, trees based on factors like climate, adaptability,
etc. A green belt will be provided along the plant boundary of the site. The green belt will consist of native perennial green
and fast-growing trees.
Materials

118. Cement: Ordinary Portland Cement (OPC) of minimum 43 grade conforming to IS: 8112, Portland slag cement conforming
to IS: 455 and Portland Pozzolana cement conforming to IS: 1489 will be used for all concrete and other works

119. Reinforcement steel: Reinforcement steel confirming to IS: 1786 for high yield strength bars and IS: 432 for MS bars will
be used

120. Structural steel: Structural steel will conform to Grade – A of IS: 2062 for rolled sections and plates up to 20mm thickness.
For plates above 20 mm thickness, steel conforming to Grade – B of IS: 2062 will be used except for crane girder where
steel conforming to Grade
– C of IS: 2062 will be used

121. All other construction materials like sand, aggregates, bricks etc., shall conform to the relevant IS codes

122. All structures will be designed for the most critical combinations of dead loads, live loads, wind loads and seismic loads
and other forces which can occur during the design life of the facility. All designs will be carried out in SI units and will be
as per relevant IS standards

Dead Load

123. The dead load comprises the actual weight of walls, partitions, floors and roofs of structures etc., which are permanent
attachment to buildings. Unit weights of common building materials will be taken from IS: 875 (Part-I).

Live load

124. The live loads will be considered as occurring over areas not occupied by major equipment. Weight of equipment and
forces acting on its supports will be taken from vendor’s drawing and the supporting structures will be designed for such
forces. Unless reliable loading data is available live loads will be taken as per IS: 875 (Part-II)
Wind loads

125. The basic wind speed of 50 m/s will be considered as per IS: 875 (Part-III). The wind will be assumed to blow in any
direction and most unfavorable condition will be considered for design.
Seismic loads

126. The power plant is in seismic Zone – III as per IS: 1893 and seismic forces will be considered accordingly. The importance
factor for all power plant buildings/structures will be taken as 1.75
CHAPTER – VII

VII. ENVIRONMENTAL ASPECTS

1. The environmental impact of the proposed combined heat and power plant, covering the following aspects is presented
in this chapter:
- Site features
- Air pollution
- Water pollution
- Thermal pollution
- Noise abatement
- Pollution monitoring and surveillance systems

Site feature

2. The site proposed for the installation of the combined cycle power plant is located at Ennore, near Chennai City, Tamil
Nadu. The Site is mainly located near industrial area and coal- based power plants. Within the vicinity plant, there are no
any national parks, wildlife sanctuaries, tropical forests and biosphere reserves.

Air Pollution

3. The expected air pollutants from a combined heat and power plant are:
- Nitrogen oxides in flue gas
- Sulfur dioxide in flue gas

4. RLNG, which is the main fuel proposed in the gas turbines is a clean fuel without any constituent to generate the
particulate matter in flue gas. Hence, there would be no particulate matter in the flue gas of the combined heat and power
plant.

5. In case of NG firing there would not be any emission of Sulphur dioxide, as the NG does not have any Sulphur content.
The only pollutant in the flue gas would be oxides of nitrogen (NOx). Typical values of NOx in the flue gas would be less
than 51 ppm (15% oxygen volume dry basis) and this would be achieved using low NOx dry type hybrid burners in the gas
turbines. The values of NOx would be about 25 ppm, but for guarantee purposes a value less than 51 ppm would be
considered as stipulated by World Bank norms.

Table VII-1: Emission guidelines as per World Bank


Combustion Technology Nitrogen Dioxide Dry Gas, Excess O2, Content (%)
Gas Turbine 51 ppm 15 %
6. Online monitors would be used to constantly monitor oxides of nitrogen in the flue gas and
in case of excess amount of any pollutant, suitable corrective action would be taken. In
view of the above-mentioned provisions, the installation of the combined cycle power plant
would not have any significant impact on the ambient air quality.

7. The height of stack shall be selected to meet the ambient air concentration limits as
stipulated in the Table- VII.1 above.

Water pollution

8. The sources of effluents from the proposed power plant are the following:
- RO reject water
- Water Treatment Plant
- Blow down of Cooling Tower and side stream filtration
- Plant Area Drains
- Plant Oily water drains
- GT compressor wash water

Plant Area Drains

9. The plant drains water from main plant area and such other areas will be led to existing
effluent treatment pond. The oil contained drain shall be treated in Oil water separators
and transferred to the common effluent pond. Treated water from outlet of oil water
separator shall be collected in common effluent pond. Waste oil separated & sludge is
collected in sludge oil sump and disposed outside.

Noise Abatement

10. Gas turbine would be provided with enclosure to ensure noise level within code
guidelines. Gas engines would be provided with silencers in both intake air and exhaust
gas systems to reduce the noise level.

11. The Environmental (Protection) Rules, stipulate the ambient air quality standards in
respect of noise for industrial area as follows:
- Day time - 75 dB (A)
- Nighttime - 70 dB (A)

12. The far field noise level from the gas turbine / gas engine at the plant boundary will be
within the limits stipulated.
Gaseous Fuel Vents and Liquid Condensate

13. All the gas lines and gas conditioning skid vent connections would be terminated at
a safe height of about 3m above the operating platform level. The vent lines would be
terminated with flame arrestors. The condensate removed from the fuel gas in the
scrubber would be collected in a collection tank and disposed suitably.

Pollution Monitoring and Surveillance System

14. A well-defined environmental monitoring programme would be instituted with trained and
qualified staff that would monitor the ambient air as well as stack gas quality to ensure that
the quality of effluents is maintained within the permissible levels. The stack would be
provided with suitable ports to monitor the exhaust gas quality from the stacks. Suitable
analysers will be provided for exhaust gas quality analysis. The quality of water effluents
from the plant would be analysed on daily basis or as required to ensure that effluents are
maintained within the permissible levels.

Impact of Pollution / Environmental Disturbances

15. The proposed combined heat and power would require less land area compared to similar
capacity fossil fuel fired cogeneration plants and would use a clean gaseous fuel. NOx,
SOx emissions would be minimum. The water effluents would be treated in the existing
effluent treatment plant and reused. Hence, it is considered that there would be no
adverse impact on either the air or the water quality in and around the proposed combined
heat and power plant.

List of Permits/Clearances

16. Table VII-2 provides the list of permits, clearance and the licenses that needs to be
obtained for the project and its responsible person.

Table VII-2: List of Permits, Clearances and Licenses & the responsibility matrix
SL. NO CLEARANCES AUTHORITY RESPONSIBILITY
1.0 STATUTORY CLEARANCES
1.1 Pollution clearance, water State Pollution Control Owner
and air Department
1.2 Environmental clearance Ministry of Environment & Owner
Forest
1.3 Aviation Airport Authority of India Owner
Clearance/No Objection
for
Tallest
Structure
SL. NO CLEARANCES AUTHORITY
1.4 Consent for Operation of the State Government
Plant Authorities
1.5 No Objection Certificate for State Government
setting up the facility Authorities
2.0 NON-STATUTORY CLEARANCES
2.1 Land availability at Plant Government/Private Land
area
2.3 Transportation of FuelDepartment of Petroleum and
(Secondary Fuel) Natural Gas, Ministry of Railways,
Shipping and
Surface Transport
2.4 Real Estate, Rights & right to access State Government
and use of Site, including Right of Authorities
Way for all
corridors to the Facility
3.0 OTHER CLEARANCES/ APPROVALS
3.1 Approval as per Explosives Act and Chief Controller of
Rules Explosives
3.2 Approval and Registration of HRSG Chief Inspectorate of Boilers
as per Indian Boiler
Regulation
3.3 Approval as per Indian State Electrical
Electricity Act and Rules for Electrical Inspectorate
Installation
3.4 Approval as per Indian Petroleum Act Chief Controller of
and Petroleum Rules for storage and Explosives
transport of Petroleum
Products

3.5 Approval as per gas cylinder rules Chief Controller of


and handling and transport of Explosives
compressed
gases
3.6 Approval of weigh bridge Inspector of Weights and
and weigh scales Measures
3.7 (a) Collection, storage and State Pollution Control Board
disposal of
waste
SL. NO CLEARANCES AUTHORITY RESP
ONSIBI
LITY
(b) Site clearances, safe State Pollution Control Contra
report and safety Board ctor
audit
3.8 Approval of Fire Protection Authorized Agencies Contra
Scheme approved by Insurance ctor
3.9 Confirmation of Collector / Directorate of Town and Planning Owner
Directorate of Town and Planning
for the use of the site for the
construction and operation of the
Power
Station and Fuel Facility
3.10 Consent for the Directorate of Town and Planning Owner
development of Project Site – State
and the Township site Government Authorities
3.11 Approval of Chief Inspector of Chief Inspector of Contra
Factories of the proposed design Factories ctor
and construction of power station
and fuel
facility
3.12 Allocation / approval of State Electricity Board Owner
electric supply for bulk
construction power
3.13 Carriage entrance to Municipal Corporation/Assistant Contra
property Engineer Building or ctor
concerned authorities.

3.14 Approval of building Municipal Corporation Contra


proposals and layout ctor
3.15 Approval of building layout with fire Municipal Corporation Chief Fire Contra
safety concerns and receipt of No Office or concerned authorities ctor
Objection
Certificate
3.16 Approval of reinforced cement and Municipal Corporation/Assistant Contra
concrete design calculation (RCC) Engineer Building or ctor
concerned authorities

3.17 No Objection Certificate State Pollution Control Contra


regarding air & fugitive Board ctor
emissions
SL. NO CLEARANCES AUTHORITY RESPONSIBILITY
3.18 No objection Certificate for Relevant State Authorities Contractor
Chimney and Registration
3.19 No Objection Certificate for Municipal Contractor
sewage water treatment and Corporation/Assistant
associated plumbing Engineer Sewage
and Planning
or
concerned
authorities
3.20 No Objection Certificate for Municipal Contractor
Storm Water Drainage Corporation/Assistant
Design Engineer Storm
Water
Drainage or
concerned
authorities
3.21 To review the frequency Telecommunication Owner
used for Power Line Carrier Department
Communication (PLCC)
system to ensure no
interference with other
power line users
3.22 No objection certificate for State Government Chief Contractor
plant layout with regard to Electrical Engineer
electrical

equipment,
operational safety
3.23 No Objection Certificate for Municipal Corporation Contractor
storage of construction
Materials and chemicals,
etc.
3.24 No Objection Certificate for Chief Commissioner Contractor
storage of construction fuel of Police
oils and chemicals, etc.
3.25 No Objection Certificate for Chief Controller of Contractor
storage of Distillate Oil Explosives
3.26 No Objection Certificate for Municipal Corporation Contractor
road opening and asphalting
Work including traffic Work.
3.27 Local approval for operating Municipal Corporation Owner
the plant
3.28 Local approval Municipal Corporation Owner
of Architectural
plans
for
township
SL. NO CLEARANCES AUTHORITY RESPONSIBILITY
3.29 Local approval of other Municipal Corporation Contractor
Architectural plans
3.30 Commencement Certificate Municipal Corporation Contractor
up to Plinth
3.31 Commencement Certificate Municipal Corporation Contractor
up to Full Height
3.32 Consent of the Controller of Chief Controller Contractor
Explosives to the of Explosives
possession and use of
explosives for the purpose
of
blasting
3.33 Consent under the FactoriesDirectorate of Town and Contractor
Act, relating to firefighting
Planning of
capacities State
Government.
3.34 Clearance of Lifts Inspector Lifts of Relevant Contractor
Sate Government
3.35 Approvals / clearances for Concerned Authorities Contractor
labour / manpower like
License from labour
commissioner

for
Construction

labour, Registration of
Workers or exemption to be
claimed if group insurance
taken for
some, etc.
3.36 Any other Appropriate Authorities Contractor
clearances
relevant to the
Project
Execution
3.37 Export Authorisation Appropriate Authorities of Contractor
(Export license) exporting country
CHAPTER –VIII

VIII. PROJECT EXECUTION

1. The success factor of any project is directly related to adoption of an appropriate project
delivery method. Various methods available for the execution of the project are as follows;

 Public Private Partnership (PPP)


 Independent Power Producer (IPP)
 Engineering Procurement and Construction (EPC)

Public Private Partnership (PPP)

2. The idea of cooperation between public entity and private organisation in order to meet the
growing needs of society and country has been developing through centuries. The
experience gained in the area of PPP clearly indicates that the main reasons for
partnerships are risk sharing and the ability of the private sector to deliver, finance,
maintain, and operate a project at lower costs than the public sector. A public–private
partnership (PPP) is a government service or private business venture which is funded
and operated through a partnership of government and one or more private sector
companies. These schemes are sometimes referred to as PPP or P3. PPP involves a
contract between a public sector authority and a private party, in which the private party
provides a public service or project and assumes substantial financial, technical and
operational risk in the project. In some types of PPP, the cost of using the service is borne
exclusively by the users of the service and not by the taxpayer. In other types (notably the
private finance initiative), capital investment is made by the private sector on the basis of a
contract with government to provide agreed services and the cost of providing the service
is borne wholly or in part by the government. Government contributions to a PPP may also
be in kind (notably the transfer of existing assets). In some other cases, the government
may support the project by providing revenue subsidies, including tax breaks or by
removing guaranteed annual revenues for a fixed time period.

3. There are various PPP models available for the execution and the major ones are as
below;

 Build Operate and Transfer ( BOT): The private-sector partner finances, builds, owns
and operates the power plant in perpetuity. The public-sector partner's constraints are
stated in the original agreement and through on-going regulatory authority.
 Build-Own-Operate-Transfer (BOOT): The private-sector partner is granted
authorization to finance, design, build and operate the power plant (and to charge
user fees) for a specific period of time, after which ownership is transferred back to
the public-sector.

4. Objectives of PPP model is to make sure government services are delivered in the most
economical, effective and efficient manner, to increase overall economic growth by
creatingopportunities for private sector and appropriate allocation of risk and
returns between public and private sector.

5. Major features of the PPP are as follows;


 The land is provided by the Owner on which the Project is set up by the Private
developer
 The Project would be financed and executed by the Private developer.
 The Owner will enter into a PPA agreement with the developer for purchasing the
power generated at the agreed rates with provision for escalation and fixing the yearly
take off.
 The risk in this mode would be the availability of the Gas to operate the plant.
Availability of the fuel for the contracted period is a risk which the developer has to
take.
 In the event the agreed power is not taken, then the developer will have to be
compensated for the shortfall in the revenue which would be again a burden to the
Owner.
 In the present scenario, there is high doubt about any developer coming forward to
set up the plant and operate considering the prevailing market conditions and gas
availability for a long term.
 Under the present scenario, there is sufficient power available in the grid which can
be sourced through the energy exchange portal and this would be more economical.

Independent Power Producer (IPP)

6. An Independent Power Producer (IPP) is a result of privatization and economy


liberalization in infrastructure in various parts of the world. IPPs have taken various forms
as the electricity markets evolved in various countries and regions. The evolutions are
closely related to dynamics of structural/regulatory, economic/financial, technological, and
environmental conditions.

7. An IPP is a power-generating entity that typically sells the power it generates under a
power purchase agreement (PPA) with the incumbent utility, or large customers. It is
common to see the PPA take the form of build own operate transfer (BOOT), which
permits an investor to “build,” “own,” and “operate” the generation facilities and then
“transfer” them to the host purchaser upon the termination of the contract. In fully
restructured markets, IPPs may also operate on a purely commercial basis in which
generators can offer their production in the Spot Markets.

8. Major features of the IPP are as follows;


 The demand for the electricity to be produced at a competitive price while earning
acceptable returns is of paramount importance for an IPP to invest in the project
 This is similar to the PPP with only difference is that the land to be arranged by the
Developer including the availability of the fuel for operation of the Plant.
 The developer may have an option to deliver the excess power to other users by
entering a PPA.
 In the present scenario, there is high doubt about any developer coming forward to
set up the plant and operate considering the prevailing market conditions.
 Availability of the fuel for the contracted period is a risk which the developer has to take.

Engineering Procurement and Construction (EPC)

9. Engineering, procurement and construction (EPC) contracts are the contracts used
primarily in complex industrial and infrastructure projects like power plants, bridges, dams
etc. EPC contracts involve a deal between the owner and a contractor, who is required to
deliver certain design, construction, logistics, transport etc. related work to the Project
financer. As it transfers the liability to the contractor and mitigates risks of the project, it is
favourable for the Project financer.

10. Single package or multiple package procurement philosophy are available in EPC.

11. Major features of the EPC are as follows;


 Single responsibility of the Contractor executing the job
 The complete Risk with regard to the Construction and Commissioning is with the
Contractor
 Owner would be able to monitor the progress effectively with the Contractor
 This is suited when Owner does not have the requisite skilled persons to monitor the
Project
 Project can be completed within the agreed schedule.
 On successful commissioning the Plant will be handed over to the Owner ,who would
do the O&M, or may appoint an O&M operator to operate the Plant.
 Owner to enter into an LTSA with the OEM for the maintenance of the Turbines.

12. The EPC contract plays vital role in power project development. Due to investment of
private partners in PPP/IPP, risk is more to private sector, mainly to the lenders or
financers which goes into bad loans and delay in project completion. Because of these risk
factors nowadays there is low interest from the investors in PPP / IPP.

13. To revive PPP (Public Private Partnership) in highway construction, Government of India
has introduced Hybrid Annuity Model (HAM). The HAM is a mix of PPP (BOOT) and EPC
model. In this model the Government will contribute up to 40% of the project cost through
five equal payments (annuity), whereas the 60% of the project cost will be raised by the
developer from loan or equity. Advantage of HAM is that it gives enough liquidity to the
developer and the financial risk is shared by the government. While the private partner
continues to bear the construction and maintenance risks as in the case of BOOT model,
he is required only to partly bear the financing risk. This model can be explored for the
power project also.

14. Based on the above discussion it is recommended to execute the proposed project
through EPC contract, the Contractor would be responsible for detailed engineering,
procurement, project management, construction, testing, commissioning up to satisfactory
performance test and handing over the project.
15. The preliminary market analysis indicates that the schedule completion of the proposed
project would be about 34 months from the Notice to proceed (refer Exhibit-5). The
schedule has been arrived based on the following:
 Zero date for the project has been considered as the date of placement of order
for Engineering Procurement and Construction (EPC) contract.
 It has been assumed that the clearances by different agencies of the
government would be obtained prior to placement of order for EPC contract

16. Exhibit-5 provides the preliminary project milestone chart for the project.

Operation and Maintenance of Advance class gas turbines

17. The two most important factors for the advanced class gas turbine are availability and
maintenance cost. Gas turbines and particularly their hot gas path components exhibit
relatively high maintenance cost and short in-service inspection cycles, in comparison with
most main components of the power plant.

18. Operating the advanced class gas turbines is becoming significantly expensive due to
associated risk in new technology, high cost of spares, uncertainty and increase in fuel
price. However, the advanced class machines provide higher efficiency and longer life of
parts. Spare parts management plays an important role in achieving the desired plant
availability at an optimum cost.

19. There are a number of ways to mitigate the involed risk in operation and maintenance of
these gas turbines like the traditional approach of performing the operation and
maintenance by the owner, letting the operation and maintenance to the O&M contractor
and the fixed price maintenance contract.

Transactional Piecemeal Order

20. Transactional Piecemeal order is the traditional way of performing the maintenance of the
power plant. The required spare parts would be procured on as and when required basis.
This would require a dedicated and skillfull operation and maintenance team, and
procurement team.

21. The major disadvantage is that it does not provide the Owner, a predictable fixed long
term maintenance cost and does not cover any gurantees. The overall risk lies with the
owner.

Long Term Service Agreement (LTSA)

22. Long Term Service Agreement (LTSA) otherwise means maintenance agreements,
contractual service agreements, and perhaps most commonly, long term service
maintenance agreement is an agreement between the Customer and the third party. The
Third party could be Original Equipment Manufacturer (OEM) / Non OEM who would
undertake the responsibility for maintenance and repairs of the facility, for an agreed fee.
23. By transfering agreed risk to the contractor, LTSA offer the owner a mechanism for
controlling maintenance cost and maximizing the reliability while minimizing the need for
internal resources to manage and perform maintenance.

24. LTSA typically cover replacement of parts, repair of parts and services for a planned gas
turbine maintenance and inspection activities over a set period of time or a set number of
major outages. LTSA typically commit the contractor for providing on a relatively “fixed-
price” basis, maintenance services for the equipment and with predictable cashflow. LTSA
also includes diagnostic and technical support on unplanned maintenance work.

25. While LTSA offers many advantages, caution has to be exercised in drafting the contract
to mitigate the risk. Some of the major aspects to be considered while drafting LTSA are
as follows;
 Inappropriate allocation of prolonged start-up risk: The pricing of LTSA is based on
number of factored fired hours, number of starts or combination of both. This basis
often fails to distinguish the hours or starts occurring before commercial operation
date (COD). As a result, these could be charged to the Owner under LTSA, even
though they are attributable to the OEM. This could be mitigated while entering into a
Contract.
 Performance Guarantee: Standard LTSA includes only the guarantees for
improvement in performance degradation and does not include the response time and
the delay in the outage.
 Defining the schedule maintenance: LTSA should clearly define the contractor’s
scope of work, list of equipment / components involved for the schedule maintenance
to avoid any disputes.
 Defining the Extra Work: Most LTSA includes Extra Work, and the owner can request
contractor to perform other services that are normally not included in the contract.
Care should be taken to ensure that the Extra Work/ other services as per owner’s
request is not a part of maintenance work already required to be performed by
contractor under LTSA.
 Term of LTSA: Often, the term of LTSA will expire upon the conclusion of an agreed
scheduled maintenance cycle. This would result in a risk if the operational profile of
the equipment changes during the term of LTSA. Hence, to mitigate this risk suitable
sunset clause need to be incorporated in the contract.
 Extended End-of-Term parts life warranty: Care should be taken to ensure that the
contractor provides warranty for the last installed parts until the next scheduled
maintenance.

26. LTSA can be incorporated along with the EPC specification during the detailed
engineering stage.
CHAPTER –IX

IX. PROJECT COST ESTIMATION AND TARIFF CALCULATION

Basis of Project Cost Estimate

1. The project cost estimate has been worked out based on prevailing prices and rates as on
September 2020. The cost have been worked out based on the American Association for
Cost Estimation – Maturity level of Class 4. Class 4 estimates are generally prepared
based on limited information and subsequently have fairly wide accuracy ranges. They are
typically used for project screening, determination of feasibility, concept evaluation, and
preliminary budget approval. Typical accuracy ranges for Class 4 estimates are -15% to -
30% on the low side, and +20% to +50% on the high side, depending on the technological
complexity of the project, appropriate reference information, and other risks (after
inclusion of an appropriate contingency determination). Ranges could exceed those
shown if there are unusual risks.

2. The Project is considered to be executed through limited equipment / system packages.


The total project cost estimate includes equipment / systems such as gas turbine
generators and auxiliaries, heat recover steam generators and auxiliaries, steam turbine
generator and auxiliaries, fuel gas system, water systems, control and instrumentation
system, electrical system and balance of plant required for the power plant, spares,
erection and commissioning charges, taxes and duties, insurance, overheads and pre-
operative expenses.

Cost of Land

3. The land for the proposed for the combined cycle power plant is Ennore thermal power
station complex and it is with TANGEDCO. Hence cost for the land acquisition and R&R is
not included in this project cost estimate.

Basis of Capital Cost Estimate

4. The cost of heavy-duty gas turbine generators, heat recovery steam generators and
steam turbine generators and other auxiliary systems are based on in-house cost
database for similar range of CCPP plants. The cost includes design, supply, erection,
testing & commissioning of the systems.

5. The cost of dismantling of any existing structures and underground facilities are not
envisaged in the estimate.

6. The civil & structural cost is estimated based on prevailing steel, cement & rebar cost in
the market. The Piling foundation is considered for the purpose of project cost estimate.
The main stack and bypass stack shall be of steel construction.

7. The estimation covers cost towards tapping off sea water from the proposed intake for
upcoming 660 MW coal-based power plant, fuel gas pipeline near to the boundary and,
plant switchyard. However, it does not include the cost for transmission network and any
other outside plant facilities.
8. The cost for establishment / extension of colony for power plant O&M staffs are not
included in the estimate.

9. The cost of spares has been estimated as 2.5% of the supply cost for mechanical, C&I
and electrical items.

10. The taxes & duties for supply and services are considered as per GST structure for
indigenous items and as per custom duty for offshore items.

Natural Gas Pricing and Basis of Tariff Calculation

11. TANGEDCO is planning to obtain the RLNG from IOCL, Ennore terminal through a long-
term contract. The prevailing price of IOCL (May 2020) is as follows;

- FE Component = 5.4973 USD/MMBTU


- INR Component = 106.91 Rs/MMBTU
Considering the above for the estimation purpose, the fuel cost is considered as
$7/MMBTU. However, the actual gas price shall be fixed as per gas supply agreement
between GAIL/IOCL & TANGEDCO. Further the fuel cost is considered as fixed cost and
no escalation is considered.

12. The following details are considered for computing interest during construction (IDC) and
estimation of cost of generation.

Table IX-1: Assumptions for Cost Estimation


Sl. No. Particulars Value
1 Installed capacity, kW 794,570
2 Minimum Emission Load, kW 407,357
3 Operation hours @ 100% MCR 12 hours
4 Operation hours @ MEL 12 hours
5 Heat rate @ 100% MCR 1386 kcal/kWh
6 Heat rate @ MEL 1468 kcal/kWh
7 Weighted average station heat rate 1498 kcal/kWh
as per CERC
8 Debt /Equity ratio 70: 30
9 Interest rate for project loan 12% on loan amount
10 Rate of return on equity 15.5%
11 Working capital interest rate 11.5%
12 Depreciation 5.28% for 12 years Balance value for
remaining 13 years with salvage of 10%
Sl. No. Particulars Value
13 Average Availability Factor 97.6%
14 Plant Load Factor (Average for 25 74%
years) – Arrived based on the
generation & the availability factor
15 Discount Rate 9.35%
16 Exchange rate Rs 75.5 / US$
Rs. 86.85 / Euro

Capital Cost Estimate

13. The general break-down of preliminary project cost is furnished in Appendix-3.

14. The preliminary project cost works out to Rs.4279.51 Crore including interest during
construction, financing charges and considering taxes and duties. Cost per MW of
installed capacity works out to Rs 5.35 Crore.

15. The preliminary project cost for the choose option is illustrated in Table IX-2

Table IX-2: Capex Breakdown


Sl. Cost
No. Break Down (Rs. Crore) Remarks
1.0. Cost of Land & Site Development
1.1 Land 0 Not applicable
1.2 Rehabilitation & Resettlement (R&R) Not applicable
Preliminary Investigation and Site
1.3 Development 0
Total Land & Site Development 0

2.0. Plant & Equipment


Quote from Market Source
(includes delivery to site @
2.1 Gas Turbine Generator Island 2225.79
7.5% Freight & clearance
Charges)
2.2 Steam Turbine Generator Island Included in item 2.1
2.3 HRSG Island Included in item 2.1
2.4 BOP Mechanical
2.4.1 Fuel handling and storage system 5
2.4.2 External water supply system Not applicable
2.4.3 CW system 65
2.4.4 Cooling towers Included in item 2.4.3
2.4.5 Clarification plant Included in item 2.4.3
2.4.6 Chlorination Plant Included in item 2.4.3
Air Conditioning and Ventilation
2.4.7 System 5
Sl. Cost
Break Down Remarks
No. (Rs. Crore)
2.4.8 Fire Fighting System Included in item 2.4.3
2.4.9 Hydrogen generation system 3
2.4.10 HP/LP piping 10
Total BOP Mechanical 88.00

2.4 BOP Electrical


2.4.1 Switch Yard Package 38.5
Main Transformers included
2.4.2 Transformers Package 10 in 2.1
Main plant Switchgear
2.4.3 Switch Gear Package 8 included in 2.2
2.4.4 Cables, Cable Facilities & Grounding 5 Main plant included in 2.3
2.4.5 Lighting 3
2.4.6 Black start DG Set 30
Total BOP Electrical 95

GT, ST Control systems &


2.5 C&I Package 5 DCS included in 2.1

Total Plant and Equipment


excluding Taxes and Duties 2413.45

2.6 Taxes and Duties


Freight & Insurance on imported item
2.6.1 @ 10% 222.58 For item 2.1
Taxes & Duties (GST - 18% & for GT:
2.6.2 Customs Duty - 5%) 366.74
Total Taxes & Duties 589.32

Total Plant and Equipment


including Taxes and Duties 3002.77

Initial Spares (2.5% of Total Plant &


3.0. Equip. incl. Taxes & Duties) 75.07

4.0. Civil Works


Considered 8% of the Total
Total Civil Works 240.22
plant cost

Construction & Pre-Commissioning


5.0. Expenses
Erection Testing and Commissioning
(1% of Total Plant & Equip.excluding
5.1 Taxes & Duties) 20.70
5.2 Site Supervision 5
5.3 Operator's Training 0.5
Sl. Cost
Break Down Remarks
No. (Rs. Crore)
Construction Insurance / Project
5.4 Insurance 333.88
5.5 Tools and Plants Included in 5.1
5.6 Start-up fuel Included in 5.1
Total Construction and Pre-
commissioning Expenses 360.07

6.0. Overheads
6.1 Establishment 0.65
6.2 Design & Engineering 145.23
6.3 Audit and Accounts
6.4 Contingency @ 5% 114.72
Total Overheads 260.60

7.0. Capital Cost Excluding IDC & FC 3938.74

8.0. IDC, FC, FERV & Hedging Cost

8.1 Interest During Construction (IDC) 313.20


8.2 Financing Charges (FC) 27.57
Total of IDC, FC, FERV & Hedging
Cost 340.77

Capital Cost Including IDC, FC,


9.0. FERV & Hedging Cost 4279.51

Phasing of Expenditure

16. The phasing of expenditure including IDC and financing of the proposed units is expected
to be incurred as shown below in Table-IX-3.

Table IX-3:Phasing of Expenditure


Initial Phasing
Period
Amount, %
0 Month 10.00%
th
4 Month 5.00%
8th Month 20.00%
12th Month 20.00%
16th Month 15.00%
20th Month 10.00%
24th Month 10.00%
28th Month 5.00%
Initial Phasing
Period
Amount, %
32nd Month 5.00%
Note: Considering the project schedule is 34 months

Cost of Generation

17. The two-part tariff model has been adopted to calculate the cost of generation. As per this
model the tariff for energy is sum of two components, a fixed charge component and a
variable charge component as discussed below.

18. Fixed Charges

The items of cost forming a part of the fixed charge components are:

- Interest on term loan


- Return on equity
- Interest on working capital
- Depreciation
- Operation and Maintenance

The fixed cost based on discount rate of 9.35 % for 25 years of the proposed cogeneration
plant at station bus bar after allowing for auxiliary power consumption and fuel gas cost of
US$ 7/MMBTU works out to be Rs.2.29/kWh at 73.8% PLF

19. Variable Charges: The variable charge component of the tariff includes cost of RLNG
required annually for power generation according to load factor. The variable cost based
on discount rate of 9.35 % for 25 years of the proposed cogeneration plant at station bus
bar after allowing for auxiliary power consumption and fuel gas cost of US$ 7/MMBTU
works out to be Rs.3.25/kWh at 73.8% PLF

20. The levelized cost of generation per kWh based on discount rate of 9.35 % for 25 years of
the proposed cogeneration plant at station bus bar after allowing for auxiliary power
consumption and fuel gas cost of US$ 7/MMBTU works out to be Rs.5.54/kWh at 73.8%
PLF.

Sensitivity Analysis

21. Variation of Capex: A sensitivity analysis is carried out with variation of estimated Capex
and the influence on Cost of generation (Fixed & Variable Cost) is furnished in below
graph;
Figure IX-1: Variation in Capital Cost Vs Cost of Generation
17. Variation of Gas Price: The below graph illustrates the variation in cost of generation
(Fixed & variable) due to the variation in landed gas price;

Figure IX-2: Variation in Gas Price Vs Cost of Generation


18. Variation of Plant Load Factor: The below graph illustrates the variation in Plant Load
Factor and its effect on the cost of generation (Fixed & variable);

Figure IX-3: Variation in PLF Vs Cost of Generation


Note: The above PLF is based on plant operating at weighted average load of 100% MCR and MEL. In case the plant operates at 100% Load with
90% PLF the Fixed cost is about Rs. 1.89/kWh and variable cost is about Rs. 3.13/kWh

19. Variation of H Class Vs F Class Machine: The below graph illustrates the variation in Plant
Load Factor and its effect on the cost of generation (Fixed & variable) for H class & F
class machines;

Figure IX-4: H Class Vs F Class


Note: The above PLF is based on plant operating at weighted average load of 100% MCR and MEL. In case the F Class machine as the
plant is of with 2 on 1 configuration, one GT+ HRSG can be shutdown to achieve low MEL.

RLNG SPECIFICATIONS

Gross Heating Value of Gas

The Gas offered at the Delivery Point shall have minimum Gross Heating Value in a gaseous state
equal to 8500 kilo calories per Standard Cubic Meter)

Composition of Gas

The Gas to be supplied by Seller to Buyer, shall have the following composition:

Composition Of Gas
Component Specifications
Methane (C1) not less than 80 Mol
%
Ethane (C2) not more than 12
Mol %
Propane (C3) not more than 4.50
Mol %
Butanes (C4) and heavier not more than 2.5
Mol %
Pentanes (C5)and heavier not more than 0.35
Mol %
Non Combustible gases other than Non Hydrocarbons including not more than 6.0
CO2 & N2 Mol %

Total Sulphur including H2S 10 ppm by weight


Impurities Gas shall be
reasonably free from
dust gum
forming
constituents
and other
deleterious
solid and/or
liquid matter;
Water content / moisture No free water will be
present

- From IOCL
Sea Water analysis (Typical)

Constitutes Unit Value


Calcium (Ca) mg/l 467
Magnesium (Mg) mg/l 1258
Sodium (Na) mg/l 10789
Potassium (K) mg/l 391
Ammonia (NH3) mg/l 0.2
Bicarbonate (HCO3) mg/l 126.3
Chloride (Cl) mg/l 19247
Sulphate (SO4) mg/l 2878
Nitrate (NO3) mg/l 4
Floride (F) mg/l 1.63
Silica (SiO2) mg/l 1.38
Boron (B) mg/l 3.17
Total Suspended Solids mg/l <75
Turbidity NTU <10
Temperature Deg C 25 to 31
Source: JICA Study report on survey on Chennai sea water desalination plant
Cost
Sl. No. Break Down Remarks
(Rs. Crore)

1.0. Cost of Land & Site Development


1.1 Land 0 Not applicable as land is owned by
1.2 Rehabilitation & Resettlement (R&R) TANGEDCO
1.3 Preliminary Investigation and Site Development 0
Total Land & Site Development 0

2.0. Plant & Equipment


Quote from Market Source (inlcudes
2.1 Gas Turbine Generator Island 2225.79 delievery to site @ 7.5% Frieght &
clearance Charges)
2.2 Steam Turbine Generator Island Included in item 2.1
2.3 HRSG Island Included in item 2.1
2.4 BOP Mechanical
2.4.1 Fuel handling and storage system 5
2.4.2 External water supply system Not applicable
2.4.3 CW system 65
2.4.4 Cooling towers Included in item 2.4.3
2.4.5 Clarification plant Included in item 2.4.3
2.4.6 Chlorination Plant Included in item 2.4.3
2.4.7 Air Conditioning and Ventilation System 5
2.4.8 Fire Fighting System Included in item 2.4.3
2.4.9 Hydrogen generation system 3
2.4.10 HP/LP piping 10
Total BOP Mechanical 88.00

2.4 BOP Electrical


2.4.1 Switch Yard Package 38.5
2.4.2 Transformers Package 10 Main Transoformers included in 2.1
2.4.3 Switch Gear Package 8 Main plant Switchgear included in 2.2
2.4.4 Cables, Cable Facilities & Grounding 5 Main plant included in 2.3
2.4.5 Lighting 3
2.4.6 Black start DG Sets 30
Total BOP Electrical 95

GT, ST, HRSG Conrol system & plant


2.5 C&I Package 5 DCS included in 2.1

Total Plant and Equipment excluding Taxes and Duties 2413.45

2.6 Taxes and Duties


2.6.1 Frieght & Insurance on imported item @ 10% 222.58 For item 2.1
2.6.2 Taxes & Duties (GST - 18% & for GT: Customs Duty - 5%) 366.74
Total Taxes & Duties 589.32

Total Plant and Equipment including Taxes and Duties 3002.77

3.0. Initial Spares (2.5% of Total Plant & Equip. incl. Taxes & Duties) 75.07

4.0. Civil Works


Total Civil Works 240.22 Considered 8% of the Total plant cost
Cost
Sl. No. Break Down Remarks
(Rs. Crore)
5.0. Construction & Pre-Commissioning Expenses
Erection Testing and Commissioning (1% of Total Plant &
5.1 Equip.excluding Taxes & Duties) 20.70
5.2 Site Supervision 5
5.3 Operator's Training 0.5
5.4 Construction Insurance / Project Insurance 333.88
5.5 Tools and Plants Included in 5.1
5.6 Start-up fuel Included in 5.1
Total Construction and Precommissioning Expenses 360.07

6.0. Overheads
6.1 Establishment 0.65
6.2 Design & Engineering 145.23
6.3 Audit and Accounts
6.4 Contingency @ 3% 114.72
Total Overheads 260.60

7.0. Capital Cost Excluding IDC & FC 3938.74

8.0. IDC, FC, FERV & Hedging Cost

8.1 Interest During Construction (IDC) 313.20


8.2 Financing Charges (FC) 27.57
Total of IDC, FC, FERV & Hedging Cost 340.77

9.0. Capital Cost Including IDC, FC, FERV & Hedging Cost 4279.51
PHASING OF EXPENDITURE AND IDC CALCULATION IN RS. CRORES

Equity 30% INT 12.00% Loan 70%


Phasing of Expenditure Phasing of Expenditure
Closing
Period without IDC Equity Debt IDC with IDC
Value Percent Loan Value Percent
I 393.874 10.00% 393.874 0.000 0.000 0.000 393.874 9.24%
II 196.937 5.00% 196.937 0.000 0.000 0.000 196.937 4.62%
III 787.748 20.00% 590.811 196.937 2.954 196.937 790.702 18.55%
IV 787.748 20.00% 0.000 787.748 17.724 984.685 805.472 18.89%
V 590.811 15.00% 0.000 590.811 38.403 1575.496 629.214 14.76%
VI 393.874 10.00% 0.000 393.874 53.173 1969.370 447.047 10.49%
VII 393.874 10.00% 0.000 393.874 64.989 2363.244 458.863 10.76%
VIII 196.937 5.00% 1.000 195.937 73.836 2559.181 270.773 6.35%
IX 196.937 5.00% 0.000 196.937 73.851 2560.181 270.788 6.35%
Total 3938.74 100.00% 1182.622 2756.118 324.931 4263.67 100.00%

1st Iteration
I 393.874 9.24% 393.874 0.000 0.000 0.000 393.874 8.83%
II 196.937 4.62% 196.937 0.000 0.000 0.000 196.937 4.41%
III 790.702 18.55% 688.290 102.412 1.536 102.412 789.284 17.69%
IV 805.472 18.89% 0.000 805.472 15.154 907.884 802.902 17.99%
V 629.214 14.76% 0.000 629.214 36.675 1537.098 627.486 14.06%
VI 447.047 10.49% 0.000 447.047 52.819 1984.145 446.693 10.01%
VII 458.863 10.76% 0.000 458.863 66.407 2443.008 460.281 10.31%
VIII 270.773 6.35% 1.000 269.773 77.337 2712.781 471.211 10.56%
IX 270.788 6.35% 0.000 270.788 77.352 2713.796 274.289 6.15%
Total 4263.67 100.00% 1280.101 2983.570 327.280 4462.96 100.00%

2nd Iteration
I 393.874 8.83% 393.874 0.000 0.000 0.000 393.874 9.28%
II 196.937 4.41% 196.937 0.000 0.000 0.000 196.937 4.64%
III 789.284 17.69% 748.076 41.208 0.618 41.208 788.366 18.58%
IV 802.902 17.99% 0.000 802.902 13.280 844.110 801.028 18.88%
V 627.486 14.06% 0.000 627.486 34.736 1471.596 625.547 14.74%
VI 446.693 10.01% 0.000 446.693 50.848 1918.289 444.722 10.48%
VII 460.281 10.31% 0.000 460.281 64.453 2378.570 458.327 10.80%
VIII 471.211 10.56% 0.000 471.211 64.617 2389.500 261.554 6.16%
IX 274.289 6.15% 0.000 274.289 75.471 2652.859 272.408 6.42%
Total 4462.96 100.00% 1338.887 3124.070 304.023 4242.76 100.00%

3 rd Iteration
I 393.874 9.28% 393.874 0.000 0.000 0.000 393.874 9.26%
II 196.937 4.64% 196.937 0.000 0.000 0.000 196.937 4.63%
III 788.366 18.58% 682.018 106.348 1.595 106.348 789.343 18.57%
IV 801.028 18.88% 0.000 801.028 15.206 907.376 802.954 18.89%
V 625.547 14.74% 0.000 625.547 36.604 1532.923 627.415 14.76%
VI 444.722 10.48% 0.000 444.722 52.659 1977.645 446.532 10.50%
VII 458.327 10.80% 0.000 458.327 66.204 2435.972 460.078 10.82%
VIII 261.554 6.16% 0.000 261.554 63.253 2239.199 260.190 6.12%
IX 272.408 6.42% 0.000 272.408 77.165 2708.380 274.102 6.45%
Total 4242.76 100.00% 1272.829 2969.934 312.686 4251.43 100.00%
4 th Iteration
I 393.874 9.26% 393.874 0.000 0.000 0.000 393.874
II 196.937 4.63% 196.937 0.000 0.000 0.000 196.937
III 789.343 18.57% 684.617 104.726 1.571 104.726 789.319
IV 802.954 18.89% 0.000 802.954 15.186 907.680 802.934
V 627.415 14.76% 0.000 627.415 36.642 1535.096 627.453
VI 446.532 10.50% 0.000 446.532 52.751 1981.628 446.625
VII 460.078 10.82% 0.000 460.078 66.350 2441.706 460.224
VIII 260.190 6.12% 0.000 260.190 63.352 2241.818 260.289
IX 274.102 6.45% 0.000 274.102 77.363 2715.809 274.300
Total 4251.43 100.00% 1275.428 2975.998 313.214 4251.95

5 th Iteration
I 393.874 9.26% 393.874 0.000 0.000 0.000 393.874
II 196.937 4.63% 196.937 0.000 0.000 0.000 196.937
III 789.319 18.56% 684.775 104.544 1.568 104.544 789.316
IV 802.934 18.88% 0.000 802.934 15.180 907.478 802.928
V 627.453 14.76% 0.000 627.453 36.636 1534.930 627.447
VI 446.625 10.50% 0.000 446.625 52.747 1981.555 446.621
VII 460.224 10.82% 0.000 460.224 66.350 2441.779 460.224
VIII 260.289 6.12% 0.000 260.289 63.351 2241.844 260.288
IX 274.300 6.45% 0.000 274.300 77.368 2716.079 274.305
Total 4251.95 100.00% 1275.586 2976.368 313.201 4251.94

6 th Iteration
I 393.875 9.26% 393.875 0.000 0.000 0.000 393.874
II 196.938 4.63% 196.938 0.000 0.000 0.000 196.937
III 789.319 18.56% 684.769 104.549 1.568 104.549 789.316
IV 802.931 18.88% 0.000 802.931 15.180 907.480 802.928
V 627.449 14.76% 0.000 627.449 36.636 1534.929 627.447
VI 446.623 10.50% 0.000 446.623 52.747 1981.552 446.621
VII 460.225 10.82% 0.000 460.225 66.350 2441.777 460.224
VIII 260.289 6.12% 0.000 260.289 63.351 2241.840 260.288
IX 274.306 6.45% 0.000 274.306 77.368 2716.083 274.305
Total 4251.94 100.00% 1275.582 2976.372 313.201 4251.94

You might also like