System Integration with IET

Step by step Engineering Work flow CET - 61850/OPC server for MicroSCADA
5. - Load server with same .scd file
PCM600 (e.g. IED670) - Use OPC client software (Softing freeware) to
1.
- Create your project structure connect to 61850/OPC server for confirmation e.g.
- Insert template in CAP531 Bay Loc/Rem switch position is working properly.
- Do necessary Parameter Setting changes (e.g. IED name, 61850 communication is running
30' IP,..)
- Graphical display engineering
- Assign inputs/outputs in SMT (Signal Matrix Tool)
Export .icd files for each device (export scl on device level)
6. IET (CCT)
Finalize MicroSCADA database engineering:
- Generate Loadfiles (for MicroSCADA)
- Note: Get rid of duplicated LN:IX
2. IET – Project Explorer, SLD, SCD MicroSCADA db is
Single -
20' -
Create your project structure
SCD (station configuration diagram)
Line - SLD (single line diagram)
- Note: For IED670 <V2.0 no FBD
shall be used (Bottom up engineering) MicroSCADA (Picture Editor and db Imort)
Feeder 1' Export to CCT Picture Engineering (old GUI): Use basically LIB510
Block 7. No need to generate process objects except for the station picture
function!
Verify OI length; enter correct OI attributes in picture function
System 10' editor!
configuration - Insert Station picture function ( generate process objects)
- Insert Bay picture function
Insert Device picture function (Note: 5AO output command!)
IET (CCT) - Bottom up engineering: Import database:
3. - 5' Import .icd files on device level
Reference Error messages may appear:
created
- 15' Data Type Templates: Import Logical Node Template e.g. missing scale: add scale or change scale name in CCT to
Drag‘n‘drop LN
to S/S Section
- 20' IEC61850 Object mapping applicable scales
- 15' Data Flow engineering (rcb, gcb, dataset,…)
Export SCL on station level: .scd OPC PO List (MicroSCADA Tool - internal)
8.
MicroSCADA Process Object list:
- Assign one STA for each device
- Save file in sys_/active/sys
UN, OA, BA attributes will be set (since db can only be updated
through this!)
PCM600
4. - Take a backup of your project before you continue!
(Export)
- Import .scd file on station level
- Open SMT: goose input block appears (if you have
another IED) 9.
30' DA Client (MicroSCADA Tool - external)
Download SMT - Delete any existing STA in this tool
Test with ITT Synthesizer - Use Auto configure menu to import PO list
Don’t forget to adjust SPA Transparent db point (LD0…)
Verify Notifier facilties to verified proper connection to
MicroSCADA by the simulation of e.g. Bay Loc/Rem switch.