BASIS OF COSTING FOR STATIC EQUIPMENT & PIPING

BASIS OF COSTING DATE EFFECTIVE FROM : 10/02/2022


REVIEW OF BASIS OF COSTING ON : 10/03/2022
BASIS OF COSTING FOR STATIC EQUIPMENT & PIPING
S. No. Item Description Particulars Unit Cost Remarks
1 Pressure Vessel (Shop Material supply & Fabrication cost for SA 516 Rs.110/kg (CS Flange) Note - 1 &
Fabricated) Gr 70 (excluding Rubberlining & Painting) Rs.120/kg (Forged Note - 4
WNRF Flange)

2 a) Atmospheric Tanks - Vertical Material Supply & Fabrication cost for IS 2062 Rs.85/kg (CS Flange) Note - 1 &
(Shop Fabricated) Gr. B (excluding Rubberlining & Painting) Rs.90/kg (Forged Note - 4
WNRF Flange)

2 b) Atmospheric Tanks - Material Supply & Fabrication cost for IS 2062 Rs.95/kg Note - 1 &
Horizontal (Shop Fabricated) Gr. B (excluding Rubberlining & Painting) Note - 4

2 c) Atmospheric Tanks - Material Supply & Fabrication cost : Shell - IS Rs.105/kg Note - 1 &
Horizontal (Shop Fabricated) 2062 Gr. B & Dish - BQ Plate (excluding Note - 4
Rubberlining & Painting)
3 DG Tower (Shop Fabricated) Material Supply & Fabrication cost for IS 2062 Rs.85/kg Note - 1 &
Gr. B (excluding Rubberlining & Painting) Note - 4

4 a) Site Fabricated Tanks Material - IS 2062 Gr. B : Supply + Fabrication Rs.95/kg Note - 2,
+ Erection + Power Charges + Hydro Testing + Note - 4 &
Transportation charges to Paint yard (excluding Note 7
Rubberlining & Painting)
4 b) Site Fabricated Tanks (PWHT Material - SA 516 Gr.60 - Supply + Fabrication Rs.105/kg Note - 3,
Tank) + Erection + Power Charges + Hydro Testing + Note - 4 &
Transportation charges to Paint yard (excluding Note 7
PWHT & Painting)
5 a) Rubber lining (4.5 mm thick) Pressure Vessel / Shop & Site fabricated Tanks Rs. 2200/m2- to 2500/m2- Note - 5
depending on vendor and
location
5 b) Rubber lining (3.0 mm thick) Piping (Shop Lining) Rs. 1800/m2- to 2000/m2- Note - 5
depending on vendor and
location
6 Painting (External) As per tender spec To be checked case to Note - 6
case basis
7 Painting (Internal) As per tender spec To be checked case to Note - 6
case basis
8 SS 304 / SS 304 L / SS 316 / As the Nickle Price is not firm, there are - -
SS 316 L Material fluctuation in the market price, kindly get the
quote from the vendor and also shall be
discussed regarding Trend.
9 a) CS Pipes & Fittings Fabrication - Site Rs. 150/Inch-Dia Note - 7
9 b) CS Pipes & Fittings Laying - Site Rs. 70/Inch-Dia-m Note - 7
10 a) SS 304 Pipes & Fittings Fabrication - Site Rs. 350/Inch-Dia Note - 7
10 b) SS 304 Pipes & Fittings Laying - Site Rs. 70/Inch-Dia-m Note - 7
11 a) SS 316 Pipes & Fittings Fabrication - Site Rs. 400/Inch-Dia Note - 7
11 b) SS 316 Pipes & Fittings Laying - Site Rs. 70/Inch-Dia-m Note - 7
12 Super Duplex Pipes&Fittings Fabrication - Site Rs. 750/Inch-Dia Note - 7
Notes :
1 GST & Transportation charges are Extra for the Vessels / Tanks. Rs. 10 to Rs. 12 shall be added for Normalisation /
Stress relieving of Pressure vessels, where ever applicable for Pressure Vessels.
2 Normally we will supply the Plates to Fabricator at site.Transportation charges of Steel Plates are included in this cost.
The basis is made as, Rs. 60/kg (for supply) and Rs. 35/kg (for Fabrication, erection, Power charges, Hydro testing,
Transportation charges to Paint Yard). GST is excluded in this rate.
3 Normally we will supply the Plates to Fabricator at site. Transportation charges of Steel Plates are included in this cost.
The basis is made as, Rs. 67.5/kg (for supply) and Rs. 37.5/kg (for Fabrication, erection, Power charges, Hydro
testing, Transportation charges to Paint Yard). For PWHT of Tank, separate quote has to be got from Vendors and the
same shall be included extra along with Diesel cost and additional Structural support (to raise the tank from foundation
for PWHT) & Lifting cost of tank. GST is excluded in this rate
4 The Weight basis rate mentioned above are applicable on the FINISHED WEIGHT (mentioned in GA
Drg.) of Pressure Vessel & Storage Tank.
5 Supply and Application charges (excluding GST) are included in this price.
6 Details are to be worked out and shall be made ready for some repeated cases.
7 The Site rates are for normal sites. Suitbale provision should be made for difficult sites.