Professional Documents
Culture Documents
Maintenance
S T E A M T U R B I N E M A I N T E N A N C E
Turbine Disassembly and Reassembly Procedure 13. Properly Rig Casing Cover and Remove
1. Record Running Data and discuss the operating a. Plan your Laydown Area First
conditions of the turbine with client. b. Cover Must Come Up Level
Specifically any known problems with the c. Use Chain Blocks
turbine since last overhaul. d. Flip Cover
6. Record Running Position Reference with Rotor 19. Place Rotor in Center of Axial Float
against Inboard Thrust Bearing
20. Rig and Remove Rotor
7. Remove Outboard Thrust Bearing and Check a. Plan your Laydown Area First
Nozzle Clearance b. Use Chain Blocks
c. Use Soft Slings
d. Rotor has to stay Level
33. Install Labyrinth Seals
21. Visually Inspect the turbine for deposits or a. Verify Match Marks
unusual damage or wear. b. Replace Springs Do Not Use Old
Springs
22. Remove Lower Diaphragms c. At this Time Wedge Bottom
a. Match Mark to Case Labyrinths in order to check top and
b. If Centerline Supported, Match Mark bottom Labyrinth Clearances
the Bolts and Shims d. Place Lead Wire or Plasti Gauge on
Lower Half Labyrinth Seals
23. Remove Upper Diaphragms
a. Match Mark to Case 34. Install Radial Bearing Lower Halves
31. Reinstall Upper Diaphragms 42. Remove All Labyrinth Seal Wedges
General
This instruction establishes a standard procedure for taking turbine rotor axial clearances.
Important
Four (4) measurements must be taken and recorded prior to lifting the turbine cover:
1. Thrust clearance
2. Nozzle clearance
3. Total rotor float
4. Depth micrometer reading to end of shaft
Without these readings, internal clearances taken after the cover is removed are of little value since all axial
clearances are referenced from the nozzle and the nozzle is located in the upper cover of most turbines.
Procedure
1. Mark the rotor and take all readings with the rotor in the same position (position a - c and d).
2. Check and record the turbine thrust clearance. Mount a dial indicator on the end of the shaft. Bar the rotor in
both directions and record the readings. Note: when baring the rotor, make sure it is a hard bump
a) Bar the rotor in the direction of steam flow (against the active thrust shoes) This will be the running position
of the rotor.
b) Establish a reference reading using a depth micrometer from the end of the shaft to a machined surface on the
bearing housing. This can be used to reestablish the running position at any time.
c) Remove thrust bearing cap and re-establish reference reading taken in step (b).
e) Mount a dial indicator from the bearing bracket to the shaft and bar the rotor in the direction opposite to
steam flow until it makes contact. Record the reading, this should be the nozzle clearance.
Remove the active side thrust bearing and bar the rotor in the direction of steam-flow to obtain the total rotor
float.
S T E A M T U R B I N E M A I N T E N A N C E
NOTE: ALL DIAPHRAGMS MUST BE SEATED AGAINST THEIR SEALING FACE BEFORE
CHECKING AXIAL CLEARANCES.
5. Once the above readings are obtained, the rotor should be positioned in the center of its float. The turbine
cover can then be removed.
b) Position the rotor in the opposite direction of the steam flow the amount recorded in 3(e) above (nozzle
clearance).
c) If the clearance taken in 3(e) above was truly the nozzle clearance, there should be some clearance between
the rotor and all diaphragms, except for diaphragms having a design clearance the same as the nozzle clearance.
d) If the rotor is contacting a diaphragm, that diaphragm could be the striking point instead of the nozzle.
Therefore, if a diaphragm is contacting, remove the diaphragm and take new readings. Reinstall the turbine
cover (dowel pins and four bolts) and the thrust bearing. Repeat steps 3 and 4, record new readings. The
difference between the two axial clearance readings recorded for step 3(e) will be the amount that the
diaphragm is out of-position.
e) If the nozzle clearance recorded in step 3(e) was not within design tolerances, the rotor must be repositioned
and the reading for rotor running position taken in step 3(b) must be adjusted accordingly.
g) Record the axial clearances of each stage (inlet side) at four locations on each wheel. Where outlet side
clearances are shown on the turbine assembly drawing, they should also be recorded. Record clearances at the
following locations:
The minimum clearance recorded is the controlling clearance to determine compliance with design tolerances.
h) Rotate the rotor 90o and recheck axial clearances at positions b, c and d.
NOTE: During reassembly of thrust bearing to check nozzle clearance and thrust clearance, the thrust
housing should be installed for each step to eliminate a false reading due to tilting of thrust bearing. All
diaphragms should be forced in the direction of the steam flow.
S T E A M T U R B I N E M A I N T E N A N C E
Benchmark= Benchmark=
AS BUILT
0 Degrees 90 Degrees
Left Side Right Side Left Side Right Side
Location Shroud Platform Platform Shroud Shroud Platform Platform Shroud
Clearance
Design
Deviation
Benchmark corrected deviation=
Clearance
Design
Deviation
Benchmark corrected deviation=
Clearance
Design
Deviation
Design
Deviation
S T E A M T U R B I N E M A I N T E N A N C E
General
This instruction establishes a procedure for inspection of the Turbine Steam Chest Nozzle Control
Valves and Operating Gear Assembly. This inspection take place at intervals of every four to five
years of operation, during scheduled outages.
The following critical items must be inspected and any problems reported:
1. Visually check steam chest internals and valve assembly for any abnormal wear, cracks or
problem areas.
2. Dye check valve seat welds.
3. Check clearance of lifting bar in accordance with manual.
4. Check tack welds and tightness of all nuts.
Disassembly Procedure
Note: Refer to Instruction Manual for the specific Nozzle Valve and Operating Gear Assembly
Drawing.
If none of these conditions exist, check valve timing and proceed to Reassembly.
S T E A M T U R B I N E M A I N T E N A N C E
9. Use blocks, if necessary, to support the combined weight of the lifting bar and valves during
the next steps.
10. Remove nuts, lock washers and spindles and disconnect springs. Remove upper linkage and
pointers from valve spindles. Slide spindles through the steam chest cover.
11. To remove a valve, it is necessary to remove the welds locking the valve stem hardware.
12. Place the valve assembly in the steam chest so the valves rest in their seats and the bar rests on
the valves. By measurement from the steam chest Joint face to the top of the bar, parallel the
bar axially and horizontally with the Joint face within .002, using shims under the low end of
the bar to make adjustments.
13. Record the readings taken above in the appropriate blocks, L and R, on Exhibit A.
14. Push down on each valve stem holding the valve firmly and straight in its seat. Snug each
adjusting nut against the top of the bar. Remove the valve bar assembly from the steam chest
and place it on suitable supports. Mount the base of a dial indicator on the bar and indicate to
the top of the valve stem of each valve to determine the clearance between the top of each
valve and the bottom of the bar. Be careful not to tilt the valve.
15. Record the readings taken above in Row C under the appropriate valve number on Exhibit A.
16. The cold bar clearance shown on the Nozzle Valve and Operating Gear Assembly drawing for
the unit is the decimal dimension between the top of the valves and the bottom of the bar with
the bar at its lowest point of travel (Servo on its "closed" stop). This dimension allows for the
thermal expansion of the assembly and is the same for all of the valves in the assembly.
Record this dimension in Row B under each valve on Exhibit A.
17. The valve settings are tabulated on the applicable nozzle valve and Operating Gear Assembly
drawing. Record these valve settings in Row A of Exhibit A.
18. In Row D of Exhibit A record the sum of Rows A, B and C for each valve. With a dial
indicator mounted as described in Step 14, use the adjusting nuts to set each valve to the
dimensions recorded in Row D. Lock the valve adjusting nuts in accordance with the
procedure shown on Exhibit B.
Reassembly
1. Parallel the valve lever of the operating gear to the Joint face of the steam chest cover.
2. Assemble the valve spindles and attach the spindles to the operating gear
3. Adjust the valve spindles so the top of the lifting bar is parallel within .002 with the cover joint
face. The distance between the top of the lifting bar and the steam chest cover Joint face is the
measurement obtained in Step 12 (Blocks L & R of Exhibit A) minus one-half (1/2) of the
total bar lift tabulated on the Nozzle Valve and Operating Gear Assembly drawing.
4. Lock the valve spindles to the operating gear lever assemblies with the locknuts provided.
5. Place the cover back on the steam chest and tighten the bolts, using the sequence outlined in
the instruction manual.
S T E A M T U R B I N E M A I N T E N A N C E
6. With the valve operating gear and steam chest cover assembled to the steam chest and the
lifting bar resting on the valves, Jack up the operating gear lever arm to raise the valve
spindles an amount equal to the cold bar setting shown on the Nozzle Valve and operating
Gear Assembly drawing (Row B on Exhibit A.)
7. With the servo motor in place and the power piston on its "closed valves" stop, adjust the
power piston rod clevis until the connecting pin holes line up with the hole in the valve gear
connecting link.
8. Insert pin and secure lock nuts and set screws.
9. Set the position indicators on the valve spindles .250 .001 from the spindle gland with the set
screw provided. Record these two dimensions by stamping on the respective packing gland.
These dimensions will facilitate reassembly of the valve lift bar in the horizontal position
assuming the spindles have not been disassembled from the lift bar.
10. After assembly of nozzle valve rack, the pedestal bearings of lever should be lubricated using
a lubricant as per instruction 9.402 (Exhibit H). Although it is not Demag Delaval’s policy to
recommend a specific brand, it has been found that Never-Seez pure nickel special nuclear
grade having a temperature rating of 2600 degrees F is suitable for this application.
Valve Number 1 2 3 4 5 6 7
Valve Setting A
TOTAL D
S T E A M T U R B I N E M A I N T E N A N C E
The cleanliness of the bearing and oil can also be There is little friction between the wings, and
determined, since deposits are often trapped in the bearing can react quickly to load changes.
the base ring. Evidence of water contamination, Depending on the nature and magnitude of the
particularly in vertical machines, may go unnoticed t hrust load, the wing contact areas will increase
unless the base ring is examined. in time. The contact region of the wings, again
noted by bright areas, will normally appear larger
LEVELING PLATES on the lower leveling plates. If the rotating
The spherical pivot in the rear of each thrust shoe collar is not perpendicular to the shaft axis, the
rests in the center of a flat area on the hard e n e d leveling plates will continuously equalize, causing
upper leveling plate. This flattened area is susceptible rapid wear.
to indentation due to the point contact of the pivot.
The indentation is easily identified by a bright contact SHOE SUPPORT
area. This area indicates where the shoe operates The shoe support is the hardened spherical plug
on the upper leveling plate, and its depth gives an in the rear face of each thrust shoe. Based on the
indication of load.Close examination of the upper magnitude and nature of the thrust loads, the
leveling plate near the contact area may also produce spherical surface will flatten where it contacts
evidence of electrical pitting. the upper leveling plate. The contact area will
appear as a bright spot on the plug. If evidence
As noted previously in SECTION I, the upper of hard contact exists (a large contact spot), rest
leveling plates interact with the lower leveling the shoes (pivot down) on a flat surface. If the
plates on radiused “wings.” The upper leveling shoes do not rock freely in all directions they
plates are typically hardened; the lowers are not. should be replaced.
When new, the leveling plates have line contact.
S T E A M T U R B I N E M A I N T E N A N C E
Ca v i t a t i o n
Cavitation damage appears as discreet irre g u l a rly-
shaped babbitt voids which may or may not
extend to the bond line. It may also appear as
localized babbitt erosion. The location of the
damage is important in determining the trouble
s o u rce (Figs. 23-25).
OPERATIONAL DATA
Another important source of diagnostic information
is unit operational data. Identifying periods
of load or speed changes, recent maintenance, or
the performance of related machinery may also
help determine the root cause of distress.
Vibration data or an analysis may help discover
existing problems, as well as examining the
remaining bearings in a troubled unit.
TILT PAD BEARING CLEARANCE CHECK
Pivoted Shoe Journal Bearing Clearance Check
Generally, it is advisable to perform this flush with a flushing rig independent from the installed lube
oil pumping system. Flushing rigs normally have greater capacity for flow than the installed system
and can reduce the required flushing time if contamination is present.
Experience has indicated that efficient results during flushing can be obtained by breaking the system
into sections and progressively flushing the system while maintaining the highest oil velocities
(minimum obstructions ) and incorporating both mechanical and thermal shocking. It should be noted
that the use of screens during the flushing of oil systems is not intended to clean the system, but to
visually aid in determining the progression and ultimately the completion of the flushing. Because
screens are not intended to actually clean the system they should not be installed during the initial
phase of flushing.
1. Inspect and clean as necessary the installed lube oil console reservoir, piping, filter system,
and cooling system.
2. Loose shipped piping must be inspected and cleaned as needed prior to installation. Piping
fabricated on site, must be hand-cleaned, washed, blown dry, inspected, and either capped or
immediately installed to prevent contamination. All site fabricated pipe should be made from
chemically cleaned new pipe. Pipe that has been cleaned mechanically, either by brush or
sandblast, is unacceptable for any type of service, be it oil, water, steam, air, gas or chemicals.
3. A determination of the ultimate locations of jumpers and screens placement will be made by
the Field Service Representative( FSR) and the site authorized representative. A schedule
should also be prepared to include personnel and resource requirements.
4. Screens should be prepared in advance for installation during the flushing period. Although
ultimate screen placement may vary depending on considerations specific to each installation,
the FSR will, as a minimum, request screens be prepared for eventual installation following
locations:
Outlet connection of the flushing rig or console downstream of the installed filters. These must
be installed where a horizontal run of pipe precedes the screen, or in the bottom of a vertical
run when the flow is downwards.
At each bearing inlet, at the last flange to the case where a horizontal run precedes the screen.
At each oil seal inlet, at the last flange to the case where a horizontal run precedes the screen.
See the caution statement concerning gas seals.
At the outlet of overhead tanks, preferably at the bottom of a run of pipe.
At the last flange of the drain header prior to returning to the reservoir tank. Experience has
shown that using a conical screen or "witches hat " in this location proves advantageous during
the flushing procedure. It is important that the field fabricated piping accommodate this type
of screens .
Screens should be fabricated from 100 mesh stainless steel, and supported between two gaskets
properly sized and appropriate for the service conditions for which they will be used. When ever
possible screens should be installed in a horizontal plane at the bottom of a vertical run.
5. Make provisions to thermally shock the system by rapidly varying the oil temperature between
90°F - 180°F. Be careful not to exceed the Max. temperature rating of the pumps seals or drop
below the minimum oil viscosity required for pump lubrication.
6. Make provisions to vibrate the piping during the flushing cycles. Mechanical vibrators or
nitrogen injection may be used. In areas where it is not practical to install mechanical
vibrators, the piping should be manually shocked.
7. Prepare jumpers for installation in the areas predetermined by the FSR. Typically this will
include jumpers around all control system components, such as steam inlet stop valves, servos,
actuators, governors, and compressor seals. Provisions must be made to deal with hydraulic
accumulator bottles. They can be filled and allowed to drain three or four times, then blocked
off from flow until the system flushing is completed. Overhead tanks should be cleaned as
necessary.
8. Due to the variation in bearings and bearing bracket designs, each unit must be evaluated
individually to determine whether the bearings need to be removed and hand cleaned or if they
should be flushed in situ. This determination will be made by the FSR.
9. Screens and filters may require changing often. A sufficient number of screens should be made
up for each connection to accommodate rapid change out. Ten (10) sets of screens and three
(3) sets of filter elements are considered a basic starting set.
Flushing
When all preparations listed above have been made, initial flushing phase may be started.
1. Identify a section downstream of the filters, usually at the first convenient flange of field
piping. Isolate this section by attaching the previously prepared jumper hose and terminate this
jumper in the drain header.
2. Begin the initial phase with no screens installed except the return screen in the end of the drain
header.
3. Flush with mechanical and thermal shocking. Periodic cycling of the pumps should also been
done. Continue this process for 4 hours.
4. After approximately 4 hours of unobstructed flushing, install a screen at the end of this run and
continue flushing for 2 hours.
5. After 2 hours a screen check should be done. Base on the amount of particles found, the FSR
will make a determination whether to remove the screens or continue flushing with the screens
installed.
6. When a screen if flushed for at least two hours with no visible particle, the next section of the
system may be tied in and flushed following the same the same procedure. ( The original
screen is removed )
7. If the section being flushed includes an overhead tank, this tank must be inspected and cleaned
(if needed) each time the screens are inspected. In addition to a clean screen, the criteria for
this section before moving to the next section will include a clean tank.
Flushing the system is a 24-hour-a-day operation. The first few days will involve changing screens as
they clog up. It is recommended that a dedicated crew be assigned to this task in sufficient numbers to
complete the change of screens in a timely manner. The temperature should be varied throughout the
flushing period. As the screens show marked decrease in particles to the point that it would be
possible to actually count their numbers, less frequent change out will occur. Differential pressures of
the filters should be continuously monitored and changed whenever the maximum differential is
observed. Particle counts are guidelines for the progression of the flushing operation and, as such are
not final acceptance criteria. After the system has been incrementally flushed up to the bearing and
seal flanges with no evidence of particles to the unaided eye for two consecutive four-hour flushing
cycles, the system is ready to proceed into the next phase of flushing and evaluation.
At this point, any dead end areas of the system that are accessible, such as blind flanges, bearing
brackets and all overhead tanks, should be opened and hand cleaned to remove any accumulation of
settled or trapped debris.
Acceptance
Secondary flushing can now begin. This should be accomplished utilizing clean screens and new filter
elements and continuing vibration and temperature cycles. Final acceptance is conditional on three
consecutive 4-hour flushes with no particles being visually detected on any screens located at the last
section just before entering the unit at bearings or seal locations. Once this has been achieved, the
piping system should be returned to its normal operating condition with all temporary flushing
hardware removed. Utilizing the installed lube oil console with a screen installed on the drainer
header connection to the console, and all jumpers removed, bearings installed, and control system
components operational, the system should be placed in operation and all components cycled through
their operational limits to remove any further debris. When two consecutive 4-hour flushes with no
visible particles on the screen in the drain header has been obtained and no operational problems
noted, the system is considered acceptable for operation.
CAUTION: OIL TEMPERATURE SHOULD NOT EXCEED 180° F AT ANY TIME, SINCE
COMPONENTS OF THE FILTERING SYSTEM MAY DETERIORATE UNDER HIGH
TEMPERATURES.
CAUTION: JUMPER HOSES SHOULD BE EITHER NEW OR NOT BEEN PREVIOUSLY USED
FOR ANY OTHER SERVICE OTHER THAN OIL.
CAUTION: IT IS RECOMMENDED THAT THE FLUSHING OIL NOT BE REUSED FOR UNIT
OPERATION. IF UNIT OIL IS USED FOR FLUSHING AND IT BECOMES NECESSARY TO
REUSE IT, THEN OIL SHOULD BE PUT THROUGH A SUITABLE OIL PURIFIER TO
REMOVE ANY SLUDGE OR DIRT.
This lengthy approach to flushing will insure a properly cleaned system. The time spent to do it right
from the start will be far less than shortcuts taken that may lead to possible damage in the near future.
It is the responsibility of the installation contractor, in conjunction with the plant owner/operator to
make the final acceptance determination.
Steam Blowing of Piping
I. General
The purpose of the Steam Blow is to remove any scale, corrosion or foreign bodies in the steam
piping leading up to the turbine. This is to prevent any damage to the turbine, blocked steam strainers
or blocked piping to the turbine auxiliaries.
If the steam blows were not carried out, the customer must be informed in writing of the
consequences f not performing the steam blows and must sign and accept all risk.
A. Safety
Before starting the steam blowing, all piping must be insulated. This is to reduce the risk due
to accidental burns and fire. Clearly identify danger area with barricades and insure safety
personnel clear the area before each steam blow.
All steam systems leading up to the turbine are subject to steam blows. This includes main
steam, seal steam, auxiliary steam to air ejectors; as well as all bypass lines and reducing
stations.
The piping is normally blown all the way up to the turbine connection point. If possible
remove the turbine trip valve or obtain a blow down kit from the valve manufacturer. It is
recommended that any items susceptible to damage, such as valve seats and flow measurement
devices be removed from the system during the steam blow.
Flange Imperfections
On seating, the gasket must be capable of overcoming the macro and micro imperfections.
Macro defects are imperfections such as flange distortions, non-parallelism, scoring,
troughs, while superficial imperfections such as minor scratches and minor scores are considered
micro imperfections.
The hydrostatic end force is the force produced by the internal pressure which acts
to separate the flanges.
Ring Type Joints
The ring type joint was initially developed for use in the petroleum industry, where high pressure/temperature applications
necessitated the need for a high integrity seal. They are mainly used in the oil field on drilling and completion
equipment. Ring type joints are also commonly used on valves and pipework assemblies, along with some high
integrity pressure vessel joints.
Reuse
Ring type joints are designed to have a limited amount of positive interference, which ensures that the ring type joint seats
correctly into the groove on compression. Their reuse is not recommended for two reasons:
Hardness of Materials
On compression of the flange assembly, it is imperative that the ring type joint be significantly softer than the flange
groove so that the gasket plastically deforms and not the groove. The use of harder ring type joints can result in flange
groove damage.
Gasket Installation
A FLEXITALLIC gasket will provide a reliable seal
when properly installed in the application for which it • Type • Proper material
was designed. Please remember that the performance of • Grade • Appropriate coating or plating
a bolted joint is not solely dependent on the gasket itself, • Class • Correct stud/bolt length
but on a combination of variables, many of which are
outside the control of the gasket manufacturer. Assembly
In an effort to achieve a high degree of success in
Experience has shown that leakage is not necessarily a attaining a leak-free joint several steps are required. It is
sole indication of a faulty gasket, but is more likely to be imperative that a regimented bolt up procedure is
the result of improper installation, assembly or bolting applied. As a minimum the following is suggested:
practices, damaged flanges, or a combination
of the myriad of variables associated in a bolted • Install a new gasket on the gasket seating surface and
gasketed assembly. bring the mating flange in contact with the gasket.
When installing the gasket the following are to be • Do not apply any compounds on the gasket or gasket
considered: seating surfaces.
Gasket Quality • Install all bolts, making sure that they are free of any
Obviously gasket quality is important. Always deal with foreign matter, and well lubricated. Lubricate nut
reputable suppliers and/or manufacturers who are bearing surfaces as well.
capable of high quality products and sound technical
support. (Lubrication will not be required for PTFE coated
fasteners.)
NEVER INSTALL A PREVIOUSLY USED
GASKET! • Run-up all nuts finger tight.
12. What do you do if Client Instructs you to Not Follow Sulzer Procedures?