Professional Documents
Culture Documents
Document ID SP-2380
Security Restricted
Version 1.0
Keywords: This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any
part of this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted
in any form by any means (electronic, mechanical, reprographic recording or otherwise) without prior written
consent of the owner.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 1
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 2
i Document Authorisation
Authorised for Issue
Document Authorisation
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 3
ii Revision History
The following is a brief summary of the most recent revisions to this document. Details of all revisions
prior to these are held on file by the issuing department.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 4
TABLE OF CONTENTS
i Document Authorisation............................................................................................................... 3
ii Revision History ........................................................................................................................... 4
iii Related Business Processes ....................................................................................................... 4
iv Related Corporate Management System (CMS) Documents...................................................... 4
1 Introduction .................................................................................................................................. 6
1.1 Purpose .................................................................................................................................. 6
1.2 Distribution, Intended use and regulatory considerations ...................................................... 6
1.3 Definitions .............................................................................................................................. 6
1.4 Abbreviations ......................................................................................................................... 7
1.5 Comments on this SP ............................................................................................................ 7
1.6 Conflicting Requirements ....................................................................................................... 7
1.7 Exceptions .............................................................................................................................. 7
1.8 References ............................................................................................................................. 8
2 Design .......................................................................................................................................... 9
2.1 Introduction ............................................................................................................................ 9
2.2 PE liner design basis.............................................................................................................. 9
2.3 Wall thickness calculation .................................................................................................... 10
2.4 Selection of Outside Diameter ............................................................................................. 11
2.5 Pulling force calculations...................................................................................................... 11
2.6 Stub end design ................................................................................................................... 13
2.7 Retainer ring design ............................................................................................................. 13
2.8 Vent Design .......................................................................................................................... 14
3 Construction ............................................................................................................................... 15
3.1 Introduction .......................................................................................................................... 15
3.1.1 Tight fit liner .......................................................................................................................... 15
3.1.2 Loose fit liner ........................................................................................................................ 15
3.2 Inspection of liner materials ................................................................................................. 16
3.3 Storage ................................................................................................................................. 16
3.4 Handling ............................................................................................................................... 16
3.5 Transportation ...................................................................................................................... 16
3.6 Pre-insertion of PE liner. ...................................................................................................... 17
3.7 Liner Installation ................................................................................................................... 19
3.8 Hydrostatic testing................................................................................................................ 20
3.9 Testing after commissioning ................................................................................................ 21
3.10 Shop Lining: ......................................................................................................................... 21
APPENDIX 1 – SOP for (PE) liner pulling force calculations ............................................................ 23
APPENDIX 2 – SOP for PE Liner wall thickness, Stub end and Retainer ring design ..................... 24
APPENDIX 3 – Standard Drawing for Vent design ........................................................................... 25
APPENDIX 4 – USER COMMENT FORM ........................................................................................ 31
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 5
1 Introduction
1.1 Purpose
This specification is intended for design, construction and commissioning of polyethylene lined CS
flowlines, pipelines and piping systems. Applications are for both buried and above ground, for oil,
water and multiphase (GLR ≤ 300) service.
1.3 Definitions
1.3.1 General Definitions
Tight fit lining It’s a construction methodology where the HDPE Pipe liner has a
larger outside diameter than the inside diameter of the steel pipe. The
liner pipe is compressed radially as it passes through the roller
reduction box.
Loose fit lining It’s a construction methodology where the HDPE Pipe liner has a
smaller outside diameter than the inside diameter of the steel pipe.
The liner pipe is pulled out through the pipeline, then expands during
hydrotest.
Annulus gap Space between the PE liner outer diameter (prior to expansion) and
the carbon steel inner diameter. This gap will be closed after the
hydrotest.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 6
1.4 Abbreviations
In case of conflict among documents or sections, the more stringent requirements shall apply, unless
otherwise agreed with the Purchaser in writing.
1.7 Exceptions
Vendor shall make a formal request with full supporting information and justification when a deviation
from standard is requested. Vendor is required to notify any inaccuracy or ambiguity encountered in
this document.
Any proposed exceptions or changes to this specification shall be submitted to the Pipeline CFDH
for approval. Any work completed with unauthorised modifications shall be rejected by the Company.
All deviations shall be handled as per PR-2066.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 7
1.8 References
In this SP, reference is made to the following publications:
PDO Standards
GU -969 Pipeline Stress Analysis
API RP 15LE Recommended practice for Polyethylene line pipe and fittings
NOTE: Unless specifically designated by date, the latest edition of each publication shall be used,
together with any amendments, supplements, revisions thereto.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 8
2 Design
2.1 Introduction
This section covers the design of PE liners for flowlines, pipelines and piping systems.
The PE liner design shall be carried out by approved engineering consultant as per AVME PSG-101
and confirmed by the approved installation contractor under AVME PSG 105 and 106.
Installation technique (tight fit / loose fit) shall be specified by Company Pipeline TA2 based on cost
analysis (Material, installation cost, contractor capability,… etc.)
For sour service applications, CS line pipes shall be supplied as per SP-2347.
Design of PE liner system including pulling forces calculations and wall thickness shall be prepared
as per the SOPs detailed in (Appendix-1 and 2) and submitted for Company Pipeline TA2 review and
approval.
a. Minimum wall thickness of the liner shall not be less than 6 mm.
b. It is the responsibility of the design consultant to design the PE liner, calculate the pulling
force and finalizing the sections length after consultation with installation contractor and
obtain the necessary approval from Company pipeline TA2.
b. PE Liner shall be designed with minimum 1.5 bar collapse pressure for loose and tight fit
liners.
a. The maximum operating temperature for PE lined shall not exceed 65°C including PE-RT
b. PE Liner shall be designed with 3 bar collapse pressure for loose and tight fit liners.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 9
Where,
(swell) = Liner linear swell (%)
h = Liner wall thickness (mm)
PE MATERIAL PROPERTIES
Below properties values as per SP-2094 shall not be interpolated, values of higher temperature shall
be considered.
Table 1
Table 2
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 10
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 11
• The max. pulling length (Fpull) can be calculated as per the below formula.
PE liner shall be designed to sustain the thermal expansion due to the temperature
difference between the max. operating temperature and the installation temperature
as per below formula. Stretching is applicable only for loose liners.
Where;
L stretch : Max. stretch length = α (T MOT – T ambient)
α : Differential thermal expansion between PE liner and CS pipe
E : Modulus of elasticity of PE liner
A : Cross section area of PE liner
• Pulling force calculations shall be revalidated at site based on the actual installation
temperature.
• The maximum pulling length should not exceed 700m as detailed in Appendix-1.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 12
a. PE flanges, Stub end and extrusion flange ring shall be moulded or machined from
extruded material and shall be from the same PE grade. The wall thickness of the HDPE
flanges shall be equal to the wall thickness of liner pipe.
b. For tight fit method, Consultant shall make a proposal for stub end and retainer ring design
in consultation with Construction Contractor and submit to Pipeline TA2 for approval.
c. Allowable compressive strain of Stub end is restricted to 7.5% as per TN-38 of PPI.
d. Diameter of bolt holes should be obtained from ASME B16.5 or ASME B16.47 Series A as applicable
e. The collar thickness (tc) should be 1.5 times the PE liner wall thickness.
Figure-1
2.7 Retainer ring design
Retainer ring is used to hold the stub ends in place (to avoid the plastic material from deformation).
Allowable hoop stress shall be 90% SMYS of the selected material for retainer ring.
Diameter of bolt holes should be obtained from ASME B16.5 or ASME B16.47 Series A as applicable.
Figure-2
Non-metallic phenolic type shall be used for isolation system as per SP-1236.
The retainer ring shall be analysed for bulking under the applied clamping force due to bolting torque.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 13
• To allow monitoring of the integrity of the PE liner during the service life.
Vent holes shall be designed such that no extrusion of the PE liner will occur. The following are
applicable for the vent design:
• One vent with valve shall be provided for section length less than 150 m. For section
length greater than 150 m, two vents shall be provided.
• For flange rating of 300# and below, vents may be flanged with U shaped vent points
facing down and continuously kept open during operation.
• For flange rating of greater than 300#, vents shall be supplied with valves and U-shaped
vent points facing down and kept closed during normal operation. Refer Appendix 3 for
standard drawings.
• The vent points shall be supplied with valve and U-shaped pipe facing down and only
opened for venting activity. Continuous venting is not permitted.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 14
3 Construction
3.1 Introduction
This section outlines general requirements for field installation of PE liners in carbon steel pipelines
and flowlines. Carbon steel construction shall be executed as per SP-1208.
In order to optimize the number of field joints, the length of PE liner can be supplied with random
length of 17-18m.
Installation of PE liners shall be undertaken only by Company approved Contractors under AVME
(PSG-105 and 106) working in accordance with written procedures and method statements approved
by the company. The procedures and ITP shall be detailed in the Quality Plan and shall cover as a
minimum the following areas:
Materials handling and control.
Site and pipe preparation and stringing.
Liner prefabrication and fusion.
Pulling through and stub end installation.
Testing and inspection.
Pre-commissioning.
No work shall be commenced until the relevant procedures have been approved.
Requirements for leak and hydro testing of the carbon steel line, the PE liner as well as the lined
carbon steel line are given in Section 3.8.
The following method of construction are approved by Company: -
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 15
a. Scratches in pipe: surface scratches and nicks in PE pipes may not exceed a depth of 5%
of the nominal PE wall thickness.
3.2.3 Compliance
The Contractor is responsible for complying with all of the provisions of this specification.
The Company may make any investigation necessary to satisfy that there is compliance by the
Contractor and may reject any material that does not comply with this specification.
3.3 Storage
All liner pipes shall be packed and stored in accordance with a procedure agreed by the Company. For
periods longer than 3 months, polyethylene pipe shall be stored under cover with adequate protection
from direct sunlight to avoid UV degradation and/or deformation. If the pipe has to be stored in the
open air before, during or after shipment, it shall be suitably protected from environmental
contamination. The packing shall avoid ingress of moisture or dirt to the inside of the pipe.
Coils shall be stored stacked flat one on top of the other. Straight lengths shall be stored on horizontal
racks in such a way to prevent damage to the pipe. In either form, PE pipe shall not be allowed to
touch ground, hot water or steam pipes and shall be kept away from hot surfaces.
3.4 Handling
All pipes shall be cleaned, dried, packed, handled and transported to arrive at its destination without
distortion or damage. Dragging of HDPE Pipe or coils over rough ground shall not be permitted.
Storage & handling damages beyond acceptable limits shall be rejected.
3.5 Transportation
The minimum requirements for transportation shall be as specified API RP 5L1 and API RP 5LW2.
Pipe transported by sea shall not be shipped as deck cargo.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 16
• Locations for cutting and flanging of the line and any requirement for separate spooled sections
need to be determined. The longest continuous length of liner which can be installed in straight
pipe depends on diameter and wall thickness but is generally reduced in practice by local
curvature of the line. Breaks are also required at road crossings, changes in ID and any bends
of radius. (In general, minimum bend radius shall not be less than:
• 25D for pipe NPS of less than 8”
• For more than one bend, Qualifications shall be carried out with the following conditions:
a. Trail liner pulling shall not indicate any scratch in the liner equal to more than 5% of the
liner wall thickness.
b. Pulling force recorded during pulling shall be within the limits specified in the approved
pulling force calculations.
c. There shall not be any indication of wall thickness loss in the CS bends due to wire rope
friction during pulling. UT measurement of thickness on the CS bends before and after
pulling the liner shall not show any decrease in wall thickness.
d. Pulling direction should be in such a way that it minimizes friction between the wire rope
& the carbon steel bends. This can be optimized by ensuring that pulling head is inserted
as close as possible to the bends location and exit at the straight section.
e. The above qualification shall be witnessed and approved by Company Pipeline TA2.
• Inner edges of CS flanges at the raised face side shall be rounded off to avoid sharp edges.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 17
Sr. Test pipe Qualification Angle of Qualification Bend Qualification Number Qualification
No. Size range bend range radius range of bends range
1 6" - 10" ≤ 10" X° ≤ X° RxD ≥RxD n ≤n
2 12" - 16" 12" to 18" X° ≤ X° RxD ≥RxD n ≤n
3 20" - 24" 20" to 28" X° ≤ X° RxD ≥RxD n ≤n
4 28" - 40" 30" to 42" X° ≤ X° RxD ≥RxD n ≤n
Table 4
Where;
X° : Bend angle in degree
R : Radius of curvature
D : CS outside diameter
n : Number of bends.
Example for clarity purpose, 1st row of table means that 6" line, 4 numbers of 25D bends - 45°
mock-up can qualify all sizes up to 10", up to 4 bends, equal or more than 25D bends and angles
up to 45°.
3.6.3 Vent point assemblies
Every PE lined pipeline and flowline shall have vent points. The minimum number of vent points &
arrangement shall be as stated in section 2.8 of this specification.
Vent holes shall be designed such that no extrusion of the PE liner will occur. Metallic chips resulting
from vent hole drilling shall be removed from the bore and sharp edges of the vent hole at the inner
surface of the carbon steel pipes shall be removed.
• The working area within the bell hole is required to be of sufficient size to accommodate the pipe
fusion machine and operator.
• The entry slope shall be sufficiently shallow to enable the liner pipe to bend smoothly from
ground level to the pipeline depth without severe abrasion against the steel flange during pull-
through. (Provision may also be required for pulling from two directions within a single bell
hole)
• Provision of enough length and width to enable the pipe ends to be offset for flange welding
and pulling in of the liner.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 18
• Sizing pig,
• Cleaning pig
• Cup pig
• Segment of liner pipe (for loose liner)
Once the wireline has been passed through the pipeline section, the pig train is pulled through, the
pulling force being continuously monitored and recorded to determine the location of any
constrictions.
The disc plate diameter shall be of sufficient diameter to verify that internal weld beads do not protrude
excessively taking into account the dimensional tolerances of the steel pipe. Disc plate size shall not
be less than the OD of PE liner for loose liner. For tight fit, the OD of PE liner shall not be less than
97.5% of ID or max 15mm less than ID of carbon steel whichever is higher.
The liner test segment attached to the pig train should emerge without serious damage. Minimum
length of test liner segment shall not be less than the two complete 90° bend length plus 2 meters.
Scuffing of the liner surface is permissible but sharp longitudinal scars or other penetration damage
exceeding 0.5 mm or 5% of the wall thickness, whichever is larger, is unacceptable. Weld protrusion
shall not exceed 1.5mm and would require rectification by further pigging using a breaker pig or by
other means prior to continuing with liner installation. After rectification another liner test segment
shall be pulled through.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 19
• Pulling shall not be carried out at the average surface temperatures more than 60°C or
any single reading exceeding 65° C. Precautions shall be taken to ensure that no debris
is introduced into the line on the external or internal surface of the liner.
• If the use of a friction reducing agent is proposed by the Contractor, the type and
application method shall be approved by the Company.
3.7.3 Installation of stub ends and retainer rings
Connections between PE lined pipes and CS piping shall be flanged. No other joining methods shall
be permitted unless agreed with the Company. End flange dimensions, joining and liner stretching
details shall be clearly specified in the contractor procedures submitted for company approval.
After the PE liner has been pulled in, stub ends shall be fusion welded to each end. The method shall
be detailed by the Contractor but will generally involve the following steps:
• Welding a to the liner segment trailing end and pulling into the steel flange.
• Clamping and stretching the liner from the leading end, enough to trim to required length and
butt the second flange adapter. (Normally a minimum 100 m segment length is required for this
technique to accommodate the necessary elastic strain).
• Releasing the clamp to allow the liner to contract on to the steel flange face.
• Fitting metal retaining rings around the liner flanges. These are designed to a controlled
thickness to limit compression of the PE flanges to a pre-determined value when bolting
adjacent segments and to prevent spreading of the PE material under load.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 20
For Tight fit liners: Rate of pressurization can be followed as per SP-1212. When the pressure
reaches the design pressure of flowline or pipeline hold at least 1 hour to inspect the vents for any leak.
• Before commencing any activity, the contractor representative shall inspect the flanged steel
pipe for its lining suitability. Carbon steel flanges inside edges shall be ground to a radius of
minimum 6mm and the internal welding bead should be flush ground.
• HDPE liner fusion and extrusion procedure including the bed trimming and vent holes shall be
approved by Company non-metallic material engineer TA2. Technician shall be qualified prior
start-up of any activity in accordance with SP-2094.
• The liner shall be fully inserted into CS spool until the stub end is in full contact with CS flange.
Insertion of liner can be done either by pushing or pulling method for straight spools. Pulling
method shall be used for spools with bend(s). The excess length of the liner is marked at the
other end using pencil at 200 from the face of the CS flange.
• Pulling force calculation and stretching required for shop lining shall be calculated as specified
in section 2.5.
• Once the maximum expansion / stretch accomplished the liner pipe shall be arrested within
the CS spool by a restraining mechanism. The cutting location on the liner which shall include
the width of the slip-on flange to be extrusion welded to the liner shall be marked and the liner
cut to remove the excess length.
• After cutting, the joint preparation and fit-up shall be carried out before commencing extrusion
welding. The slip-on flange shall be clamped to the steel flange by a minimum of two
diametrically opposed clamps to prevent any movement. Only qualified welding procedure,
welder, welding rods and welding equipment shall be used for the extrusion welding operation.
The expansion length, temperature details shall be recorded in the approved format. All the
welding parameters shall be recorded in the extrusion welding joint record.
• The detailed clamping/holding arrangement for expanded this extrusion welding shall be
submitted for company quality or materials for approval.
• Contractor shall ensure that the arrangement shall not allow any movement of the liner pipe
and flange being welded until the welding operation is completed including the cooling of the
joint.
• The welded joint shall be allowed to cool to ambient temperature before removing any defects.
The joint shall be flush externally and suitable grinders shall be used to achieve a good finish.
• The spool shall be hydro-tested before and after the insertion of PE liner.
• The Contractor shall be responsible for maintaining, fusion welding, inspection, test and as-
built documentation during installation and compiling a package of hand-over documentation
on completion of the work.
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 22
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 23
Access to ASSAI for 1 Gather all reference 1.1 Check if all data is frozen in terms of Reference docs:
reference documents to collect line size, design parameters, route, Project alignment sheets OR
documentation all the required input before proceeding with calculations Routing plan
data and ensure they Station approach dwgs
are latest by checking 1.2 Check the deliverable register, to Process Engg Flow scheme
revisions in deliverable confirm latest revisions of reference (PEFS)
Via - Livelink / PDO
register. documents. CS WT calcs report
LAN PE WT calcs report
1.3 Make a note of all revision numbers of
the documents used in the Abbreviations:
Process Performer: Cycle Time: 1 days
calculations; If new revisions are CS – Carbon steel
Pipeline Engineer issued verify the changes in the input ID – Inside diameter
data (if any), and revise calculations to
OD – Outside diameter
reflect the changes.
PE – Polyethylene
PEFS - Process Engg
Flow scheme
WT – Wall thickness
Data gathering 2 Collect all information 2.1 Ensure use of PE100 grade properties Reference Standards
required for pulling like -Young’s Modulus, density, tensile SP-2094 : Specification for PE
force calculations strength, coefficient of thermal liners in CS flowlines & pipelines
Via – Livelink / PDO expansion, CS line ID, PE liner OD &
LAN WT….etc
SP-2094 CMS link
2.2 Allocate section numbers in alignment
sheets
Cycle Time: 3 days
2.3 For each section note the following:
Section length
Number of bends
Radius of bend
Type of bend
Process Performer:
Pipeline Engineer
Access to approved / 3 Use approved / 3.1 Enter all inputs in spreadsheet
See
validated PE liner calcs validated spreadsheet
pulling force attached
spreadsheet. calcs.xlsm Excel file
Cycle Time: 1 day
Via - email
Process Performer:
Pipeline Engineer
Document Owner Version (Revision) Effective Date Approval Document Location Page
UEMP UEMP/SOP1/ 20-May-19 UEMP / Badar Al Habsi 1 of 5
Ver1.0
SOP for Polyethylene (PE) liner pulling force calculations
Pipeline Function team
PE pulling force 4 Perform PE pulling 4.1 Calculate the pulling force based on
calculations force calculations below:
DLo = PE liner OD
DLi = DLo – 2 x tL DLi = PE liner ID
tL = PE liner thk
Via approved
spreadsheet - Steps AL= π x (DLo^2 - DLi^2)/4 AL = Area of PE Liner
4.1
W = ρ x AL W = weight of PE liner per unit length
ρ = Density of PE liner
For Straight sections (without bends): Lliner = Liner length Straight section
Cycle Time: 2 days
Fpull = Lliner x W x f + Freduce (if
f = 0.4 (friction factor)
applicable)
Process Performer: Fpull = pull in force.
Pipeline Engineer
Document Owner Version (Revision) Effective Date Approval Document Location Page
UEMP UEMP/SOP1/ 20-May-19 UEMP / Badar Al Habsi 2 of 5
Ver1.0
SOP for Polyethylene (PE) liner pulling force calculations
Pipeline Function team
Document Owner Version (Revision) Effective Date Approval Document Location Page
UEMP UEMP/SOP1/ 20-May-19 UEMP / Badar Al Habsi 3 of 5
Ver1.0
SOP for Polyethylene (PE) liner pulling force calculations
Pipeline Function team
No
No
Yes
Is Total Fpull
> Fmax?
Yes
Is L > Lmax?
No
No
Section Length not
Section length is acceptable
acceptable
Calculation document 6 Review and approval 6.1 Client TA2 Pipeline Reviews and
approval of calculation report provides comments on the document
6.2 Pipeline Engineer incorporates
Via – ASSAI Cycle Time: 4 days comments (if any)
6.3 Client TA2 Pipeline approves
Process Performer: document
Client TA2 Pipeline &
Pipeline Engineer
Document Owner Version (Revision) Effective Date Approval Document Location Page
UEMP UEMP/SOP1/ 20-May-19 UEMP / Badar Al Habsi 4 of 5
Ver1.0
SOP for Polyethylene (PE) liner pulling force calculations
Pipeline Function team
Document Owner Version (Revision) Effective Date Approval Document Location Page
UEMP UEMP/SOP1/ 20-May-19 UEMP / Badar Al Habsi 5 of 5
Ver1.0
Revision: 1.0
Petroleum Development Oman LLC Effective: Dec-20
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 24
Special Requirements Procedure Overview Instructions and Explanations Key Point Images
STEP 1.0 : Data Collection
Access to ASSAI / SPO 1 Gather all 1.1 Check if all data is frozen in terms of line Reference
for reference reference size, design envelop before proceeding - Pipeline design data summary
documentation documents to with calculations. sheet
collect all the - SP-2380
required input 1.2 Check the deliverable register (DDM), to
data and ensure confirm latest revisions of reference Symbols
Via - Livelink / PDO
they are latest by documents which identified in the D = CS Outside diameter (mm)
LAN checking revisions incoming steps. E = Modulus (@ 5% Sec Value)
in deliverable t = CS wall thickness (mm)
register. 1.3 Make a note of all revision numbers of the ID = CS Inner diameter (mm)
Process Performer:
documents used in the calculations; If ε (swell) = Linear swell (%)
Pipeline Engineer new revisions are issued verify the Pc = Min Collapse pressure (bar)
changes in the input data (if any), and R = Average radius of the Liner (mm)
Cycle Time: 1 day
revise calculations to reflect the changes. h = PE Liner Wall thickness (mm)
hmin = Minimum Wall Thickness of the
PE Liner (mm)
Abbreviations
CS – Carbon Steel
WT – Wall Thickness
PE – Poly Ethylene
DP – Design Pressure
SMYS – Specified Minimum Yield
Strength
TN – Technical Note
PPI – Plastic Pipe Institute
Document Owner Version (Revision) Effective Date Approval Document Location Page
PDEMP19 (Zaid Al-Mawali) UEMP/SOP4 16-Dec-2020 UEMP (Badar Al Habsi) 1 of 7
Version 2.0
SOP for HDPE Liner wall thickness and Stub End design
Yes
h = hmin h < hmin
No
h to be considered
Yes
No SPE+PE, SPE+CS,
Increase “ h “ SPE+ROTO ≤ SA
Yes
End
Print results from
spreadsheet
Document Owner Version (Revision) Effective Date Approval Document Location Page
PDEMP19 (Zaid Al-Mawali) UEMP/SOP4 16-Dec-2020 UEMP (Badar Al Habsi) 2 of 7
Version 2.0
SOP for HDPE Liner wall thickness and Stub End design
Process Performer:
Pipeline Engineer
A - Coefficient of squared
X2 = (- B - SQRT ( ( B )2 – [ 4 * A * C ] ) ) / ( 2 * A ) term in the quadratic
equation.
Where:
B - Coefficient of single
A=1 powered term in the
quadratic equation.
B = - 0.0165 * ε (swell)
C - Constant in quadratic
C = - Pc / ( 2.334 * E ) equation.
No
Document Owner Version (Revision) Effective Date Approval Document Location Page
PDEMP19 (Zaid Al-Mawali) UEMP/SOP4 16-Dec-2020 UEMP (Badar Al Habsi) 3 of 7
Version 2.0
SOP for HDPE Liner wall thickness and Stub End design
Document Owner Version (Revision) Effective Date Approval Document Location Page
PDEMP19 (Zaid Al-Mawali) UEMP/SOP4 16-Dec-2020 UEMP (Badar Al Habsi) 4 of 7
Version 2.0
SOP for HDPE Liner wall thickness and Stub End design
The value of ODRR need to be selected by using “Trial and DBH = Diameter of Bolt
Holes (mm), refer to
Error Method”:
ASME B16.5, Tables as
per applicable flange
- if ODRR < ADRR & Sh ≤ SA , then acceptable rating
- if ODRR ≥ ADRR or Sh > SA , then not acceptable
ADRR = Retainer Ring
tRR = ( ODRR – IDRR ) / 2 (Note-1) Allowable Diameter (mm)
SA = 0.9 * SMYS of the selected material for Retainer Ring ODRR = Retainer Ring OD
(mm)
PHT = 1.25 * DP
tRR = Retainer Ring
Sh = ( PHT * ODRR ) / ( 2 * tRR ) thickness (mm)
SA = Allowable Hoop
Stress (Mpa)
Sh = Calculated Hoop
Stress (Mpa),
∆lROTO = Change in
rotolining thickness (mm)
tROTO = Rotolining
Thickness (mm)
5.6 Calculate the Retainer Ring Width
wX+X = Width of Retainer
∆lPE = tC * 7.5% (Note-2) Ring (mm)
∆lROTO = tROTO * 7.5% (Note-2) Note:
1. In case this thickness
wPE+PE = (2 * tc) + (2 * RF) - (2 * ∆lPE) results in impractical
dimensions, the consultant
shall propose practical
wPE+CS = tc + (2 * RF) - ∆lPE
thickness for approval by
TA2.
wPE+ROTO = (tc + tROTO) + (2 * RF) – (∆lPE + ∆lROTO)
2. Allowable compressive
strain (%) is restricted to
7.5%, refer to TN-38 of PPI.
Symbols:
Document Owner Version (Revision) Effective Date Approval Document Location Page
PDEMP19 (Zaid Al-Mawali) UEMP/SOP4 16-Dec-2020 UEMP (Badar Al Habsi) 5 of 7
Version 2.0
SOP for HDPE Liner wall thickness and Stub End design
Via - Email
Cycle Time: 2 days
HDPE Liner Wall
Process Performer: Thickness and Stub
Pipeline Engineer
Document Owner Version (Revision) Effective Date Approval Document Location Page
PDEMP19 (Zaid Al-Mawali) UEMP/SOP4 16-Dec-2020 UEMP (Badar Al Habsi) 6 of 7
Version 2.0
SOP for HDPE Liner wall thickness and Stub End design
Document Owner Version (Revision) Effective Date Approval Document Location Page
PDEMP19 (Zaid Al-Mawali) UEMP/SOP4 16-Dec-2020 UEMP (Badar Al Habsi) 7 of 7
Version 2.0
Revision: 1.0
Petroleum Development Oman LLC Effective: Dec-20
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 25
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 26
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 27
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 28
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 29
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 30
SP-2380 – Specification for design and construction of PE liner in Carbon steel flowlines
and pipelines
User Feedback Page
Any user who identifies an inaccuracy, error or ambiguity is requested to notify the
custodian so that appropriate action can be taken. The user is requested to return
this page fully completed, indicating precisely the amendment (s) recommended.
Name:
Ref ID Date:
Printed 16/12/2020 SP-2380: Design and construction of PE lined Carbon steel lines Page 31