You are on page 1of 1

ESTIMASI SCHEDULE PROGRES PINTU BESI PT.

MITRA KONSTRUKSI
PROJECT PROJECT START PROJECT END
NAMA PROYEK
DURATION DATE DATE
BTB SCHOLL - PLUIT 45 Aug 10, 2022 Sep 24, 2022

Aug 10, 2022


Aug 11, 2022
Aug 12, 2022
Aug 13, 2022
Aug 14, 2022
Aug 15, 2022
Aug 16, 2022
Aug 17, 2022
Aug 18, 2022
Aug 19, 2022
Aug 20, 2022
Aug 21, 2022
Aug 22, 2022
Aug 23, 2022
Aug 24, 2022
Aug 25, 2022
Aug 26, 2022
Aug 27, 2022
Aug 28, 2022
Aug 29, 2022
Aug 30, 2022
Aug 31, 2022
Sep 01, 2022
Sep 02, 2022
Sep 03, 2022
Sep 04, 2022
Sep 05, 2022
Sep 06, 2022
Sep 07, 2022
Sep 08, 2022
Sep 09, 2022
Sep 10, 2022
Sep 11, 2022
Sep 12, 2022
Sep 13, 2022
Sep 14, 2022
Sep 15, 2022
Sep 16, 2022
Sep 17, 2022
Sep 18, 2022
Sep 19, 2022
Sep 20, 2022
Sep 21, 2022
Sep 22, 2022
Sep 23, 2022
Sep 24, 2022
Sep 25, 2022
No Description Duration Start Date End Date

Aug 10, 2022 Aug 12, 2022 x x x


1 Gambar kerja 2

Progres produksi
Aug 13, 2022 Sep 02, 2022 x x x x x x x x x x x x x x x x x x x x x
2 20
Frame / Kusen

Progres produksi
Aug 16, 2022 Sep 05, 2022 x x x x x x x x x x x x x x x x x x x x x
3 20
Door / Daun Pintu

Progres Pengecatan
Aug 18, 2022 Sep 09, 2022 x x x x x x x x x x x x x x x x x x x x x x x
4 22
Kusen & Pintu

RENCANA KIRIM KIRIM


Sep 10, 2022 Sep 11, 2022 x x
5 1
Kusen & Pintu

Sep 10, 2022 Sep 24, 2022 x x x x x x x x x x x x x x x


6 PEMASANGAN 14

NOTE:
- PROGRES PRODUKSI SETELAH SHOPDRAWING DI APPROVED