Professional Documents
Culture Documents
Abstract—Over the past several years, several bush- leads. All of the draw leads checked during the failure
ings equipped with draw leads have failed in service. investigations involved arcing footprints between the draw
These bushings are not isolated to a single manufactur- lead cable and central tube at one or more locations along
er and all of them have passed standard routine and the length of the bushings. Several accompanying bush-
type tests. A common characteristic of each failure is ings had the same type of damage. All failed bushings did
the arcing marks found between the draw lead cable so violently with explosion and usually with subsequent
and the tube in the center of the bushing. Most of the fire.
bushings also failed violently, in that the bushing ex-
ploded and caused a fire. Some of the bushing failures occurred on peaking pow-
er generator step-up transformers. Peaking power genera-
The purpose of this panel session paper is four fold: tors are most often natural gas fired and may consist of tens
First, extensive investigations have already been con- of megawatts to several hundred megawatts. These instal-
ducted on aspects of certain failure mechanisms, and
lations consisted of the generator, an SF6 circuit breaker
the findings will be reported. Second, other possible,
and a step-up transformer to connect the generator to the
but as yet uninvestigated, failure modes are given.
utility transmission system. A typical system has a 50 feet
Third, it is hoped this report will draw the interest of
others in the industry who will add to the knowledge separation between the transformer and the breaker. Power
surrounding this subject. Fourth, suggestions are made is supplied on demand and is switched off when released
to prevent or alleviate the problem. by the user. These systems are regularly used in many
places of the world.
It is not known exactly what causes the arcing in the
first place, but it is currently thought that it is initiated Although occurrences of similar arcing between the lead
by a transient of some kind then is sustained by the and tube have been found, such occurrences have been
power frequency service voltage. Possible transient rather rare in the past. The authors have performed various
generators and the ensuing failure mechanism are de- individual studies in an attempt to explain the arcing phe-
scribed. nomenon and subsequent failure mode(s) involved. The
ultimate mode of failure is not yet clear, but some general
Index Terms— Bushings, draw leads, arcing, failure conclusions are evident.
mechanism, chopped wave, high frequency, fast front
transients, grounding resistance, SF6 breakers, discon- II. PHYICAL EVIDENCE OF FAILURES
nect switches, switching, re-ignition, current chopping
Several common elements surround the bushing failures,
and as well as a few differences. Below is a summary of
I. INTRODUCTION elements that seem to be present when the failures occur:
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
2
7. SF6 breakers and or SF6 circuit switchers generator. The load current in the HV circuit in this partic-
8. Power distribution systems rarely switched, mostly ular case was about 10 A.
lightly loaded.
9. Peaking power GSU transformers switched often, The distribution of failures according to phase placement
loaded near rating (See text). is five, three and five for phases A, B and C respectively.
10. 15 to 132 MVA base rating. All of the outside phase bushings and one of the center
11. Failures occurred within 4-13 years of installation phase bushings was mounted at an angle, whereas the other
but main tank gassing reported within 2 years of in- two center phase bushings were vertical.
stallation.
12. 50 ft separation between transformer and breaker. Figure 1 shows a cross section of a draw lead bushing
13. Overhead cables. involved in the failures The flashovers seem to occur
14. Mostly leads wrapped with only 20 mils of cotton somewhat randomly distributed over a large region above
tape. and below the flange and inside the tube. General failure
15. Occasional occurrence with insulated leads. locations were as given in Table 1. Note that all of the
16. More than one bushing manufacturer. failed bushings applied to conservator oil preservation
17. More than one transformer manufacturer. systems had major damage, often including the arc marks
18. Typically angle mounted outside phase bushings in the draw lead system, above the flange. All but one of
and vertical center bushings on 3-phase installa- the bushings using an inert gas system received major
tions (See text). damage below the flange.
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
3
end of the lead and cable were melted away in several this lead, but there were circular areas of thin film growth
cases. Most cases involved shards from the top porcelain, consistent with very localized heating (lower right).
shards flying across the station yard.
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
4
smaller arc scars (upper left), and some showing repeated the condenser to the inside surface of the mounting flange.
strikes (upper right). The adjacent copper cable strands
show signs of arc scars (lower left). One of the sections of Several of the upper porcelains exploded and scattered
the insulated cable shows the dark discoloration and a broken shards over the substations. Arc marks were also
small hole through which an arc passed. (lower right). The found on the outer surface of the top of at least two mount-
dark discoloration on the lead insulation is due to alumi- ing flanges. These marks are thought to have occurred
num and copper fretting wear This works into the cotton after the explosion of the upper porcelain and before vol-
cord, and it can be expected that a conductive path is tage could be relayed off.
formed. Once arcing begins, the fretting wear is burned
away and is largely replaced by sludge.
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
5
Power frequency – 1 minute at 460 kV the winding with a draw-lead or with a direct connection to
Power frequency – 1 minute at 485 kV the bottom of the bushing. Consequently, they had copper
tubes instead of the present aluminum tube, and the tubes
After the arcing phenomena became suspect, the bushing were much thicker so as to carry the bushing’s 1200 A
manufacturer set up tests to prove that a voltage difference rating.
was present when transient waves were applied to the
bushing. The bushing was set up in air and a reduced In addition, transient overvoltages and re-ignitions
chopped wave impulse was applied. A flashover occurred have been studied and reported in Europe when shunt reac-
through a piece of print paper. tors are switched with SF6 breakers [1, 2].
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
6
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
7
C. Observations
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
8
involved in this investigation, SF6 circuit breakers or cir- impedance is only a little less than that the overhead lines,
cuit switchers are used to energize and deenergize the so the bulk of the wave splits up into two parallel paths, the
transformers. The associated disconnect switches are only central lead and the tube in the center of the bushing. The
used to isolate the circuit breaker from the bus or transfor- lead wave reaches the electrical windings where it may see
mer and are not expected to create any transients. a much higher surge impedance, and may or may not be
reflected, depending on the relative surge impedances. The
About half of the transformers in this investigation are tube wave reaches to the end of the tube and doubles in
utility distribution supply transformers and are switched magnitude.
very infrequently – on a 5 or 7 year schedule for mainten-
ance. Energization to connect a transformer can occur at In order to determine whether sufficient voltage is
the maximum peak of the source voltage (1 PU phase to created to cause arcing between the lead and the tube, and
ground), results in about one-half PU fast front transient to whether enough energy is created by the ensuing arc path,
the transformer and the other half PU traveling into the bus. the bushing model shown in Figure 14 was used in con-
Deenrgization is normally done after the load is transfer to junction with different computer analysis programs. The
another source resulting in magnetizing current switching. bushing tube is shown in dark gray, and the central lead
Magnetizing current interruption is relatively “mild” but with its inductance, Ll, in black. The lead and tube are
statistically a reigntion could occur with an associated fast joined at the bushing cap. The condenser element is cha-
front transient. racterized by capacitance, C4. Capacitor C1 is the effec-
tive capacitance between lead and tube. Winding capacit-
For the generator peaking transformers which can be ance, C3, is the capacitance between the high voltage
switched 100 to 200 times per year, the nature of the winding and tank. C2 is the capacitance between high
switching precludes significant switching transients as voltage and low voltage windings. In the model, C2 and
noted above. The circuit breaker is used to synchronize the C3 are effectively in parallel.
energized transformer to the system and does so with es-
sentially zero voltage across the open contacts resulting in H1 V1
no fast front transients. Removal of the transformer is the
“reverse” with the transformer staying energized after the
breaker is open with little or no voltage across the circuit
breaker. The likelihood of fast transients is eliminated.
170
Switching devices not directly adjacent to the transformer 85
103 V3 Lc
can generate fast front transients at the transformer. For Ll
example, when a dead transmission line attached to the
substation bus is energized, fast front transients are sent V2
down the line and also into the substation bus and ultimate-
ly to all the transformers on that bus. This can occur with C1
60 C4
routine line switching for maintenance, or when the line
breaker recloses and reenergizes after clearing a fault.
Similar fast front transients can be generated with discon-
nect switches located throughout the substation which are V4
used to energize or deenergized bus sections. The magni-
tude and rise time of the front will vary depending upon the
location and voltage across the contacts. C3
C2
As outlined above, it is thought that arcing is initiated Figure 14. Finite element model of bushing and
by a high frequency or fast front transient and then sus- transformer.
tained by the power frequency service voltage. Following
are possible explanations for the events that occur, leading Taking a simplistic view, the surge impedance in the
up to failure:
overhead cable and bushing are in the order of 450 and 300
ohms, respectively. Hence, about 80 % of the HFT wave
A. Initial Failure due to Transient Voltage
will enter the lead and the tube [10], and will proceed all
Regardless of the source, the leading hypothesis is that a the way down the lead to the winding at point V4. If the
HFT reaches the bushing and starts to reflect when it wave reaches the winding, point V4, it sees a surge imped-
reaches the bottom of the bushing. The bushing surge ance of about 2900 ohms. At this point, the HFT wave will
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
9
increase by 81 % in amplitude, making the total peak 1.81 about 4000 pf.
times 0.8 = 1.45 p.u. of the HFT voltage. Meanwhile, 3. C1 is the lead to tube capacitance at about 500 pf.
voltage on the tube doubles when the HFT hits the end of 4. Ll is the lead inductance at 5.2 μH
the tube, creating a peak of 1.6 p.u. 5. Lc is the tube inductance to typical point of flashover
at 3.9 μH.
This is not the complete story, however, since the veloc- 6. Transformer winding air core inductance of 0.02 H is
ities of the waves in the lead and tube must be taken into large and can be ignored.
account. They are different because of their respective 7. R is the earth resistance back to the breaker and is
inductances and capacitances, and the mutual inductance assumed to be 4 ohm.
between them. Calculations indicate that the velocity of 8. Once flashover between lead and tube occurs, switch
the lead wave is about 40 % of the speed of light, or about Sc1 is closed and ionization path resistor Rsc1 is in-
4.7 x 109 inches/sec, and the tube wave is 30 %, or about troduced.
3.5 x 109 inches/sec. Also, the lead wave must travel about V1 H1
100 inches farther than the tube wave since that is the ap- t(0-) t(0+)
proximate length of lead between the bottom of the bushing
and the winding. Hence, the time that it takes the lead Ssource
wave to reach the winding and return to the bottom of the i6 LC, μH Ll/2
bushing is:
I2 Rsc1 I1
ΔT(lead) = ΔT(top to winding) + ΔT(winding to bottom) Sc1
170 + 200 V3 C1 V2
ΔT ( lead ) = = 0.035 + 0.041 = 0.076 μs
4.9 x10 9 Vsinwt
I3 Ll/2
Meanwhile, the time that it takes for the tube wave to i5
reach the bottom of the bushing and start its return up the I4 V4
tube is:
C4 C2+C3
170 400 kV R
ΔT ( tube ) = = 0.049 μs
3.5 x10 9
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
10
When and if the lead does flash over to the tube, switch B. Continued Erosion due to Power Frequency Voltag-
Sc1 in Figure 15 closes and current flows in resistor Rsc1, es
as shown in Figure 17.
By calculation and by test, it has been confirmed that
once arcing occurs and if metal beads form point to point
contact between the lead and the tube, then substantial
current-sharing becomes possible with at least 55 % of the
current taking the path of the tube, dependent on the degree
of contact. Figure 19 shows a cut-away view of the lead
and one side of the tube.
10
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
11
0.0
X 0.00001 0.0001 0.001 0.01 0.1 1
Contact Resistance, Ohms
11
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
12
12
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
13
the load current flowing through the tube 7. Work is encouraged to investigate the point of fla-
9. The tube heats up to the degree that it starts to degrade shover within the tube. Some of these have been
the adjacent paper insulation in the bushing condenser above the flange and some below. Oil level may
outside the tube. be an important factor in such occurrences.
10. The entire condenser eventually fails radially, pressure 8. Industry Standards work is encouraged to assess
builds up within the bushing due to gases generated by the adequacy of existing standards and determine
degradation of oil and insulation, and the bushing ex- improvements that may lead to greater bushing
plodes, often resulting in fire. robustness. Bushings and lead assemblies in this
11. In some cases, a small hole is burned in the aluminum investigation are able to pass all existing industry
standards. The intention of such standards is to
tube. This may occur due to either the heat generated
have type tests and routine tests that are more se-
by the arcing or the resultant flashover in the condens-
vere than stresses that they may be subjected to in
er.
the field. In this case the evidence supports the
need for a relook at typical applications, utiliza-
XI. RECOMMENDATIONS tion techniques, ratings, and testing methods. This
is a similar finding as has been noted by the IEEE
It is recommended that periodic DGA measurements be Transformers Committee for transformers exposed
made on the tank oil in order to prevent failures of existing to switching devices and has led to the develop-
transformers and bushings. More elaborate measures on ment of Guide IEEE C57.142 [4].
existing transformers include:
1. removal of the bushings and adding additional in- XIII Acknowledgements
sulation to the draw lead.
2. Longer term, it is recommended that wording be The authors wish to thank the managements of Trench
added to transformer/ bushing test standards to Limited and of Waukesha Electric Systems and of the
prevent this problem from occurring in the future. many supporting businesses who have sponsored and as-
sisted this investigation. The authors furthermore wish to
XII. FUTURE WORK specifically thank Shirish (Sam) Mehta and Larry Kriege of
Waukesha Electric Systems and David Wallace and Keith
Ellis of Trench Limited for their excellent support in re-
Further work is recommended on several fronts:
searching events and in assisting with analysis. Other
1. Failure mode exploration is encouraged to ex- noteworthy support was offered by Alexander D.(Don)
amine accelerated aging between lead and tube to Kline with PSPICE simulations, by Nigel McQuin with
better understand lead and tube erosion at power switching characteristics studies, and by Dr. Russ Crutcher
frequencies. in examining the arc energy related beads of metal which
2. Gassing studies are encouraged for both the main facilitate contact between the leads and the tube.
tank gases as well as the gases in the bushing con-
denser. Such gases may be the best indicators of
imminent problems in process. Gassing within the
tube would appear to push the oil column lower.
Rapid heating may be associated with arcing loca-
tions that are not fully submerged.
3. Partial discharge studies are encouraged. Gassing
within the condenser may be detectable by the XI. REFERENCES
bushing capacitance tap.
4. Environmental factors may well be important con- [1] An Investigation of Transient Overvoltage Generation when Switch-
tributors. Many of the failures appear to be asso- ing High Voltage Shunt Reactors by SF6 Breaker, Z. Ma, C. A. Bliss,
ciated with installations in particularly dry condi- A. R. Penfold, A. F. W. Harris, S. B. Tennakoon, IEEE Transactions
on Power Delivery, Vol. 13, April, 1998, pp. 472-479.
tions. Modeling is encouraged. Ideal solutions to [2] Switching Overvoltages at the Disconection of the High Voltage
bushing problems will be effective in all soil con- Shunt Reactor in the Romanian Power System, P. C. Stroca, I. Mer-
ditions. fu, M Stroica, M Merfu, A. Campeanu, S. A. Smart, presented at the
5. Relevance of voltage class is an important factor. 2009 IEEE/PES Power Systems Conference and Exposition, Seattle,
WA, April, 2009.
All voltage classes need to be robust.
[3] Engineering reports of field failures and of transformer analysis.
6. Relevance of Transformer MVA. In the analysis, [4] P57.142/D5.1 Guide To Describe The Occurrence and Mitigation Of
a significant portion of the current may travel Switching Transients Induced By Transformer, Switching Device,
down the tube to the point of failure. This would and System Interaction
seem to suggest that larger transformers are more [5] Inductance Calculations by Frederick W. Grover, 1946, 1973, by
Dover Publications, Inc. 180 Varick St, New York, NY 10014.
vulnerable. [6] Elements of Power Systems Analysis by William D. Stevenson, Jr.,
McGraw Hill Book Company, Inc., 1962, New York.
13
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
14
14
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
15
advanced to Vice President and Technical Director. Also during this time, Testing Techniques Sub-committee of the PSIM Committee. He is also an
he was responsible for the oversight of the startup of the Bradenton, active member of several working groups within the Transformers Com-
Florida operation, the transition to Magnetek and a member of the senior mittee.
management team during the purchase of the Waukesha Transformer
Operation by Magnetek. Dr. Robert C. Degeneff is president of
Mr. Ganser has been engaged in the consulting business, doing busi- Utility Systems Technologies, Inc. which
ness as Transformer Consulting Services since 1996. He has over 45 years builds electronic voltage regulators and
experience in the Transformer Industry covering the spectrum from Engi- power quality mitigation equipment and
neering, Quality Assurance, Testing and Senior Management. This expe- provides consulting to the utility industry.
rience includes both the OEM and the Repair Industry. Prior to assuming his role at UST, Dr.
Mr. Ganser holds a BSEE degree for the University of Notre Dame in Robert Degeneff was Professor of Electric
South Bend, Indiana. He also holds an MBA degree from Marquette Power Engineering at Rensselaer Polytech-
University in Milwaukee, Wisconsin. He attended the Magnetek Institute nic Institute in Troy, New York for 17
of Management for Senior Managers at the University of Southern Cali- years. The department was involved in
fornia in Los Angeles, California. research into the design and performance of
Mr. Ganser is a Registered Professional Engineer in the State of Ohio. utility and industrial power apparatus.
He is a Life member of the IEEE, a member of CIGRE, a member of the Before joining RPI , Dr. Degeneff was with General Electric for 16 years,
Power Engineering Society and the Transformers Committee and Principal initially as a Senior Development Engineer with GE's Large Power Trans-
Member of the International Electrical testing Association Category D former Department and later, as a manager in various positions of increas-
Consultant. ing responsibility in the power transformer business, HVDC systems, and
utility planning.
Larry Coffeen is a Senior Research Dr. Degeneff received his B.Eng degree from Kettering Institute and
Engineer for NEETRAC, a re- his masters and D.Eng from RPI. He is a member of Tau Beta Pi, Eta
search organization with a mem- Kappa Nu and Sigma Xi. He is a PE in New York, Fellow in the IEEE
bership of power equipment and 2008 recipient of the Herman Halprin Award . He has published over
manufacturers and electric utilities. seven dozen papers (two IEEE prize papers), chapters in 5 books and
NEETRAC is also a part of the holds eight patents.
school of Electrical and Computer
Engineering at the Georgia Insti- Bjorn Lofgren has a BSEE from Stock-
tute of Technology. Larry’s holm, Sweden.
current work includes the devel- He has been in the Circuit Breaker indus-
opment of test techniques and test try for 32 years in design, development,
equipment to perform ON-line testing and management. Currently Bjorn
transformer, CCVT, and power is Circuit Breaker R&D manager for
line carrier trap frequency response analysis. Siemens Energy, Jackson, Mississippi.
Before joining NEETRAC, Larry was employed for 29 years by Geor-
gia Power Company. As a Senior Test Engineer, he performed Transmis- Bjorn is active in several working groups
sion Substation Testing and High Voltage Laboratory test work. After the of the IEEE/PES Switchgear committee.
formation of NEETRAC in 1996, Larry continued to work in the High
Voltage Laboratory and develop new field test technology for substation
equipment.
Larry received a Bachelor of Electrical Engineering degree from Geor-
gia TECH in 1970. He is a senior member of IEEE and a Member of the
IEEE, PES, and PSIM (Power System Instrumentation & Measurements)
Committee since 1987. Larry contributed actively to IEEE Std 4-1995,
“IEEE Standard Techniques for High Voltage Testing” as an active mem-
ber of the High Voltage Testing Techniques subcommittee of PSIM. He is
contributing to the current IEEE Std 4-1995 revision as a corresponding
member of HVTT PSIM. Larry has been a contributing member of the
IEEE, Transformers Committee, FRA Guide Working Group from 2003 to
the present.
Larry holds five U.S. patents relating to power transformer FRA test-
ing, MOV lightning arrester and polymer insulator field test methods.
15
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.
16
16
Authorized licensed use limited to: Universidad de chile. Downloaded on December 11,2021 at 00:05:36 UTC from IEEE Xplore. Restrictions apply.