You are on page 1of 17

 

Background

Disaster struck Uttarakhand’s Chamoli District on 7 February 2021, when a massive flash
flood ravaged through the valleys of the Rishi Ganga, Dhauliganga and Alaknanda rivers.
More than 7 0 p e o p l e h a v e b e e n c o n f i r me d d e a d a n d a n o t h e r 1 3 4 p e o p l e
r e p o rt e d mi s s i n g . The flood swept away the unfinished Tapovan Vishnugad Hydropower
Project and inflicted substantial damage on the Rishi Ganga Hydropower Project. Even as
rescue and relief efforts were underway, a glacial lake outburst flood (GLOF) was suggested
as the reason for the flood, possibly triggered by glacier collapse. Some reports even used
the term “glacier burst”, possibly referring to a GLOF. In the immediate aftermath of the
event, ICIMOD decided not to comment on the cause of the flood for two reasons. Firstly,
while understanding the cause is important to identify possibilities of similar hazards in this
and other areas, the priority in the first few days and weeks should be rescue and relief.
Secondly, as a regional knowledge institution, we felt it important to verify and corroborate
all available information to come up with a credible reason for the flood. Now, two weeks
after the event, we have adequate information to present our understanding of this flood
event. The purpose of this report is to share our understanding of the cause and
downstream propagation of the flood. The report also touches upon the cascading nature of
floods, the challenges to infrastructre development, and the need to consider environmental
sustainability while planning infrastructure development in fragile mountain environments.

Key messages

The Chamoli flood was not caused by a GLOF as there were no significant glacial lakes in
the area


The flood was triggered by a massive rockslide just below Ronti peak, of ~22 mio m of
rock mixed with ice and snow

The energy of the fall melted the ice creating the source of flood. This remobilized the
debris and ice on the valley floor deposited by previous events, pushed the stream water
and created an excessive flood wave.

A couple of days prior to this, a strong western disturbance resulted in heavy precipitation
in the area, which increased the flood magnitude downstream

Comprehensive monitoring of mountain environments is recommended

Infrastructure in the flood path, particularly hydropower projects, exacerbated the impact of
the flood. Infrastructure development in fragile mountain environments should consider a
sustainability framework, including environmental sustainability

2. General description of the area


The flood event took place in the Tapovan area of Joshimath in Chamoli District,
Uttarakhand State. The region consists of high mountain ranges with steep topography,
including the second highest peak in India, Nanda Devi (7816 masl; Fig. 1). The mountain
ranges are made up of h i g h g ra d e me t a m o r p h i c a n d v o l c a n i c r o c k s . The Lower
Himalaya Range to the south is composed of sedimentary and low-grade metamorphic
rocks. The Chamoli flood occurred in an area about 60 km northeast of where the
devastating U t t a ra k h a n d f l a s h f l o o d o c c u rr e d i n 2 0 1 3 . The Chamoli flood took place
on the Rishi Ganga River on the northern side of Nanda Ghumti peak (7050 masl). The
Rishi Ganga is a tributary of the Dhauliganga River, which originates from the Raikhana
Glacier (5375 masl) to the north and meets the Alaknanda River further downstream. The
high-altitude area consists of glaciers and snow peaks which melt during the spring and
summer season and provide meltwater to downstream areas. Because of the perennial
sources of water and steep topography, hydropower plants have been constructed across
many tributaries. Presently, about 3900 MW of hydroelectricity is generated in Uttarakhand,
out of its estimated hydropower potential of 20,000 MW (Agrawal et al. 2017), with
several u n d e r c o n s t ru c t i o n p ro j e c t s e x p e c t e d t o a d d a n o t h e r 3 2 0 0 MW .
Figure 1: (a) Location map showing rockslide origin and flood path along the Ronti Gad,
Rishi Ganga, Dhauliganga and Alaknanda rivers. (b) Longitudinal profile of flow path
including rockslide source area.
Figure 2: Average monthly temperature and precipitation of the area (1980-2019). Data
source: ERA5 reanalysis

The climate of the area is characterised by warm-wet summers (June-September) and cold-
wet winters (December-February). The difference between average monthly maximum and
o
minimum temperature is about 20  C, which is higher in the winter season compared to
summer (Fig. 2). The area receives precipitation from both westerlies and the summer
monsoon, with annual average precipitation around 1000 mm; of this, winter precipitation
due to western disturbances contributes 28% and summer precipitation 42%.

3. The source of the flood

Figure 3: 3D view of the origin of the rockslide and the debris flow captured on a satellite
image (CubeSat) at 10:30 IST, just before it reached the Tapovan Hydropower Project site
(dotted black line shows the sediment deposited on the adjacent slopes of the river valley).
The release zone of the rockslide is marked in red.
Figure 4: Pre (left) and post (right) event images showing scarp of the rockslide origin and
its sliding surface along the joint plane, including directly impacted and sediment deposited
area along the Ronti Gad River valley. The rockslide has an approximate width of 550 m at
the upper edge at 5,500 masl (Images from Maxar portal accessed through the USAID
SERVIR Programme; the post event image is from 10 February 2021).

a. Initial suggestions about the flood and counter arguments

As news and videos of the debris flow that hit the Tapovan Hydropower Project site around
10:30 IST on 7 February surfaced, i n i t i a l s u g g e s t i o n s w e r e t h a t a g l a c i a l l a k e
m u s t h a v e b u r s t . As the upstream areas from the location of the first videos were
investigated, it quickly became clear that no lakes were present in the catchment prior to
the event. Some m e d i a o u t l e t s e v e n c a l l e d i t a “g l a c i e r b u r s t ” , a term not
recognized by the scientific community. As the first high resolution images (taken by
coincidence just as the debris flow passed the valley; see Figure 3) became available,
approximately 7 hours after the event, it was clear that an avalanche, landslide or rockfall
had happened approximately 22 km upstream of the hydropower site, just below Ronti peak
in the Nanda Devi massif. The location of the source was clearly identifiable from the
imagery (Figure 3) while no other source (flood paths, emptied lake, or avalanche scour)
could be identified.
b. What we now think is the source of the flood

Based on available imagery and relying on published data, we are able to make
approximate calculations of the mass movements that have taken place. We examined pre-
and post-event imagery and found that a crack had formed prior to the event (Fig. 4 and 5)
at the site where the rock detachment followed by a rockslide happened (Fig. 4). This
failure eventually propagated along a 550 m wide crest starting at an elevation of 5500
masl reaching down to nearly 4500 masl. Analysis of e l e v a t i o n m o d e l s p re - a n d p o s t -
e v e n t  suggests that the scarp left by the rockslide is 150 m deep, 100 m on average and
consists largely of rock and relatively little ice (Fig. 4). It is 39° steep, 1060 m long and
2 3
has an area of ~350,000 m . This results in an approximate volume of 22 mio m , which
3
corresponds with the DEM differencing that puts it at 25 mio m . Relying on modelled
glacier thickness (21 to 25 m for the three glacierettes in the inventory, which corresponds
to typical heights of such hanging glaciers; Farinotti et al. 2019), we can estimate the

fraction of rock to be 85% and ice 15% and calculate a total mass of ~52 * 10 kg. With a
straight slide line of 1.6 km (5500 to 3900 masl), this results in total potential energy of
14
8.24 * 10  J.  This energy is converted to kinetic energy during the fall and dissipated as
6 3
enough heat to melt 2.7 * 10  m  of ice (with 335 kJ per kg of ice necessary at 0 °C).
Considering that not all the mass was converted into energy during the fall, this number is
likely a lot lower (Huggel et al. 2005). As Huggel et al. (2005) argue and has been
conclusively shown in experiments (Arakawa 1999) and for a large co-seismic event
(Eberhart-Phillips et al. 2003), fluidization can also happen simply from a very large impact
on present ice, which possibly happened in this case.
Fig 5: A crack is visible at the top of the failure zone on 6 February, one day before the
event. There is substantial snow on 6 February, but much of this had melted by 10
February, three days after the event.

6 3
During an ice avalanche in 2016, a volume of ~7.2 * 10  m  of ice was dislodged to the
west of the rockslide in 2021, taking bed rock with it along the way, resulting in a mixed
7 3
ice-debris deposit of ~1.5 * 10  m . Sentinel-2 Imagery from 2 December 2020, when the
area was not snow covered yet, shows that a large part of this deposit was still present in
the valley below when the event on 7 February 2021 happened (Fig. 6). In a similar case
in Langtang Valley in Nepal, a co-seismic avalanche resulted in a large compound deposit
of ice, snow, and debris. As debris settles on top during the fall (as in the case here), ice
was protected from melt by a debris layer of several metres thickness (Fujita et al. 2017;
Kargel et al. 2016). A big part of the ice body is still present in Langtang even today,
nearly 6 years later. As some of this ice body was still present just after the event below
Ronti peak in 2021 (Fig. 5), we can conclude that a fraction of this previous deposit (< 7.2
6 3
* 10  m ), was fluidized by the available energy. There are also reports from observers of
the event of a pungent smell, suggesting w a t e r - s a t u ra t e d s e d i me n t s w e r e mo b i l i s e d
and added to the fluid content of the debris flow.

Figure 6: Location of the impact site of both the 2016 and 2021 events, on an image from
10 February 2021. On the right, between two small lakes, a body of ice is still visible
covered in fresh debris. Note that the tongue of this glacier is many hundreds of metres
upstream and therefore this ice is not connected to the main glacier body in the valley.

From the 200 to 400 m high surge of debris (h) on the adjacent headwalls below, we can
-1
estimate the velocity of the fall at between 60 and 90 m s  (Chow 1959; Evans et al.
2001, 1989; Pierson 1985). Assuming an average velocity for the resulting debris flow of
-1 
~20 m s the debris flow took about 18 minutes to reach the Tapovan Hydropower Project
3 -1
site and was able to move ~1000 m  s  of water, assuming that only 75% of the energy
from the rockslide was used to fluidize the deposited ice below. This would explain to a
large part, how such a strong flood wave was able to reach downstream areas without a
previous body of water being present.

c. What triggered the rockslide?


i. Precedent weather conditions A strong western disturbance passed across Kashmir and
northwest India from 4 to 6 February 2021. It was fully charged with convective instability
that may have contributed to the heavy precipitation. This unfortunate event occurred on 7
February. Numerical simulation of some of the attributes have been carried out which depict
strong evidence of heavy precipitation contributing to high flows downstream. The analysis
of wind pattern and geopotential height contours at 500hPa level indicate that the trough of
an active westerly wave was passing over Kashmir and northwestern latitudes of India with
a strong vorticity and convergence combination at the leading edge of the westerly. The
trough of this western disturbance showed great potential of convective instability as severe
Convective Available Potential Energy (CAPE) conditions were found on the rear end of the
low pressure area. The numerical simulation on 4 February is presented in Figure 7 which
shows heavy precipitation over that region. The western disturbance travelled with relatively
slower speed and its stagnancy produced concentrated precipitation.

Figure 7: Precipitation on 4 February, 18:00 UTC (Source: WRF – 5 km numerical simulation


by Pa k i s t a n M e t e o ro l o g i c a l D e p a rt me n t )

Precipitation data derived from Global Precipitation Measurement (GPM) Mission suggests
that there were continuous precipitation events from 3 to 5 February which resulted in
approximately 58 mm of cumulative precipitation(Fig. 7). Most of the precipitation in the high
altitude areas of Chamoli would have occurred as snowfall.

ii. Climate change

o
Maximum temperature in the Chamoli area has increased at the rate of 0.032  C per year
between 1980 and 2018 which is statistically significant at 99.9% confidence level,
o
compared to minimum temperature which has increased at 0.024  C per year at 90%
confidence level (Fig. 8).The trends were analysed using Mann–Kendall (MK) and Sen slope
estimation (Kendall 1975; Mann 1945; Sen 1968). Furthermore, January 2021 was the
warmest January on record in Uttarakhand for six decades. Note also the dramatic reduction
in snow cover between 6 and 10 February as shown in Figure 4. While a hazard event like
the flood at Chamoli cannot be directly attributed to climatic changes, the i n c re a s e d
t h a w - f re e z e c y c l e o f p e rm a f ro s t c o u l d h a v e p a rt i a l l y c o n t ri b u t e d t o t h e
event.

Figure 8: Maximum temperature trends in the Chamoli area (Data source: ERA5 reanalysis
data, 1980-2019).

iii. Other factors

At the same headwall, a large ice avalanche was previously released somewhere between
7  3
19 September and 9 October 2016, which deposited ~1.5 * 10 m  of ice and more bedrock
in the valley below (Figure 9). The resulting destabilization of the rock due to the lack of
ice cover (glacial debuttressing, stress-release fracturing), and increased exposure to solar
radiation and hence an increased freeze thaw cycle, in combination with a large snowfall
event preceding the event of 7 February 2021 and rapid melt water production, may have
favoured the fracturing of rock. This can however not explain the depth of the fracture
(~150 m), which must have evolved over a longer period of time. Fracture zones at the
runout of the rockslide visible before the event suggest that such detachments have
happened at the same location previously. Permafrost thaw and frost cracking has been
used to explain increased rockfall activity in the Alps (Deline et al. 2015; Gruber and
Haeberli 2007); however, that generally only applies for the first ~10 m of bedrock.
As the debris moved downstream, it p u s h e d ru n n i n g ri v e r w a t e r a h e a d o f i t ,
i n c l u d i n g w a t e r f ro m s m a l l p o n d i n g s t ru c t u re s a l o n g t h e r i v e r p a t h .  Besides,
the water stored in the 60 metre long diversion dam of the Rishi Ganga Hydropower
Project, including in its desilting chamber, should also have contributed to the flood water
which was seen before the debris flow in the videos posted on social media.

4. Cascading impacts and environmental sustainability

The event and related debris flow/flood caused damage to four hydropower projects a l o n g
t h e R i s h i G a n g a , D h a u l i g a n g a a n d A l a k n a n d a r i v e r p a t h  (Table 1). The Rishi
Ganga Hydropower Project (13.2 MW) near Raini village, located 14 km downstream from
the impact site (Figure 10), was the first to be hit by the debris after the rockslide. The
unfinished Tapovan Vishnugad Hydropower Project (520 MW) (Fig. 11), 8 km downsteam
from Rishi Ganga Hydropower Project, was the second hydropower plant hit by the flood.
The diversion dam of this run-of-the river type project faced massive damage from
sedimentation and the dam was filled with debris, which can be seen in the remote sensing
images taken before and after the event (Fig. 10 and 11).

Figure 10: Pre and post images from the MAXAR portal shows the Rishi Ganga
Hydropower Project and bridge 700 m downstream of the hydropower site completely
washed away (Images accessed through the USAID SERVIR Programme; the post event
image is dated 10 February 2021)
Figure 11: Tapovan Vishnugad Hydropower dam site before and after the flood (10 February
2010). The dam is fully covered by debris. (Images accessed through the USAID SERVIR
Programme)

Table 1: Hydropower projects affected by the Chamoli flood

S Name (Latitude, Capacity (status) Dis


N longitude) (km

1 Rishi Ganga Hydropower Project 30.478, 79.699 13.2 MW (Operational) 14

2 Tapovan Vishnugad Hydropower Project 30.493, 79.628 520 MW (Under 22


construction)

3 Vishnuprayag Hydro Electric Project (Jaypee 30.566, 79.547 400 MW (Operational) 35


Group)

4 Vishnugad Pipalkoti Hydro Electric Project 30.433, 79.424 444 MW (Under 55


construction)

As highlighted by the IPCC 2019 report (Hock et al. 2019), the mountainous regions are
exposed to many cryosphere-related hazards. The frequency, magnitude and areas of these
hazards are projected to change as the cryosphere continues to decline. The escalation of
cascading hazards to a cascading disaster is a common phenomenon observed in the
Hindu Kush Himalaya region (Cutter 2018; Vaidya et al. 2019). One of the prominent recent
examples is the Uttarakhand flood of 2013, which started with heavy rainfall and caused a
chain of events including landslides, flash floods, and the Chorabari lake outburst and debris
flow, which killed more than 6,000 people and damaged roads, bridges, and buildings (Allen
et al. 2016; Ray et al. 2016). Similar hazard events or in combination with other
geophysical processes can damage several hydropower stations, which can be further
exacerbated with future floods in the context of global climate change (Nie et al. 2021).
Hock et al (2019) also suggest that snow avalanches involving wet snow even in winter will
occur more frequently in the mountainous regions. Nie et al. (2021) reported 105 existing
hydropower projects (HP) (≥ 40 MW) with an installed capacity of 37 GW, 61 projects (≥40
MW) currently under construction (39 GW) and 890 projects (≥10 MW) in various stages of
planning (242 GW) in the Karakoram-Himalaya region. Most of the existing hydropower
projects were built in the past two to three decades, mainly starting from the downstream
sections. Now these projects are gradually moving upstream where the exposure to
mountain hazards is high, the chances of multiple hazards happening in combination and
occurring more frequently, and cascading effects can create compounding impacts on the
system. Hydropower projects are particularly at risk because of the proximity of their
infrastructure (such as diversion dams/reservoirs) to the river network where water-related
hazards occur (Kumar and Katoch 2016). Many hydropower projects have been damaged by
events like the Chamoli flood. For example, the Dig Tsho 1985 GLOF event in the Everest
region, the 2015 earthquake, the 2014 Jure landslides, the 2013 Uttarkhand flood, and the
2016 Bhote Koshi GLOF (Nepal) damaged hydropower plants in Nepal and India (Vaidya et
al. 2021). Conversely, hydropower infrastructure also impacts the local environment, causing
changes in natural flow regimes and environmental flows, alteration of aquatic ecosystems,
and deterioration of water quality, among others.

5. Conclusion and recommendations

The rockslide-triggered flash flood in Chamoli is one of many possible hazards in the HKH
mountains. Mountain hazards like glacial lake outburst floods, torrential floods, debris flows,
landslides, and avalanches, especially caused by the coupling of avalanches, glacier
movement, snow melt, and extreme precipitation are common in this region. While this
event cannot be directly attributed to climate change, it is well known that climate change
can lead to increase in the frequency and severity of mountain hazards (Krishnan et al.
2019; Vaidya et al. 2019; Hock et al. 2019). It is necessary to carry out quantitative studies
on the status of mountains, understand their formation mechanism, and monitor dynamic
processes in order to have advance knowledge of impending hazard events and improve
preparedness. These should be done through ground based research, analysis of geospatial
information, and modelling. All these need sustained investments from national agencies
including establishment of environmental monitoring, analysis and information systems.
Collaborative efforts between institutions within the region and with international institutions
can help in building robust systems and capacity within the region. The HKH is a multi-
hazard environment. Often these hazards are of a cascading nature with multiple hazards
interconnected with a primary hazard trigger and a chain of secondary and tertiary hazards.
Human interference in the mountain environment is rapidly increasing. Mountain settlements
are increasing in size and land use patterns are changing. Infrastructure such as roads and
hydropower projects are rapidly penetrating mountain landscapes. The interplay between
natural hazards with human settlements and infrastructure is an important aspect, which can
significantly escalate the impacts of event like the Chamoli flood. Disaster risk management
therefore needs to incorporate a multi-hazard risk assessment approach. In the aftermath of
recent disaster events, the role of infrastructure, especially hydropower and its interplay with
natural hazards has emerged as a topic of strong debate. These events have raised the
question: Is hydropower a boon or bane? With the need to green the energy sector and the
challenges with solar and wind energy, hydropower seemed to be a viable option. However,
hydropower development faces multiple challenges. Apart from financial and technical
challenges, it faces strong environmental and social challenges. On the environmental front,
hydropower development impacts environmental flows, water quality, and the health of
aquatic and terrestrial ecosystems. At the same time the physical environment poses many
challenges to hydropower development and sustainability. Climate change related flow
variations, extreme events, erosion and sedimentation, and GLOF/LDOFs, are some of the
environmental challenges to hydropower. A comprehensive sustainability  framework
considering financial, environmental and social sustainability can help make hydropower a
viable energy option. Vaidya et al. (2021) argue that for the sustainability of hydropower in
the HKH region, environmental threats need to be minimized by mitigating risk through both
structural (e.g. erosion protection work) and non-structural measures (e.g. operating rules).
Besides this, mitigating the risk of climate change and flow variability is of paramount
importance for future energy security for which a better understanding of future climate
projections and water availability is needed. That understanding can be reflected in the
design and location consideration of future hydropower projects in the region.

Acknowledgement:
(This report benefited significantly from discussions with national and international experts,
and particularly with colleagues in GAPHAZ – Glacier and Permafrost Hazards in Mountains,
a scientific standing group of the International Association of Cryospheric Sciences and
International Permafrost Association).

You might also like