Professional Documents
Culture Documents
GD/SP/NDT/2
Issue Date: December 2019
This document is a reference document within the company Safety Case, all changes to this
document shall be notified to the Head of SHES before any changes are initiated.
GD/SP/NDT/2
2 of 47 GD/SP/NDT/2
Version Control
Implementation date
December 2019
Review date
February 2022
Document owner
Engineering
Management approval
Head of Engineering
Disclaimer
This safety and engineering document is provided for use by Cadent Gas Limited and such of its contractors as
are obliged by the terms and conditions of their contracts to comply with this document. Where this document is
used by any other party it is the responsibility of that party to ensure that this document is correctly applied.
Document History
December 2019
GD/SP/NDT/2 3 of 47
Comments and queries regarding the technical content of this document should be directed to:
Cadent
Ashbrook Court
Prologis Park
Central Boulevard
Coventry
CV7 8PE
December 2019
4 of 47 GD/SP/NDT/2
Contents
1. Scope ................................................................................................................................5
2. References ........................................................................................................................5
3. Definitions ..........................................................................................................................5
4. Destructive Testing ............................................................................................................5
5. Non-Destructive testing method .........................................................................................5
6. Personnel Qualification ......................................................................................................6
7. Non-Destructive Testing of Procedure Test Welds .............................................................7
8. Non-Destructive Testing of Production Welds ....................................................................7
9. Radiographic Examination .................................................................................................9
10. Manual Ultrasonic Examination of Welded Joints .............................................................13
11. Automatic or Phased Array Ultrasonic Examination .........................................................15
12. Magnetic Particle flaw Detection ......................................................................................15
13. Dye penetrant Flaw Detection ..........................................................................................16
14. Non-Destructive Testing of repaired Production Welds ....................................................16
15. Records ...........................................................................................................................17
Appendix A - References .......................................................................................................18
Appendix B - Management of Site Radiography ....................................................................19
Appendix C - Site Radiation Safety Monitoring Checklist and Report Sheet ..........................28
Appendix D - Requirements for Automatic Ultrasonic Inspection ...........................................31
Appendix E - Requirements for Manual Phased Array Ultrasonic Inspection .........................41
December 2019
GD/SP/NDT/2 5 of 47
1. Scope
1.1. This specification details the requirements for non-destructive testing of welded joints
in carbon, carbon manganese and stainless steel materials specified for use on the
company network only.
1.2. Where National or International standards referenced in this document require
specific items to be agreed between the contracting parties the requirements of this
specification shall apply.
1.3. This specification is not intended for the revalidation of welded joints in pressure
containing components. In such cases reference to GD/PM/NDT/1 should be made.
Where non-destructive testing alone cannot confirm that a welded joint fully meets
the acceptance criteria of a qualified welding procedure. Additional destructive testing
may be needed to prove that the requirements of the appropriate welding standard or
specification have been met.
2. References
2.1. This Specification makes references to the documents listed in Appendix A. Unless
otherwise specified, the latest edition of the documents apply, including all
amendments.
3. Definitions
3.1. For the purpose of this specification the terms and definitions used in BS EN 1330
shall apply.
Dressing: Light grinding in the weld area where the parent pipe or fitting is not
reduced in wall thickness below the minimum allowed by the relevant
specification.
4. Destructive Testing
4.1. The Employer reserves the right to require the complete removal of production welds
to confirm the results of Non-Destructive Testing and to prove that the mechanical
properties of the weld conform to specification criteria. Destructive testing shall
consist of the removal of complete welds for mechanical testing in accordance with
the appropriate welding standard or specification.
December 2019
6 of 47 GD/SP/NDT/2
criteria on length but could prove detrimental to the weld integrity due to the through
wall extent of that defect.
5.3. When the GD/SP/P/2 workmanship defect acceptance criteria is applied in
conjunction with automated ultrasonic testing (AUT) or semi-mechanised (MPA)
ultrasonic system, due cognisance shall be taken of the ability of the AUT system or
semi-mechanised ultrasonic system to estimate the through wall extent of a defect.
Even though a defect appears to meet the acceptance criteria on length the
Employer reserves the right to reject the defect due to excessive depth
5.4. Operators of all types of non-destructive testing equipment should be required to
demonstrate to the approval of the Employer the capability of the equipment and
examination procedure to detect flaw indications. The operator may be asked to
demonstrate their ability to make correct interpretation of defect indications given by
the equipment.
5.5. Welds shall be examined in the as-welded, or post weld heat treated condition
(PWHT), as applicable. If the weld has been subject to PWHT the non-destructive
testing shall follow this treatment.
5.6. Local dressing of the weld reinforcement may be required to confirm transverse
indications. Where local dressing is used to aid the interpretation of non-destructive
testing or to confirm defect indications, care shall be taken to maintain the material
minimum design thickness.
6. Personnel Qualification
6.1. Personnel performing non-destructive examination in accordance with this
specification shall be qualified. The qualification shall be to the appropriate grade(s)
in the TWI BGAS approval scheme. The Employer may consider personnel approved
though the CSWIP/PCN as an alternative.
a) Near vision acuity shall permit reading a minimum of Jaeger number 1 or times
roman N 4.5 or equivalent letters at not less than 30 cm with one or both eyes,
either corrected or uncorrected.
b) Colour vision shall be sufficient that the inspector can distinguish and
differentiate contrast between the colours used in the NDT method concerned.
6.3. All personnel engaged in activities associated with this specification shall comply with
all the relevant safety requirements of the particular work location, such as the
requirement for Personnel Protective Equipment (PPE), Safety passport, confined
space training where applicable and site induction. Where a method statement or risk
assessment for the inspection activity is available then this must be read and
understood and all requirements adhered to. However, if the documents are not
available then advice must be sought before work commences.
December 2019
GD/SP/NDT/2 7 of 47
All test butt welds shall be examined visually and by X-radiography. Automatic
Ultrasonic testing (AUT) or Manual Phased array (MPA) may be substituted for X-
radiography when agreed between the contracting parties. If AUT is used then it shall
be carried out in accordance with Appendix D of this specification, when the
examination is carried out with MPA then this shall be in accordance with Appendix E
of this specification. Where access permits, the weld root region shall be examined
by MPI or DPI as appropriate.
All fillet test welds shall be examined visually and by MPI or DPI as appropriate. MPI
shall be the preferred method to be used for the examination of carbon steel welds.
The DPI method should be used for the examination of austenitic stainless-steel
welds. Complementary Non- destructive testing methods may be required to identify
flaw characteristics.
7.2. The results from visual examination and non-destructive testing shall be assessed
according to the appropriate acceptance criteria of the welding standard specified.
December 2019
8 of 47 GD/SP/NDT/2
8.1.3. To assist interpretation the weld cap may be ground to a smooth contour prior to
examination.
8.1.4. When required by the Employer the primary method of weld examination shall be
supplemented by a complimentary method of non-destructive testing. The Employer
shall specify the supplementary non-destructive testing method to be used.
For pipeline construction, the number of welds to be examined using a
supplementary non-destructive testing method and the extent of the examination
shall be determined by the Employer. The pipe diameter, thickness, length, material
and welding process used to manufacture pipeline welds shall determine the
minimum examination level required.
8.1.5. For Class I welding of installation pipe work, all fittings attached by butt welds, shall
have the weld root examined from the bore by MPI or DPI as appropriate, where
access is possible. Local dressing of the root may be carried out if necessary to
assist interpretation.
8.1.6. For Class I welding of fillet welds (e.g. Set-on fittings and attachments) all welds shall
be examined by MPI or DPI, as appropriate. When required by the Employer
supplementary ultrasonic examination of fillet welds shall be carried out. For Class II
welding the number or percentage of fillet welds to be examined by MPI or DPI, as
appropriate, shall be agreed with the Employer prior to production welding
commencing.
8.1.7. All Non-destructive testing procedure specifications shall be submitted to the
Employer for approval prior to production welding commencing.
8.1.8. For welds which will not be pressure tested (Golden Welds) then the initial weld
examination shall be supplemented as follows:
Initial Examination Supplementary Inspection
Radiography Full Automatic Ultrasonics (AUT)
or
Manual Phased Array Ultrasonics
(MPA)
or
Manual Ultrasonics
Fully Automatic Radiography
Ultrasonics (AUT) or
Manual Phased Array Ultrasonics
(MPA)
or
Manual Ultrasonics (using
independent operator)
Manual Phased Array Radiography
Ultrasonics (MPA) or
Fully Automatic Ultrasonics (AUT)
or
Manual Ultrasonics (using
independent operator)
December 2019
GD/SP/NDT/2 9 of 47
Note,
(1) Independent operator means a different operator to the person
carrying out the initial review and sentencing of inspection data.
(2) In all cases the weld cap shall be examined using Magnetic
Particle inspection.
8.1.9. The single sided Ultrasonic inspection (Manual or Manual Phased Array*) of Golden
welds shall not be permitted. The scanning technique used shall examine the fusion
face and weld body from both sides of the weld joint.
*If the Golden weld is on a transition between pipes of different wall thicknesses then
the thicker pipe shall be counter bored to provide an equal wall thickness either side
of the joint.
9. Radiographic Examination
9.1. General
9.1.1. The main requirement of the Ionising Radiations Regulations is that NDT contractors
should adopt working practices capable of keeping radiation exposures of employees
as low as reasonable practicable.
If work involves routine radiography of readily moveable articles, an assessment shall
be made to establish whether site radiography is appropriate or if the articles may be
taken to a purpose-built enclosure for examination. Appendix B provides a flowchart
and guidance to facilitate the assessment.
Before any radiography is carried out a copy of the local rules as defined by the
Ionising Radiations Regulations shall be given to the employer. These will identify the
names and contact details for both the radiation protection adviser (RPA) and the
radiation protection supervisor (RPS). The local rules shall be displayed on the site
office notice board and at all locations where radiography is being carried out.
9.1.2. The Radiography shall be carried out in accordance with BS EN ISO 17636-1 when
using films or BS EN ISO 17636-2 for digital detectors and to the requirements of this
specification. The minimum standard of radiography produced shall be in accordance
with Class B (improved techniques). Class A shall not be permitted without the
written agreement of the Employer and only where Class B cannot be achieved for
sound technical reasons.
9.1.3. The use of fluoro-metallic screens or pre-packed films is dependent upon continuing
satisfactory field performance. Damaged screens shall not be used. The Employer
has the final decision whether screens or the use of pre-packed films are acceptable.
To provide acceptable film contrast the radiographic film shall be placed in close
contact with the intensifying screens and the object under examination. Lack of film
screen contact, even if local, may cause rejection of the radiograph
9.1.4. Fine grain high contrast direct type film or ultra-fine grain high contrast direct type film
meeting the requirements of BS EN 584-1 Class C4 should be used. Any variation to
this requirement shall be stated on the radiographic procedure sheet and shall be
approved for use by the Employer.
9.1.5. All radiographs shall be interpreted when dry
9.1.6. Permanent marking of the pipe as in BS EN ISO 17636-1or BS EN ISO 17636-2, as
appropriate Clause 6.5 shall be by waterproof marker only. No hard stamping shall
be permitted.
December 2019
10 of 47 GD/SP/NDT/2
9.1.7. Suitable padding shall be used on external X-ray sets to prevent damage to the pipe
coating
9.1.8. The minimum information to be displayed on the radiograph to ensure traceability will
be agreed between the Employer and the contractor prior to work commencing.
December 2019
12 of 47 GD/SP/NDT/2
procedure for this test shall be submitted to the Employer for approval prior any work
commencing.
9.8.3. If radiographic images are to be stored digitally, the proposed method of storage,
retrieval and the definition and sensitivity of the recorded image shall be approved by
the Employer prior to storage commencing.
Any software required to view the results shall be included on the data disc. Any
software licenses shall be agreed prior to production welds being examined. The
software version/number shall be clearly visible on all display presentations. The
software shall be capable of displaying the retrieved radiographic image in the
original format viewed by the interpreter at the time of sentencing.
December 2019
14 of 47 GD/SP/NDT/2
10.4.1. Calibration of the probe beam angles shall be carried out at least daily using the BS
EN ISO 2400 test block. The flaw detector time base and amplification shall be
calibrated before examining each weld.
10.5.2. The examination level for butt welds shall be to BS EN ISO 17640 Table A1 as
follows
Pipe Thickness Examination Level Notes
4.8mm<t<15mm A T-scan required
15mm<t<40mm B T-scan required
December 2019
GD/SP/NDT/2 15 of 47
December 2019
16 of 47 GD/SP/NDT/2
December 2019
GD/SP/NDT/2 17 of 47
15. Records
The results of all non-destructive testing examinations shall be recorded on an
appropriate record form. The examination report shall include, as a minimum, the
information required by the appropriate national standard and this specification.
For AUT and MPA records shall be as required in Appendix D and E as appropriate
Radiographs shall be stored in a secure and dry environment. The films shall be
retained for a minimum period of one year or for the life of the contract. After this
period, where it can be confirmed that records exist, the films may be disposed of.
December 2019
18 of 47 GD/SP/NDT/2
Appendix A - References
This Specification makes reference to the documents listed below
December 2019
GD/SP/NDT/2 19 of 47
B1 SCOPE
This procedure identifies the controls necessary for the management of site
Radiography. Adherence to these requirements should be audited as per the
requirements of construction checklist Appendix C.
This procedure shall also be used to determine the most appropriate method of
conducting radiography. The procedure provides a decision tree, which shall be used
to determine whether items requiring radiography testing should be transported off-
site to a purpose-built enclosure for radiography.
Implementation of these requirements does not imply that sufficient data has been
included to demonstrate compliance with Ionising Radiation Regulations, it is the
responsibility of the Radiographic Subcontractor and the main works contractor to
ensure these regulations are complied with in full.
B.2 INTRODUCTION
The main requirement of the Ionising Radiations Regulations is that NDT contractors
should adopt working practices capable of keeping radiation exposures of employees
as low as reasonably practicable.
The HSE guidance on complying with Ionising Radiations Regulations clearly states
that if work involves routine radiography of readily moveable articles it is nearly
always reasonably practicable to carry it out in an adequately shielded enclosure or
cabinet. Where practicable, using a suitable shielded enclosure shall always be the
first choice for radiography work. This enclosure can either be constructed on site or
articles can be transported to a purpose-built enclosure off site.
The flowchart in figure B1.0 of this Appendix, provides a process which shall
demonstrate that the selected method for conducting radiography keeps radiation
exposures of employees as low as reasonably practicable.
Where site radiography is the only practicable option the objective of this document is
to provide best practice guidelines to enable radiographic subcontractors to
undertake site radiography in a safe, consistent and auditable manner across all
projects.
The main responsibility for the implementation of this procedure lies with the
specialist
Radiographic Sub-contractor and the main works Contractor.
Adequate information on radiation safety shall be included within the contractor’s site
induction talk and relevant toolbox talks shall be provided to personnel likely to be in
the vicinity of radiographic works.
All personnel are responsible for ensuring that site radiography is undertaken in a
safe manner, any deviation to the planned safe system of work shall be reported
immediately to the project supervisor for rectification. A formal audit to ensure these
requirements are implemented as per the checklist Appendix C
a) Radiography is carried out in-situ with suitable local shielding and boundary
monitoring.
b) Radiography is carried out on site in a controlled area with suitable local
shielding and boundary monitoring.
c) Radiography is carried out on site in a temporary enclosure.
d) Articles are transported off site where radiography is carried out in a purpose-
built enclosure.
The flowchart in figure B.1.0 shall be used to determine the most appropriate method
when carrying out radiography. The size and transportability of pipework fabrications
may vary throughout a project, therefore to take account of this the flowchart may
need to be run more than once.
The factors, which may influence the selection of the most appropriate radiography
method for each stage of a project, are:
B.6 REQUIREMENTS
B.6.1 SUBMISSION OF DOCUMENTATION FOR CLIENT REVIEW
B.6.1.1 In accordance with the Ionising Radiation Regulations this shall include the
production of prior risk assessments and the methodology for dealing with the
risks, that shall as a minimum identify the following;
• Equipment used;
• Equipment ratings;
• Type of film;
• Storage of film;
• Film processing;
• Handling of chemicals; and
• Manual handling of radiography equipment.
Notification shall be sent to the HSE within the required notification period (28
and 7 days respectively) prior to site radiography being undertaken. This shall
include advising the location and timescales for the proposed radiography. A
copy of all notifications shall be available on site for audit purposes.
Processed film shall be stored in a suitable dry location separate from the
processing dark room.
December 2019
22 of 47 GD/SP/NDT/2
When sealed sources are in transport on the spread, relevant radiation signs
shall be posted on both sides and to the rear of the vehicle. When the source
is in the vehicle and is left unattended for any reason, the vehicle shall be left
in a secure state to prevent unauthorised access.
All lifting equipment (slings, belts, chains etc) shall be suitably controlled,
identified and have current test certification.
All inspection and test equipment used to provide primary measurement shall
be uniquely identified, subject to formal control and calibrated to a known
national standard.
B.6.2.10 QMS
December 2019
GD/SP/NDT/2 23 of 47
The role and responsibilities of the RPS shall be clearly identified and
communicated in writing to the individual.
In addition to other training, the RPS shall have received adequate instruction
in the following:
• Understanding / Interpretation of Ionising Radiation Regulations
• Requirements of the local site rules and contingency requirements
• Requirements for method statements and suitable risk assessments.
B.6.4.1 PPE
All personnel shall wear the PPE identified by the project risk assessment.
Named TLDs / film badges shall be worn at all times by classified workers
and shall be clearly visible at all times whilst on the spread, under no
circumstance are they to be left in overall pockets, in crew cabs etc.
Consideration should also be given to the use of electronic dosemeters /
alarms. Unnamed (i.e. spare numbered) TLD shall only be accepted during
the first month of a new workers contract period.
December 2019
24 of 47 GD/SP/NDT/2
B.6.4.3 PRECAUTIONS
Barriers shall prevent access to the controlled area. The following precautions
shall also be included, radiation signs, warning lights and RPS contact details.
On pipelines the spoil heap and right of way fencing may provide natural
barriers, however where there is a likelihood of public access, e.g. footpaths,
playing fields etc, all relevant points of access shall have barriers and relevant
signage. It is the responsibility of the radiographic subcontractor to ensuring
that the requirements of Ionising Radiation regulations are complied with.
December 2019
GD/SP/NDT/2 25 of 47
Spare bulbs and batteries shall be available with the crew(s) for all safety
critical equipment.
Where risk assessment requires, suitable shielding shall be available with the
crew(s),
All radiographic crew(s) shall have access to a mobile phone and/or two-way
radio for contact purposes.
B.6.4.13 AUDITS
1/7. Where it is feasible pipework should be pre-fabricated off site and radiographed
in a purpose-built enclosure.
December 2019
GD/SP/NDT/2 27 of 47
2. Some pipework can only be constructed in situ and therefore may not be
transportable from site. Other pipework fabricated on site may either by too large of
heavy to be reasonably practicable to transport off site.
9. Although it may not be practicable to transport some items off site because of the
size of the fabrication, these items should still be radiographed in a controlled area
on site if they can be moved around site.
10. Where pipework can fit within a temporary enclosure it should be transported to
such an enclosure for radiography if it is available on site, otherwise it should be
moved to a controlled area for radiography.
11. Where items fabricated on site cannot be moved because they are constructed in
situ the only reasonably practicable option may be to conduct the radiography in situ
providing the appropriate local shielding. Consideration may have to be given to
conducting the radiography out of hours to ensure that the radiation exposure of
employees is kept as low as reasonably practicable.
December 2019
28 of 47 GD/SP/NDT/2
December 2019
GD/SP/NDT/2 29 of 47
December 2019
30 of 47 GD/SP/NDT/2
December 2019
GD/SP/NDT/2 31 of 47
D.1 SCOPE
D.1.1 This specification details the minimum the Company requirements for an AUT system
requirements, AUT procedure approval and AUT system operator/interpreter
competency.
D.1.2 Any AUT system and examination procedure proposed for use shall, as a minimum,
meet the requirements of this specification and be approved by the Company prior to
any production weld examination being carried out.
D.2 REFERENCES
D.3 QUALIFICATION
D3.1 Before any system is used for the inspection of production welds on the pipeline it
shall be qualified to the satisfaction of the Company. The procedure for qualification
may be to scan a weld which may be agreed by the Company and report any flaws
that are outside the acceptance criteria in accordance with the relevant standard. The
results from the qualification scan may be analysed by the Company to confirm
acceptance of the system and operators.
D3.1.1 The proposed AUT system shall be used to scan a pre-production weld
produced using the approved contract weld bevel design. The pre-production
weld shall be manufactured during the welding procedure qualification stage
and shall contain deliberately induced weld defects typical of the welding
process being employed. The test weld shall be radiographed to confirm the
type and orientation of defects produced.
The results of the AUT scan and radiography shall be reported to the
Employer and shall size all defects found for both length and depth. Following
review by the employer a number of the defects shall be sectioned and the
though wall depth of those defects established. This may confirm that the
defect error sizing tolerance to be applied is adequate.
D3.2 In addition to the qualification of the system a number of items shall be agreed by the
Company before the system is used to inspect any production welds these include
D3.3 Where there are any significant changes to a system, the equipment may require re-
qualification to an agreed procedure. Significant change shall include, but not be
limited to.
• System operator
D3.4 Before the ultrasonic system is used for examination of production welds the system
shall be tested. After calibration of the complete system, a weld shall be scanned
followed, by re-calibration with the probe transport system removed between each
scan. If any of the echo amplitudes from the reflectors of the calibration block deviate
more than 2dB from the initial calibration, the system shall not be used until
acceptable corrections have been made. For an acceptable test 3 satisfactory scans
and recalibrations are required.
D4.1 The ultrasonic system shall use phased array pulse echo technology and time of
flight diffraction (TOFD).
D4.2 The system shall include probe sets specifically designed to detect transverse defect
indications on both the internal and external weld near surface zones. The transverse
defect scanning unit does not require a complimentary TOFD scan.
D4.3 The weld scanning direction (clockwise or anti-clockwise relative to a fixed datum)
shall be agreed with the Company and shall be consistent for all production girth
weld examination.
D4.4 The system shall have sufficient examination channels, configured so that the
complete weld through thickness can be examined in a single circumferential scan.
D4.5 The volume of weld examined by each channel shall be divided into primary
examination zones of a height not exceeding 3 mm.
D4.6 The system shall provide an overlap at the start and/or end of the scans of at least
100 mm.
D4.7 The recording or marking system shall clearly indicate the location of imperfections
relative to the 12 o’clock position of the weld, with +/- 10 mm accuracy. The system
resolution shall be such that each segment of recorded data from an individual
inspection channel does not represent more than 1mm of circumferential weld
distance.
December 2019
GD/SP/NDT/2 33 of 47
Dedicated, higher frequency, TOFD probes shall be used in all AUT systems
employed to give the best sizing performance. The probe frequency shall be agreed
by the Employer prior to system qualification trials.
The instrument shall provide a record of the TOFD D-scan image; this shall
compliment the AUT system in confirming the presence and the sizing of weld
defects. TOFD shall not be used in place of Pulse Echo.
D4.9 The instrument shall meet the requirements for ultrasonic instruments detailed in BS
EN 12668-1.
D5.1 Prior to the examination of any production pipeline welds the proposed examination
procedure shall be submitted to the Company for review and acceptance. The
procedure shall contain but not be limited to the following.
D.6 OPERATORS
December 2019
34 of 47 GD/SP/NDT/2
D6.2 All operators/interpreters shall be trained and competent in the use of the particular
AUT/TOFD equipment that they may be expected to operate. Documentary evidence
of adequate training and ongoing practical ability shall be provided to the Company
for each proposed operator/interpreter.
D6.3 AUT/TOFD interpreters shall be qualified to CSWIP / PCN level 2 ultrasonic operator
or have provided evidence of training and competency to the satisfaction of the
employer. Operators /interpreters possessing an equivalent qualification in an
alternative scheme may be proposed by the contractor for consideration by the
Company.
D6.5 Operators shall not be changed without the prior approval of the Company.
D.7 PREPARATION:
D7.1 The scanning band shall be positioned adjacent to the completed weld at the same
distance used for calibration of the unit. Prior to welding, a reference line shall be
scribed on the pipe surface at a distance specified by the AUT contractor from the
centre line of the weld. This may provide a datum to ensure band positioning within a
tolerance of ± 1 mm.
D7.2 The scanning area shall be free of spatter and other irregularities, which may
interfere with the movement of the transducers, or the transmission of acoustic
energy into the material. The longitudinal seam welds shall be ground flush and
smooth for a specified distance, normally in the range of 150mm from the factory
bevel face to ensure that no transducers are lifted from the pipe surface. The pipe
coating shall be cut back from the original factory bevel face for a distance, of
150mm. The internal Pipe seam shall be ground back 50mm from the weld bevel to
prevent interference with the ultrasonic beam during scanning
D7.3 The “0” starting point and the scanning direction shall be clearly marked on the
surface of the pipe by permanent marker or paint.
D7.4 The location of the pipe seam welds may be identified and recorded on the final
inspection report for each weld.
D7.5 The weld and adjacent pipe may be allowed to cool to a maximum temperature of
600 C before scanning can commence unless otherwise agreed with the Company.
The difference in temperature between the calibration block and weld being tested
shall be less then 100 C
D.8 SCANNING
D8.1 Acoustic coupling shall be achieved using a non-toxic liquid medium. When choosing
the medium, consideration shall be given to the Health, Safety and Environmental
impact of any materials used.
December 2019
GD/SP/NDT/2 35 of 47
D8.2 No residue from the liquid medium shall remain on the pipe surface after the liquid
has evaporated.
D8.3 Positive confirmation of acoustic coupling, during the weld examination scan is
required for each weld examination. The loss of signal amplitude associated with
inadequate coupling shall be specified by the contractor and agreed with the
Company (see section 18 a). Any loss of acoustic coupling during a weld
examination may require a complete re-examination of the weld (see Section 18).
D8.4 The operator shall keep a log book detailing the performance/characteristics data
and identification for instruments and transducers. The log book shall be updated as
changes are made, or, as additional information is gathered. The log book shall be
kept at the place of inspection and be made available for review upon request.
D8.5 Each weld shall be numbered in the sequence used in the pipe tracking system as
specified by the Company inspection team.
D8.6 Transition welds joining pipes of different wall thickness may only be examined by
AUT when the thicker material is counter-bored back at least 70mm from the weld
face.
D9.1 The maximum allowable circumferential scanning velocity (Vc), shall be determined
according to
Vc ≤ W c * PRF/3
D10.1 A reference block(s) shall be used to establish sensitivity, qualify the examination
system and monitor the system performance on an ongoing basis. The block(s) shall
be manufactured from a section of (unflawed, project specific) line pipe material
provided by the Company or their main contractor.
D10.2 The AUT contractor shall supply the necessary reference blocks. The design of the
block(s) shall be specific to the weld bevel geometry and pipe thickness to be used
on the project. The Company reserves the right to retain any or all reference blocks
on completion of any pipeline inspection.
D10.3. The AUT contractor shall submit their design for a reference block(s), detailing the
number, orientation and location of FBH and transverse EDM slot reflectors or other
reflectors, to the Company for approval before manufacture.
December 2019
36 of 47 GD/SP/NDT/2
D10.4 Details of the specific weld geometries shall be provided in order to determine the
particulars and numbers of calibration blocks required, including the calibration
reflectors required and their relative positions.
D10.5 The preferred principal calibration reflectors are normally 2mm Diameter flat bottom
holes (FBH) and 1mm deep surface slots. Other reflector dimensions and types may,
however, be used, if it is demonstrated during the system qualification that the defect
detection and sizing capabilities of the system is acceptable.
D10.6 The Calibration block shall contain a reflector designed to represent a burn-through
this will typically be a 4mm Diameter Hemispherical hole to a depth of 2mm on the
inside centreline of the block.
D10.7 The calibration blocks shall be designed with sufficient surface area so that the
complete transducer array may traverse the target areas in a single pass.
D10.8 The calibration block shall be identified with a hard-stamped unique serial number
providing traceability to the examination work and the material source of supply for
which the standard was manufactured. Records of the serial number, wall thickness,
bevel design, diameter and ultrasound velocity shall be kept and be available.
D10.10 The lateral position of all calibration reflectors shall be such that there may be
no interference from adjacent reflectors, or from the edges of the blocks.
D10.11 Dimensional verification of all calibration reflectors and their position shall be
performed and recorded by an independent party. The record of this
verification shall be presented to the Company before pipeline production
welds are examined.
D10.12 A calibration block register shall be established. The register shall include all
calibration blocks to be used identified with the unique serial number and
include the dimensional verification records, ultrasound velocity, name of the
plate/pipe manufacturer and the heat number. The register shall be available
for review.
D10.13 The surface condition of the reference blocks shall be made to be typical of
that of the pipe ends to be AUT scanned, including any roughness due to grit-
blasting, surface corrosion, painting or power brushing.
D11.1 Static calibration - The system shall be set-up and calibrated using the reference
standard block in accordance with the AUT contractors approved procedure.
December 2019
GD/SP/NDT/2 37 of 47
D11.2 For each pulse echo ultrasonic transducer in each examination channel the peak
signal response from the target reflector shall be maximised and then adjusted to
80% full screen height (FSH). This shall be the Primary Reference Level (PRE).
D11.3 The ultrasonic transducer stand-off distance, the gain level required to attain the
PRE, and the signal to noise ratio (S/N) shall be recorded.
D11.4 With each transducer positioned for the peak signal response from the calibration
reflector the detection gates are to be set. The gate shall start before the theoretical
weld preparation and a suitable allowance shall be included to allow for the width of
the heat affected zone, so that complete coverage of the heat affected zone is
achieved. The gate ends shall be after the theoretical weld centreline, including a
suitable allowance for offset of the weld centreline after welding.
D11.5 Gate settings shall be set in accordance with the AUT contractors approved
procedure. The settings for gate start and gate length for each examination channel
shall be recorded.
D11.6 Ideally for TOFD the time gate start should be at least 1 s prior to the time of arrival
of the lateral wave and should be past the first back wall echo.
D11.7 Dynamic calibration – With the system optimised the reference / calibration standard
shall be scanned at the same travel speed at which the examination may be
performed. The positional accuracy of the recorded target reflectors relative to each
other shall be within ± 2 mm and with respect to the zero datum be within ± 10 mm
over the circumference. Gate settings shall not deviate by more than 0.25 mm from
the reference positions.
D11.8 The output display chart / record produced during the dynamic calibration scan shall
confirm that all ultrasonic transducers produce an 80% FSH signal response from
each calibration reflector in its correctly assigned position.
D11.9 Subsequent system calibration charts produced during field inspection, shall be
comparable with the dynamic output display chart / record and shall meet the set-up
reference standards.
D11.10 All calibration signals shall be within the range 70 to 99% FSH, if during the
dynamic field calibration the signal falls outside this range then one of the
following may apply.
D11.11 When a signal is over 99%FSH then the results for all welds scanned since
the last successful calibration may be reviewed and where an indication has
been identified in the effected channel then these shall be re-scanned to
confirm the original diagnosis
D11.12 If when checking the calibration any signal falls below 70% FSH then all
welds inspected since the last successful calibration scan shall be re-tested
unless otherwise agreed by the Company
D12.1 The system shall be calibrated by scanning the reference / calibration block(s) at the
start of each work period and before and after the examination of each weld:
December 2019
38 of 47 GD/SP/NDT/2
D12.2 Subject to satisfactory performance and at the discretion of the Company, the
frequency of calibration may be reduced to a minimum of 1 calibration scan for each
10 consecutive welds or every 1 hours whichever comes first.
D12.3 Hard copy recordings of all calibration scans, indicating any gain changes required to
maintain sensitivity, shall be included as part of the final report. The last weld number
examined before calibration and the time at which the calibration was performed shall
appear on each calibration chart.
D12.4 The peak signal responses from each calibration shall be recorded. Any gain
changes required to maintain proper sensitivity shall also be recorded.
• Using three slots for the internal surface calibration and three slots for the
external surface calibration.
• One of the three slots to be at 10% of the wall thickness, one to be at 10% PLUS
a height margin and one to be at 10% MINUS a height margin
• The height margin to be calculated so as to be equivalent to a difference in the
ultrasonic beam path, between the send and receive transducers, of a quarter
wavelength, at the transducer nominal frequency.’
The system sensitivity shall be set at 9db above that required to give a signal of 80%
of full screen height from the largest signal of the three slots.
D.14 REPAIRS:
Defective welds that have been repaired shall be re-examined in accordance with
this specification, visually and by X-radiography or visually and to an ultrasonic
method approved by the Employer.
D15.1 Before any inspection using this procedure is carried out, the criteria for weld defect
acceptance shall be agreed with the Company. For normal pipeline projects this may
December 2019
GD/SP/NDT/2 39 of 47
be obtained by using an Engineering Critical Assessment (ECA), but where this is not
available then the requirements of the Company welding specification GD/SP/P/2
shall be used.
D15.2 The defect length may normally be defined as being from the point at which the full
interacting defect first attains a signal of 30% of Full Screen Height (FSH) to that
point where it lasts falls below 30% of FSH
D15.3 Where two or more defects occur in close proximity to each other, they shall be
assessed for interaction to the requirements of BS 7910 clause 7.1.2.2 and figure 9
D15.4 The ECA requirements are unique to each project / pipe wall thickness and pipe
diameter. An ECA to allow specific defect acceptance criteria shall be produced for
each pipeline project prior to the commencement of inspection.
D15.5 To allow for combined AUT system and interpreter error, all recorded defect heights
shall be increased by an amount to be agreed by the Employer prior to
commencement of production weld examination. This value may vary according to
the AUT system used and operator competence. The AUT contractor shall provide
evidence and fully demonstrate to the satisfaction of Employer that the sizing error
value to be adopted is accurate. Where no evidence can be provided, all defect
heights recorded may be increased by 3.0mm before the length acceptance is
carried out.
D15.6 All transverse indications that exceed the threshold shall be evaluated as cracks.
D15.7 When any three out of ten welds consecutively tested fail to meet the ECA
acceptance criteria, then at the discretion of the Employer the accept / reject
requirements shall revert to the workmanship standard of the applicable welding
standard in use (e.g. the Company GD/SP/ P/2, clause 12). The application of the
ECA acceptance criteria cannot be reintroduced until the reason for the defective
welding has been identified and rectified.
D.16 SOFTWARE
D16.1 Any software required to view the results shall be included on the data disc which
may be provided as part of the final results. Any software licenses shall be agreed
before any of the production welds are examined.
D16.2 The version number of any software shall be clearly visible on all display and printout
presentations.
D17.1 Indications recorded from sources other than weld imperfections shall be evaluated.
Their nature shall be clearly identified on the examination report.
D17.2 The recording threshold for porosity detection channels shall be at least 14 dB more
sensitive than the reference reflector.
December 2019
40 of 47 GD/SP/NDT/2
D17.3 It is recommended that the recording threshold for TOFD remains at the calibration
threshold.
D17.4 Channel output signals shall be arranged on the recoding media in an agreed order.
The function of each channel shall be clearly identified. The hard copy recording shall
be corrected to account for any variation introduced due to different circumferential
positions of the transducers.
D17.5 The welding foreman responsible for weld production shall be immediately notified of
any defect recorded during the AUT scan. The exact position of the defect shall be
marked on the pipe surface using permanent markers.
D17.6 The AUT record shall be annotated with the size evaluation of each weld
imperfection selected for assessment. Comments shall be added, as necessary to
allow a later re-evaluation by another operator.
D17.7 Before any weld is accepted by AUT any complementary Inspection shall be take into
account, such as visual inspection of caps, so that all inspections are considered as
part of the total weld sentencing.
D.18 RE-EXAMINATION
a) Scanning exhibiting a loss of coupling i.e. a drop-in echo amplitude of more than
10dB from the level though a clean weld, where the length is more than the allowable
defect length for the effected channel.
b) Any calibration scan that shows that the system is “out of calibration”, shall be
subject to the requirements of 11.10.
D19.2 The electronic data shall display the results in the same manner that the operator
viewed at the time of inspection. A print option shall be provided as part of the
software.
D19.3 A Scan and TOFD data shall be saved as part of the original weld scan data and
included in the weld record.
D19.4 The electronic data for each weld scanned shall be saved and provided to the
employer at agreed intervals during the project, it shall be stored such that each weld
can be identified by the file name.
December 2019
GD/SP/NDT/2 41 of 47
E.1 SCOPE
E.1.1 This specification details the minimum the Company requirement for a MPA system,
MPA procedure approval and MPA system operator/interpreter competency.
E.1.2 Any MPA system and examination procedure proposed for use shall, as a minimum,
meet the requirements of this specification and be approved by the Company prior to
qualification and use in production.
E.1.3 Only welds in pipes 50mm nominal diameter and above, and 4.8mm wall thickness
and above shall be examined with MPA
E.1.4 When required by the Employer, phased array examination shall be applied to welds
as described in BS EN ISO 13588 and this specification.
E.1.5 The examination level for butt welds shall be to BS EN ISO 13588 Table 1 Testing
level B.
E.2 REFERENCES
E.3 QUALIFICATION
E3.1 Before any system is used for the inspection of production welds it shall be qualified
to the satisfaction of the Company. When required by the Employer the procedure for
qualification may include the scanning of a weld or welds* and to report any flaws
that are outside the acceptance criteria in accordance with the relevant standard. The
results from the qualification scan shall be analysed by the Company to confirm
acceptance of the system and operators.
*When required by the Employer the proposed MPA system shall be used to scan a
pre-production weld produced using the approved contract weld bevel design. The
pre-production weld shall be manufactured during the welding procedure qualification
stage and shall contain deliberately induced weld defects typical of the welding
process being employed. The test weld shall be radiographed to confirm the type and
orientation of defects produced.
The results of the MPA scan and radiography shall be reported to the Employer and
shall size all defects found for length and width.
E3.2 In addition to the qualification of the system a number of items shall be agreed by the
Company before the system is used to inspect any production welds these include
December 2019
42 of 47 GD/SP/NDT/2
E3.3 Where there are any significant changes to a qualified system, the equipment may
require re-qualification to an agreed procedure. Significant change shall include, but
not be limited to.
E4.1 The inspection shall also include scans specifically designed to detect transverse
defect indications, with the approval of the employer, these scans may be by a
standard manual ultrasonic scan.
E4.2 The weld scanning direction (clockwise or anti-clockwise relative to a fixed datum)
shall be agreed with the Company and shall be consistent for all production weld
examination.
• A Frame for holding the passed array probe(s) in the correct location for scanning
• A-scan data storage
• Encoder to record position of probe accurately to within ± 2.0mm
• Adjustable gain control with maximum 2db steps over a range of at least 60db
• One or more gates, each adjustable for start position and length
• Recording threshold between 5 and 100% of full screen height
• Signal outputs that record signal amplitude and time/ beam travel distance
E4.4 The system shall provide an overlap at the start and/or end of the scans of at least 30
mm.
E4.5 The encoder shall clearly indicate the location of imperfections relative to the 12
o’clock position of the weld. The system resolution shall be such that each segment
of recorded data does not represent more than 1mm of circumferential weld distance.
E4.6 The instrument shall meet the requirements for ultrasonic instruments detailed in BS
EN 12668-1.
E5.1 Prior to the examination of any production welds the proposed examination
procedure shall be submitted to the Company for review and acceptance. The
procedure shall contain but not be limited to the following.
December 2019
GD/SP/NDT/2 43 of 47
A technique sheet will be produced for each pipe wall thickness to be tested, detailed
the actual scan settings to be used including a diagram showing ultrasonic coverage
of the weld being tested.
E5.2 The Scanning sensitivity will be set using Side Drilled holes with a maximum
diameter of 2.5mm.
E5.3 The reference blocks used for calibration shall meet the requirements of BS EN ISO
13588 A.2, curved reference blocks shall be used having diameters from 0.9 to 1.5
times the pipe to be tested OD, For Pipe OD greater than 300mm a flat reference
block may be used.
E5.4 The weld will be inspected using a combination of sectorial and linear scans
designed to cover the HAZ, root, fusion face, cap and weld volume.
E5.5 Welds in pipe with a nominal wall thickness over 9.0mm shall be inspected using the
following 3 scans:
1. A scan of the weld root area with either a linear or sectorial set up but
concentrated on looking for weld root defects
2. Weld Fusion face scan using a linear scan with an angle set to impinge on the
fusion face at an angle as near as practicable to 90 degrees
3. Weld volume and Cap scan using a sectorial scan
All scans will be gated to cover the HAZ and weld volume. Where both sides of a
weld are being tested at the same time or the nominal pipe wall thickness is under
9.00mm, then the number of scans may be reduced to prevent the system being
overloaded with data, this must be agreed with the Company during qualification of
the system and before any inspections are carried out.
December 2019
44 of 47 GD/SP/NDT/2
E5.6 When an inspection of a pipe to fitting is carried out this should be carried out from
both sides of the weld whenever possible, where this is not possible then a single
sided scan is acceptable providing the scan consists of 2 sectorial scans with the
sound emission point at 2 different positions. The additional scans will be included in
the procedure submitted for approval. Where single sided ultrasonic inspection is
used this shall be supplemented by an inspection of the weld cap using
Magnetic Particle inspections to the requirements of Section 12 of this
specification.
E5.7 Transition welds joining pipes of different wall thickness may only be examined by
MPA when the thicker material is counter-bored back by machining to the
requirements of GD/SP/P/16 or where it can be demonstrated that the heat effected
zone (HAZ), both fusion faces and the weld volume can be inspected with the
proposed procedure.
E5.8 The minimum length of counter-bore required for MPA inspection shall be 25mm.
whenever counter-bore operations are carried out care must be taken not to reduce
the wall thickness below the minimum design thickness.
E5.9 All scan settings should allow for the probe standoff to move slightly during scanning.
E.6 OPERATORS
E6.2 All operators/interpreters shall be trained and competent in the use of the particular
equipment that they may be expected to operate. Documentary evidence of
adequate training and ongoing practical ability shall be provided to the Company for
each proposed operator/interpreter.
E6.3 Operators /interpreters shall be qualified to PCN / CSWIP level 2 phased array
ultrasonic operator. Operators /interpreters possessing an equivalent qualification in
an alternative scheme or having provided evidence of training and competency to the
satisfaction of the employer, may be proposed for consideration by the Company.
E6.5 Operators shall not be changed without the prior approval of the Company.
E.7 PREPARATION:
E7.1 The scanning area shall be free of spatter and other irregularities, which may
interfere with the movement of the transducers, or the transmission of acoustic
energy into the material. The longitudinal seam welds shall be ground flush and
smooth for a specified distance, normally in the range of 100mm from the factory
bevel face to ensure that no transducers are lifted from the pipe surface. The pipe
December 2019
GD/SP/NDT/2 45 of 47
coating shall be cut back from the original factory bevel face for a distance, of
100mm. The internal pipe seam shall be ground back 50mm from the weld bevel to
prevent interference with the ultrasonic beam during scanning
E7.2 The zero “0” starting point and the scanning direction shall be clearly marked on the
surface of the pipe by permanent marker or paint.
E7.3 The weld and adjacent pipe shall be allowed to cool to a maximum temperature of
600 C
before scanning can commence unless otherwise agreed with the Company. The
difference in temperature between the calibration block and weld being tested shall
be less then 100 C
E.8 SCANNING
E8.1 Acoustic coupling shall be achieved using a non-toxic liquid medium. When choosing
the medium, consideration shall be given to the Health, Safety and Environmental
impact of any materials used. The same couplant shall be used for calibration and
subsequent testing.
E8.2 No residue from the liquid medium shall remain on the pipe surface after the liquid
has evaporated.
E8.3 The operator shall keep a log book detailing the performance/characteristics data
and identification for instruments and transducers. The log book shall be updated as
changes are made, or, as additional information is gathered. The log book shall be
kept at the place of inspection and be made available for review upon request.
E8.4 Each weld shall be numbered in the sequence used in the pipe tracking system as
specified by the Company inspection team.
E.11 REPAIRS:
Defective welds that have been repaired shall be re-examined visually and in
accordance with the original examination method.
E12.2 Where two or more defects occur in close proximity to each other consideration shall
be given to the effects of their interaction
December 2019
46 of 47 GD/SP/NDT/2
E12.3 All transverse indications that exceed the threshold shall be evaluated as cracks.
E12.4 A defect will be rejected if the through wall extent exceeds 2.0mm in welds where the
materials nominal wall thickness is 12.7mm or below, on material above 12.7mm
then the maximum allowable defect height will be 3.0mm
E.13 SOFTWARE
E13.1 Any software required to view the results shall be included on the data disc which
may be provided as part of the final results. Any software licenses shall be agreed
before any of the production welds are examined.
E13.2 The version number of any software shall be clearly visible on all display and printout
presentations.
E14.1 Indications recorded from sources other than weld imperfections shall be evaluated.
Their nature shall be clearly identified on the examination report.
E14.2 The exact position of the defect shall be marked on the pipe surface using permanent
markers.
E14.3 Before any weld is accepted by MPA any complementary inspection shall be taken
into account, such as visual inspection, so that all examinations are considered as
part of the total weld sentencing.
E.15 RE-EXAMINATION
a) Scanning exhibiting a loss of coupling i.e. a drop in echo amplitude of more than
10dB from the level through a clean weld for more than 3 lines of data per 20mm
scanned.
b) Any calibration scan that shows that the system is “out of calibration”,
E16.2 The electronic data shall display the results in the same manner that the operator
viewed at the time of inspection. A print option shall be provided as part of the
software.
E 16.3 The electronic data for each weld scanned shall be saved and provided to the
employer at agreed intervals during the project, it shall be stored such that each weld
can be identified by the file name
December 2019
GD/SP/NDT/2 47 of 47
Cadent
Ashbrook Court
Prologis Park
Central Boulevard
Coventry
CV7 8PE
Copyright Cadent Gas Limited.©, all rights reserved. No part of this publication may be
reproduced in any material form (including photocopying and restoring in any medium or
electronic means and whether or not transiently or incidentally) without the written
permission of Cadent Gas Limited. except in accordance with the provisions of the
Copyright, Designs and Patents Act 1988.
December 2019