I PEKERJAAN PERSIAPAN
1 Bouwplank 15,00 m1 15.000,00 292.500,00
2 Air kerja 1,00 ls 85.000,00 110.500,00
3 Keamanan 1,00 ls 100.000,00 130.000,00
SUB TOTAL I 533.000,00
IV PEKERJAAN DINDING -
1 Pasangan dinding Celcon + sopi2 103,50 m2 58.000,00 7.803.900,00
2 Plester aci dinding 201,00 m2 28.000,00 7.316.400,00
SUB TOTAL IV 15.120.300,00
V PEKERJAAN ATAP
1 Rangka atap baja ringan 56,50 m2 135.000,00 9.915.750,00
2 Papan listplank grc 18,00 m1 30.000,00 702.000,00
3 Genteng plentong 52,50 m2 72.000,00 4.914.000,00
4 Plasing 12,50 m1 15.000,00 243.750,00
5 Genteng nok 6,50 m1 30.000,00 253.500,00
SUB TOTAL V 15.775.500,00
Type 36 - 01
HARGA
JUMLAH
NO. JENIS PEKERJAAN VOLUME SAT. SATUAN
( RP ) ( RP )
VI PEKERJAAN PLAFOND -
1 Plafond givsum 9 mm +rangka hollo 45,00 m2 95.000,00 5.557.500,00
2 List plafond 1x4 60,00 m1 12.500,00 975.000,00
3 Menhol 60x60 1,00 bh 65.000,00 84.500,00
SUB TOTAL VI 6.617.000,00
IX PEKERJAAN SANITAIR
1 KM / WC
Closet jongkok 1,00 set 300.000,00 390.000,00
Floor drain 1,00 bh 80.000,00 104.000,00
Kran dinding 1,00 bh 65.000,00 84.500,00
2 Dapur -
Kitchen zink 1,00 bh 275.000,00 357.500,00
Kran bebek 2,00 bh 165.000,00 429.000,00
SUB TOTAL IX 1.365.000,00
Type 36 - 02
HARGA
JUMLAH
NO. JENIS PEKERJAAN VOLUME SAT. SATUAN
( RP ) ( RP )
X PEKERJAAN LISTRIK -
1 Box MCB 4 Group + MCB 4 ex Hager 1,00 set 350.000,00 455.000,00
2 fitting lampu 6,00 bh 12.500,00 97.500,00
3 Saklar single 4,00 bh 18.000,00 93.600,00
4 Saklar seri 1,00 bh 18.000,00 23.400,00
5 Stop kontak 4,00 bh 20.000,00 104.000,00
6 Intalasi titik lampu 6,00 ttk 185.000,00 1.443.000,00
7 Intalasi stop kontak 4,00 ttk 185.000,00 962.000,00
8 Intalasi kabel feeder 8,00 m1 34.000,00 353.600,00
SUB TOTAL X 3.532.100,00
Type 36 - 03
HARGA
JUMLAH
NO. JENIS PEKERJAAN VOLUME SAT. SATUAN
( RP ) ( RP )
REKAPITULASI
I PEKERJAAN PERSIAPAN 533.000,00
II PEKERJAAN TANAH dan PONDASI 4.645.641,00
III PEKERJAAN BETON 12.295.790,00
IV PEKERJAAN DINDING 15.120.300,00
V PEKERJAAN ATAP 15.775.500,00
VI PEKERJAAN PLAFOND 6.617.000,00
VII PEKERJAAN PINTU DAN JENDELA 8.085.220,00
VIII PEKERJAAN KERAMIK LANTAI & DINDING 7.954.050,00
IX PEKERJAAN SANETARI 1.365.000,00
X PEKERJAAN LISTRIK 3.532.100,00
XI PEKERJAAN INST AIR BERSIH & AIR KOTOR 809.900,00
XII PEKERJAAN CAT 3.733.080,00
XIII PEKERJAAN LAIN2 2.223.000,00
JUMLAH 82.689.581,00
JASA PELAKSANA 10 % 8.268.958,10
TOTAL 90.958.539,10
DIBULATKAN 90.958.000,00
LUAS BANGUNAN 36,00
HARGA BANGUNAN / M2 2.526.611,11
Type 36 - 04