You are on page 1of 8

Energy Challenges

The Future of
Coal-Based Power Generation
JAMES R. KATZER, CONSULTANT

C
oal is used to generate more
than half of the electricity pro- Despite its image as a dirty fuel,
duced in the U.S., and about coal remains an economic choice for
40% of the electricity produced glob-
ally (1). For China and India, the coal- baseload power generation —
based fraction is much higher.
Global CO2 emissions from coal- and it can, in fact, have very low emissions.
based power generation exceed 7 bil-
lion m.t./yr — about 41% of the total reserves and limited reserves of other Gulf Coast, with 2000–2004 costs
energy-related CO2 emissions. The fossil fuels; the U.S., with about 255 indexed to 2007
U.S. and China emitted similar billon m.t. of recoverable coal, has • only commercially demonstrated
amounts — roughly 2.5 billion m.t. 27% of the world total (1). technologies are considered
each in 2006 (2). Power plants are Worldwide, primary energy • cost estimates are for the Nth plant
some of the largest single-point demand is projected to grow by just (where N is a single-digit number) for
sources of CO2 emissions, with a typi- over 50% by 2030, with electricity those technologies that are still evolv-
cal 1,000-MWe coal-fired power plant demand doubling. Coal-based power ing, such as integrated gasification
emitting more than 6 million m.t./yr. will, by necessity, account for a large combined cycle (IGCC) and pulverized
Total CO2 emissions from some of the portion of this growth, and will essen- coal combustion with CO2 capture
larger (3,000–6,000 MWe) power tially maintain its current share of the • the levelized cost of electricity
plants in several countries are given in electricity generation portfolio. Thus, (COE) (i.e., the constant-dollar price
Table 1 (3, 4). the use of advanced technology to required over the life of the plant to
Coal is a critical fuel for power minimize the environmental footprint cover all operating expenses, payment
generation. It remains the least expen- of coal-based power generation must of debt, and accrued interest on initial
sive of all the fossil fuels — at $1–$2 be a major objective. project expenses, plus the payment of
per million Btu, compared with This article, which is based on the an acceptable return to investors) is
$6–12 per million Btu for natural gas work done for MIT’s “The Future of calculated using the EPRI-recom-
and oil. It is also very abundant, with Coal” study (6), focuses on the tech- mended approach.
proven global reserves estimated to nologies that are available and under This analysis allows a rough cost
be about 900 billion m.t. — the development for generating electricity comparison among the technologies to
equivalent of about 160 years’ supply from coal. It includes discussion of be made. Actual costs will depend on
at current production rates (5). Today, their costs and environmental perfor- the coal type, plant site and location,
the three largest coal consumers — mance related to criteria pollutants dispatch strategy, and a myriad of other
China, the U.S., and India — have (e.g., SO2, NOx, particulate matter), design and operating decisions. (Fur-
about half of the world’s coal and of their amenability to CO2 capture ther details are available in Ref. 6.) The
and sequestration. In order to compare point of this discussion is to compare
technologies, a common set of design the technologies with and without CO2
Table 1. CO2 emissions from some criteria and operating conditions and capture. (The technologies and costs
large coal-fired power plants (3, 4).
assumptions was selected: for CO2 transport and geologic storage
Plant CO2 Emissions, • each plant is a greenfield unit are treated independently.)
Name Location million m.t./yr with a 500-MWe net generating
Taichung Taiwan 37.5 capacity Pulverized-coal power generation
Poryong South Korea 34.4 • it burns Illinois No. 6 high-sulfur Figure 1 shows the typical unit
Tuoketuo China 29.5 coal operations that are used in an
Vindhyachal India 26.4 • it has a capacity factor of 85% advanced pulverized-coal (PC) com-
Hekinan Japan 26.3 • emissions are controlled to some- bustion plant without CO2 capture.
Janschwalde Germany 24.9 what below today’s best demon- The system can be depicted as three
Miller Alabama 18.7 strated performance technology blocks: the boiler block,
Gibson Indiana 18.5
WA Parish Texas 18.3
• cost estimates are based on de- the steam-cycle turbine block, and the
tailed designs for a plant on the U.S. fluegas clean-up block. The design and

CEP March 2008 www.aiche.org/cep S15


Energy Challenges

energy is needed to compress the CO2


Fluegas Train Boiler House Turbine Building Power Distribution Grid
to a sufficiently high pressure to con-
Fluegas Feed vert it to a supercritical fluid.
Cleaned Water
Fluegas For a supercritical generating
Ammonia unit, the overall efficiency is reduced
7 6
Lime 2 Main
Emulsion
1 Steam by about 9 percentage points, from
Electric
8 Power about 38% to 29%. To maintain con-
5 11
3 13 14 stant electrical output, a PC plant
10
4 equipped to capture 90% of the CO2
4
12 9 in the fluegas requires 32% more
Cooling coal than a plant without CO2 cap-
Air Ash 11 10 Circulating Tower
Gypsum Fly Ash
Coal Condensate Water
10
ture. Improvements can be expected,
Cooling but there are physicochemical and
1 Steam Generator 8 Steam Turbine Air thermodynamic limitations to how
2 DeNOx Unit 9 Condenser
3 Air Preheater 10 Pump large these improvements can be.
11 Feedwater Heater
4
5
Fan
Electrostatic Precipitator 12 Feedwater Tank Fresh Water The main disadvantage of CO2 cap-
6 Desulfurization Unit 13 Generator ture from air-blown PC plants is that
7 Stack 14 Transformer
the fluegas has a relatively low CO2
concentration (because of the large vol-
■ Figure 1. Shown here is the typical flowsheet for an advanced pulverized-coal (PC)
power-generation facility that relies on coal combustion. ume of nitrogen — 79 vol.% — that is
present in the combustion air, and thus,
operating conditions of the steam- we need to move to the highest-effi- the fluegas stream). This issue can be
cycle block largely determine the over- ciency generation that is economically addressed, at a cost, by combusting the
all generating efficiency of the system. justified to reduce CO2 emissions. coal in oxygen rather than air. For PC
For conventional PC combustion Coal combustion power genera- combustion, such an approach is
plants, the typical operating conditions tion with CO2 capture. Because it is known as oxy-fuel PC combustion.
of the steam-cycle block and the commercially proven for capturing Another approach is the production
resulting overall electrical generating CO2 emissions from gas streams in of power in an integrated gasification
efficiency (based on the higher heat- other applications, amine absorption combined cycle (IGCC) facility.
ing value, HHV) are: would be the logical technology Using this approach, the coal is gasi-
• subcritical steam cycle unit — choice for capturing CO2 from PC fied (rather than combusted) with oxy-
typical steam-cycle operation at combustion plants today. It would be gen and steam to produce a syngas
1,000°F and 2,500 psi, 33%–37% unit applied as a process unit at the end of stream consisting of hydrogen and
efficiency the fluegas train, as shown in Figure 2 carbon monoxide (with some impuri-
• supercritical steam cycle unit — for supercritical generation. However, ties), which can be burned in a tur-
typical steam-cycle operation to a relatively large amount of energy is bine. For CO2 capture, the CO can
1,050°F and 3,530 psi, 37%–42% unit needed to recover the CO2 from the be converted to CO2 and H2 via the
efficiency amine solution and thus regenerate the water-gas shift reaction. The CO2
• ultra-supercritical steam cycle solution to capture more CO2. Less is ultimately removed from the
unit — typical steam-cycle operation
to 1,110ºF–1,140°F and 4,650 psi, Lime Slurry
42%–45% unit efficiency. Stack Gas
Today’s existing U. S. coal fleet Feed Air
2,480 m.t./h Fuegas
2,770,000 kg/h
121°C, 1 atm
consists mainly of subcritical units Boiler/Superheater Clean-up
CO2 Capture and
with a limited number of supercritical 238 atm/566°C
Removal:
Particulates 99.9% Recovery
units, although interest in supercritical 3,500 psi/1,050°F NOx 90% 90% Removal
Coal Feed SOx 99+%
technology in the U.S. has recently 243 m.t./h Supercritical CO2
increased. Europe and Japan have High-Pressure 491 m.t./h
Steam CO2 Drying and 150 atm
built about a dozen ultra-supercritical Ash and Wet Solids
Compression
units during the last decade (7). Steam Turbine/ Low-Pressure Steam
Moving from subcritical to ultra- Generator

supercritical generation reduces coal Electric Power


500 MWe Net
consumption by more than 20% per
kWeh of electricity generated. And, ■ Figure 2. Process flow schematic of a supercritical 500-MWe pulverized coal unit with
the higher the efficiency, the lower the CO2 capture; amine absorption technology is a logical choice for capturing CO2 emissions
CO2 emissions per kWeh of electricity from the back end of the fluegas train, but it reduces generating efficiency by about
generated. As a result, at a minimum, 9 percentage points.

S16 www.aiche.org/cep March 2008 CEP


Feed Air Nitrogen
in terms of type (water-slurry or dry
Air Stack Gas feed, operating pressure, etc.) and the
651,000 kg/h 490,000 kg/h
Separation 2,770,000 kg/h
Unit 121°C, 1 atm amount of heat removed from it. For
Oxygen (95%)
electricity generation without CO2
Combustion Air
160,000 kg/h capture, radiant and convective cool-
Radiant Cooling/
ing sections follow directly behind the
Quench Gasifier Sulfur Removal Combustion Turbine/ Heat-Recovery gasification reactor. These capture
Steam Generator/
Coal Feed 41.8 atm/1,343°C
99.4% Removal Generator
Turbine/Generator waste heat from the syngas stream to
(Slurry or Dry) (615 psi/2,450°F) produce high-pressure steam for addi-
185,000 kg/h
Bottom Slag tional power generation in the steam
21,500 kg/h Electric Power Electric Power
500 MWe Net
turbine. In this configuration, the over-
all efficiency of the unit can approach
■ Figure 3. Process flow schematic for a typical 500-MWe IGCC unit without CO2 capture; or somewhat exceed 40%.
the projected generating efficiency with a radiant-cooling gasifier is better than 38%. IGCC with CO2 capture. To cap-
ture CO2 from an IGCC system, two
syngas stream at high pressure, before oxygen is used to combust sufficient additional components are required —
the syngas is combusted in the gas carbon in the gasifier at 500–1,000 a pair of water-gas-shift reactors, and
turbine. IGCC is discussed in greater psig to increase the temperature to an additional absorption unit to scrub
detail later. around 1,500°F. At this temperature, CO2 out of the syngas stream (Figure
water (steam) that is added to the coal 4). This is in addition to the absorption
Oxy-fuel PC combustion reacts with the remaining carbon, con- unit required to scrub the H2S out of
The more-advanced oxy-fuel com- verting it to a mixture of carbon the syngas that is present in all IGCC
bustion technology helps to address the monoxide and hydrogen (syngas) with systems. In the water-gas-shift reac-
issue of high CO2 capture and recovery a range of minor impurities. This syn- tion, the carbon monoxide in the syn-
costs, but it does so at the expense of gas stream is cleaned and then burned gas is reacted with steam to produce
requiring an air separation unit (which in a turbine in a combined-cycle pow- CO2 and H2. Removal of the CO2
would be needed to produce an onsite er block (i.e., a setup that combines yields a relatively pure hydrogen
oxygen source for enhanced combus- both a gas turbine and secondary stream (which can then be burned
tion) with its associated energy costs steam turbine), much like the natural cleanly in the gas turbine).
(8). When coal is burned in essentially gas combined cycle (NGCC) units Because the CO2 in the syngas
pure oxygen, the resulting fluegas is that are in use today. stream after the water-gas-shift reac-
virtually pure CO2 and H2O after par- Because in an IGCC unit all the tion is present at a relatively high con-
ticulate and SO2 removal. The advan- gases are contained at high pressure, centration in a high-pressure stream,
tage is gained through the ability to high levels of particulate, sulfur and the energy required to capture this
directly compress this fluegas stream, mercury removal can be cost-effec- CO2 is less than that required to cap-
with drying, to produce supercritical tively achieved. Emissions levels from ture the comparably more-dilute CO2
CO2 for sequestration. an IGCC system should be similar to that is present in typical PC-combus-
This technology is in active pilot- those from an NGCC unit. Mineral tion fluegas.
plant development and the early matter in the coal is removed as a Today, IGCC without CO2 capture
stages of commercial demonstration, vitreous slag. has been demonstrated in several
with at least two 10–25-MWe com- The gasification reactor is the large power-generating units in the
mercial demonstrations moving for- biggest variable in an IGCC system, U.S., Europe and Japan. At a smaller
ward. Because of the early state of
development, the performance and
Feed Air Nitrogen
cost estimates are not as firm as are 801,000 kg/h
Air
604,000 kg/h
Stack Gas
Separation 3,140,000 kg/h
those for PC or IGCC systems. How- Unit 121°C, 1 atm
ever, oxy-fuel PC combustion has the Oxygen (95%)
Combustion Air
2,890,000 kg/h
potential to provide a lower COE, and 197,000 kg/h
a lower cost per quantity of CO2
avoided, than the respective costs for Quench Gasifier Cooling Sulfur Combustion Turbine/
CO2 Capture/
Knockout and Removal Heat-Recovery
Compression
PC combustion with CO2 capture. Coal Feed
41.8 atm/1,343°C Water-Gas 99.9+%
90% Removal
Steam Generator/
(615 psi/2,450°F) Shift Removal Turbine/Generators
(Slurry or Dry)
228,000 kg/h
Integrated gasification Bottom Slag
29,900 kg/h Electric Power
combined cycle (IGCC) Carbon Dioxide 500 MWe Net
The other oxygen-enhanced option 456,000 kg/h, 150 atm

is IGCC generation, shown without ■ Figure 4. Application of commercial shift and CO2 removal technologies to an IGCC unit
CO2 capture in Figure 3. Typically, make it a viable option for power generation in a carbon-constrained world.

CEP March 2008 www.aiche.org/cep S17


Energy Challenges

Table 2. Performance and costs of coal-fired power-generation technologies. higher compression costs at
higher elevations due to the
Subcritical PC Supercritical PC Oxy-Fuel PC IGCC lower ambient pressure have
Without With Without With With Without With a larger impact on overall
Capture Capture Capture Capture Capture Capture Capture IGCC economics. Under
these conditions, potentially
Heat Rate, Btu/Weh 9,550 13,600 8,870 11,700 11,200 8,890 10,900 significant reductions in the
Efficiency (HHV) 34.3% 25.1% 38.5% 29.3% 30.6% 38.4% 31.2% CO2 capture/recovery cost
CO2 Emitted, g/kWeh 931 127 830 109 104 824 101
for PC combustion could
Total Plant Cost, make it economically com-
$/kWeh $1,580 $2,760 $1,650 $2,650 $2,350 $1,770 $2,340 petitive with IGCC with
CO2 capture in certain appli-
Cost of Electricity cations. In addition, the
Investment Charge, power industry still has lin-
¢/kWeh @15.1% 3.20 5.6 3.35 5.37 4.77 3.59 4.75 gering concerns about the
Fuel, ¢/kWeh operability and availability
@$1.50/MMBtu 1.49 2.04 1.33 1.75 1.67 1.33 1.64
of IGCC.
O&M, ¢/kWeh 0.75 1.60 0.75 1.60 1.45 0.90 1.05
COE, ¢/kWeeh 5.45 9.24 5.43 8.72 7.9 5.82 7.44 Thus, it is too early to
close the door on any of
Cost of CO2 Avoided — 47.1 — 45.7 34.0 — 22.3 these technologies.
vs. Same Technoogy
Without Capture Rehabilitating coal’s
‘dirty’ reputation
Basis: 500-MWeh plant, Illinios No. 6 coal, 85% capacity factor, COE at bus-bar, in 2007 dollars. Coal-based power gener-
ation has the reputation of
scale, gasification with integrated bers include the cost of CO2 capture being dirty, largely based on air emis-
water-gas shift and CO2 removal is and compression to convert it to a sions considerations. Table 3 com-
commercially practiced for hydrogen supercritical fluid, but they do not pares the commercially demonstrated
production. However, they have yet include the cost of CO2 transport and and projected emissions performance
to be integrated and demonstrated at injection (discussed later). of conventional PC combustion and
the scale of operation required for Its lower COE would appear to IGCC (7, 9).
power generation. make IGCC the technology of choice Electrostatic precipitators (ESPs)
for CO2 management in power gener- or baghouses are employed on all
Points of comparison ation. However, oxy-fuel combustion U.S. PC units, so typical particulate
Table 2 summarizes the operating has significant potential. Further- matter (PM) emissions are very low.
and cost parameters associated with more, the cost difference between Improved ESP or wet ESP designs can
conventional PC combustion, oxy-fuel IGCC and conventional PC combus- reduce PM emissions even further, but
coal combustion, and IGCC technolo- tion narrows when lower-rank coals at a cost. Today, fluegas desulfuriza-
gies. These figures are indicative of are used and/or when the plant is tion (FGD) is applied on only a little
the costs for a plant built on the U.S. sited at a higher elevation. Because more than a third of U.S. PC capacity,
Gulf Coast in 2007 dollars, and allow IGCC requires greater levels of com- so typical SOx emissions remains quite
for comparison among the competing pression than PC combustion, the high. The “best commercial” perfor-
power-generation options.
Without CO2 capture, conventional Table 3. Commercially demonstrated and projected
PC combustion has the lowest cost of emissions performance of PC and IGCC power generation.
electricity; the COE for IGCC is about
Particulates, SO2, NOx, Mercury,
10% higher. However, when CO2 cap- Technology Case lb/MMBtu lb/MMBtu lb/MMBtu % removed
ture is considered, IGCC yields the
PC Plant Typical 0.02 0.22 0.11 —
lowest COE.
Best Commercial 0.015 0.04 0.03 90
The cost of CO2 capture and com- (99.5%) (99+%) (90+%)
pression for supercritical PC is about w/ CO2 Capture 0.01 0.0006 0.03 75–85
3.3¢/kWeh; for IGCC, it is about one- (99.5+%) (99.99%) (95+%)
half that, 1.6¢/kWeh. The cost of CO2 IGCC Plant
avoided is about $46/m.t. of CO2 for Best Commercial 0.001 0.015 0.01 95
conventional PC combustion, about (99.8%)
$34/m.t. for oxy-fuel combustion, and w/ CO2 Capture 0.001 0.005 0.01 95+
about $22/m.t. for IGCC. These num- (99.9%)

S18 www.aiche.org/cep March 2008 CEP


Table 4. Incremental cost of emission controls emissions control used on global warming. For instance,
for an advanced PC power-generation plant. as the design basis for today, the total use of CO2 for EOR is
this analysis, which is 35–40 million m.t./yr, which could be
Capital Cost.* O&M, COE,** somewhat better than supplied by a few early CCS projects,
$/kWe ¢/kWeh ¢/kWeh today’s best demon- or by the CO2 emissions of just two of
Particulate Matter 50 0.18 0.28
strated commercial per- the largest coal-fired power plants in
NOx 32 0.11 0.17 formance, relative to no the U.S. (Table 1). Larger-volume,
SO2 190 0.22 0.60 emissions control. This long-term storage will likely need to
incremental cost is rely on deep saline aquifers. These
Incremental Cost about 1¢/kWeh, or geologic formations underlie large
vs. No Control 273 0.51 1.05*** about 20% of the portions of the U. S. (Figure 6), partic-
5.5¢/kWeh total COE ularly those areas with a large amount
* Incremental capital costs are for a new plant.
** Incremental COE impact for Illinois No. 6 coal with 99.3% PM (13–15). CO2 capture of coal-based power generation and
reduction, 99.4% SO2 reduction, and 90+% NOx reduction. and recovery will where additional capacity is expected
*** When this is added to the “no control” COE for supercritical
PC, the total COE is 5.5¢/kWeh
increase the COE some- to be added.
what more than this, The primary mode of CO2 transport
mance in Table 3 refers to emissions about 2¢/kWe-h, based on today’s for sequestration operations will be via
reductions that have been demonstrat- technology. Cost reductions can be pipelines. There are more than 2,500
ed at full commercial scale (7, 9, 10). expected when this technology km of CO2 pipeline in the U.S. today,
Further reductions are possible. When begins to be commercially practiced. with a capacity in excess of 40 million
CO2-capture technologies are imple- m.t./yr CO2. These pipelines were
mented, emissions levels are expected The lifecycle of carbon developed to support EOR operations,
to be lower (11). capture and sequestration primarily in west Texas and Wyoming,
The “best commercial” emissions The entire lifecycle of carbon and involve the transport of CO2 as a
performance levels for IGCC are one- capture and sequestration (CCS) is dense single phase at ambient tempera-
third to one-tenth those of a conven- illustrated in Figure 5. The discus- tures and supercritical pressures. To
tional PC combustion facility, and with sion that follows considers the last avoid corrosion and hydrate formation,
CO2 capture would be even lower. two boxes in the figure — pipeline water levels are typically kept below
In addition, IGCC produces a dense, transport and injection — and their 50 ppm. The pipeline technology is
vitreous slag that ties up most of the estimated impacts on COE. well-established.
toxic components so that they are not Although oil and gas reservoirs and However, rather than having long-
easily leachable (12), and IGCC uses enhanced oil recovery operations distance CO2 pipelines running across
about 30% less water than supercritical (EOR; in which CO2 is injected under the country, a typical CCS power
PC systems. Although this does not high pressure into aging oil and gas plant project might look something
address the entire lifecycle for coal, reservoirs, to stimulate production) are like the one shown in Figure 7 (16). A
coal use in the electricity-generation often discussed as potential locations good location would be one that has
step can, in fact, be much cleaner than for underground long-term CO2 stor- sufficient storage capacity accessible
it typically is with the use of additional age, these storage-sites-of-opportunity within about a 100-km radius. Loca-
advanced control technology. have limited long-term potential to tion is important, but once sited, the
Table 4 gives the estimated incre- sequester CO2 on the scale that will CO2 storage requirement for the life-
mental cost to achieve the level of be needed to have a major impact time of the power plant — which
would be on the order of a billion bar-
rels of liquid CO2 — should be within
Coal or Air or that area. Different portions of the
Natural Gas Oxygen reservoir would be utilized over the
life of the plant.
Pipeline transport costs are highly
Energy CO2 CO2 CO2 CO2 Storage non-linear with respect to the amount
Conversion Capture Transport (Sequestration) of CO2 transported. These economies
Process
of scale help to bring down the overall
- Post-combustion - Pipeline - Depleted Oil/Gas Fields transportation costs for large CCS pro-
- Pre-combustion - Tanker - Saline Reservoirs jects. For example, for 6 million
Useful - Oxy-fuel Combustion - Unmineable Coal Seams
Products - Ocean m.t./yr of CO2, the estimated transport
(Electricity, Fuels, - Mineralization cost is about $1.00/m.t. per 100 km; at
Chemicals, Hydrogen)
30 million m.t./yr of CO2, the cost
■ Figure 5. Shown here is the range of options for the carbon capture and sequestration falls to about $0.25/m.t. per 100 km
steps following energy generation. (17). However, these are average

CEP March 2008 www.aiche.org/cep S19


Energy Challenges

costs, and actual values can vary sig-


nificantly from project to project, due
to both physical (e.g., the terrain the
pipeline must traverse) and political
considerations. For a 1-GWe coal-fired
power plant, pipeline capacity of
about 6–7 million m.t./yr of CO2
would be needed, at a cost of about
$1.00/m.t. of CO2 per 100 km.
The major cost for injection and
storage is associated with drilling the
wells. Other significant costs include
site selection, permitting, characteriza-
tion and monitoring, as well as lines
and connectors required for injection.
In general, no additional pressurization
U.S. Coal-Fired Power Plants (2000)
of the CO2 is required because of the
By Capacity (MW) high pressure in the pipeline and the
0 – 250 Oil and Gas Fields Total Coal-Fired Capacity ≈ 330 GW pressure gain due to the gravity head of
0 – 1,000 Saline Aquifers the CO2 in the well bore. Monitoring
1,001 – 4,000 Coalbeds
costs are expected to be small, on the
order of $0.1–$0.3/m.t. of CO2 (16).
■ Figure 6. Deep saline aquifers, oil and gas fields, and coal beds — which could be Costs for injecting the CO2 into
considered for deep geological storage of CO2 — are located across the U.S., and they geologic formations will vary depend-
coincide with existing coal-based power plants in the U.S. Source: (6). ing on the formation type and its prop-
erties. For example, costs increase as
reservoir depth increases and as reser-
voir injectivity (i.e., the rate at which
supercritical CO2 can be injected into
CO2 pipeline and injection wells
used during the subsequent
the geologic formation) decreases —
decades of full plant operations the lower the injectivity, the more
wells must be drilled for a given rate
of CO2 injection. Injection costs typi-
cally range from $0.5/m.t. to $8/m.t.
of CO2 (17). Although limited in
scale, combining storage with EOR
can help offset some of the capture
and storage costs. EOR credits, mea-
sured in terms of additional oil pro-
duced due to CO2 injection, of up to
$20/m.t. of CO2, may result.
Projected costs, on a levelized
per-kWeh basis, are summarized in
CO2 pipeline and injection wells Table 5. These numbers are on the high
used during the first decade of end of the current range of estimates.
Initial CO2 pipeline and injection full plant operations
well used during plant start-up
Transport and injection costs, which
and validation phase include the costs of constructing pipe-
lines and drilling the injection wells, as
well as the system operating costs, are
significant, but both are small and do
not represent potential economic show-
stoppers. In general, the largest costs
are for capture and compression.
Planning for a CCS-enabled power plant must include a robust CO2 storage plan for all For IGCC facilities, the projected
phases of the plantʼs operations over its entire half-century operational lifetime. cost of CCS would increase the bus-
■ Figure 7. The conceptual elements of a typical carbon capture and storage (CCS) bar cost (i.e., the cost at the power
project are shown here. Source: (16). plant gate) of electricity by about

S20 www.aiche.org/cep March 2008 CEP


Table 5. Costs of CCS project ments for PC with capture could several years to fully achieve the
for PC and IGCC generation make it economically competitive learnings that such demonstrations
with capture. with IGCC in certain applications, have to offer.
and with oxy-fuel coal combustion, Effective demonstration of techni-
PC, IGCC, as well. Thus, it is too early to pick cal, economic and institutional fea-
CCS Step ¢/kWeh ¢/kWeh
winners for coal-based power genera- tures of CCS at commercial scale with
Capture 2.7 1.21 tion with CO2 capture. coal combustion and gasification
Compression 0.6 0.4 Using today’s proven, advanced plants will give policymakers and the
Transport 0.19 0.18 control technologies, criteria pollu- public confidence that a variety of
Injection 0.68 0.64
tant emissions from coal-based practical carbon-mitigation options
Total 4.0 2.4 power generation can be very low. exist, shorten the deployment time,
With CO2 capture, overall emissions and reduce the cost for CCS when a
50%, from 5.8¢/kWeh to about can be even lower, resulting in a comprehensive policy regarding car-
8.2¢/kWeh. This power would be small environmental footprint. With bon emissions is adopted. It will also
very-low-emissions (or “green”) elec- CO2 capture and sequestration, coal help to maintain opportunities for the
tricity, with low CO2 emissions. Fur- can provide base-load electricity that lowest-cost and most widely available
thermore, it is economically competi- is cost-competitive with wind and energy form to meet society’s energy
tive with electricity generated by new nuclear facilities. Thus, coal needs in an environmentally accept-
wind power and by new nuclear remains an economic choice for able manner. If completed expedi-
power plants (1). base-load generation of very-low- tiously, this program can provide the
Comprehensive geological studies emissions electricity. U. S. with a variety of robust technical
suggest that there are no technical options for addressing CO2 emissions
show-stoppers for CO2 injection and The path forward from power generation.
storage, with respect to its efficacy The technologies for power gen- Furthermore, honing the required
and safety. However, a variety of eration with CO2 capture are all technologies will involve the core of
technical issues — such as the time commercially available today and chemical engineering, and will require
dependence of injectivity, flow behav- can be expected to improve in cost a significant amount of chemical engi-
ior of the injected CO2 volume in the and performance as they benefit from neering talent and experience. In addi-
reservoir, rate of dissolution in the more expansive operation at com- tion, the need to improve current tech-
saline water, rate of mineralization, mercial scale. Major R&D break- nologies and develop new technologies
and extent and type of monitoring throughs are not needed to allow for will require much innovation by chem-
required — must be resolved. their use today. ical engineers. Thus, the importance
During 30 years of successful It is also technically feasible to and the scale of the energy issues dis-
injection experience, no critical issues safely and effectively store large cussed here certainly point to critical
have arisen. For instance: the Sleipner quantities of CO2 in saline aquifers, challenges for the profession. CEP
Project in Norway (18) has been and the U.S. storage capacity appears
Article continues with Literature Cited on next page
injecting 1 million m.t./yr of CO2 into very large, although, as mentioned
the Utsira Saline Formation since earlier, some technical issues still need
JAMES R. KATZER is an independent energy
1996 using a single well bore; Wey- to be resolved. A broad range of regu- consultant (P.O. Box 1346, Blue Hill, ME,
burn in Canada (19) has injected 0.85 latory issues, including permitting 04614; jrksail@comcast.net). A member of
million m.t./yr of CO2 into the Mid- guidelines and procedures, liability the National Academy of Engineering, he
serves on several National Research Council
vale reservoir for EOR since 2000; and ownership, monitoring and certifi- panels that are studying resource needs and
and In Salah (20) has been injecting cation, site closure, and remediation, commercial status of a range of energy tech-
1 million m.t./yr of CO2 into the water also require resolution. For CCS to be nologies to meet U.S. energy needs. As a
visiting scholar at the Massachusetts Insti-
leg of the gas field. available on a large scale, it is critical tute of Technology from 2004 to 2007, he
None of these projects have en- to gain political and public confidence was the executive editor/director of the MIT
countered any problems, and to date in the safety and efficacy of long-term study entitled, “The Future of Coal in a
there has been no sign of CO2 leakage. geologic storage of CO2. Carbon Constrained World” (6). Prior to that,
he was manager of strategic planning and
To resolve these issues and estab- program analysis for ExxonMobil Research
Key points lish CCS as a viable technology for and Engineering Co., and he held a succes-
About half of U.S. coal reseves managing CO2 emissions, it is neces- sion of technical and management positions
in Mobil Oil Corp. Before joining Mobil, Katzer
are bituminous coal, and half are sub- sary to establish three to five large- was a professor on the chemical engineering
bituminous coal and lignite. With scale (1 million m.t./yr CO2) CCS faculty at the Univ. of Delaware. He has
lower-rank coals and higher plant demonstration projects in the U.S. authored more than 80 publications in
technical journals, holds several patents, and
elevations, the gap between IGCC These projects should use different- has co-authored and edited several books.
and conventional PC combustion generation technologies, focus on He received a BS from Iowa State Univ. and a
with capture narrows. Cost improve- different geologies, and operate for PhD in chemical engineering from MIT.

CEP March 2008 www.aiche.org/cep S21


Literature Cited
1. Organization for Economic Cooperation and Development and 12. Electric Power Research Institute, “Long-Term Leaching Tests
International Energy Administration, “World Energy Outlook with Coal Gasification Slag,” Report No. GS-6439, EPRI, Palo
2006,” OECD/IEA, Paris (2006). Alto, CA (1989).
2. Energy Information Administration, “Emissions from Energy 13. Oskarsson, K., et al., “A Planner’s Guide for Selecting Clean-Coal
Consumption for Electricity Production and Useful Thermal Output Technologies for Power Plants,” World Bank Technical Paper No.
at Combined-Heat-and-Power Plants,” in “Electric Power Annual,” 387, World Bank, Washington, DC (1997).
EIA, www.eia.doe.gov/cneaf/electricity/epa/epa_sum.html (2007). 14. Tavoulareas, E. S., and J. P. Charpentier, “Clean Coal
3. Tollefson, J., “Countries with Highest CO2-Emitting Power Technologies for Developing Countries,” World Bank Technical
Sectors,” Nature, 450, p. 1 (2007). Paper No. 286, World Bank, Washington, DC (1995).
4. “Carbon Monitoring for Action,” www.carma.org. 15. Rutkowski, M. D., et al., “The Cost of Mercury Removal in an
5. BP, plc, “Statistical Review of World Energy 2006,” BP (2006). IGCC Plant,” Final Report prepared by Parsons Infrastructure and
6. Massachusetts Institute of Technology, “The Future of Coal: Technology Group for U.S. Dept. of Energy, National Energy
Options in a Carbon-Constrained World,” MIT, Cambridge, MA, Technology Laboratory (Sept. 2002).
http://web.mit.edu/coal/ (Mar. 2007). 16. Dooley, J. J., et al., “Carbon Dioxide Capture and Geologic
7. PowerClean Thematic Network, “Fossil Fuel Power Generation Storage,” A Technology Report from the Second Phase of the
State-of-the-Art,” PowerClean Thematic Network of the European Global Energy Technology Strategy Program, Battelle Memorial
Union Fifth Framework Energy R&D Programme, J. McMullan, Institute (Apr. 2006).
Chairman, Univ. of Ulster, Coleraine, U.K., pp. 9–10 (2004). 17. Intergovernmental Panel on Climate Change, “IPCC Special
8. Dillon, D. J., et al., “Oxyfuel Combustion Processes for CO2 Report on Carbon Dioxide Capture and Storage,”
Capture from Advanced Supercritical PF and NGCC Power Plants,” http://arch.rivm.nl/env/int/ipcc/pages_media/SRCCS-
Proceedings of the 7th International Greenhouse Gas Technologies final/IPCCSpecialReportonCarbondioxideCaptureandStorage.htm
Conference, Vancouver, BC (2004). (2005).
9. U.S. Environmental Protection Agency, “Continuous Emissions 18. Arts, R., et al., “Monitoring of CO2 Injected at Sleipner using
Monitoring System (CEMS) Data Base of 2005 Power Plant Time-Lapse Seismic Data,” Energy, 29 (9–10), pp. 1383–1392
Emissions Data,” U.S. EPA, Washington, DC (2005). (2004).
10. Thompson, J., “Integrated Gasification Combined Cycle (IGCC) 19. Wilson, M., and M. Monea M., eds., “IEA GHG Weyburn CO2
— Environmental Performance,” presented at Platts IGCC Monitoring and Storage Project Summary Report 2000–2004,”
Symposium, Pittsburgh, PA (2005). Proceedings of the 7th International Greenhouse Gas Technologies
11. Holt, N., “Preliminary Economics of SCPC and IGCC with CO2 Conference, Vancouver, BC (2004).
Capture and Storage,” presented at the Second International 20. Riddiford, F., et al., “Monitoring Geological Storage: In Salah Gas
Freiberg Conference on IGCC and XtL Technologies, Freiberg, CO2 Storage Project,” Proceedings of the 7th International
Germany (May 2007). Greenhouse Gas Technologies Conference, Vancouver, BC (2004).

DOE Restructures FutureGen to Emphasize Carbon Capture and Storage


he U.S. Dept. of Energy (DOE) recent- tional, will be the cleanest coal-fired ment. While hydrogen production is no
T ly announced the restructuring of its
FutureGen project — with a new focus
plants in the world. Each of these plants
will sequester at least one million metric
longer part of the the FutureGen project,
it remains an imporant component of
on demonstrating cutting-edge carbon tons of carbon dioxide annually and other DOE efforts.
capture and storage (CCS) technologies help meet our nation’s growing
at multiple commercial-scale integrated energy demand.” Financial backing
gasification combined cycle (IGCC) The plants that will be selected to President Bush’s propossed fiscal
clean-coal power plants. participate in the program would each year 2009 budget includes $648 million
Under this new strategy, DOE will generate at least 300 MW of electricity. for DOE’s Office of Fossil Energy. Of
support industry’s efforts to build IGCC (The exact number of plants will be that, $407 million would go to coal
facilities by providing funding for CCS at determined in the coming months, research, including development of
multiple plants that will be operational based on industy input regarding the more-efficient gasification and turbine
by 2015. Building on research and costs and feasibility of building clean- technologies, innovations for existing
development advancements in IGCC and coal facilities.) Together, these plants coal power plants, and large-scale CCS
CCS technologies achieved over the past will capture and sequester at least twice injection tests. The other $241 million
five years, this approach will allow the as much carbon dioxide annually as the would fund the demonstration of cost-
demonstration of IGCC-CCS clean-coal original FutureGen concept announced effective CCS technologies for coal-fired
technology in a more cost-effective way, in 2003. power plants, including $156 million for
to enable wider use and more-rapid FutureGen was conceived to create the restructured FutureGen project and
commercialization, according to DOE. one near-zero-emissions, 275-MW $85 million for the Clean Coal Power
U.S. Secretary of Energy Samuel W. power plant that would produce hydrogen Initiative. This represents a $129-million
Bodman remarks:“We are eager to and electricity from coal on a smaller- increase over FY2008, and is the largest
demonstrate CCS technology on than-commercial scale and would serve amount requested for DOE’s coal pro-
commercial plants that, when opera- as a laboratory for technology develop- gram in more than 25 years.

S22 www.aiche.org/cep March 2008 CEP

You might also like