Project :
Date / Day :
Time
Work Place :
Inspected by
Compliance/ Remarks
Implemented? (i.e. specify good practices, problem
Inspection Items observed, proposed corrective/
Yes () No (X)* N/A preventative actions, etc.)
PPE
a. Use approved PPE
b. Condition of PPE
c. Correct wear PPE
d. Maintenance of PPE
e. Others (ply specify)
Ladder safety
a. Material ladder
b. Condition of ladder
c. Maintenance of ladder
Floor Opening
a. Enclosure of floor opening
floor
b. Provision of proper signage
in place
c. Others (please specify)
Edge Protection
a. Provision of suitable hard
barricade/ netting
b. Provision of proper signage
in place
Page 1 of 4
JAZZ CITY
Compliance/ Remarks
Inspection Items Implemented? (i.e. specify good practices, problem
Yes () No (X)* N/A observed, proposed corrective/
preventative actions, etc.)
c. Others (please specify)
Working at Height
a. Supervision
b. Provision of Personal
Protective Equipment (PPE)
c. Permit To Work (PTW)
d. Protection of life lines
e. Safety nets
f. Work on steep roofs
g. Others (please specify)
Access to Work Place
a. Ingress and egress to the site
b. Access to work place
c. Access from floor to floor
d. Adequate lighting
e. Provision of overhead
protection
f. Others (please specify)
Electrical Safety
a. Warning signage
b. Provision of proper wiring
c. Provision of electrical
distribution board
d. Condition of electrical cables
e. Provision of residual current
devices
f. Others (please specify)
Page 2 of 4
JAZZ CITY
Compliance/ Remarks
Inspection Items Implemented? (i.e. specify good practices, problem
Yes () No (X)* N/A observed, proposed corrective/
preventative actions, etc.)
Material Storing Area
a. Storage area condition/
bunded/ shed
b. Provision of warning signage
c. Cleanliness
d. Barricading / isolating
e. Others (please specify)
Health and Welfare
a. First aid box/ first aid room
b. Site toilet/ septic tank/ resting
area
c. Drinking water
d. Fire extinguisher and fire
protection
e. Pest control
f. Others (please specify)
Excavation and Shoring
a. Warning signage and
barricade
b. Access & Egress
c. Excavation method and
supervision
d. Shoring design by P.E.
e. Others (please specify)
Chemical/ Scheduled Waste/ Fuel Storage
a. Labelling & signage
b. MSDS accessibility
c. Roof and bunded/ dripping
tray
d. Spill kits (rags, sand, saw
dust, shovel, etc.)
e. Register of chemicals
f. Others (please specify)
Public Safety / Traffic / Road safety
a. Warning / road signage &
lights
b. Road barrier
c. Vehicular control / traffic
control
d. Safe handling of construction
materials and machinery
e. PPE
f. Housekeeping along work
area
g. Others (please specify)
Centralised Living Quarters
a. Fire protection equipment
b. Solid waste temporary storage
Page 3 of 4
JAZZ CITY
Compliance/ Remarks
Inspection Items Implemented? (i.e. specify good practices, problem
Yes () No (X)* N/A observed, proposed corrective/
c. Housekeeping & cleanliness preventative actions, etc.)
surrounding / toilet
/washroom/kitchen
d. Perimeter drainage
e. Electrical wiring / plug/socket
f. Canteen condition
g. Lighting
h. Cloth drying area
i. Cooking equipment condition
(stove, gas etc)
j. Rice cooker, water heater
k. Others (pls specify)
Fire Fighting Appliances & Prevention
a. Serviced and validity of fire
extinguisher
b. Requirement of fire
certificate
c. Regulating the establishment
of fire safety organisation in
designated premises
Page 4 of 4