Events Register

Event identification Event Analyses Event Consequences Event Notifications Outcome

ASC reference Date of Comments / Remark


Due to Ref of Customer/
Letter ,Mail, Customer/ Contract
ASC/ Cost impact Date of ASC Subcontractor Recovered
Ref, Event description Event Date Site Root Cause delay in days MOM record with Subcontractor Amendment Time extension
Customer/ if any Notification reply to ASC Amount
Customer/ reply to ASC Reference
Subcontractor? Notification
Subcontractor Notification

WE START STEEL & CARPENTRY WORK FOR BASEMENT SHEAR WALL &
RETAINING WALL BUT TIL NOW THERE ARE NOT AS BUILT DRAWINGS Yes, disruption and
1 01.06.2018 AL KHOPER TECHNICAL OFFICE DID NOT FINISHE IT AL KHOPER
FOR ELECTRO MECHANIC , STRUCTURE & ARCH. DRAWINGS TO AVOID delay impact.
ANY MISTAKES WHICH HAPPENED IN THE PREVIOS PROJECTS .

NO APROVAL FOR PRE CAST DRAWINGS AND TIL NOW PRE CAST Yes, disruption and
2 01.06.2019 AL KHOPER THE APPROVAL TAKE TOO MUCH TIME . AL KHOPER 50
FACTORY DID NOT START POURING ELEMENTS . delay impact.

CONSULTANT REQUEST MANY TIMES TO VISIT THE PRE CAST FACTORY


3 01.06.2020 AL KHOPER THE PRE CAST FACTORY AL KHOPER 60 Yes, delay impact.
BUT NO ANY APPOINTMENT .

THE WEATHER IS VERY HOT WITH HUMIDITY MORE THAN 60% EVERY Non-giving site possession and access to the Yes, disruption and
4 01.06.2021 AL KHOPER AL KHOPER
DAY workplace delay impact.

MOJ Asked for coordination with site consultant to visit SCECo with M.O.J
5 SCECo Representative to provide them with a a report with a last update today to AL KHOPER AL KHOPER nothing
submit this report to consultant project main management .

PMH 9 -9905-v1- Events Register page 1 /1