10-KW With Quotation with IP65 Inverter

Sr. Item Detail Unit Price Quantity Total


Jinko/LongiSolar 535-540W
1 Solar Panels MonoPerc 40500 18 729,000
Half Cut
Nitrox 12kw Hybrid Inverter 48V
2 Inverter 510,000 1 510,000

3 Battery Pylontech Lithium Ion 100 ah 48V 295,000 1 295,000


Galvanized Panels 2 pv Frame 2
Mounting Structure
4 mm 5,000 10 50,000
5 Flexible DC Wire 2 Core 6 MM DC Cable 45,000 1 45,000
6 Miscellaneous Hardware Protector Breaker etc 55000 1 55000
7 Installation Complete Installation 50,000 1 50,000
Total 17,34,000

430, Kings Crystal Bungalows, Sukkur Sindh. burraqstarsolution@gmail.com 0333-7102194.

1
PROPOSED LOAD DETAILS
REQUESTED BY: HAFIZ RASHEED AHMED

Proposed Load Details – 10KW


Equipment Qty Wattage Total Wattage Surge Wattage
AC 1.5 Ton Inverter base 3 1,800 5400 10800
Fridges 2 450 900 1800
LED TV 3 150 450 900
Lighting Load 30 20 600 1200
Fan, Exhausts 12 120 1440 2880
Freezer/Water Motor 1 300 300 300
Total Load 9090 Aprox 19180 W Aprox

430, Kings Crystal Bungalows, Sukkur Sindh. burraqstarsolution@gmail.com 0333-7102194.

2
Core Elements
Sr # Items Specifications
1 Solar Panels Jinko/Longi/Canadian 540/545w(Mono PERC Half cut)
2 Battery Hyundai/phoenix/ Lithium ion( Pylontech)
3 Inverter Inverex IP65/Huawei
4 Online monitoring system Smart Solar

Structure
5 Structure type Galvanized
6 Framing 2PV/3PV
7 Mounting Details Pre-Galvanized GI Rust Proof Sheet
8 Civil Work Details At Client's End

AC/DC Cables
9 DC Cable 8mm Double insulated Fire proof and smoke proof
10 AC Cable 4mm (Min)
11 Cable Interconnections MC4 Connectors (IP65, Slocable, Solid pin)

Cable Tie, PVC Duct, Flexible Pipes, Insulation tapes, Thimbles


12 Cable Accessories

LV Switchgear
13 AC Breaker Schneider/ABB/Legrand
14 Disconnect Switch for Utility Schneider or equivalent LOT
15 Distribution Box Smart Solar

Earthing/Lightening Protection Equipment(Optional)


16 Lightening Arrestor Copper Lightening Arrestor
17 Panel to Panel Earthing Cable 2.5mm single core
18 Inverter Earthing Cable 2.5mm single core
19 DC/AC Bores (optional) JOB till Mositure level

Net- Metering Facility(Optional)


20 Preperation of Application Complete Application/ Documentation as per DESCOM Requirements
21 Application Submission & Processing Submission to LESCO, Signatures of SDO, Follow ups
22 Generation License Approval of License from NEPRA (Can take upto 4 months by wapda)
23 Bi-Directional meter Demand Notice (optional) As per Agreement
430, Kings Crystal Bungalows, Sukkur Sindh. burraqstarsolution@gmail.com 0333-7102194.

3
Warranty
Item Description Warranty

Solar Module
• Canadian Solar/Jinko Solar/Longi Solar * 12/30 Years

Inverter
• Crown/Inverex ** 5 Years

Battey
• Hyundai/phoenix ***1 Year
• Lithium ion ****5 Years

* 12 years 90% output and 30 years 80% output Linear Warranty


** 4 Years Warranty according to the warranty sheet of Crown/Inverex, over voltage or surge from grid side is not covered in warranty
*** Battery warranty will not be claimed if there is overcharging from inverter or maintenance of water checking is not done by client

430, Kings Crystal Bungalows, Sukkur Sindh. burraqstarsolution@gmail.com 0333-7102194.