WE START STEEL & CARPENTRY WORK FOR BASEMENT SHEAR WALL &
RETAINING WALL BUT TIL NOW THERE ARE NOT AS BUILT DRAWINGS Yes, disruption and
1 01.06.2018 AL KHOPER TECHNICAL OFFICE DID NOT FINISHE IT AL KHOPER
FOR ELECTRO MECHANIC , STRUCTURE & ARCH. DRAWINGS TO AVOID delay impact.
ANY MISTAKES WHICH HAPPENED IN THE PREVIOS PROJECTS .
NO APROVAL FOR PRE CAST DRAWINGS AND TIL NOW PRE CAST Yes, disruption and
2 01.06.2019 AL KHOPER THE APPROVAL TAKE TOO MUCH TIME . AL KHOPER 50
FACTORY DID NOT START POURING ELEMENTS . delay impact.
THE WEATHER IS VERY HOT WITH HUMIDITY MORE THAN 60% EVERY Non-giving site possession and access to the Yes, disruption and
4 01.06.2021 AL KHOPER AL KHOPER
DAY workplace delay impact.
MOJ Asked for coordination with site consultant to visit SCECo with M.O.J
5 SCECo Representative to provide them with a a report with a last update today to AL KHOPER AL KHOPER nothing
submit this report to consultant project main management .