ACTIVITY SHEET for PIPING

Diameter of Pipe (Average) 10 in

PIPING FABRICATION (GENERAL)

Original
Activity ID Phase Activity Description Duration
(HRs)
PRE-TRUNAROUND PHASE
FAB-0001 PRE Marking of Spools as per Isometric 2.0
FAB-0005 PRE Pre-Fabrication of Spools 4.0
FAB-0010 PRE Inspection 1.0
FAB-0015 PRE Preheating of Joint, If Req 2.0
FAB-0020 PRE Welding of Spools 2.0
FAB-0025 PRE DPT / RT / UT, If Req 4.0
FAB-0030 PRE PWHT of Joint, If Req 2.0
FAB-0035 PRE Shifting of Spools to Sandblasting Yard 1.0
FAB-0040 PRE Sandblasting and Painting 3.0
FAB-0045 PRE Shifting of Spools to Site 1.0
FAB-0050 PRE Marking/Tagging of Lines as per Isometric 2.0
FAB-0055 PRE Obtain Work Permit for Scaffolding 1.0
FAB-0060 PRE Erection of Scaffolding, If Req 10.0
FAB-0065 PRE Obtain Work Permit for Insulation Removal 2.0
FAB-0070 PRE Removal of Insulation from Existing Line 10.0
TRUNAROUND PHASE
FAB-0075 SD Obtain Work Permit 1.0
FAB-0080 SD Blinding of the Lines 3.0
FAB-0085 SD Marking of Lines for Cutting 3.0
FAB-0090 SD Removal of Instruments from Existing Line 6.0
FAB-0095 SD Removal of Pipe Supports from Existing Line 3.0
FAB-0100 SD Cutting of Lines as Marked 5.0
FAB-0105 SD Removal of Old Spool 3.0
FAB-0110 SD Installation of New Spool 5.0
FAB-0115 SD Fitup of New Spool 2.0
FAB-0120 SD Inspection by Client 1.0
FAB-0125 SD Preheating of Joint, If Req 3.0
FAB-0130 SD Welding of New Spool 2.0
FAB-0135 SD DPT / RT / UT, If Req 2.0
FAB-0140 SD PWHT of Joint, If Req 4.0
FAB-0145 SD Re-Installation of Pipe Supports 4.0
FAB-0150 SD Preparation for Hydrotest 2.0
FAB-0155 SD Hydrotesting of New Line 5.0
FAB-0160 SD Air Blowing of Pipe Loop 6.0
FAB-0165 SD Touch Up Paint, If Req 2.0
FAB-0170 SD Re-Installation of Instruments at Line 6.0
FAB-0175 SD Final Inspection 2.0
FAB-0180 SD De-Blinding 1.0
POST TRUNAROUND PHASE
FAB-0185 POST Re-Installation of Insulation 10
FAB-0190 POST Removal of Scaffolding 10
FAB-0195 POST House Keeping 2
FAB-0200 POST Shifting of Material to Warehouse 2

NOTE:
(Duration of the above activities shall be based on Total Dia Inches and time frame provided by client.)
All the above activities & durations are tentative and subject to change as per requirement according to the Scope of
Work, Site Scenario, type and dimensions of the equipment.