Professional Documents
Culture Documents
Sector: CONSTRUCTION
Qualification Title: CARPENTRY NC II
Unit of Competency: STRIP FORMWORKS COMPONENTS
Module Title: STRIPPING FORMWORKS COMPONENTS
RYDEN INTERNATIONAL TECHNOLOGICAL INSTITUTE
(R.I.T.I), INC.
Zone 2 San Agustin, Canaman, Camarines Sur
Remember to:
Work through all the information and complete the activities in each
section.
Read information sheets and complete the self-check. Suggested
references are included to supplement the materials provided in this
module.
Most probably your trainer will also be your supervisor or
manager. He/she is there to support you and show you the correct way to
do things.
You will be given plenty of opportunity to ask questions and practice
on the job. Make sure you practice your new skills during regular work
shifts. This way you will improve both your speed and memory and also
your confidence.
Use the Self-checks, Operation Sheets or Job Sheets at the end of
each section to test your own progress.
When you feel confident that you have had sufficient practice, ask
your Trainer to evaluate you. The results of your assessment will be
recorded in your Progress Chart and Accomplishment Chart.
You need to complete this module before stripping formworks
assigned to you.
NOMINAL DURATION :
CERTIFICATE LEVEL : NC II
PREREQUISITE :
LEARNING OUTCOMES:
Upon completion of this module, the trainee/student must be able to:
ASSESSMENT CRITERIA
• Work instruction is secured from immediate superior according to company rules
and regulations.
• Appropriate PPE is selected and used according to job requirements and OSHC
specifications.
• Formwork components and accessories staging area is identified and
prepared based on job requirements.
• Formwork components power, hand tools and equipment are selected
and prepared consistent with job requirements.
• Unexpected situations are responded to in line with company rules and
regulations.
• Housekeeping is performed according to safety regulations.
CONDITIONS:
You must be provided with the
following:
1. WORKPLACE LOCATION
2. TOOLS AND EQUIPMENT
Crow bar Hard hat
Claw Hammer Hard shoes
Pliers Goggles
Wrench Gloves
Shovel Circular Saw
Scaffolding
3. TRAINING
MATERIALS Leaning
Packages Bond
paper
Ball
pens
Manuals
Related References
ASSESSMENT METHOD
Portfolio
A. Introduction
Stripping formwork can be one of the most hazardous phases of
concrete construction. While falling objects are the primary hazard, there
may also be fall hazards as a result of floor collapse and manual tasks
hazards from a person working in awkward postures, repetitive handling of
materials and limited task variety. As with formwork erection, the stripping
operation must be carried out in an orderly, progressive manner.
B. Exclusion zone
Only persons involved in the stripping operation should be permitted in
the area to be stripped. Stripping are as should be cordoned off and signs
should be displayed. The signs should require persons to keep out of the
area.
Danger
FORMWORK STRIPPING IN PROGRESS
AUTHORISED PERSONS ONLY
The period for which forms should be left in place depends upon the
temperature of air, the shape and position of structural member (i.e.
horizontal vertical or inclined), the nature of the loads likely to come and
the character of the cement and cement paste. Generally, the use of rapid
hardening cement, higher temperatures, low water cement ratio and
lighter loads, will permit early removal of formwork.
Under normal conditions where temperature is above 20ºC and
ordinary cement is use, forms may be removed after the expiry of the
period given below:
COLUMN A
Particulars of the structural COLUMN B
member Period of removing of
formwork
1. Slabs (props or vertical
supporting member left under) A. 24 – 28 hours
2. Bottom of beams over 6 m
span and bottom of arch ribs over 6 B. 3 days
m span
3. Bottom of slabs above 4.5
m span, bottom of the beams up to C. 5 days
6 m span, and bottom of arch ribs
up to 6 m span
4. Beams soffits (props left
under) D. 7 days
5. Vertical slides of
slabs, beams columns and E. 14 days
wall
6. Bottom of slabs up to a F. 21 days
span of 4.5 m.
Check your answer with the answer key below. If you fail to get it
right, refer back to corresponding resources until you make it perfect.
1. B
2. F
3. E
4. D
5. A
6. D
ASSESSMENT CRITERIA
• Formwork components and accessories are removed carefully,
safely and sequentially.
• Formwork components and accessories are sorted, arranged
and properly staged according to company rules and
regulations/manufacturer's recommendations.
• Formwork components and accessories are cleaned, oiled and
stored according to company rules and
regulations/manufacturer's recommendations.
• Formwork components and accessories, which are beyond
repair, are discarded otherwise repaired in accordance with
company rules and regulations.
• Unexpected situations are responded to in line with company
rules and regulations.
• Housekeeping is performed according to safety regulations.
CONDITIONS:
You must be provided with the
following:
1. WORKPLACE LOCATION
2. TOOLS AND EQUIPMENT
Crow bar Hard hat
Claw Hammer Hard shoes
Pliers Goggles
Wrench Gloves
Shovel Circular Saw
Scaffolding Brooms
3. TRAINING MATERIALS
Portfolio
B. Striking
The specification will normally give guidance on when forms can be
struck and these times may be governed by the size and shape of the
member, the concrete mix, and the weather.
• To strike the wallform, ties and clamps should be loosened
gradually, a little at a time.
• To remove the props, release the props evenly in small stages
starting at the middle of the span and working out towards the
supports. This can avoid overloading of the props at the centre of
the span due to large deflection at the center.
• Always withdraw or hammer down projecting nails as the
formwork is struck from the concrete.
• Make sure that other trades are kept away from areas below those
where striking is being done.
Note:
a. Always observe safety measures because stripping form is a
very dangerous work on the part of the worker. Be careful
in removing the forms because the materials and fresh and
concrete output when get damaged won’t be used again.
b. Remember that the fresh concrete can already carry its weight
after 24-48 hours or more from the pour of the concrete.
3. Remove braces
4. Remove the cleats
5. Remove/pull out nails used in the 4 sides forms with the use of
claw hammer, claw bar or pincer.
6. Remove tie/wires or bolts with the use of pliers or wrench.
7. Make a soft hammer strike on the form to loosen it from the
concrete.
Assessment Method:
Performance Criteria Checklist
CRITERIA YES NO
1. Were I able to stripped without damage to forms
or concrete?
Provision must be made for the removal and storage large sections of
formwork. A level storage area is required to store formwork after striking.
They should be well cleaned before storing because the grout remaining
on the forms will become hard and stubborn making it difficult to reuse.
Metal panels need a light coating of oil before storage to prevent rust.
All forms need to be carefully stacked and stored. Panels of forms
should be kept horizontal and face to face. The forms and components
should be clearly marked and kept together for easy identification on re-
use. A tidy store reduces wastage, damage and losses.
Cleaning
As soon as the formwork has been struck, it should be cleaned, not left
until it is wanted again.
• Timber and plywood forms should be cleaned with a stiff brush to
remove any grout; a timber scraper should be used for
stubborn bits of grout.
• With glass reinforced plastics, a brush and wet cloth are all that
should be needed.
• When steel forms are to be put in store or are not going to be
used for some time, they should be lightly oiled to prevent
rusting.
• Timber and untreated plywood should also have a coat of release
agent applied for protection if they are not going to be re-used
immediately.
• Any depressions, splits and nail holes should be repaired with
plastic wood or similar material, followed by a light rubbing down.
• Before concreting, the insides of the forms should be cleaned.
Where the forms are deep, temporary openings should be
provided for inspection.
1. Clean timber and plywood forms with a steel brush to remove any
grout; a timber scraper should be used for stubborn bits of grout.
2. Apply release agent to timber and untreated plywood for protection
if they are not going to be re-used immediately.
3. Repair any depressions, splits and nail holes with plastic wood or
similar material, followed by a light rubbing down.
4. Keep panels horizontal and face to face when storing.
5. Mark the forms and components for easy identification on re-use.
Assessment Method:
Performance Criteria Checklist
CRITERIA YES NO
1. Did I clean the timber and plywood forms from
stubborn grout?
ASSESSMENT CRITERIA
• Appropriate PPE is selected and used according to job requirements
and OHSA specifications.
• Formworks components are shored and re-shored in accordance
with stripping procedures.
• Shores are removed in accordance with standard dismantling
procedures.
• Shores, tools and equipment are cleaned, maintained and stored
properly according to company rules and regulations.
• Unexpected situations are responded to in line with company rules
and regulations.
• Daily report is accomplished according to company rules and
regulations.
CONDITIONS:
You must be provided with the
following:
1. WORKPLACE LOCATION
2. TOOLS AND EQUIPMENT
Crow bar Hard hat
Claw Hammer Hard shoes
Pliers Goggles
Wrench Gloves
Shovel Circular Saw
Scaffolding Brooms
3. TRAINING
MATERIALS Leaning
Packages Bond
paper
Ball
pens
Manuals
Related References
ASSESSMENT METHOD
Portfolio
Check your answer with the answer key below. If you fail to get it
right, refer back to corresponding resources until you make it perfect.