INSPECTION CHECKLIST FOR BLOCKS Ref.# CHK-AAI-SAM-0017 Rev.

01

Inspection Date:
PROJECT: Design & Build of Lusail Security Complex
CLIENT: ASHGHAL (PWA)
CONTRACTOR: Al Aali International
CHECKED BY
S.NO DESCRIPTION STATUS CONTRACTOR SIGN REMARKS
NAME

Supplier/Subcontractor PQ & Material is


1. Approved by Consultant
YES/NO

Is the Country of Origin Certificate, Warranty


2. certificate attached?
YES/NO

Is Qatar Sustainability Assessment System


3. (QSAS) Compliance certificate attached? (If YES/NO
applicable )

4. QCDD approval attached (If any) YES/NO

5. Quantity as per Delivery Note YES/NO

6. Storage as per requirements YES/NO

7. Material delivered without Damage YES/NO

8. Correct Sizes and quantity YES/NO

Test reports, Batch certificate attached?


9. YES/NO
(If any)

10. HSE clearance attached? YES/NO

CONSULTANT’S REMARKS:

For For
CONTRACTOR ENGINEER

Date Date:
Note: Contractor should ensure incorporation of all comments
Safety of Work and Workers is total responsibility of Contractor

Page 1 of 1

Format No. AAI/QAQC/SDF/003-1 Rev.01, Date-14-05-2022